36-Sec 01 26 73 - BITUMINOUS MATERIAL PRICE ADJUSTMENT.pdf

PDF 123 KB Posted

Attached to
Heritage Hills WWTP Discharge Interconnection, Contract No. 6715-11 State and local contract opportunity
Solicitation number
Not on record
Issued by
Bucks County, Pennsylvania

About this file

This is a specification document for bituminous material price adjustment provisions issued by the Pennsylvania Department of Transportation (PennDOT) for application to the Upper Makefield Township 2026 Road Program, a local road construction project in Pennsylvania involving milling, base repair, leveling course, manhole rim adjustments, and wearing course work. The specification applies to projects where more than 100 tons of asphalt cement, including asphalt cement residue in emulsions or cut backs, will be used in bituminous materials placed as part of the construction work. PennDOT posts monthly index prices for asphalt cement (PG 64S-22) using price data obtained on the last Wednesday of each month from a survey of producers doing business in Pennsylvania, with data from eastern region producers averaged to compute the index price for Zone 1 districts.

The specification establishes a price adjustment mechanism based on the ratio of the current month's price index (IP) to the price index in the proposal (IB). When this ratio falls between 0.90 and 1.10, no price adjustment is made. When the ratio falls below 0.90, the owner receives an automatic price rebate; when above 1.10, the contractor receives a price increase. Both adjustments are calculated using formulas that factor in the quantity of bitumen in the mixture placed. The specification provides equivalent tonnage calculation methods for bituminous mixtures placed on a square yard basis, a gallons per square yard basis, or a gallon basis, each using different variables including surface area, design depth, design density, and specific gravity. Cumulative price adjustments under $500 are disregarded, and contractors may request partial payments once unpaid accrued increases exceed $10,000 or once every 12 months. If bituminous materials are placed after contract time expiration and liquidated damages apply, the lower of the actual placement price index or the contract expiration price index is used. Contractors must obtain prior written approval before furnishing bituminous material if the current price index indicates a 50% or greater increase over the proposal index.

