Operation & Maintenance of the South Bay Wastewater Treatment Plant

Closed Pre-Solicitation Posted

Not the latest version. See the latest special notice from .

Solicitation number
FY26OMSBIWTP
Agency
Responses due
Set-aside
No set-aside

Opportunity facts

NAICS code
221320 Sewage Treatment Facilities
Place of performance
San Diego, California 92154, United States

Notice details come from SAM.gov. Updated .

About this opportunity

The United States Section of the International Boundary and Water Commission (USIBWC) is seeking a contractor to provide comprehensive operation and maintenance (O&M) services for the South Bay International Wastewater Treatment Plant (SBIWTP) located in San Diego County, California under Solicitation No. 191BWC26R0001. The contract requires full-service O&M including day-to-day management, personnel administration, plant influent and effluent sampling and laboratory testing, equipment operation and maintenance, system monitoring, data recording and reporting, quality control, capital improvements, vehicle fleet management, grounds maintenance, and chemical supply for the facility and its associated conveyance systems. The resulting contract will be a hybrid structure combining Firm-Fixed Price (FFP), Time and Materials (T&M), and Cost Reimbursable (CR) services for a base year plus four option years, with a contract start date of April 1, 2026. Evaluation will be based on seven factors: past performance, specialized experience, staffing and key personnel, safety requirements, financial stability, phase-in plan, and SCADA experience, with technical factors weighted more heavily than price in a best-value trade-off approach. The proposal submission deadline is January 16, 2026, at 5:00 PM MST via secure SharePoint, with the SharePoint access request deadline of January 15, 2026, at 12:00 PM MST; the question submission deadline has passed, though late questions may be submitted at the Contracting Officer's discretion.

This procurement is not a set-aside, and the current incumbent contractor is Veolia Water West America Operating Services, Inc. under contract 191BWC20C0003. The SBIWTP is a 25-35 million gallon per day (MGD) wastewater treatment facility that processes wastewater originating in Tijuana, Baja California, Mexico, with plans to expand to 50 MGD by 2031 and a peak hourly flow capacity of 75 MGD. The facility, located at 2995 Clearwater Way in San Diego, consists of advanced primary treatment completed in September 1997 and secondary treatment completed in January 2011, serving critical cross-border environmental and public health objectives. Small business utilization goals have been established at 23 percent overall, with specific targets for veteran-owned (3%), service-disabled veteran-owned (3%), HUBZone (3%), small disadvantaged (5%), and women-owned small business (5%) participation. The contractor must comply with multiple regulatory requirements including NPDES permit conditions, prevailing wage determinations, cybersecurity standards (NIST SP 800-171 Revision 3), and binational coordination protocols with Mexican stakeholders, while supporting the facility's ongoing Progressive Design-Build rehabilitation and expansion project executed by PCL Construction and Stantec Consulting Services.

Notice text

12 versions

Update #12 · Latest ·

Amendment 0008: aditional Q&As. 

Amendment 0007: Clarification on Page Limits and Proposal Requirements

Ammendment 006

Update section L04B Access Request Deadline: All access requests must be submitted no later than 01/15/2026, at 12:00 PM MST. SharePoint Access Period: Vendors will be granted access to upload proposals starting January 15, 2026Proposal Submission Deadline: All proposals must be uploaded by Friday, January 16th, 2026, at 5:00 PM MST. Late uploads will not be accepted, and expired links will not be reactivated.

Amendment 005 corrects the Governemt's responce to Q&A #110 removing "Hard Copy and Electronic Copy: Both are required."

Corrected response: 

Page Size and Limits: Standard Page Size: 8.5" x 11", Maximum Length: Technical Proposal: 20 double-sided pages (or 40 single-sided), Qualifications Proposal (Phase One): 10 double-sided pages (or 20 single-sided); Exclusions from Page Count: Cover page, table of contents, resumes, client authorization letters, divider pages, and OSHA forms.11" x 17" Sheets: Allowed only for schedules or organizational charts. Counted as one 8.5" x 11" page toward the page limit. Font and Readability: Minimum Font Size: 10-point for body text. This does not apply to graphics, captions, tables, and charts. Legibility: Proposals must be clear, easy to read, and logically presented. Submission Format: Electronic Format: PDF only. Must be either a high-quality scan or a document produced directly to PDF. Page Numbering: All pages must be consecutively numbered, including tables and exhibits.

