This document provides details for a federal construction contract opportunity to renovate a warehouse for pandemic preparedness. The scope of work includes raising approximately 6,000 square feet of roof and adding 3,800 square feet of mezzanine storage space. It also involves interior renovations, new HVAC and electrical systems, and controlled substance storage upgrades. The pre-solicitation notice estimates the project value between $2-5 million. As a Service-Disabled Veteran-Owned Small Business set-aside, the solicitation will only be open to SDVOSBs. The solicitation and drawings are expected to be available on April 2nd, with proposals due on May 7th and award without discussions using LPTA. The completion period is up to 330 days from NTP. Interested offerors should attend the scheduled site visit and monitor amendments on SAM.
View the file
Other files
Show all 37
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SECTION 31 62 00
DRIVEN OR DRILLED MICROPILES (2021.04.28 ADD_001)
PART 1 GENERAL
1.1 DESCRIPTION
A. This section specifies materials and installation required for the construction of impact driven foundation high capacity drilled and grouted micropiles. (2021.04.28 ADD_001)
1.2 RELATED WORK
A. Materials testing and inspection during construction: Section 01 45 29, TESTING LABORATORY SERVICES.
B. Concrete, including materials, reinforcing steel, and mixes: Section
03 30 00, CAST-IN-PLACE CONCRETE.
C. Steel: Section 05 12 00, STRUCTURAL STEEL FRAMING.
D. Subsurface investigation: Section 01 00 00, GENERAL REQUIREMENTS, Article, PHYSICAL DATA.
1.3 CONTRACT BASIS
A. Contract price for piles will be based upon length of piles shown and number of pile load tests indicated in the Contract Documents. Length of piles will be measured from tip to point of cutoff.
1. Adjustment of contract price shall be based upon total length of piles placed and not on length of individual piles placed. When total length of completed piles is greater or less than length shown, contract price adjustment will be made in accordance with Articles, DIFFERING SITE
CONDITIONS, CHANGES and CHANGES-SUPPLEMENT of the GENERAL CONDITIONS as applicable.
2. No payment will be made for withdrawn, broken or rejected piles, piles out of tolerance, or for portion of pile remaining above cutoff point.
3. Contract price and time will be adjusted in accordance with Articles, DIFFERING SITE CONDITIONS, CHANGES and CHANGES-SUPPLEMENT of the
GENERAL CONDITIONS as applicable, when artificial materials that are not shown are encountered.
1.4 TOLERANCES
A. Install piling with a maximum variation of 75 mm (3 inches) of center of any pile from location shown. Piles shall not be out of plumb more than
2 percent. Top of any pile at elevation of cutoff shall be within 25 mm
(inches) of the planar location indicated. Manipulation of piles to atast Text Box 31 62 00 - 1 atast Text Box 10-01-12 rev 21-05-07(Amendment #3)
Renovate Warehouse for Pandemic Preparedness
VA Project No. 589A4-20-158
10-01-12
31 62 00 - 2 force them into position will not be permitted. Piles shall be checked for heave, and those found to have heaved shall be redriven replaced to the required tip elevation. Piles damaged or driven outside the above tolerances shall be replaced, or additional piles driven placed at locations specified by the Contracting Officer at no expense to the
Government. (2021.04.28 ADD_001)
1.5 QUALITY ASSURANCE
A. Installer Qualifications: A firm experienced in installing piles similar in material, design, and extent indicated for this Project, whose work has resulted in a history of successful in-service performance:
1. Installer's responsibility includes providing a qualified professional engineer to prepare pile driving installation records. (2021.04.28
ADD_001)
B. Testing Agency Qualifications: An independent testing agency qualified according to ASTM C1077 and ASTM E329 for testing indicated, as documented according to ASTM E548 shall be engaged by the Contractor and approved by the COR.
C. Welding Standards: Qualify welding procedures and personnel according to
AWS D1.1.
