01 35 26 pgs 12-13 - Amendment 3.pdf

PDF 549 KB Posted

Attached to
Z2DA--Renovate Warehouse for Pandemic Preparedness PN: 589A4-20-158
Solicitation number
36C25521R0075
Issued by

About this file

This document provides details for a federal contract solicitation to renovate a warehouse for pandemic preparedness. The solicitation involves renovating an existing 12,500 square foot warehouse owned by the Department of Veterans Affairs to raise part of the roof and add a 3,800 square foot mezzanine. Scope of work includes interior renovations, upgrading the building envelope and HVAC system, new data cabling and electrical work. The estimated price range for completion is $2-5 million. Pursuant to applicable laws, this project will be solicited as a total small business set-aside for Service-Disabled Veteran-Owned Small Businesses. Interested offerors should monitor the System for Award Management for any amendments. The solicitation package will be available on or around April 2, 2021 with a proposal due date of May 7, 2021. An organized site visit will be scheduled. Questions must be submitted by email with the subject line as specified.

View the file

Other files

File Type Posted
AD102 Amendment 3.pdf PDF
MD101 Amendment 3.pdf PDF
M-301 Amendment 3.pdf PDF
EL101 Amendment 3.pdf PDF
EP101 Amendment 3.pdf PDF
S-501 Amendment 3.pdf PDF
AF101 Amendment 3.pdf PDF
PD101 Amendment 3.pdf PDF
M-102 Amendment 3.pdf PDF
M-101 Amendment 3.pdf PDF
AE101 Amendment 3.pdf PDF
AE401 Amendment 3.pdf PDF
M-500 Amendment 3.pdf PDF
P-101 Amendment 3.pdf PDF
S-301 Amendment 3.pdf PDF
PH101 Amendment 3.pdf PDF
AF502 Amendment 3.pdf PDF
ED101 Amendment 3.pdf PDF
11 00 00 Beam Scale Cut Sheet - Amendment 3.pdf PDF
AC102 Amendment 3.pdf PDF
31 62 00 Driven or Drilled Micropiles - Amendment 3.pdf PDF
36C25521R0075 0003.docx DOCX document
AD101 Amendment 3.pdf PDF
PH103 Amendment 3.pdf PDF
S-001 Amendment 3.pdf PDF
00 01 10 pg 4 - Amendment 3.pdf PDF
ATTENDANCE ROSTER.pdf PDF
36C25521R0075 0002.docx DOCX document
589A4-20-158 GeoTech Report.pdf PDF
36C25521R0075 0001.docx DOCX document
Drawings 589A4-20-158 VOL 3- 1 page.pdf PDF
36C25521R0075_1.docx DOCX document
Drawings -589A4-20-158 VOL 2- 2 pages.pdf PDF
Drawings-589A4-20-158 VOL 4-1 page.pdf PDF
S02-Specifications 589A4-20-158- Volume 1 -630 pages.pdf PDF
S02-Specifications 589A4-20-158 - Volume 2 Divs 21-48- 848 pages.pdf PDF
Drawings 589A4-20-158 VOL 1- 90 pages.pdf PDF
Show all 37

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Renovate Warehouse for Pandemic Preparedness

VA Project No. 589A4-20-158

07-01-20 – Rev 04-29-21 (Addendum #1)

01 35 26 -12

4. The AHA list will be reviewed periodically (at least monthly) at the

Contractor supervisory safety meeting and updated as necessary when procedures, scheduling, or hazards change.

5. Develop the activity hazard analyses using the project schedule as the basis for the activities performed. All activities listed on the project schedule will require an AHA. The AHAs will be developed by the contractor, supplier, or subcontractor and provided to the prime contractor for review and approval and then submitted to the

Facility Safety Manager or Contracting Officer Representative or

Government Designated Authority.

1.6 PRECONSTRUCTION CONFERENCE:

A. Contractor representatives who have a responsibility or significant role in implementation of the accident prevention program, as required by 29 CFR 1926.20(b)(1), on the project shall attend the preconstruction conference to gain a mutual understanding of its implementation. This includes the project superintendent, subcontractor superintendents, and any other assigned safety and health professionals.

B. Discuss the details of the submitted APP to include incorporated plans, programs, procedures and a listing of anticipated AHAs that will be developed and implemented during the performance of the contract. This list of proposed AHAs will be reviewed at the conference and an agreement will be reached between the Contractor and the Contracting

Officer's representative as to which phases will require an analysis.

In addition, establish a schedule for the preparation, submittal, review, and acceptance of AHAs to preclude project delays.

C. Deficiencies in the submitted APP will be brought to the attention of the Contractor within 14 days of submittal, and the Contractor shall revise the plan to correct deficiencies and re-submit it for acceptance. Do not begin work until there is an accepted APP.SPEC

WRITER NOTE: If the contract will involve (a) work of a long duration or hazardous nature, or (b) performance within a Government facility that on the advice of VA construction safety representatives involves hazardous operations that might endanger the safety of the public, patients and/or Government personnel or property, the SSHO and atast Text Box (Amendment #3)

Renovate Warehouse for Pandemic Preparedness

VA Project No. 589A4-20-158

07-01-20 – Rev 04-29-21 (Addendum #1)

01 35 26 -13

Superintendent and/or Quality Control Manager must be separate persons

(See Section 1.7(C) for choice).

1.7 “SITE SAFETY AND HEALTH OFFICER” (SSHO) AND “COMPETENT PERSON” (CP):

A. The Prime Contractor shall designate a minimum of one SSHO at each project site that will be identified as the SSHO to administer the

Contractor's safety program and government-accepted Accident Prevention

Plan. Each subcontractor shall designate a minimum of one CP in compliance with 29 CFR 1926.20 (b)(2) that will be identified as a CP to administer their individual safety programs.

B. Further, all specialized Competent Persons for the work crews will be supplied by the respective contractor as required by 29 CFR 1926 (i.e.

Asbestos, Electrical, Cranes, & Derricks, Demolition, Fall Protection, Fire Safety/Life Safety, Ladder, Rigging, Scaffolds, and

Trenches/Excavations).

C. These Competent Persons can have collateral duties as the subcontractor’s superintendent and/or work crew lead persons as well as fill more than one specialized CP role (i.e. Asbestos, Electrical, Cranes, & Derricks, Demolition, Fall Protection, Fire Safety/Life

Safety, Ladder, Rigging, Scaffolds, and Trenches/Excavations).

However, the SSHO has be a separate qualified individual from the Prime

Contractor’s Superintendent and/or Quality Control Manager with duties only as the SSHO

D. The SSHO or an equally-qualified Designated Representative/alternate will maintain a presence on the site during construction operations in accordance with FAR Clause 52.236-6: Superintendence by the Contractor.

CPs will maintain presence during their construction activities in accordance with above mentioned clause. A listing of the designated

SSHO and all known CPs shall be submitted prior to the start of work as part of the APP with the training documentation and/or AHA as listed in

Section 1.8 below.

E. The repeated presence of uncontrolled hazards during a contractor’s work operations will result in the designated CP as being deemed incompetent and result in the required removal of the employee in accordance with FAR Clause 52.236-5: Material and Workmanship, Paragraph (c).

atast Text Box (Amendment #3)