Addendum 01 Section 01 00 00 - 506-20-102.pdf

PDF 348 KB Posted

Attached to
Z2DA--506-20-102 Upgrade Basement Building 1W (23NR9KA30)
Solicitation number
36C25023B0027
Issued by

About this file

This is a pre-solicitation announcement for an upcoming invitation for bids from the Department of Veterans Affairs for project 506-20-102 to upgrade the basement of Building 1W at the LTC Charles S. Kettles Veterans Administration Medical Center in Ann Arbor, Michigan. The project scope includes interior renovation of approximately 14,000 square feet of existing basement and sub-basement spaces, including the electrical shop and recreation therapy office. Mechanical, electrical, and plumbing systems will be upgraded. The project also includes asbestos abatement. The estimated cost is between $1,000,000 and $5,000,000. The solicitation is anticipated to be issued on or around March 20, 2023 via SAM.gov. The contract type will be firm-fixed-price with an anticipated award within 120 days of bid opening. This acquisition is set aside for qualified service-disabled veteran owned small businesses. Offerors must be verified in VIP and registered in SAM prior to submitting offers. The eventual awardee must also have a current VETS-4212 report and SAM registration.

View the file

Other files

File Type Posted
Notice of Award Contract 36C25024C0025 Oct 31 - 506-20-102.pdf PDF
36C25023B0027 0007.pdf PDF
36C25023B0027 0006.pdf PDF
14.15_E602 - PANELBOARD SCHEDULES RFI 28 - 506-20-102.pdf PDF
1-AE114 - PHASE A5 NEW WORK PLAN RFI 29 - 506-20-102.pdf PDF
105126 Plastic Lockers for RFI 29 Answer - 506-20-102.pdf PDF
1-AE112 - PHASE A3 NEW WORK PLAN RFI 29 - 506-20-102.pdf PDF
123100 Metal Casework for RFI 29 Answer - 506-20-102.pdf PDF
000110 TOC for RFI 29 Answer - 506-20-102.pdf PDF
36C25023B0027 0005.pdf PDF
14.03_1-EP101 - BASEMENT POWER PLAN - NEW WORK - RFI 28 - 506-20-102.pdf PDF
36C25023B0027 0004.pdf PDF
S04 - Pre-Bid 2nd Site Visit Agenda - 506-20-102.pdf PDF
S04 - Pre Bid 2nd Site Visit Attendance Log - 506-20-102 signed.pdf PDF
BID SPECIFICATIONS 2023-0510 Update - 506-20-102.pdf PDF
36C25023B0027 0003.pdf PDF
Addendum 01 Section 11 41 21 - 506-20-102.pdf PDF
36C25023B0027 0002.pdf PDF
RFI No. 14 Drawing Q and A - 506-20-102.pdf PDF
Asbestos Assessment-07.2022 - 506-20-102.pdf PDF
Addendum 01 Section 11 73 00 - 506-20-102.pdf PDF
S04 - Pre-Bid Walk Through Attendance Sheet signed - 506-20-102.pdf PDF
36C25023B0027 0001 - 506-20-102.pdf PDF
S04 - Pre-Bid Site Visit Agenda signed - 506-20-102.pdf PDF
RFI Form - 506-20-102.pdf PDF
EMR Certification Form - 506-20-102.pdf PDF
Brand Name Only Justification Security Cameras - 506-20-102.pdf PDF
Brand Name Only Justification Fire Alarm System - 506-20-102.pdf PDF
Brand Name Only Justification Nuclear Storage Flooring - 506-20-102.pdf PDF
Drawings - 506-20-102.pdf PDF
Brand Name Only Justification Building Controls - 506-20-102.pdf PDF
36C25023B0027 Apr 6 - 506-20-102.pdf PDF
SPECIFICATIONS 2023-0405 - 506-20-102.pdf PDF
Wage Determination MI20230101 Feb 24 - 506-20-102.pdf PDF
36C25023B0027.docx DOCX document
Show all 35

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Ann Arbor VAMC: Project #506-20-102 Upgrade Basement Bldg. 1-West

03-01-20 i

SECTION 01 00 00

GENERAL REQUIREMENTS

TABLE OF CONTENTS

1.1 SAFETY REQUIREMENTS

1.2 GENERAL INTENTION

1.3 STATEMENT OF BID ITEM(S)

1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR

1.5 CONSTRUCTION SECURITY REQUIREMENTS

1.6 OPERATIONS AND STORAGE AREAS

1.7 ALTERATIONS

1.8 DISPOSAL AND RETENTION

1.9 RESTORATION

1.10 PHYSICAL DATA

1.11 PROFESSIONAL SURVEYING SERVICES

1.12 AS-BUILT DRAWINGS

1.13 WARRANTY MANAGEMENT

1.14 USE OF ROADWAYS

1.15 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT

1.16 TEMPORARY USE OF EXISTING ELEVATORS

1.17 TEMPORARY TOILETS

1.18 AVAILABILITY AND USE OF UTILITY SERVICES

1.19 TESTS

1.20 INSTRUCTIONS

1.21 GOVERNMENT-FURNISHED PROPERTY

1.22 RELOCATED ITEMS

Addendum 01 – 04/2023 Ann Arbor VAMC: Project #506-20-102

03-01-20

01 00 00 -1

GENERAL REQUIREMENTS

SECTION 01 00 00

GENERAL REQUIREMENTS

1.1 SAFETY REQUIREMENTS

Refer to section 01 35 26, SAFETY REQUIREMENTS for safety and infection control requirements.

1.2 GENERAL INTENTION

A. Visits to the site by Bidders shall be made only by appointment with the Medical Center

Contracting Officers Representative (COR).

B. Offices of FFE Inc. at 4445 Lake Forest Dr., Suite 600, Cincinnati, OH 45242, as

Architect-Engineers, will render certain technical services during construction. Such services shall be considered as advisory to the Government and shall not be construed as expressing or implying a contractual act of the Government without affirmations by Contracting Officer or his duly authorized representative.

C. All employees of general contractor and subcontractors shall comply with VA security management program and obtain permission of the VA police, be identified by project and employer, and restricted from unauthorized access.