D. Pre-installation Conference: Contractor shall conduct conference at
Project site prior to pile installation.
1.6 DELIVERY, STORAGE, AND HANDLING
A. Deliver piles to Project site in such quantities and at such times to ensure continuity of installation. Handle and store piles at Project site to prevent physical damage:
1. Protect pile coatings and touch up damage to coatings before driving installing piles. (2021.04.28 ADD_001)
1.7 PROJECT CONDITIONS
A. Protect structures, underground utilities, and other construction from damage caused by pile driving installation(2021.04.28 ADD_001).
B. Site Information: Contractor is responsible for evaluating and implementing the information provided in the geotechnical report prepared for the Project.
1.8 DESIGN MODIFICATIONS
A. Where piles are installed exceeding specified tolerances for plumb or location, the foundation design will be analyzed by the COR and if atast Text Box 10-01-12 rev 21-05-07(Amendment #3) atast rev 04-29-21 (Amendment #3)
10-01-12
31 62 00 - 3 necessary redesigned by the CORCOR. The costs for analysis, redesign, and remediation shall be responsibility of Contractor.
B. Additional piles and pile cap modifications necessitated by redesign shall be furnished and installed, at no additional cost to the Government.
1.9 SUBMITTALS
A. Submit in accordance with Section 01 33 23, SHOP DRAWINGS, PRODUCT DATA, AND SAMPLES.
B. Product Data: For each type of pile product, accessory, and paint indicated.
C. Shop Drawings: Show fabrication and installation details for piles, including driving installation points, splices, field-cut holes, and pile caps. (2021.04.28 ADD_001)
1. Indicate welds by standard AWS symbols, distinguishing between shop and field welds, and show size, length, and type of each weld.
2. Include arrangement of static pile reaction frame, test and anchor piles, equipment, and instrumentation. Submit structural analysis data signed and sealed by the qualified professional engineer responsible for their preparation.
3. Include design mixes, qualification data, material test reports, material certifications, pile driving installation equipment information. (2021.04.28 ADD_001)
D. Reports: Wave equation analysis report, driving placement of each pile, pile location plumbness, welding, and static pile test reports.
(2021.04.28 ADD_001)
E. Hammer: Include type, make, maximum rated energy, and rated energy per blow of hammer; weight of striking part of hammer; weight of drive cap;
details, type, and structural properties of hammer cushion; and details of follower and jetting equipment.
F. Certificates: Preservative treatment of timber piles. For each type of preservative-treated timber product include certification by treating plant stating type of preservative solution and pressure process used, net amount of preservative retained, and compliance with applicable standards. For waterborne-treated products include statement that moisture content of treated materials was reduced to levels indicated before shipment to Project site.
atast
10-01-12
31 62 00 - 4
G. Warranty of chemical treatment manufacturer for each type of treatment.
(2021.04.28 ADD_001)
E. Welding certificates.
F. Design Mixes: For each concrete mix. Include revised mix proportions when characteristics of materials, Project conditions, weather, test results, or other circumstances warrant adjustments.
G. Steel Reinforcement Shop Drawings: Comply with ACI 315. Furnish shop drawings prepared by a Professional Engineer licensed in the State of the project.
H. Pile Load Testing:
1. A schedule and sequencing plan for pile testing and installation.
2. Pile Load Test Work Plan:
a. At least two weeks before commencing pile load testing work, the
Contractor shall submit a pile load test work plan describing the equipment, apparatus, procedures, and schedule for testing ACP’s in accordance with ASTM D1143 and as specified herein, to verify the design pile capacity. The work plan shall also include the proposed instrumentation of the test pile indicating depth, location, and details of the pile.
b. As part of the Pile Load Test Work Plan, submit shop drawings and other information describing the loading and test monitoring arrangement for pile load tests, including the following:
1) Structural design of the test load support/reaction frame.
2) Details of equipment and apparatus to be used for the monitoring load and pile movements.
