36C77622B0035 0002.pdf

PDF 123 KB Posted

Attached to
Y1AZ--EHRM Infrastructure Upgrades Construction - St. Cloud Federal contract opportunity
Solicitation number
36C77622B0035
Issued by
Department of Veterans Affairs Technology Acquisition Center Austin

About this file

This federal contract modification amends solicitation 36C77622B0035 to provide responses to technical questions, updated specifications and drawings, and addendum information. The contractor shall furnish all labor, materials, tools and equipment for infrastructure improvements including electrical, bonding, UPS, building management system interfaces, access security, HVAC assessments, expansions and renovations, data center/server room upgrades, fiber infrastructure backbone upgrades, and hazardous materials abatement at the St. Cloud Veterans Affairs Health Care System. All work must be completed according to the amended specifications and contract drawings. The Department of Veterans Affairs Technology Acquisition Center Austin is the contracting agency.

View the file

Other files for this federal contract opportunity

Other files attached to Y1AZ--EHRM Infrastructure Upgrades Construction - St. Cloud, newest first.
File Type Posted
Atch 41 - Construction Wage Rates - Stearns 7-29-22.pdf PDF
Technical Questions - LATE - St. Cloud 8-10-22.pdf PDF
01-M204 - ROOF REMODEL -MECHANICAL.pdf PDF
Atch 3 - Specifications Volume 3 - Asbestos addendum.pdf PDF
Atch 4 - General 1 of 2 addendum.pdf PDF
Atch 6 - BLDG 1 - 1 of 2 addendum.pdf PDF
Atch 8 - BLDG 2 addendum.pdf PDF
Atch 9 - BLDG 3 addendum.pdf PDF
Atch 12 - BLDG 6 addendum.pdf PDF
Atch 13 - BLDG 7 and 13 addendum.pdf PDF
Atch 27 - BLDG 96 addendum.pdf PDF
Atch 30 - BLDG 111 addendum.pdf PDF
Atch 31 - BLDG 112 addendum.pdf PDF
Specifications Addendum Information.pdf PDF
Drawings Addendum Information.pdf PDF
Atch 1 - Specifications Volume 1 addendum.pdf PDF
Atch 11 - BLDG 5 addendum.pdf PDF
Atch 17 - BLDG 11 addendum.pdf PDF
Atch 18 - BLDG 14 addendum.pdf PDF
Atch 28 - BLDG 108 addendum.pdf PDF
Atch 33 - BLDG 116 addendum.pdf PDF
Site Visit Sign-in Sheets - 6-28-22 - 6-30-22.pdf PDF
36C77622B0035 - 6-9-22.pdf PDF
Atch 6 - BLDG 1 - 1 of 2.pdf PDF
Atch 16 - BLDG 10.pdf PDF
Atch 19 - BLDG 28.pdf PDF
Atch 22 - BLDG 49.pdf PDF
Atch 35 - ADHC.pdf PDF
Atch 4 - General 1 of 2.pdf PDF
Atch 5 - General 2 of 2.pdf PDF
Atch 8 - BLDG 2.pdf PDF
Atch 23 - BLDG 50.pdf PDF
Atch 24 - BLDG 51.pdf PDF
Atch 27 - BLDG 96.pdf PDF
Atch 31 - BLDG 112.pdf PDF
Atch 10 - BLDG 4.pdf PDF
Atch 34 - BLDG 118.pdf PDF
Atch 1 - Specifications Volume 1.pdf PDF
Atch 7 - BLDG 1 - 2 of 2.pdf PDF
Atch 12 - BLDG 6.pdf PDF
Atch 15 - BLDG 9.pdf PDF
Atch 18 - BLDG 14.pdf PDF
Atch 21 - BLDG 48.pdf PDF
Atch 25 - BLDG 54 and 69.pdf PDF
Atch 26 - BLDG 95 and 88.pdf PDF
Atch 28 - BLDG 108.pdf PDF
Atch 30 - BLDG 111.pdf PDF
Atch 32 - BLDG 115.pdf PDF
Atch 36 - Parking Structure.pdf PDF
Atch 40 - Limitations on Subcontracting - Construction.docx DOCX document
Show all 50

Y1AZ--EHRM Infrastructure Upgrades Construction - St. Cloud has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

5. PROJECT NUMBER (if applicable)

CODE 7. ADMINISTERED BY

2. AMENDMENT/MODIFICATION NUMBER

CODE

6. ISSUED BY

8. NAME AND ADDRESS OF CONTRACTOR

4. REQUISITION/PURCHASE REQ. NUMBER 3. EFFECTIVE DATE

9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED

PAGE OF PAGES

10A. MODIFICATION OF CONTRACT/ORDER NUMBER

10B. DATED

BPA NO. 1. CONTRACT ID CODE

FACILITY CODE CODE

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers

E. IMPORTANT:

is extended,

(a) By completing Items 8 and 15, and returning __________ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY is not extended.