Amendment 004 incorporates the O&M PWS amended 16 December 2025 and updates the RFI. Both are added to the attachments of this solicitation. 

Amendment 003 Amendment 003 incorporates changes to the PWS, Q&A, adds attachments, and changes the due date of proposal to 16 January 2026. Question due date has passed but questions can still be submitted in accordance with instructions below, but the Contracting Officer has the discretion if an answer is warranted.  

Note - PWS added as attachment. Amendment 002 is adding updating Clauses and changing dates below:

Key Deadlines & Due Dates

Questions & Clarifications

•             Deadline to Submit Questions changed to 10:00 AM PST (11:00 AM MST), November 26, 2025

Proposal Submission

•             SharePoint Access Request Deadline changed to December 5, 2025, 12:00 PM MST

•             SharePoint Upload Window Opens changed to December 8, 2025

Solicitation Close

•             Solicitation Closing Date changed to December 22, 2025, 5:00 PM MT 

Questions shall be submitted via- SharePoint: request access to philip.johnson@ibwc.gov, seone.jones@ibwc.gov and suzette.smith@ibwc.gov, once access is requested you will receive confirmation. Each vendor must submit all solicitation and site visit questions in writing by 10:00 AM PST (11:00 AM MST) on November 17, 2025 referencing Solicitation No. 191BWC26R0001.

Only the individual who requested access will be granted permission to the vendor’s designated Q&A folder. Access links are unique and must not be shared or forwarded.

All questions must be uploaded directly to that folder, then an email notification must be sent to Philip.Johnson@ibwc.gov confirming submission.

Each question must identify the specific solicitation page or section it refers to.

File Naming Convention
File name must follow this format:
[YYYYMMDD]_[CompanyName]_191BWC26R0001_QA.docx
Example: 20251105_ABC_Engineering_191BWC26R0001_QA.docx

Submission Requirements
1. Upload one consolidated document per company.
2. Use Word or Excel format only.
3. Include page or section references for each question.
4. Do not include photos or unrelated attachments.
5. Questions will be answered publicly through the SAM.gov.

 

------------------------------------------------

Attachment 14 was revoked 

Amendment 001 - Changing Site Visit date to Friday, 7 November 2025

Current contract 191BWC20C0003 

INTRODUCTION

The United States Section of the International Boundary and Water Commission (USIBWC), has a requirement for contract for the operation and maintenance (O&M) of the South Bay International Wastewater Treatment Plant (SBIWTP) and facilities located in San Diego County, California.  Type of contract, Firm Fixed Priced, Cost Reimbursable, Hybrid, etc. to be determined.  

The Contractor shall provide, all labor, material, management (including bi-national participation with Mexico), and other resources required to perform full-service O&M of the SBIWTP and its conveyance system, plus Canyon Collectors, Pump Stations, and South Bay Land Outfall (SBLO). Full service operation and maintenance is defined as complete facility operation and maintenance, including but not limited to providing day-to-day contract management, planning, supervision, administration, personnel; plant influent and effluent sampling and laboratory testing; equipment operation, maintenance, servicing, repair and replacement; system monitoring and operation; data recording, markups of plant as built, management and reporting; quality control; capital improvements; vehicles and vehicle fleet management, operation, maintenance and repair; housekeeping; grounds maintenance; consumable supplies including chemicals, and other services related to the operation and maintenance of the SBIWTP.   