3) Data on testing and measuring equipment including required jack, load cell and/or gauge calibrations.
4) Sample field data recording sheets or examples of automated data acquisition records proposed for recording load test data.
c. A minimum of one test pile shall be loaded to twice the required design load. The load test may be performed on a pile that is to remain, or it may be performed on a sacrificial pile at the
Contractor’s option. (2021.04.28 ADD_001)
I. Record drawings at Project closeout according to Division 01 Section
"Closeout Procedures."
atast
10-01-12
31 62 00 - 5
1.10 APPLICABLE PUBLICATIONS
A. Publications listed below form a part of this specification to extent referenced. Publications are referenced in text by the basic designation only.
B. American Society for Testing and Materials (ASTM):
A27/A27M-10.............Standard Specification for Steel Castings, Carbon, for General Application
A36/A36M-08.............Standard Specification for Carbon Structural Steel
A82/A82M-07.............Standard Specification for Steel Wire, Plain, for
Concrete Reinforcement
A148/A148M-08...........Standard Specification for Steel Castings, High
Strength, for Structural Purposes
A252-10.................Standard Specification for Welded And Seamless
Steel Pipe Piles
A416/A416M-10...........Standard Specification for Steel Strand, Uncoated
Seven-Wire for Prestressed Concrete
A496/A496M-07...........Standard Specification for Steel Wire, Deformed, for Concrete Reinforcement
A572/A572M-07...........Standard Specification for High-Strength Low-Alloy
Columbium-Vanadium Structural Steel
A588/A588M-10...........Standard Specification for High-Strength Low-Alloy
Structural Steel with 345 Mpa (50 ksi) Minimum
Yield Point to 100 mm (4 in) Thick
A615/A615M-09b..........Standard Specification for Deformed and Plain
Carbon Steel Bars for Concrete Reinforcement
A690/A690M-07...........Standard Specification for High-Strength Low-Alloy
Nickel, Copper, Phosphorus Steel H-Piles and
Sheet
Piling with Atmospheric Corrosion Resistance for
Use in Marine Environments
A706/A706M-09b..........Standard Specification for Low-Alloy Steel
Deformed and Plain Bars for Concrete
Reinforcement
A767/A767M-09...........Standard Specification for Zinc Coated
(Galvanized) Steel Bars for Concrete
Reinforcement
A775/A775M-07b..........Standard Specification for Epoxy Coated Steel
Reinforcing Bars atast
10-01-12
31 62 00 - 6
A884/A884M-06...........Standard Specification for Epoxy Coated Steel Wire and Welded Wire Reinforcement
A934/A934M-07...........Standard Specification for Epoxy Coated
Prefabricated Steel Reinforcing Bars
C33-C33M-11a............Standard Specification for Concrete Aggregates
C1077-11c...............Standard Practice for Agencies Testing Concrete and Concrete Aggregates for Use in Construction and Criteria for Testing Agency Evaluation
D25-99(2005)............Standard Specification for Round Timber Piles
D1143/D1143M-07el.......Standard Test Methods for Deep Foundations Under
Static Axial Compressive Load
D3689-07................Standard Test Method for Individual Piles Under
Static Axial Tensile Load
D3966-07................Standard Test Method for Piles Under Lateral Loads
D4945-08................Standard Test Method for High Strain Dynamic
Testing of Piles
E94-04(2010)............Standard Guide for Radiographic Examination
E164-08.................Standard Practice for Ultrasonic Contact
Examination of Weldments
E165-09.................Standard Test Method for Liquid Penetrant
Examination
E329-11c................Standard Specification for Agencies Engaged in
Construction Inspection, Testing, or Special
Inspection
E548-94e1...............Standard Guide for General Criteria Used for
Evaluating Laboratory Competence
E709-08.................Standard Guide for Magnetic Particle Examination
C. American Welding Society (AWS):
D1.1/D1.1M-2010.........Structural Welding Code - Steel
D. American Wood-Preservers Association (AWPA):
M4-08...................Standard for the Care of Preservative Treated Wood
Products
T1-11...................Use Category System: Processing and Treatment
Standard
U1-11...................Use Category System: User Specification for
Treated Wood
M6-96...................Brands Used on Forest Products
E..American Concrete Institute (ACI):
atast
10-01-12
31 62 00 - 7
315-99..................Details and Detailing of Concrete Reinforcement
F..Society for Protective Coatings (SSPC):
Paint 16-82(2004).......Coal Tar Epoxy-Polyamide Black (or Dark Red) Paint
PART 2 - PRODUCTS
2.1 PILES
A. General: Piles shall be end-bearing piles with capacity as noted on
Drawings. Piles shall be steel micropiles. Submit details of type proposed for installation, showing cross-sections, end closures, and details of connections for approval by COR before delivery of any material to project site.