12. ACCOUNTING AND APPROPRIATION DATA

(REV. 11/2016)

is required to sign this document and return ___________ copies to the issuing office. is not, A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER NO. IN ITEM 10A.

15C. DATE SIGNED

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER

Contractor

16C. DATE SIGNED

14. DESCRIPTION OF AMENDMENT/MODIFICATION

16B. UNITED STATES OF AMERICA

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER 16A. NAME AND TITLE OF CONTRACTING OFFICER

15B. CONTRACTOR/OFFEROR

STANDARD FORM 30 PREVIOUS EDITION NOT USABLE

Prescribed by GSA - FAR (48 CFR) 53.243

(Type or print) (Type or print)

(Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

(Number, street, county, State and ZIP Code)

(If other than Item 6)

(Specify type of modification and authority)

(such as changes in paying office, appropriation date, etc.)

(If required)

(SEE ITEM 11)

(SEE ITEM 13)

(X)

CHECK

ONE

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

(Signature of person authorized to sign) (Signature of Contracting Officer)

1 3

0002 07-28-2022

656-21-235

36C776

Thomas Council Department of Veterans Affairs Program Contracting Activity Central 6100 Oak Tree Blvd, Suite 490 Independence OH 44131

00076

Department of Veterans Affairs Program Contracting Activity Central 6100 Oak Tree Blvd, Suite 490 Independence OH 44131

To all Offerors/Bidders

36C77622B0035

07-28-2022

X

X X

N/A

X 1 (ONE)

The purpose of this amendment is to provide the following:

1) Responses to Technical Questions with supporting documentation.

2) Addendum information concerning specifications and drawings. Please be advised that solicitation attachments 1 - 36 have been updated. These updated attachments, which have been posted with this amendment, are now the official specifications and drawings of record concerning this solicitation and will be incorporated into any contractual award.

Donald A. Marsh III Contracting Officer

PCAC15L3-1697

See attached document: Technical Questions - FINAL - St. Cloud 7-28-22.

See attached document: Specifications Addendum Information.

See attached document: Drawings Addendum Information.

See attached document: Atch 1 - Specifications Volume 1 addendum.

See attached document: Atch 2 - Specifications Volume 2 addendum.

See attached document: Atch 3 - Specifications Volume 3 - Asbestos addendum.

See attached document: Atch 4 - General 1 of 2 addendum.

See attached document: Atch 5 - General 2 of 2 addendum.

See attached document: Atch 6 - BLDG 1 - 1 of 2 addendum.

See attached document: Atch 7 - BLDG 1 - 2 of 2 addendum.

See attached document: Atch 8 - BLDG 2 addendum.

See attached document: Atch 9 - BLDG 3 addendum.

See attached document: Atch 10 - BLDG 4 addendum.

See attached document: Atch 11 - BLDG 5 addendum.

See attached document: Atch 12 - BLDG 6 addendum.

See attached document: Atch 13 - BLDG 7 and 13 addendum.

See attached document: Atch 14 - BLDG 8 addendum.

See attached document: Atch 15 - BLDG 9 addendum.

See attached document: Atch 16 - BLDG 10 addendum.

See attached document: Atch 17 - BLDG 11 addendum.

See attached document: Atch 18 - BLDG 14 addendum.

See attached document: Atch 19 - BLDG 28 addendum.

See attached document: Atch 20 - BLDG 29 addendum.

See attached document: Atch 21 - BLDG 48 addendum.

See attached document: Atch 22 - BLDG 49 addendum.

See attached document: Atch 23 - BLDG 50 addendum.

See attached document: Atch 24 - BLDG 51 addendum.

See attached document: Atch 25 - BLDG 54 and 69 addendum.

See attached document: Atch 26 - BLDG 95 and 88 addendum.

See attached document: Atch 27 - BLDG 96 addendum.

See attached document: Atch 28 - BLDG 108 addendum.

See attached document: Atch 29 - BLDG 109 and 57 addendum.

See attached document: Atch 30 - BLDG 111 addendum.

See attached document: Atch 31 - BLDG 112 addendum.

See attached document: Atch 32 - BLDG 115 addendum.

See attached document: Atch 33 - BLDG 116 addendum.

See attached document: Atch 34 - BLDG 118 addendum.

See attached document: Atch 35 - ADHC addendum.

See attached document: Atch 36 - Parking Structure addendum.

See attached document: OIT Design Requirements - St. Cloud - Backbone Cabling.

End of Document

File details come from the government source that posted it. Updated .