1.3 STATEMENT OF BID ITEM(S)

A. ITEM I, BASE BID: Work includes general construction, renovation, and alterations as shown on the Contract Drawings. All phases of work including closeout documents shall be completed within 450 calendar days after receipt of Notice to Proceed.

B. ALTERNATE NO.1: Work includes BASE BID, except omit parts of Phase B3 and Phase B4 shown within the Contract Documents. All phases of work including closeout documents shall be completed within 405 calendar days after receipt of Notice to Proceed.

1.4 SPECIFICATIONS AND DRAWINGS FOR CONTRACTOR

A. Drawings and contract documents may be obtained from the website where the solicitation is posted. Additional copies will be at Contractor's expense.

1.5 CONSTRUCTION SECURITY REQUIREMENTS

A. Security Plan:

1. The security plan defines both physical and administrative security procedures that will remain effective for the entire duration of the project.

2. The General Contractor is responsible for assuring that all sub-contractors working on the project and their employees also comply with these regulations.

B. Security Procedures:

03-01-20

01 00 00 -2

GENERAL REQUIREMENTS

1. General Contractor’s employees shall not enter the project site without appropriate badge.

They may also be subject to inspection of their personal effects when entering or leaving the project site.

2. Before starting work the General Contractor shall give one week’s notice to the Contracting

Officer so that security arrangements can be provided for the employees. This notice is separate from any notices required for utility shutdown described later in this section.

3. No photography of VA premises is allowed without written permission of the Contracting

Officer.

4. VA reserves the right to close down or shut down the project site and order General

Contractor’s employees off the premises in the event of a national emergency. The General

Contractor shall return to the site only with the written approval of the Contracting Officer.

C. Key Control:

1. The General Contractor shall provide duplicate keys and lock combinations to the COR for the purpose of security inspections of every area of project including tool boxes and parked machines and take any emergency action.

2. The General Contractor shall turn over all permanent lock cylinders to the VA locksmith for permanent installation. See Section 08 71 00, DOOR HARDWARE and coordinate.

D. Document Control:

1. Before starting any work, the General Contractor/Sub Contractors shall submit an electronic security memorandum describing the approach to following goals and maintaining confidentiality of “sensitive information”.

2. The General Contractor is responsible for safekeeping of all drawings, project manual and other project information. This information shall be shared only with those with a specific need to accomplish the project.

3. Certain documents, sketches, videos or photographs and drawings may be marked “Law

Enforcement Sensitive” or “Sensitive Unclassified”. Secure such information in separate containers and limit the access to only those who will need it for the project. Return the information to the Contracting Officer upon request.

4. These security documents shall not be removed or transmitted from the project site without the written approval of Contracting Officer.

5. All paper waste or electronic media such as CD’s and diskettes shall be shredded and destroyed in a manner acceptable to the VA.

6. Notify Contracting Officer and Site Security Officer immediately when there is a loss or compromise of “sensitive information”.

03-01-20

01 00 00 -3

GENERAL REQUIREMENTS

7. All electronic information shall be stored in specified location following VA standards and procedures using an Engineering Document Management Software (EDMS).

a. Security, access and maintenance of all project drawings, both scanned and electronic shall be performed and tracked through the EDMS system.

b. “Sensitive information” including drawings and other documents may be attached to e-mail provided all VA encryption procedures are followed.

E. Motor Vehicle Restrictions

1. Vehicle authorization request shall be required for any vehicle entering the site and such request shall be submitted 24 hours before the date and time of access. Access shall be restricted to picking up and dropping off materials and supplies.

2. A limited number of five (5) permits shall be issued for General Contractor and its employees for parking in designated areas only.

a. Designated parking will be in the East Parking Structure as designated by the COR.

1.6 OPERATIONS AND STORAGE AREAS

A. Working space and space available for storing materials shall be as shown on the drawings

B. Workers are subject to rules of Medical Center applicable to their conduct.

C. Execute work so as to interfere as little as possible with normal functioning of Medical Center as a whole, including operations of utility services, fire protection systems and any existing equipment, and with work being done by others. Use of equipment and tools that transmit vibrations and noises through the building structure, are not permitted in buildings that are occupied, during construction, jointly by patients or medical personnel, and Contractor's personnel, except as permitted by COR where required by limited working space.

1. Do not store materials and equipment in other than assigned areas.

2. Schedule delivery of materials and equipment to immediate construction working areas within buildings in use by Department of Veterans Affairs in quantities sufficient for not more than two work days. Provide unobstructed access to Medical Center areas required to remain in operation.

3. Where access by Medical Center personnel to vacated portions of buildings is not required, storage of Contractor's materials and equipment will be permitted subject to fire and safety requirements.

D. Phasing:

The Medical Center must maintain its operation 24 hours a day 7 days a week. Therefore, any interruption in service shall be scheduled and coordinated with the COR to ensure that no lapses in operation occur. It is the CONTRACTOR'S responsibility to develop a work plan and schedule

03-01-20

01 00 00 -4

GENERAL REQUIREMENTS

detailing, at a minimum, the procedures to be employed, the equipment and materials to be used, the interim life safety measure to be used during the work, and a schedule defining the duration of the work with milestone subtasks.

To ensure such executions, Contractor shall furnish the Contracting Officer with a schedule of approximate phasing dates on which the Contractor intends to accomplish work in each specific area of site, building or portion thereof. In addition, Contractor shall notify the COR three weeks in advance of the proposed date of starting work in each specific area of site, building or portion thereof. Arrange such phasing dates to ensure accomplishment of this work in successive phases mutually agreeable to Contracting Officer and Contractor, as follows:

PHASE A1

• PREPARE THE 10TH FLOOR FOR THE NEW ELECTRICAL SHOP RELOCATION PRIOR

TO DEMOLITION OF ITEMS WITHIN THE EXISTING ELECTRICAL SHOP.

o MECHANICAL EQUIPMENT ON THE 4TH FLOOR ASSOCIATED WITH OTHER

PHASES OF WORK CAN BE PREPARED DURING THIS PHASE TO THE EXTENT

ALLOWABLE AS TO NOT INTERFERE WITH FACILITY OPERATIONS.

o INSTALLATION OF THE ACCESS PANEL INTO SHAFT-9 ON THE SECOND

FLOOR SHALL OCCUR IN THIS PHASE AND WORK COMPLETED OUTSIDE OF

NORMAL BUSINESS HOURS.