B. Steel Micropiles
1. Pipe Steel: ASTM A252, seamless or welded, as required to achieve capacity noted on Drawings.
2. Piles may be installed either open-ended or with ends closed. Ends shall be closed with forged or cast steel conical point continuously welded to pipe. Minimum wall thickness of open-ended pipe shall be 6 mm
(0.25 inch) for diameter less than 350 mm (14 inches) and 10 mm (0.375 inch) for diameters greater than 350 mm (14 inches). Minimum wall thickness of concrete filled pipe piles installed with closed ends shall be 2.5 mm (0.10 inch). Minimum outside diameter shall be 250 mm
(10 inches) for open-ended pipe piles and 200 mm (8 inches) for pipe piles installed with closed ends.
a. Allowable design unit stresses: 0.33 f'c average cross-sectional area of pile. For pipe sections 6 mm (0.25 inch) or more in thickness, 35 percent of minimum specified yield strength is permitted on full steel area. Minimum specified yield strength shall not be assumed greater than 250 MPa (36,000 psi) for computation purposes.
b. Driving Installation (2021.04.28 ADD_001): Piles shall be driven or drilled to required penetration without distortion, damage or not exceeding a driving stress of 0.9 minimum specified yield strength.
Tip reinforcement and steel caps shall be provided as required.
Establish and maintain axial alignment of leads and pile before and during driving installation.
1) Piles may be driven placed in single length or may be spliced.
with continuous butt weld. In sections below upper splice, splices shall be spaced at not less than 6000 mm (20 feet).
atast
10-01-12
31 62 00 - 8
Shell, splices and end closures shall be watertight. Driving surfaces of shell shall be square cut. (2021.04.28 ADD_001)
2) Do not drive place pile within 3000 mm (10 feet) in granular soil and 6000 mm (20 feet) in cohesive soil of any pile in which concrete has been placed until 24 hours after concrete placement.
(2021.04.28 ADD_001)
3. Filling Casings Pile caps: Do not place concrete in any pile in a group until entire group is driven installed (2021.04.28 ADD_001). Pile interior shall be cleaned and approved by COR before placing concrete.
Place concrete using funnel or hopper. Place no concrete through water, except with written approval of the COR. Proportions of concrete so placed and method of placing shall be approved by the COR.
4. Protection: Where indicated, the steel piles shall be provided with coatings or concrete encasement.
PART 3 - EXECUTION
3.1 GENERAL
A. It shall be Contractor's responsibility to furnish a specified type of pile and casing of gauges necessary to install a satisfactory pile foundation. Conversion from one type of pile to another, or from lighter to heavier casing gauges shall be at no additional cost to the
Government.
B. Survey: Registered Professional Land Surveyor or Registered Civil
Engineer, specified in Section 01 00 00, GENERAL REQUIREMENTS, shall establish lines and levels and stake pile locations.
1. After all piles are driven and installed(2021.04.28 ADD_001) , Registered Professional Land Surveyor or Registered Civil Engineer shall make field survey of completed piling work. Submit drawing to
COR showing actual pile locations with respect to planned pile locations and indicating plumbness of piles.