View the file

Other files for this state and local contract opportunity

Other files attached to Heritage Hills WWTP Discharge Interconnection, Contract No. 6715-11, newest first.
File Type Posted
2-6715-11 CONTRACT DRAWINGS.pdf PDF
1-6715-11 CONTRACT DOCUMENTS.pdf PDF
52-Sec 32 05 19.13 - GEOTEXTILE.pdf PDF
13-Doc 00 62 16-CERTIFICATE OF INSURANCE.pdf PDF
44-Sec 32 01 17.61 - ASPHALT JOINT SEALING.pdf PDF
11-Doc 00 61 13.13 - PERFORMANCE BOND.pdf PDF
43-Sec 31 23 00 - EXCAVATION BACKFILL AND COMPACTION FOR ROADWAYS.pdf PDF
38-Sec 01 33 00 - SUBMITTALS.pdf PDF
12-Doc 00 52 00 - AGREEMENT.pdf PDF
30-Doc 00 72 00 - GENERAL CONDITIONS.pdf PDF
3-Doc 00 01 01 - TITLE SHEET AND COVER.pdf PDF
19-Doc 00 61 13.16 - PAYMENT BOND.pdf PDF
42-Sec 31 23 16.26 - ROCK REMOVAL.pdf PDF
17-Doc 00 21 13 - INSTRUCTIONS TO BIDDERS - EBID.pdf PDF
39-Doc 00 73 00 - 00 - SUPPLEMENTARY CONDITIONS.pdf PDF
25-Sec 01 22 00 - 03 - MP PAVEMENT MARKING QUANTITIES.pdf PDF
41-Sec 01 55 26 - TRAFFIC REGULATION.pdf PDF
34-Sec 01 40 00 - QUALITY CONTROL.pdf PDF
48-Doc 00 11 13 - ADVERTISEMENT FOR BIDS.pdf PDF
51-Sec 01 57 13 - EROSION SEDIMENT CONTROL.pdf PDF
45-Sec 32 01 16.71 - MILLING OF BITUMINOUS PAVEMENT SURFACE.pdf PDF
2-Doc 00 45 13 - BIDDER QUALIFICATION STATEMENT.pdf PDF
32-Sec 01 22 00 - 01 - MP BASE BID QUANTITIES.pdf PDF
54-Sec 32 17 23.33 - THERMOPLASTIC PAVEMENT MARKINGS.pdf PDF
21-Doc 00 91 13 - ADDENDA.pdf PDF
10-Doc 00 01 10 -TABLE OF CONTENTS.pdf PDF
22-Sec 01 32 36 - AUDIO-VIDEOTAPING.pdf PDF
56-2026 UMT Paving Map.pdf PDF
33-Sec 01 22 00 - 00 - MEASUREMENT AND PAYMENT.pdf PDF
53-Sec 01 60 00 - MATERIAL AND EQUIPMENT.pdf PDF
1-Doc 00 45 10 - BIDDER ACKNOWLEDGEMENT FORM.pdf PDF
20-Doc 00 73 00 - 01 - APPENDIX A PREVAILING WAGE RATES.pdf PDF
6-Doc 00 45 53 - AGREEMENT OF SURETY COMPANY.pdf PDF
15-Doc 00 65 19.16 - CONTRACTORS RELEASE OF LIENS.pdf PDF
24-Sec 01 11 13 - SUMMARY OF WORK.pdf PDF
7-Doc 00 21 13.1 - ELECTRONIC BIDDING INSTRUCTIONS.pdf PDF
31-Sec 01 22 00 - 02 - MP ALTERNATE BID QUANTITIES.pdf PDF
37-Sec 01 42 13 - ORGANIZATION AND REFERENCE ACRONYMS.pdf PDF
49-Sec 32 12 23-RESTORATION OF PAVED SURFACES.pdf PDF
28-Sec 01 29 00 - CONTRACT CONSIDERATIONS.pdf PDF
23-Doc 00 73 00 - 03 - APPENDIX B COVER.pdf PDF
16-Doc 00 61 19 - MAINTENANCE BOND.pdf PDF
29-Doc 00 73 00 - 04 - APPENDIX B PUBLIC WORKS EMPLOYMENT VERIFICATION FORM.pdf PDF
50-Sec 01 31 00 - COORDINATION AND MEETINGS.pdf PDF
35-Sec 31 11 00-CLEARING AND GRUBBING.pdf PDF
4-Doc 00 43 13 - BID BOND.pdf PDF
55-Sec 01 70 00 - CONTRACT CLOSEOUT.pdf PDF
5-Doc 00 45 19 - NON-COLLUSION AFFIDAVIT.pdf PDF
46-Sec 32 12 00 - BITUMINOUS CONCRETE PAVING.pdf PDF
18-Doc 00 65 19.19 - CONSENT OF SURETY.pdf PDF
Show all 50

Heritage Hills WWTP Discharge Interconnection, Contract No. 6715-11 has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

BITUMINOUS MATERIAL PRICE ADJUSTMENT

01 26 73-1

SECTION 01 26 73

PART 1 GENERAL

1.01 DESCRIPTION OF WORK

A. These requirements provide for a price adjustment, in the form of a payment to Contractor or a rebate to Owner, for fluctuations in the cost of asphalt cement used in the bituminous materials placed as part of the construction work specified in PennDOT Publication 408, Section 110.04. Applicable contract items include any bituminous materials specified in Section 110.04 of Publication 408.

B. These price adjustment provisions apply only to projects where more than 100 tons of asphalt cement, including asphalt cement residue contained in emulsions or cut backs, will be used in the bituminous materials specified or indicated for placement. The Pennsylvania Department of Transportation posts monthly index prices for asphalt cement (PG 64S-22) using price data obtained, on the last Wednesday of the preceding month, from a survey of producers who do business in Pennsylvania. Data provided by producers serving the eastern portion of the state is averaged to compute the index price for Zone 1 (Districts 3-0, 4-0, 5-0, 6-0, and 8-0).