BACKGROUND  

The SBIWTP is a twenty-five (25) million gallon per day (MGD) wastewater treatment plant located at 2995 Clearwater Way, in San Diego, San Diego County, California, , north of the International Boundary, and near the intersections of Monument and Dairy Mart Roads.  Construction of the plant’s advanced primary treatment phase was completed in September 1997, and construction of the secondary treatment phase was completed in January 2011.  The plant is treating wastewater originating in Tijuana, Baja California, Mexico and the SBIWTP is operated under the authority of the United States Section, International Boundary and Water Commission (USIBWC).  An average of twenty five million gallons per day (25 MGD) of effluent is being discharged through the South Bay Ocean Outfall (SBOO), and is subject to the requirements of the National Pollutant Discharge Elimination System (NPDES) Permit, Permit Number CA0108928, Order Number R9-2023-0009; the California Regional Water Quality Control Board (CRWQCB) Monitoring and Reporting Program, Number: R9-2023-0009; and the California Ocean Plan.   

In 2024, USIBWC awarded a $600M contract for the design and construction of the rehabilitation and expansion of the SBIWTP. USIBWC awarded the contract to PCL Construction (PCL) of Long Beach, California. In turn, PCL selected Stantec Consulting Services, Inc. (Stantec), of San Diego, as the design firm. The project was awarded using the Progressive Design-Build (PDB) contract delivery method consistent with Government contracting practices and regulations. 

Expansion of Capacity 

According to USIBWC's timeline, the design process of the plant’s expansion will unfold in strategic phases, with the complete plant expansion targeted for completion by 2027. The initial phase of the plant’s expansion encompasses design development for the entire SBIWTP scope, while subsequent phases will implement rehabilitation efforts concurrent with the ongoing expansion work. 

During the expansion, the PDB team will work closely with the future SBIWTP Operator of this Contract to rehabilitate the plant while also expanding it. The USIBWC and PDB team aims to enhance the plant's treatment capacity from the current 25 MGD to 35 MGD by 2025, with a subsequent expansion to 60 MGD projected for completion by 2027. This will likely be done in incremental increases of, for example, 10 MGD or 20 MGD at a time, with a maximum potential capacity of 60 MGD. Throughout the incremental expansion period, the Operations and Maintenance contract will be adjusted as needed to accommodate the changing requirements and milestones of the Progressive Design-Build project. While the PDB project team will retain responsibility for all construction activities, modifications to this contract will undergo review and receive appropriate authorization when necessary. 

There will be a sixty (60) day phase in/outperiod. The Contract will consist of a Base Year from date of award 6March 30, 2027 plus four (4) one-year option periods.  This is anticipated to be an unrestricted procurement under the NAICS code 221320 (Sewage Treatment Facilities), the small business size standard is $50 million. 

List of Attachments: 

  1. SOM- Submittal Registry (aka deliverables) 
  2. Quality Assurance Surveillance Plan (QASP) 
  3. Required Performance Metrics (RPM) 
  4. NPDES Permit R9-2023-0009; 4A CDO-R9-2025-0139
  5. List of Permits 
  6. SBIWTP Asset Registry  
  7. SBIWTP Condition Assessment Report- January 2024 
  8. SBIWTP Asset Maintenance Schedule 
  9. SBIWTP Capital Project List- April 2024 
  10. Monthly Chemical Dosage from March 2024- March 2025, updated Sep-Oct 2025
  11. Canyon Collector Daily Inspection Template 
  12. NPDES Annual Biosolids Report 2024 
  13. SBIWTP O&M Manual 
  14. SBIWTP System Security Plan (Need to Request access through file share), updated 042020
  15. NIST SP 800-17r3 
  16. Plans/Drawings 
  17. Maps 
  18. NIST SP 199 
  19. SBIWTP Sequence of Operations (SOO) 
  20. Wage Determination (WD) 
  21. IBWC Spill and Transboundary Plan 2021
  22. USIBWC SDFO Org Chart 22A 2019 Contractor Org Chart
  23. IBWC SBIWTP Capital Improvement Plan 2025-2029
  24. 2025 2025 IBWC Risk Assessment Final
  25. 2025 Tijuana wastewater flow diagram
  26. Emergency Response Plan
  27. SBIWTP PDB O&M Contract PWS 2020
  28. SBIWTP PDB Expansion PWS section 01.31.83.01
  29. CUI_SBIWTP PDB Early Work Package 1C replacement in kind
  30. Temp_Capacity_Incr_BOD_TM8 (need to request access through file share)
  31. Temp_Capacity_Inc_OM_TM10 (need to request access through file share)
  32. Plant Flow Diagram_2025_Temp_increase 35 mgd (need to request through file share)
  33. Thickening & Dewatering Service (need to request through file share)
  34. 12 months O&M reports (need to request through file share)
  35. 12 months NPDES Reports (need to request through file share)
Update #11 ·