PHASE A2

• AFTER COMPLETION OF PHASE A1, DEMOLISH EXISTING ROOMS AND ASSOCIATED

ITEMS PER SHEET 28-AD111: ELECTRICAL SHOP, ELECTRICAL SHOP STORAGE

(FG02), ELECTRICAL SHOP (FG01A), RECREATIONAL THERAPY (FG10C), OFFICE

(FG10C1), OFFICE (FG10C2).

• PROVIDE NEW CORRIDOR THAT CONNECTS BUILDING 1W WITH NEW MORGUE

AND BUILDING 28. SEE PHASE A3 FOR CONNECTION.

• PROVIDE NEW ROOMS AND ASSOCIATED WORK PER SHEETS 28-AE111 AND 28-

AC141: MORGUE CORRIDORS, WAITING ROOM, VIEWING ROOM, MORGUE COOLER,

MECHANICAL ROOM, AUTOPSY OFFICE, AUTOPSY ROOM, ANTE ROOM, SINGLE

USER RESTROOM, SINGLE USER SHOWER.

• CONTRACTOR SHALL SEQUENCE THE WORK SO THAT THE NEW MORGUE COOLER

IS OPERATIONAL PRIOR TO SHUTDOWN OF THE EXISTING MORTUARY SPACES IN

BUILDING 1W. FINAL MECHANICAL CONNECTIONS ARE REQUIRED WITHIN

BUILDING 1W DURING THIS PHASE AND SHALL BE COORDINATED WITH THE VA TO

MINIMIZE DOWNTIME OF THE AUTOPSY ROOM, PRIVATE VIEWING ROOM, AND

03-01-20

01 00 00 -5

GENERAL REQUIREMENTS

MORGUE COOLER. NIGHTS AND WEEKEND WORK SHALL BE REQUIRED FOR

THESE FINAL MECHANICAL CONNECTIONS.

PHASE A3

• DEMOLISH EXISTING ROOMS AND ASSOCIATED ITEMS PER SHEET 1-AD112:

CORRIDOR (C1), STORAGE (AB39), MECHANICAL (AB42), RESTROOM (AB43),

PRIVATE VISITATION ROOM (AB45), AUTOPSY ROOM (AB46), AUTOPSY OFFICE

(AB48).

• PROVIDE NEW ROOMS AND ASSOCIATED WORK PER SHEETS 1-AE113 AND 1-AC142:

SOUTH CORRIDOR – EAST, MISC. STORAGE, NUCLEAR WASTE STORAGE, SOUTH

CORRIDOR – WEST.

PHASE A4

• REMOVE ACCOUSTIC CEILING TILE FROM GRID PRIOR TO NEW MECHANICAL

WORK: MEN'S LOCKERS (AB94), MEN'S TOILET (AB94A), EVS BREAK ROOM (AB92),

AND TOILET ROOM (AB92A).

• REPLACE CEILING TILES AT COMPLETION OF MECHANICAL WORK.

PHASE A5

• CONTRACTOR SHALL PROVIDE FOUR-MONTH'S NOTICE TO VA C.O.R. PRIOR TO

DEMOLITION OF THIS SPACE FOR PROPER DECOMMISSIONING OF THE EXISTING

RADIATION SAFETY SPACES. RELOCATE AND DEMOLISH EXISTING ROOMS AND

ASSOCIATED ITEMS PER SHEET 1-AD114: RADIATION SAFETY STORAGE (AB31),

RADIATION SAFETY STORAGE (AB33).

• PROVIDE NEW ROOMS AND ASSOCIATED WORK PER SHEETS 1-AE114, 1-AC142, 1-

AC143: SOUTH CORRIDOR -WEST, EMERGENCY PREP STORAGE, MECHANICAL,

SLIDE STORAGE.

PHASE B1

• EXISTING BIO MED (BB09B) IS TO BE CLEARED BY VA PRIOR TO START OF

PROJECT. AN OPENING IS TO BE CREATED BETWEEN EXISTING BIO MED (BB09B)

AND EXISTING MECHANICAL (AB21A) PROVIDING ACCESS TO THE NEW

MECHANICAL ROOM (AB21A) DURING DEMOLITION. ACCESS WILL NOT BE

ALLOWED THROUGH RADIATION SAFETY STORAGE.

• DEMOLISH EXISTING ROOMS AND ASSOCIATED ITEMS PER SHEET 1-AD115:

STAGING AREA (BB18), CANTEEN VENDING (BB19), MECHANICAL (AB21A).

• PROVIDE NEW ROOMS AND ASSOCIATED WORK PER SHEETS 1-AE115 AND 1-AE142:

N&FS DRY STORAGE, FREEZER, COOLER.

03-01-20

01 00 00 -6

GENERAL REQUIREMENTS

PHASE B2

• CONTENTS WITHIN EXISTING FREEZERS SHALL BE MOVED BY THE VA TO

EXISTING FREEZERS AND COOLERS ON NORTH SIDE OF DOCK CORRIDOR FOR THE

DURATION OF THIS PHASE WORK.

• DEMOLISH EXISTING ROOMS AND ASSOCIATED ITEMS PER SHEET 1-AD113: N&FS

AND BIO MED VESTIBULE (BB09), N&FS FREEZER (BB09A), N&FS STORAGE

(BB09A), BIO MED (BB09B), PATRIOT CAFÉ STORAGE (BB13), CANTEEN FREEZER

(BB13A), CANTEEN COOLER (BB13B).

• PROVIDE NEW ROOMS AND ASSOCIATED WORK PER SHEETS 1-AE116 AND 1-AC142:

CANTEEN DRY STORAGE, CANTEEN FREEZER, CANTEEN COOLER, AND CANTEEN

VENDING.

• ACCESS TO MECHANICAL AB21A SHALL NOT BE THROUGH RADIATION SAFETY

STORAGE AB31. CONTRACTOR SHALL SEQUENCE THE WORK SO THAT ALL WORK

WITHIN MECHANICAL AB21A BE ACCESSED FROM THE TEMPORARY OPENING

PROVIDED AT THE NORTH WALL OR THROUGH THE CRAWLSPACE FLOOR ACCESS

LEADING FROM STAIR 5.