C. Reports: Submit a report in quadruplicate to COR, for each pile, detailing diameter or cross section, length, make and model of hammer, driving time, blows per minute, number of blows per 300 mm (blows per foot) in last 1500 mm (5 feet) of penetration, number of blows for each
25 mm (blows for each inch) during final 150 mm (6 inches) of penetration, (2021.04.28 atast
10-01-12
31 62 00 - 9
ADD_001)and any other pertinent information.
D. Welding (Shop and Field): Qualification of welding procedures, welders, and operators shall comply with requirements of AWS D1.1. Contractor shall keep records of test results of welding procedures and submit copies of each qualified welding operator to COR for approval before starting welding.
3.2 DRIVING INSTALLATION EQUIPMENT (2021.04.28 ADD_001)
A. Pile Hammer Equipment: Air-, steam-, or diesel-powered type capable of developing ultimate pile capacity indicated considering length and weight of pile and character of subsurface material anticipated.
B. Hammer Cushions and Driving Caps: Between hammer and top of pile, provide hammer cushion and steel driving cap recommended by hammer manufacturer for type of pile.
C. Leads: Use fixed or rigid-type pile-driver leads that will hold full length of pile firmly in position and in axial alignment with hammer.
Extend leads to within 600 mm (24 inches) of elevation at which pile enters ground. (2021.04.28 ADD_001)
3.3 STATIC PILE TESTS
A. General: Static pile tests will be used to verify design pile lengths and to confirm design load capacity of piles. Refer to Construction Document
General Notes for additional information. (2021.04.28 ADD_001)
1. Furnish test piles 1500 mm (60 inches) longer than production piles.
2. Actual length of piles will be based on results of static pile tests. B. Pile Tests: Arrange and perform the following pile tests:
1. Axial Compressive Static Load Test: ASTM D1143.
2. Axial Tension Static Load Test: ASTM D3689.
3. Lateral Load Test: ASTM D3966.
C. Equip each test pile with two telltale rods, according to ASTM D1143, for measuring deformation during load test.
D. Drive test piles at locations indicated to a tip elevation below final cutoff elevation equal to pile length specified as basis of bid, or to refusal, whichever occurs first. Piles will be considered as driven to refusal when 5 blows of hammer are required to produce a total penetration of 6 mm (0.25 inch) or less:
1. Allow a minimum of seven days to elapse after driving test piles before atast
10-01-12
31 62 00 - 10 starting pile testing.
B. Provide pile reaction frame, anchor piles, equipment, and instrumentation with sufficient reaction capacity to perform tests. Notify COR at least
48 hours in advance of performing tests. On completion of testing, remove testing structure, anchor piles, equipment, and instrumentation:
1. Number of Test Piles: Two single piles, or as directed by COR.
F. Driving Test Piles: Use test piles identical to those required for the
Project and drive with appropriate pile-driving equipment operating at rated driving energy to be used in driving permanent piles. (2021.04.28
ADD_001)
C. Test Pile Driving Records: Prepare driving records for each test pile, compiled and attested to by a qualified professional engineer. Include same data as required for driving records of permanent piles.
D. Test piles that comply with requirements, including location tolerances, may be used at production pile locations. (2021.04.28 ADD_001)
3.4 ALLOWABLE LOAD ON PILES
A. Maximum axial capacity of vertical pile shall be allowable axial load applied concentrically in direction of its axis. Structural strength of piles shall be limited by allowable unit stresses specified. Refer to drawings for required load. (2021.04.28 ADD_001)
B. Maximum allowable capacity of piles shall be established by driving control test piles (2021.04.28 ADD_001) in locations shown and conducting load tests.
1. No foundation piles shall be driven until test reports of test piles, as required by ASTM D1143 are received and written approval is given by
COR.
2. Load tests shall be conducted as specified in ASTM D1143 , standard loading procedure. The load test of a single pile shall be to twice the design load.