PART 2 - PRODUCTS

Not Used

PART 3 - EXECUTION

3.01 PRICE ADJUSTMENT CRITERIA AND CONDITIONS

A. No Price Adjustment

1. When the ratio IP/IB falls within the range of 0.90 to 1.10, no price adjustment will be made for any bituminous material placed during the relevant month.

B. Price Rebate

1. When the ratio IP/IB is calculated to be less than 0.90, Owner will receive an automatic price rebate determined according to the following formula:

P.R. = (0.90 – IP/IB) (Q) (IB) where:

P.R. = Price Rebate IP = Price Index for the last Wednesday of the month preceding the month in which the material is placed (One-Month Price Adjustment Period) IB = Price Index in the Proposal Q = Quantity tons of Bitumen in Mixture placed

C. Price Increase

1. When the ratio IP/IB is calculated to be greater than 1.10, Contractor will receive a price increase determined according to the following formula:

P.I. = (IP/IB – 1.10) (Q) (IB) where:

P.I. = Price Increase IP = Price Index for the last Wednesday of the month preceding the month in which the material is placed (One-Month Price Adjustment Period) IB = Price Index in the Proposal Q = Quantity tons of Bitumen in Mixture placed

D. Equivalent Tonnage.

1. Square Yard Basis. For bituminous mixtures placed on a square yard basis, the equivalent tonnage is computed as follows:

Bituminous Mixture Tonnage Placed = (0.000375) (A) (D) (d) where:

A = Surface Area (square yards) D = Design Depth (inches) d = Design Density* (pounds per cubic feet)

01 26 73-2

• The Design Density will be obtained from the approved JMF (Form TR-448A, Job Mix Formula Report) for the bituminous mixture placed. The Design Density will be the “Lab Density” listed on the applicable JMF. The Design Density (i.e. Lab Density) obtained from Form TR-448A will be converted to the proper units by multiplying by the density of water,

62.4 pounds per cubic foot.

• ** The Percent Bitumen will be obtained from the approved JMF (Form TR-448A, Job Mix Formula Report) for the bituminous mixture placed. The Percent Bitumen will be the “Virgin AC%” listed on the applicable JMF.

2. Gallons per Square Yard Basis. For bituminous material placed on a gallons per square yard basis according to specification, and residue content according to Bulletin 25, the equivalent tonnage is computed as follows:

Bitumen Tonnage = (0.004164) (A) (a) (g) where:

A = Surface Area (square yards) a = Actual Residue Application Rate (gallons per square yard) g = Specific Gravity of Bituminous Material

3. Gallon Basis. For bituminous material placed on a gallon basis, the equivalent tonnage is computed as follows:

Bitumen Tonnage = (0.004164) (g) (p) (No. of gallons) where:

g = Specific Gravity of Bituminous Material p = % Asphalt in Emulsion

E. Expiration of Contract Time.

1. If bituminous materials or mixtures are placed after expiration of contract time and liquidated damages are chargeable, the value for IP used to compute the price adjustment will be either the price index at the time of actual placement or the price index at the time contract time expired, whichever is less.

F. Approval.

1. Should the price index at time of placement, IP, indicate an increase of 50% or more over the price index in the proposal, IB, do not furnish bituminous material for the project without prior written approval.

G. Payment/Rebate.

1. The price adjustment will be paid, or rebated, upon approval of a work order to be prepared after completion of all work. Cumulative price adjustments amounting to less than $500 will be disregarded. Upon written request by Contractor, partial payments may be made, before total completion, when the unpaid accrued price increase exceeds $10,000 or once every 12 months.

H. Inspection of Records.

1. Owner reserves the right to inspect the records of Contractor and its subcontractors and material suppliers to ascertain actual pricing and cost information for the asphalt cement used in the bituminous materials incorporated in the work.

I. Extra Work.

1. If applicable items of work, as specified herein, are added to the contract as extra work, no price adjustment will be made for fluctuations in the cost of asphalt cement used in any bituminous materials placed in the performance of the extra work, unless otherwise approved.

END OF SECTION