PHASE B3

• DEMOLISH EXISTING ROOMS AND ASSOCIATED ITEMS PER SHEET 1-AD117: N&FS

DRY STORAGE (BB07), N&FS COOLER (BB07A), N&FS FREEZER (BB07B).

• PROVIDE NEW ROOMS AND ASSOCIATED WORK PER SHEETS 1-AE117, 1-AE143:

LINEN CACHE AND CANTEEN RETAIL. RELOCATE EXISTING CANTEEN RETAIL

INTO FUTURE LINEN CACHE AT CONCLUSION OF PHASE.

PHASE B4

• DEMOLISH EXISTING ROOMS AND ASSOCIATED ITEMS PER SHEET 1-AD118: DOCK

CORRIDOR, CORRIDOR (C4), MECHANICAL (BB03), CANTEEN RETAIL (BB05A,

BB05B) AND N&FS STORAGE (BB05C).

• PROVIDE NEW ROOMS AND ASSOCIATED WORK PER SHEETS 1-AE118 AND 1-AE143:

LINEN CACHE, CANTEEN RETAIL, BIO MED, STORAGE, NORTH CORRIDOR – WEST

AND NORTH CORRIDOR – EAST.

Scheduled work in each phase, specific area of the site, building, or portion thereof shall not commence until the VA has notified the Contractor in writing that the prior phase or phases have been completed to the VA's satisfaction, and the Contractor has provided the required advanced written notice of their intent to progress to the next phase.

03-01-20

01 00 00 -7

GENERAL REQUIREMENTS

1. Transition Between Phases: The following are instructions for obtaining approval to transition from one phase to the next. The activities described below do not replace or alter commissioning requirements.

a. Step 1: Pre-Final Inspection Request.

• To obtain the VA's confirmation that a phase is complete, the Contractor must first request a pre-final inspection by the VA, in writing. The purpose of the pre-final inspection is to ensure no significant, outstanding work remaining that may delay acceptance and occupancy by the VA. Pre-final inspection will be performed by the COR and subject-matter experts selected by the VA, as needed.

b. Step 2: Pre-Final Inspection.

• A punch list will be created by the VA to provide feedback to the

Contractor on what needs to be addressed prior to the final inspection.

This will be done to aid the Contractor in receiving approval. The punch list will be transmitted to the Contractor in writing within five business days of receipt of the Contractor's written request to the VA for the pre-final inspection.

c. Step 3: Punch List.

• The Contractor shall complete the punch list items and notify the VA of their completion and request, in writing, that the space be re-evaluated with a final inspection.

d. Step 4: Final Inspection Request.

• The final inspection will be performed by the VA project team, including the Engineer of Record. The purpose is to verify that the work is satisfactorily complete and determine whether the space is ready for occupancy and utilization by the VA.

e. Step 5: Final Inspection.

• The final inspection will be performed by the VA project team to include the A/E.

• Within 5 business days, the Contract Officer will notify the Contractor in writing that either:

• the punch list items have been completed to the VA's satisfaction and the VA determined that the work is satisfactorily complete, the space is ready for occupancy and utilization, and that the

03-01-20

01 00 00 -8

GENERAL REQUIREMENTS

Contractor may issue written notice that they are ready to proceed to the next construction phase, or;

• that the punch list items have not been completed, in which case, the Contractor shall request another pre-final inspection and the steps described above are repeated until the VA determines the work is satisfactorily complete.

f. Step 6: Transition to Next Phase.

• After the COR notifies the Contractor that the punch list items have been completed, the Contractor shall notify the COR via email the proposed date of commencing work in the next phase.

• The start date of the next phase must be a minimum of three (3) weeks after the punch list is completed.

E. Buildings No. 1W and 28 will be occupied during performance of work; but immediate areas of alterations will be vacated.

Contractor shall take all measures and provide all material necessary for protecting existing equipment and property in affected areas of construction against dust and debris, so that equipment and affected areas to be used in the Medical Centers operations will not be hindered.

Contractor shall permit access to Department of Veterans Affairs personnel and patients through other construction areas which serve as routes of access to such affected areas and equipment.

These routes whether access or egress shall be isolated from the construction area by temporary partitions and have walking surfaces, lighting etc to facilitate patient and staff access.

Coordinate alteration work in areas occupied by Department of Veterans Affairs so that Medical

Center operations will continue during the construction period.

F. When a construction area is turned over to Contractor, Contractor shall accept entire responsibility including upkeep and maintenance therefore:

1. Contractor shall maintain in operating condition existing fire protection and alarm equipment.

In connection with fire alarm equipment, Contractor shall make arrangements for pre-inspection of site with Fire Department or Company (Department of Veterans Affairs or municipal) whichever will be required to respond to an alarm from Contractor's employee or watchman.

G. Utilities Services: Maintain existing utility services for Medical Center at all times. Provide temporary facilities, labor, materials, equipment, connections, and utilities to assure uninterrupted services. Where necessary to cut existing water, steam, gases, sewer or air pipes, or conduits, wires, cables, etc. of utility services or of fire protection systems and communications systems

03-01-20

01 00 00 -9

GENERAL REQUIREMENTS

(including telephone), they shall be cut and capped at suitable places where shown; or, in absence of such indication, where directed by COR.

1. No utility service such as water, gas, steam, sewers or electricity, or fire protection systems and communications systems shall be interrupted without prior approval of COR. Electrical work shall be accomplished with all affected circuits or equipment de-energized. When an electrical outage cannot be accomplished, work on any energized circuits or equipment shall not commence without a detailed work plan, the Medical Center Director’s prior knowledge and written approval. Refer to specification Sections 26 05 11, REQUIREMENTS FOR

ELECTRICAL INSTALLATIONS, 27 05 11 REQUIREMENTS FOR COMMUNICATIONS

INSTALLATIONS and 28 05 00, COMMON WORK RESULTS FOR ELECTRONIC

SAFETY AND SECURITY for additional requirements.

2. Contractor shall submit a request to interrupt any such services to COR, in writing, 7 days n advance of proposed interruption. Request shall state reason, date, exact time of, and approximate duration of such interruption.