Amendment 0007: Clarification on Page Limits and Proposal Requirements

Ammendment 006

Update section L04B Access Request Deadline: All access requests must be submitted no later than 01/15/2026, at 12:00 PM MST. SharePoint Access Period: Vendors will be granted access to upload proposals starting January 15, 2026Proposal Submission Deadline: All proposals must be uploaded by Friday, January 16th, 2026, at 5:00 PM MST. Late uploads will not be accepted, and expired links will not be reactivated.

Amendment 005 corrects the Governemt's responce to Q&A #110 removing "Hard Copy and Electronic Copy: Both are required."

Corrected response: 

Page Size and Limits: Standard Page Size: 8.5" x 11", Maximum Length: Technical Proposal: 20 double-sided pages (or 40 single-sided), Qualifications Proposal (Phase One): 10 double-sided pages (or 20 single-sided); Exclusions from Page Count: Cover page, table of contents, resumes, client authorization letters, divider pages, and OSHA forms.11" x 17" Sheets: Allowed only for schedules or organizational charts. Counted as one 8.5" x 11" page toward the page limit. Font and Readability: Minimum Font Size: 10-point for body text. This does not apply to graphics, captions, tables, and charts. Legibility: Proposals must be clear, easy to read, and logically presented. Submission Format: Electronic Format: PDF only. Must be either a high-quality scan or a document produced directly to PDF. Page Numbering: All pages must be consecutively numbered, including tables and exhibits.

Amendment 004 incorporates the O&M PWS amended 16 December 2025 and updates the RFI. Both are added to the attachments of this solicitation. 

Amendment 003 Amendment 003 incorporates changes to the PWS, Q&A, adds attachments, and changes the due date of proposal to 16 January 2026. Question due date has passed but questions can still be submitted in accordance with instructions below, but the Contracting Officer has the discretion if an answer is warranted.  

Note - PWS added as attachment. Amendment 002 is adding updating Clauses and changing dates below:

Key Deadlines & Due Dates

Questions & Clarifications

•             Deadline to Submit Questions changed to 10:00 AM PST (11:00 AM MST), November 26, 2025

Proposal Submission

•             SharePoint Access Request Deadline changed to December 5, 2025, 12:00 PM MST

•             SharePoint Upload Window Opens changed to December 8, 2025

Solicitation Close

•             Solicitation Closing Date changed to December 22, 2025, 5:00 PM MT 

Questions shall be submitted via- SharePoint: request access to philip.johnson@ibwc.gov, seone.jones@ibwc.gov and suzette.smith@ibwc.gov, once access is requested you will receive confirmation. Each vendor must submit all solicitation and site visit questions in writing by 10:00 AM PST (11:00 AM MST) on November 17, 2025 referencing Solicitation No. 191BWC26R0001.

Only the individual who requested access will be granted permission to the vendor’s designated Q&A folder. Access links are unique and must not be shared or forwarded.

All questions must be uploaded directly to that folder, then an email notification must be sent to Philip.Johnson@ibwc.gov confirming submission.

Each question must identify the specific solicitation page or section it refers to.

File Naming Convention
File name must follow this format:
[YYYYMMDD]_[CompanyName]_191BWC26R0001_QA.docx
Example: 20251105_ABC_Engineering_191BWC26R0001_QA.docx

Submission Requirements
1. Upload one consolidated document per company.
2. Use Word or Excel format only.
3. Include page or section references for each question.
4. Do not include photos or unrelated attachments.
5. Questions will be answered publicly through the SAM.gov.