C. Approval Criteria: Allowable design capacity of test piles shall be one-half of the load that results in the lesser of the following two values:
1. Gross settlement of not more than 25 mm (1 inch), provided that loadsettlement curve shows no sign of failure.
2. Settlement not less than the value of ‘s’, where metric in-lb atast
10-01-12
31 62 00 - 11 s = (4 + 8d)/1000 +∆
(meters) s = 0.15+ d/10 +∆
(feet) where d = diameter of piles
(meters) where d = diameter of piles
(feet)
∆ = elastic deformation of the pile (meters) as determined by test pile for that area of foundation, when driven, using equivalent make and model of pile hammer and same operation of hammer, with regard to speed, height or fall, stroke, and pressure.
∆ = elastic deformation of the pile (feet) as determined by test pile for that area of foundation, when driven, using equivalent make and model of pile hammer and same operation of hammer, with regard to speed, height or fall, stroke, and pressure.
C. Additional load tests an increase in production pile length or number, and/or modifications to the pile cap may be required if the test pile fails the load test.
D. Additional costs of load test to evaluate installation discrepancies is the responsibility of the Contractor.
E. COR may require group load tests up to 150 200 (2021.04.28
ADD_001)percent of maximum allowable capacity of any pile group(2021.04.28 ADD_001). If tests disclose that bearing capacity of group is lower than required, retesting shall be at the expense of the
Owner. Retesting performed to evaluate installation discrepancies is the responsibility of the
Contractor.
G. Pile Capacity During Driving: Capacity of single piles not in clusters shall be not less than the required capacity listed on the Drawings. The pile capacity during installation shall be determined by the following formulas, modified according to the data obtained by the load test:
1. For piles with capacities of 36 metric tons (40 tons) or less.
metric in-lb
For Single-Acting R = 166.7 WH
Hammers: S + 2.5 P/W
R = 2WH
S + 0.1 P/W
For Double-Acting R = 166.7 E
Hammers: S + 2.5 P/W
R = 2E
S + 0.1 P/W atast
10-01-12
31 62 00 - 12
Where: R is the allowable static pile load in Newtons (pounds).
W is the weight of the striking part of the hammer in Newtons
(pounds).
H is the effective height of fall in meters (feet).
E is the actual energy delivered by the hammer per blow in
Newton meters (foot pounds).
S is the average net penetration in mm (inches) per blow for last five blows after the pile has been driven to a depth where successive blows have produced approximately equal net penetration for a minimum distance of last 75 mm (3 feet).
P is the weight of the pile in pounds. If P is less than W, P/W shall be taken as unity.
2. Dynamic pile stresses should not exceed stresses mentioned above.
(2021.04.28 ADD_001)
3.5 INSTALLATION
A. Order of Driving Installation: Install piles in such an order and with sufficient spacing to insure against distortion or injury to piles already in place.
1. Hammer capacity shall be not less than 20338 Newton meters (15000 foot pounds) energy per blow.
2. Before starting to drive piles, hammer data, including cap-block arrangement, weight and length of stroke of striking parts of hammer, number of operating blows per minute, piston area, and effective piston pressure to be maintained shall be submitted to COR for approval.
3. Do not start pile-driving operations until earthwork fills have been completed or excavations have reached an elevation of 150 to 300 mm (6 to 12 inches) above bottom of footing or pile cap.
4. Provide a proper anvil and cushion to prevent pile butt damage.
5. Cap or cushion block shall consist of one solid block of hardwood of proper shape and dimensions to fit hammer. Grain of the block shall be parallel to the axis of pile. If laminated materials are used, strength of such materials shall be equal to or greater than hardwood.
Continuous or frequent introduction of materials to cushion the hammer blows will not be permitted.
6. Do not use wood chips, small blocks, shavings, or similar materials to cushion hammer blow.
7. No piles shall be driven through overburden without prior approval of
COR.
atast
10-01-12
31 62 00 - 13
8. Drilling, spudding, or jetting may be used only when approved by COR and shall be performed at no additional cost to the Government.