3. Contractor will be advised (in writing) of approval of request, or of which other date and/or time such interruption will cause least inconvenience to operations of Medical Center.

Interruption time approved by Medical Center may occur at other than Contractor's normal working hours.

4. Major interruptions of any system shall be requested, in writing, at least 15 calendar days prior to the desired time and shall be performed as directed by the COR.

5. In case of a contract construction emergency, service will be interrupted on approval of COR.

Such approval will be confirmed in writing as soon as practical.

6. Whenever it is required that a connection fee be paid to a public utility provider for new permanent service to the construction project, for such items as water, sewer, electricity, gas or steam, payment of such fee shall be the responsibility of the Government and not the

Contractor.

H. Abandoned Lines: All service lines such as wires, cables, conduits, ducts, pipes and the like, and their hangers or supports, which are to be abandoned but are not required to be entirely removed, shall be sealed, capped or plugged at the main, branch or panel they originate from. The lines shall not be capped in finished areas, but shall be removed and sealed, capped or plugged in ceilings, within furred spaces, in unfinished areas, or within walls or partitions; so that they are completely behind the finished surfaces.

I. To minimize interference of construction activities with flow of Medical Center traffic, comply with the following:

03-01-20

01 00 00 -10

GENERAL REQUIREMENTS

1. Keep roads, walks and entrances to grounds, to parking and to occupied areas of buildings clear of construction materials, debris and standing construction equipment and vehicles.

J. Coordinate the work for this contract with other construction operations as directed by COR. This includes the scheduling of traffic and the use of roadways, as specified in Article, USE OF

ROADWAYS.

1.7 ALTERATIONS

A. Survey: Before any work is started, the Contractor shall make a thorough survey with the COR of areas of buildings in which alterations occur and areas which are anticipated routes of access, and furnish a report, signed by both, to the Contracting Officer. This report shall list by rooms and spaces:

1. Existing condition and types of resilient flooring, doors, windows, walls and other surfaces not required to be altered throughout affected areas of buildings.

2. Existence and conditions of items required by drawings to be either reused or relocated, or both.

3. Shall note any discrepancies between drawings and existing conditions at site.

4. Shall designate areas for working space, materials storage and routes of access to areas within buildings where alterations occur and which have been agreed upon by Contractor and COR.

B. Any items required by drawings to be either reused or relocated or both, found during this survey to be nonexistent, or in opinion of COR, to be in such condition that their use is impossible or impractical, shall be furnished and/or replaced by Contractor with new items in accordance with specifications which will be furnished by Government. Provided the contract work is changed by reason of this subparagraph B, the contract will be modified accordingly, under provisions of clause entitled "DIFFERING SITE CONDITIONS" (FAR 52.236-2) and "CHANGES" (FAR

52.243-4).

C. Re-Survey: Thirty days before expected partial or final inspection date, the Contractor and COR together shall make a thorough re-survey of the areas of buildings involved. They shall furnish a report on conditions then existing, of resilient flooring, doors, windows, walls and other surfaces as compared with conditions of same as noted in first condition survey report:

1. Re-survey report shall also list any damage caused by Contractor to such flooring and other surfaces, despite protection measures; and, will form basis for determining extent of repair work required of Contractor to restore damage caused by Contractor's workers in executing work of this contract.

D. Protection: Provide the following protective measures:

03-01-20

01 00 00 -11

GENERAL REQUIREMENTS

1. Wherever existing roof surfaces are disturbed they shall be protected against water infiltration. In case of leaks, they shall be repaired immediately upon discovery.

2. Temporary protection against damage for portions of existing structures and grounds where work is to be done, materials handled and equipment moved and/or relocated.

3. Protection of interior of existing structures at all times, from damage, dust and weather inclemency. Wherever work is performed, floor surfaces that are to remain in place shall be adequately protected prior to starting work, and this protection shall be maintained intact until all work in the area is completed.

1.8 DISPOSAL AND RETENTION

A. Materials and equipment accruing from work removed and from demolition of buildings or structures, or parts thereof, shall be disposed of as follows:

1. Reserved items which are to remain property of the Government are noted on drawings or in specifications as items to be stored. Items that remain property of the Government shall be removed or dislodged from present locations in such a manner as to prevent damage which would be detrimental to re-installation and reuse. Store such items where directed by COR.

2. Items not reserved shall become property of the Contractor and be removed by Contractor from Medical Center.

3. Items of portable equipment and furnishings located in rooms and spaces in which work is to be done under this contract shall remain the property of the Government. When rooms and spaces are vacated by the Department of Veterans Affairs during the alteration period, such items which are NOT required by drawings and specifications to be either relocated or reused will be removed by the Government in advance of work to avoid interfering with Contractor's operation.

1.9 RESTORATION

A. Remove, cut, alter, replace, patch and repair existing work as necessary to install new work.

Except as otherwise shown or specified, do not cut, alter or remove any structural work, and do not disturb any ducts, plumbing, steam, gas, or electric work without approval of the COR.

Existing work to be altered or extended and that is found to be defective in any way, shall be reported to the COR before it is disturbed. Materials and workmanship used in restoring work, shall conform in type and quality to that of original existing construction, except as otherwise shown or specified.

B. Upon completion of contract, deliver work complete and undamaged. Existing work (walls, ceilings, partitions, floors, mechanical and electrical work, lawns, paving, roads, walks, etc.)

disturbed or removed as a result of performing required new work, shall be patched, repaired, 03-01-20

01 00 00 -12

GENERAL REQUIREMENTS

reinstalled, or replaced with new work, and refinished and left in as good condition as existed before commencing work.

C. At Contractor's own expense, Contractor shall immediately restore to service and repair any damage caused by Contractor's workers to existing piping and conduits, wires, cables, etc., of utility services or of fire protection systems and communications systems (including telephone) which are not scheduled for discontinuance or abandonment.

D. Expense of repairs to such utilities and systems not shown on drawings or locations of which are unknown will be covered by adjustment to contract time and price in accordance with clause entitled "CHANGES" (FAR 52.243-4) and "DIFFERING SITE CONDITIONS" (FAR 52.236-2).