 

------------------------------------------------

Attachment 14 was revoked 

Amendment 001 - Changing Site Visit date to Friday, 7 November 2025

Current contract 191BWC20C0003 

INTRODUCTION

The United States Section of the International Boundary and Water Commission (USIBWC), has a requirement for contract for the operation and maintenance (O&M) of the South Bay International Wastewater Treatment Plant (SBIWTP) and facilities located in San Diego County, California.  Type of contract, Firm Fixed Priced, Cost Reimbursable, Hybrid, etc. to be determined.  

The Contractor shall provide, all labor, material, management (including bi-national participation with Mexico), and other resources required to perform full-service O&M of the SBIWTP and its conveyance system, plus Canyon Collectors, Pump Stations, and South Bay Land Outfall (SBLO). Full service operation and maintenance is defined as complete facility operation and maintenance, including but not limited to providing day-to-day contract management, planning, supervision, administration, personnel; plant influent and effluent sampling and laboratory testing; equipment operation, maintenance, servicing, repair and replacement; system monitoring and operation; data recording, markups of plant as built, management and reporting; quality control; capital improvements; vehicles and vehicle fleet management, operation, maintenance and repair; housekeeping; grounds maintenance; consumable supplies including chemicals, and other services related to the operation and maintenance of the SBIWTP.   

BACKGROUND  

The SBIWTP is a twenty-five (25) million gallon per day (MGD) wastewater treatment plant located at 2995 Clearwater Way, in San Diego, San Diego County, California, , north of the International Boundary, and near the intersections of Monument and Dairy Mart Roads.  Construction of the plant’s advanced primary treatment phase was completed in September 1997, and construction of the secondary treatment phase was completed in January 2011.  The plant is treating wastewater originating in Tijuana, Baja California, Mexico and the SBIWTP is operated under the authority of the United States Section, International Boundary and Water Commission (USIBWC).  An average of twenty five million gallons per day (25 MGD) of effluent is being discharged through the South Bay Ocean Outfall (SBOO), and is subject to the requirements of the National Pollutant Discharge Elimination System (NPDES) Permit, Permit Number CA0108928, Order Number R9-2023-0009; the California Regional Water Quality Control Board (CRWQCB) Monitoring and Reporting Program, Number: R9-2023-0009; and the California Ocean Plan.   

In 2024, USIBWC awarded a $600M contract for the design and construction of the rehabilitation and expansion of the SBIWTP. USIBWC awarded the contract to PCL Construction (PCL) of Long Beach, California. In turn, PCL selected Stantec Consulting Services, Inc. (Stantec), of San Diego, as the design firm. The project was awarded using the Progressive Design-Build (PDB) contract delivery method consistent with Government contracting practices and regulations. 

Expansion of Capacity 

According to USIBWC's timeline, the design process of the plant’s expansion will unfold in strategic phases, with the complete plant expansion targeted for completion by 2027. The initial phase of the plant’s expansion encompasses design development for the entire SBIWTP scope, while subsequent phases will implement rehabilitation efforts concurrent with the ongoing expansion work. 

During the expansion, the PDB team will work closely with the future SBIWTP Operator of this Contract to rehabilitate the plant while also expanding it. The USIBWC and PDB team aims to enhance the plant's treatment capacity from the current 25 MGD to 35 MGD by 2025, with a subsequent expansion to 60 MGD projected for completion by 2027. This will likely be done in incremental increases of, for example, 10 MGD or 20 MGD at a time, with a maximum potential capacity of 60 MGD. Throughout the incremental expansion period, the Operations and Maintenance contract will be adjusted as needed to accommodate the changing requirements and milestones of the Progressive Design-Build project. While the PDB project team will retain responsibility for all construction activities, modifications to this contract will undergo review and receive appropriate authorization when necessary. 

There will be a sixty (60) day phase in/outperiod. The Contract will consist of a Base Year from date of award 6March 30, 2027 plus four (4) one-year option periods.  This is anticipated to be an unrestricted procurement under the NAICS code 221320 (Sewage Treatment Facilities), the small business size standard is $50 million. 