Methods employed shall be subject to COR's approval. Final 1500 mm (5 feet) of pile penetration shall be obtained with hammer alone.
9. Predrilling: Provide pre-excavated holes for piles driven within 4500 mm (15 feet) of existing structures or underground utilities, to depths indicated. Drill holes with a diameter less than the largest crosssection dimension of pile.
a. Firmly seat pile in predrilled hole by driving with reduced energy before starting final driving.
10. Heaved Piles: Redrive heaved piles to tip elevation at least as deep as original tip elevation with a driving resistance at least as great as original driving resistance. (2021.04.28 ADD_001)
B. Using data obtained from control test piles, drive install foundation piles to bearing stratum and driving resistance established by test piles. If allowable capacity is not obtained in bearing stratum, drive install piles deeper until required driving resistance is obtained.
Penetration of all piles in a group should not vary more than 3000 mm (10 feet) unless approved by COR. (2021.04.28 ADD_001)
C. Make no penetration measurements for purpose of determining resistance to driving when pile heads are damaged to extent that may effect measured penetration nor immediately after a fresh cushion block has been inserted under striking part of hammer. Make measurements with minimum interruption of driving. (2021.04.28 ADD_001)
C. If, during driving installation of any pile, previously driven placed piles show signs of heaving, redrive reinstall disturbed piles to their original driving resistance, at no additional cost to the Government.
(2021.04.28 ADD_001)
D. Remove soil that heaves during or after driving installation to maintain grades. Do not place concrete in empty casing until all driving and redriving has been completed within radius in which driving of adjacent pile casings may result in heaving.
F. Clean out steel pipe pile by removing soil and debris from inside pile before placing steel reinforcement.
G. Where the protective shell of treated wood is impaired at a point which after installation will be not less than 3 m (10 feet) below the ground, atast
10-01-12
31 62 00 - 14 make repairs in accordance with AWPA M4 unless the pile is damaged to such extent that it is rejected. (2021.04.28 ADD_001)
E. Withdraw damaged or defective piles and piles that exceed driving tolerances and install new piles within driving tolerances. Fill holes left by withdrawn piles as directed by COR. (2021.04.28 ADD_001)
1. Rejected piles may be abandoned and cut off as directed by COR.
2. Leave rejected piles in place and install new piles in locations as directed by COR.
3. Fill holes left by withdrawn piles that will not be filled by new piles using cohesionless soil material such as gravel, broken stone, and gravel-sand mixtures. Place and compact in lifts not exceeding 1800 mm
(72 inches).
H. Cut off tops of piles by an approved method square with pile axis and at required elevations.
3.6 FIELD QUALITY CONTROL
A. Testing Agency: Contractor will engage a qualified independent testing agency, approved by the COR, to perform field quality-control testing.
B. High-strain dynamic monitoring shall be performed and reported according to ASTM D4945 during initial driving and during restriking on 12 percent of single piles installation. (2021.04.28 ADD_001)
C. Low-strain integrity measurement shall be performed and reported for each pile.
D. Weld Testing: In addition to visual inspection, welds shall be tested and inspected according to AWS D1.1 and the inspection procedures listed below, at testing agency's option. Correct deficiencies in Work that test reports and inspections indicate does not comply with the Contract
Documents.
1. Liquid Penetrant Inspection: ASTM E165.
2. Magnetic Particle Inspection: ASTM E709; performed on root pass and on finished weld. Cracks or zones of incomplete fusion or penetration will not be accepted.
3. Radiographic Inspection: ASTM E94, minimum quality level "2-2T."
4. Ultrasonic Inspection: ASTM E164.
3.7 DISPOSAL
A. Remove withdrawn piles and cutoff sections of piles from site and legally dispose of them off Owner’s property.
- - - E N D - - -atast