1.10 PHYSICAL DATA

A. Data and information furnished or referred to below is for the Contractor's information. The

Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.

1. The indications of physical conditions on the drawings and in the specifications are the result of site investigations by Terracon.

B. Government does not guarantee that other materials will not be encountered nor that proportions, conditions or character of several materials will not vary from those indicated by explorations.

Bidders are expected to examine site of work and logs of borings; and, after investigation, decide for themselves character of materials and make their bids accordingly. Upon proper application to

Department of Veterans Affairs, bidders will be permitted to make subsurface explorations of their own at site.

1.11 PROFESSIONAL SURVEYING SERVICES

A registered professional land surveyor or registered civil engineer whose services are retained and paid for by the Contractor shall perform services specified herein and in other specification sections. The

Contractor shall certify that the land surveyor or civil engineer is not one who is a regular employee of the

Contractor, and that the land surveyor or civil engineer has no financial interest in this contract.

1.12 AS-BUILT DRAWINGS

A. The contractor shall maintain two full size sets of as-built drawings which will be kept current during construction of the project, to include all contract changes, modifications and clarifications.

B. All variations shall be shown in the same general detail as used in the contract drawings. To ensure compliance, as-built drawings shall be made available for the COR‘s review, as often as requested.

03-01-20

01 00 00 -13

GENERAL REQUIREMENTS

C. Contractor shall deliver two approved completed sets of as-built drawings in the electronic version (scanned PDF) to the COR within 15 calendar days after each completed phase and after the acceptance of the project by the COR.

D. Paragraphs A, B, & C shall also apply to all shop drawings.

1.13 WARRANTY MANAGEMENT

A. Warranty Management Plan: Develop a warranty management plan which contains information relevant to FAR 52.246-21 Warranty of Construction in at least 30 days before the planned pre-warranty conference, submit one set of the warranty management plan. Include within the warranty management plan all required actions and documents to assure that the Government receives all warranties to which it is entitled. The plan shall be in narrative form and contain sufficient detail to render it suitable for use by future maintenance and repair personnel, whether tradesman, or of engineering background, not necessarily familiar with this contract. The term

“status” as indicated below shall include due date and whether item has been submitted or was approved. Warranty information made available during the construction phase shall be submitted to the Contracting Officer for approval prior to each monthly invoice for payment. Assemble approved information in a binder and turn over to the Government upon acceptance of the work.

The construction warranty period will begin on the date of the project acceptance and continue for the product warranty period. A joint 4 month and 9 month warranty inspection will be conducted, measured from time of acceptance, by the Contactor and the Contracting Officer.

Include in the warranty management plan, but not limited to, the following:

1. Roles and responsibilities of all personnel associated with the warranty process, including points of contact and telephone numbers within the company of the Contractor, subcontractors, manufacturers or suppliers involved.

2. Furnish with each warranty the name, address and telephone number of each of the guarantor’s representatives nearest project location.

3. Listing and status of delivery of all Certificates of Warranty for extended warranty items, to include roofs, HVAC balancing, pumps, motors, transformers and for all commissioned systems such as fire protection and alarm systems, sprinkler systems and lightning protection systems, etc.

4. A list for each warranted equipment item, feature of construction or system indicating:

a. Name of item.

b. Model and serial numbers.

c. Location where installed.

d. Name and phone numbers of manufacturers and suppliers.

03-01-20

01 00 00 -14

GENERAL REQUIREMENTS

e. Name and phone numbers of manufacturers or suppliers.

f. Names, addresses and phone numbers of sources of spare parts.

g. Warranties and terms of warranty. Include one-year overall warranty of construction, including the starting date of warranty of construction. Items which have extended warranties shall be indicated with separate warranty expiration dates.

h. Starting point and duration of warranty period.

i. Summary of maintenance procedures required to continue the warranty in force.

j. Cross-reference to specific pertinent Operation and Maintenance manuals.

k. Organizations, names and phone numbers of persons to call for warranty service.

l. Typical response time and repair time expected for various warranted equipment.

5. The plans for attendance at the 4 and 9-month post construction warranty inspections conducted by the government.

6. Procedure and status of tagging of all equipment covered by extended warranties.

7. Copies of instructions to be posted near selected pieces of equipment where operation is critical for warranty and/or safety reasons.

B. Performance Bond: The Performance Bond shall remain effective throughout the construction period.

1. In the event the Contractor fails to commence and diligently pursue any construction warranty work required, the Contracting Officer will have the work performed by others, and after completion of the work, will charge the remaining construction warranty funds of expenses incurred by the Government while performing the work, including, but not limited to administrative expenses.

2. In the event sufficient funds are not available to cover the construction warranty work performed by the Government at the contractor’s expenses, the Contracting Officer will have the right to recoup expenses from the bonding company.

3. Following oral or written notification of required construction warranty repair work, the

Contractor shall respond in a timely manner. Written verification will follow oral instructions.

Failure to respond will be cause for the Contracting Officer to proceed against the Contractor.

C. Pre-Warranty Conference: Prior to contract completion, and at a time designated by the

Contracting Officer, the Contractor shall meet with the Contracting Officer to develop a mutual understanding with respect to the requirements of this section. Communication procedures for

Contractor notification of construction warranty defects, priorities with respect to the type of defect, reasonable time required for Contractor response, and other details deemed necessary by the Contracting Officer for the execution of the construction warranty will be established/

03-01-20

01 00 00 -15

GENERAL REQUIREMENTS

reviewed at this meeting. In connection with these requirements and at the time of the

Contractor’s quality control completion inspection, furnish the name, telephone number and address of a licensed and bonded company which is authorized to initiate and pursue construction warranty work action on behalf of the Contractor. This point of contract will be located within the local service area of the warranted construction, be continuously available and be responsive to

Government inquiry on warranty work action and status. This requirement does not relieve the

Contractor of any of its responsibilities in conjunction with other portions of this provision.

D. Contractor’s Response to Construction Warranty Service Requirements:

Following oral or written notification by the Contracting Officer, the Contractor shall respond to construction warranty service requirements in accordance with the “Construction Warranty

Service Priority List” and the three categories of priorities listed below. Submit a report on any warranty item that has been repaired during the warranty period. Include within the report the cause of the problem, date reported, corrective action taken, and when the repair was completed.