List of Attachments: 

  1. SOM- Submittal Registry (aka deliverables) 
  2. Quality Assurance Surveillance Plan (QASP) 
  3. Required Performance Metrics (RPM) 
  4. NPDES Permit R9-2023-0009; 4A CDO-R9-2025-0139
  5. List of Permits 
  6. SBIWTP Asset Registry  
  7. SBIWTP Condition Assessment Report- January 2024 
  8. SBIWTP Asset Maintenance Schedule 
  9. SBIWTP Capital Project List- April 2024 
  10. Monthly Chemical Dosage from March 2024- March 2025, updated Sep-Oct 2025
  11. Canyon Collector Daily Inspection Template 
  12. NPDES Annual Biosolids Report 2024 
  13. SBIWTP O&M Manual 
  14. SBIWTP System Security Plan (Need to Request access through file share), updated 042020
  15. NIST SP 800-17r3 
  16. Plans/Drawings 
  17. Maps 
  18. NIST SP 199 
  19. SBIWTP Sequence of Operations (SOO) 
  20. Wage Determination (WD) 
  21. IBWC Spill and Transboundary Plan 2021
  22. USIBWC SDFO Org Chart 22A 2019 Contractor Org Chart
  23. IBWC SBIWTP Capital Improvement Plan 2025-2029
  24. 2025 2025 IBWC Risk Assessment Final
  25. 2025 Tijuana wastewater flow diagram
  26. Emergency Response Plan
  27. SBIWTP PDB O&M Contract PWS 2020
  28. SBIWTP PDB Expansion PWS section 01.31.83.01
  29. CUI_SBIWTP PDB Early Work Package 1C replacement in kind
  30. Temp_Capacity_Incr_BOD_TM8 (need to request access through file share)
  31. Temp_Capacity_Inc_OM_TM10 (need to request access through file share)
  32. Plant Flow Diagram_2025_Temp_increase 35 mgd (need to request through file share)
  33. Thickening & Dewatering Service (need to request through file share)
  34. 12 months O&M reports (need to request through file share)
  35. 12 months NPDES Reports (need to request through file share)
Update #10 ·

Ammendment 006

Update section L04B Access Request Deadline: All access requests must be submitted no later than 01/15/2026, at 12:00 PM MST. SharePoint Access Period: Vendors will be granted access to upload proposals starting January 15, 2026Proposal Submission Deadline: All proposals must be uploaded by Friday, January 16th, 2026, at 5:00 PM MST. Late uploads will not be accepted, and expired links will not be reactivated.

Amendment 005 corrects the Governemt's responce to Q&A #110 removing "Hard Copy and Electronic Copy: Both are required."

Corrected response: 

Page Size and Limits: Standard Page Size: 8.5" x 11", Maximum Length: Technical Proposal: 20 double-sided pages (or 40 single-sided), Qualifications Proposal (Phase One): 10 double-sided pages (or 20 single-sided); Exclusions from Page Count: Cover page, table of contents, resumes, client authorization letters, divider pages, and OSHA forms.11" x 17" Sheets: Allowed only for schedules or organizational charts. Counted as one 8.5" x 11" page toward the page limit. Font and Readability: Minimum Font Size: 10-point for body text. This does not apply to graphics, captions, tables, and charts. Legibility: Proposals must be clear, easy to read, and logically presented. Submission Format: Electronic Format: PDF only. Must be either a high-quality scan or a document produced directly to PDF. Page Numbering: All pages must be consecutively numbered, including tables and exhibits.

Amendment 004 incorporates the O&M PWS amended 16 December 2025 and updates the RFI. Both are added to the attachments of this solicitation. 

Amendment 003 Amendment 003 incorporates changes to the PWS, Q&A, adds attachments, and changes the due date of proposal to 16 January 2026. Question due date has passed but questions can still be submitted in accordance with instructions below, but the Contracting Officer has the discretion if an answer is warranted.  