If the Contractor does not perform the construction warranty within the timeframe specified, the

Government will perform the work and back charge the construction warranty payment item established.

1. First Priority Code 1. Perform onsite inspection to evaluate situation, and determine course of action within 4 hours, initiate work within 6 hours and work continuously to completion or relief.

2. Second Priority Code 2. Perform onsite inspection to evaluate situation, and determine course of action within 8 hours, initiate work within 24 hours and work continuously to completion or relief.

3. Third Priority Code 3. All other work to be initiated within 3 work days and work continuously to completion or relief.

4. The “Construction Warranty Service Priority List” is as follows:

Code 1-Life Safety Systems

a. Fire suppression systems.

b. Fire alarm system(s).

c. Coolers and Freezers.

Code 1-Air Conditioning Systems

a. Air conditioning leak in part of the building, if causing damage.

b. Air conditioning system not cooling properly.

Code 1 Doors

03-01-20

01 00 00 -16

GENERAL REQUIREMENTS

a. Interior, exterior personnel doors or hardware, not functioning properly, causing security, fire or safety problem.

Code 3-Doors

a. Interior/exterior personnel doors or hardware not functioning properly.

Code 1-Electrical

a. Power failure (entire area or any building operational after 1600 hours).

b. Security lights.

c. Smoke detectors.

Code 2-Electrical

a. Power failure (no power to a room or part of building).

b. Receptacles and lights not operational (in a room or part of building).

Code 3-Electrical

a. Exterior lights not operational.

Code 1-Gas and Steam

a. Leaks and pipeline breaks.

Code 1-Heat

a. Power failure affecting heat.

Code 1-Plumbing

a. Hot water heater failure.

b. Leaking water supply pipes.

Code 2-Plumbing

a. Flush valves not operating properly

b. Fixture drain, supply line or any water pipe leaking.

c. Toilet leaking at base.

Code 3- Plumbing

a. Leaky faucets.

Code 3-Interior

a. Floors damaged.

b. Paint chipping or peeling.

c. Casework damaged.

Code 1-Roof Leaks

a. Damage to property is occurring.

Code 2-Water (Exterior)

a. No water to facility.

03-01-20

01 00 00 -17

GENERAL REQUIREMENTS

Code 2-Water (Hot)

a. No hot water in portion of building listed.

Code 3

a. All work not listed above.

E. Warranty Tags: At the time of installation, tag each warranted item with a durable, oil and water-resistant tag approved by the Contracting Officer. Attach each tag with a copper wire and spray with a silicone waterproof coating. Also submit two record copies of the warranty tags showing the layout and design. The date of acceptance and the QC signature shall remain blank until the project is accepted for beneficial occupancy. Show the following information on the tag.

1.14 USE OF ROADWAYS

A. For hauling, use only established public roads and roads on Medical Center property.

1.15 TEMPORARY USE OF MECHANICAL AND ELECTRICAL EQUIPMENT

A. Use of new installed mechanical and electrical equipment to provide heat, ventilation, plumbing, light and power will be permitted subject to written approval and compliance with the following provisions:

1. Permission to use each unit or system shall be given by COR in writing. If the equipment is not installed and maintained in accordance with the written agreement and following provisions, the COR will withdraw permission for use of the equipment.

03-01-20

01 00 00 -18

GENERAL REQUIREMENTS

2. Electrical installations used by the equipment shall be completed in accordance with the drawings and specifications to prevent damage to the equipment and the electrical systems, i.e. transformers, relays, circuit breakers, fuses, conductors, motor controllers and their overload elements shall be properly sized, coordinated and adjusted. Installation of temporary electrical equipment or devices shall be in accordance with NFPA 70, National Electrical

Code, (2014 Edition), Article 590, Temporary Installations. Voltage supplied to each item of equipment shall be verified to be correct and it shall be determined that motors are not overloaded. The electrical equipment shall be thoroughly cleaned before using it and again immediately before final inspection including vacuum cleaning and wiping clean interior and exterior surfaces.

3. Units shall be properly lubricated, balanced, and aligned. Vibrations shall be eliminated.

4. Automatic temperature control systems for preheat coils shall function properly and all safety controls shall function to prevent coil freeze-up damage.

5. The air filtering system utilized shall be that which is designed for the system when complete, and all filter elements shall be replaced at completion of construction and prior to testing and balancing of system.

6. All components of heat production and distribution system, metering equipment, condensate returns, and other auxiliary facilities used in temporary service shall be cleaned prior to use;

maintained to prevent corrosion internally and externally during use; and cleaned, maintained and inspected prior to acceptance by the Government.

B. Prior to final inspection, the equipment or parts used which show wear and tear beyond normal, shall be replaced with identical replacements, at no additional cost to the Government.

C. This paragraph shall not reduce the requirements of the mechanical and electrical specifications sections.

D. Any damage to the equipment or excessive wear due to prolonged use shall be repaired/replaced by the contractor at the contractor’s expense.

1.16 TEMPORARY USE OF EXISTING ELEVATORS

A. Use of existing elevators for handling building materials and Contractor's personnel will be permitted subject to following provisions:

1. Contractor makes all arrangements with the COR for use of elevators. The COR will ascertain that elevators are in proper condition. Contractor may use service elevators in

Building Nos. 1W (as directed by COR) for daily use between the hours of 7am to 6pm and for special nonrecurring time intervals when permission is granted. Personnel for operating elevators will not be provided by the Department of Veterans Affairs.

03-01-20

01 00 00 -19

GENERAL REQUIREMENTS

2. Contractor covers and provides maximum protection of following elevator components:

a. Entrance jambs, heads soffits and threshold plates.

b. Entrance columns, canopy, return panels and inside surfaces of car enclosure walls.

c. Finish flooring.

3. Government will accept hoisting ropes of elevator and rope of each speed governor if they are worn under normal operation. However, if these ropes are damaged by action of foreign matter such as sand, lime, grit, stones, etc., during temporary use, they shall be removed and replaced by new hoisting ropes at the contractors expense.

4. If brake lining of elevators are excessively worn or damaged during temporary use, they shall be removed and replaced by new brake lining at the contractors expense.

5. All parts of main controller, starter, relay panel, selector, etc., worn or damaged during temporary use shall be removed and replaced with new parts at the contractors expense, if recommended by elevator inspector after elevator is released by Contractor.

6. Place elevator in condition equal, less normal wear, to that existing at time it was placed in service of Contractor as approved by Contracting Officer.

1.17 TEMPORARY TOILETS

A. Contractor may have for use of Contractor's workers, such toilet accommodations as may be assigned to Contractor by Medical Center. Contractor shall keep such places clean and be responsible for any damage done thereto by Contractor's workers. Failure to maintain satisfactory condition in toilets will deprive Contractor of the privilege to use such toilets.

1.18 AVAILABILITY AND USE OF UTILITY SERVICES

A. The Government shall make all reasonably required amounts of utilities available to the

Contractor from existing outlets and supplies, as specified in the contract. The amount to be paid by the Contractor for chargeable electrical services shall be the prevailing rates charged to the

Government. The Contractor shall carefully conserve any utilities furnished without charge.

B. The Contractor, at Contractor's expense and in a workmanlike manner, in compliance with code and as satisfactory to the Contracting Officer, shall install and maintain all necessary temporary connections and distribution lines, and all meters required to measure the amount of electricity used for the purpose of determining charges. Before final acceptance of the work by the

Government, the Contractor shall remove all the temporary connections, distribution lines, meters, and associated paraphernalia and repair restore the infrastructure as required.

C. Contractor shall install meters at Contractor's expense and furnish the Medical Center a monthly record of the Contractor's usage of electricity as hereinafter specified.

03-01-20

01 00 00 -20

GENERAL REQUIREMENTS

D. Heat: Furnish temporary heat necessary to prevent injury to work and materials through dampness and cold. Use of open salamanders or any temporary heating devices which may be fire hazards or may smoke and damage finished work, will not be permitted. Maintain minimum temperatures as specified for various materials:

1. Obtain heat by connecting to Medical Center heating distribution system.

E. Electricity (for Construction and Testing): Furnish all temporary electric services.

1. Obtain electricity by connecting to the Medical Center electrical distribution system. The

Contractor shall meter and pay for electricity required for electric cranes and hoisting devices, electrical welding devices and any electrical heating devices providing temporary heat. Electricity for all other uses is available at no cost to the Contractor.

F. Water (for Construction and Testing): Furnish temporary water service.

1. Obtain water by connecting to the Medical Center water distribution system. Provide reduced pressure backflow preventer at each connection as per code. Water is available at no cost to the Contractor.

2. Maintain connections, pipe, fittings and fixtures and conserve water-use so none is wasted.

Failure to stop leakage or other wastes will be cause for revocation (at COR discretion) of use of water from Medical Center's system.

G. Fuel: Natural and LP gas and burner fuel oil required for boiler cleaning, normal initial boiler-burner setup and adjusting, and for performing the specified boiler tests will be furnished by the

Government. Fuel required for prolonged boiler-burner setup, adjustments, or modifications due to improper design or operation of boiler, burner, or control devices shall be furnished and paid by the Contractor at Contractor's expense.

1.19 TESTS

A. As per specification section 23 05 93 the contractor shall provide a written testing and commissioning plan complete with component level, equipment level, sub-system level and system level breakdowns. The plan will provide a schedule and a written sequence of what will be tested, how and what the expected outcome will be. This document will be submitted for approval prior to commencing work. The contractor shall document the results of the approved plan and submit for approval with the as built documentation.

B. Pre-test mechanical and electrical equipment and systems and make corrections required for proper operation of such systems before requesting final tests. Final test will not be conducted unless pre-tested.

03-01-20

01 00 00 -21

GENERAL REQUIREMENTS

C. Conduct final tests required in various sections of specifications in presence of an authorized representative of the Contracting Officer. Contractor shall furnish all labor, materials, equipment, instruments, and forms, to conduct and record such tests.

D. Mechanical and electrical systems shall be balanced, controlled and coordinated. A system is defined as the entire system which shall be coordinated to work together during normal operation to produce results for which the system is designed. For example, air conditioning supply air is only one part of entire system which provides comfort conditions for a building. Other related components are return air, exhaust air, steam, chilled water, refrigerant, hot water, controls and electricity, etc. Another example of a system which involves several components of different disciplines is a boiler installation. Efficient and acceptable boiler operation depends upon the coordination and proper operation of fuel, combustion air, controls, steam, feedwater, condensate and other related components.

E. All related components as defined above shall be functioning when any system component is tested. Tests shall be completed within a reasonably period of time during which operating and environmental conditions remain reasonably constant and are typical of the design conditions.

F. Individual test result of any component, where required, will only be accepted when submitted with the test results of related components and of the entire system.

1.20 INSTRUCTIONS

A. Contractor shall furnish Maintenance and Operating manuals (hard copies and electronic) and verbal instructions when required by the various sections of the specifications and as hereinafter specified.

B. Manuals: Maintenance and operating manuals and one compact disc (four hard copies and one electronic copy each) for each separate piece of equipment shall be delivered to the COR coincidental with the delivery of the equipment to the job site. Manuals shall be complete, detailed guides for the maintenance and operation of equipment. They shall include complete information necessary for starting, adjusting, maintaining in continuous operation for long periods of time and dismantling and reassembling of the complete units and sub-assembly components. Manuals shall include an index covering all component parts clearly cross-referenced to diagrams and illustrations. Illustrations shall include "exploded" views showing and identifying each separate item. Emphasis shall be placed on the use of special tools and instruments. The function of each piece of equipment, component, accessory and control shall be clearly and thoroughly explained. All necessary precautions for the operation of the equipment and the reason for each precaution shall be clearly set forth. Manuals shall reference the exact model, style and size of the piece of equipment and system being furnished. Manuals

03-01-20

01 00 00 -22

GENERAL REQUIREMENTS

referencing equipment similar to but of a different model, style, and size than that furnished will not be accepted.

C. Instructions: Contractor shall provide qualified, factory-trained manufacturers' representatives to give detailed training to assigned Department of Veterans Affairs personnel in the operation and complete maintenance for each piece of equipment. All such training will be at the job site.