Note - PWS added as attachment. Amendment 002 is adding updating Clauses and changing dates below:

Key Deadlines & Due Dates

Questions & Clarifications

•             Deadline to Submit Questions changed to 10:00 AM PST (11:00 AM MST), November 26, 2025

Proposal Submission

•             SharePoint Access Request Deadline changed to December 5, 2025, 12:00 PM MST

•             SharePoint Upload Window Opens changed to December 8, 2025

Solicitation Close

•             Solicitation Closing Date changed to December 22, 2025, 5:00 PM MT 

Questions shall be submitted via- SharePoint: request access to philip.johnson@ibwc.gov, seone.jones@ibwc.gov and suzette.smith@ibwc.gov, once access is requested you will receive confirmation. Each vendor must submit all solicitation and site visit questions in writing by 10:00 AM PST (11:00 AM MST) on November 17, 2025 referencing Solicitation No. 191BWC26R0001.

Only the individual who requested access will be granted permission to the vendor’s designated Q&A folder. Access links are unique and must not be shared or forwarded.

All questions must be uploaded directly to that folder, then an email notification must be sent to Philip.Johnson@ibwc.gov confirming submission.

Each question must identify the specific solicitation page or section it refers to.

File Naming Convention
File name must follow this format:
[YYYYMMDD]_[CompanyName]_191BWC26R0001_QA.docx
Example: 20251105_ABC_Engineering_191BWC26R0001_QA.docx

Submission Requirements
1. Upload one consolidated document per company.
2. Use Word or Excel format only.
3. Include page or section references for each question.
4. Do not include photos or unrelated attachments.
5. Questions will be answered publicly through the SAM.gov.

 

------------------------------------------------

Attachment 14 was revoked 

Amendment 001 - Changing Site Visit date to Friday, 7 November 2025

Current contract 191BWC20C0003 

INTRODUCTION

The United States Section of the International Boundary and Water Commission (USIBWC), has a requirement for contract for the operation and maintenance (O&M) of the South Bay International Wastewater Treatment Plant (SBIWTP) and facilities located in San Diego County, California.  Type of contract, Firm Fixed Priced, Cost Reimbursable, Hybrid, etc. to be determined.  

The Contractor shall provide, all labor, material, management (including bi-national participation with Mexico), and other resources required to perform full-service O&M of the SBIWTP and its conveyance system, plus Canyon Collectors, Pump Stations, and South Bay Land Outfall (SBLO). Full service operation and maintenance is defined as complete facility operation and maintenance, including but not limited to providing day-to-day contract management, planning, supervision, administration, personnel; plant influent and effluent sampling and laboratory testing; equipment operation, maintenance, servicing, repair and replacement; system monitoring and operation; data recording, markups of plant as built, management and reporting; quality control; capital improvements; vehicles and vehicle fleet management, operation, maintenance and repair; housekeeping; grounds maintenance; consumable supplies including chemicals, and other services related to the operation and maintenance of the SBIWTP.   

BACKGROUND  

The SBIWTP is a twenty-five (25) million gallon per day (MGD) wastewater treatment plant located at 2995 Clearwater Way, in San Diego, San Diego County, California, , north of the International Boundary, and near the intersections of Monument and Dairy Mart Roads.  Construction of the plant’s advanced primary treatment phase was completed in September 1997, and construction of the secondary treatment phase was completed in January 2011.  The plant is treating wastewater originating in Tijuana, Baja California, Mexico and the SBIWTP is operated under the authority of the United States Section, International Boundary and Water Commission (USIBWC).  An average of twenty five million gallons per day (25 MGD) of effluent is being discharged through the South Bay Ocean Outfall (SBOO), and is subject to the requirements of the National Pollutant Discharge Elimination System (NPDES) Permit, Permit Number CA0108928, Order Number R9-2023-0009; the California Regional Water Quality Control Board (CRWQCB) Monitoring and Reporting Program, Number: R9-2023-0009; and the California Ocean Plan.   

In 2024, USIBWC awarded a $600M contract for the design and construction of the rehabilitation and expansion of the SBIWTP. USIBWC awarded the contract to PCL Construction (PCL) of Long Beach, California. In turn, PCL selected Stantec Consulting Services, Inc. (Stantec), of San Diego, as the design firm. The project was awarded using the Progressive Design-Build (PDB) contract delivery method consistent with Government contracting practices and regulations. 

Expansion of Capacity 

According to USIBWC's timeline, the design process of the plant’s expansion will unfold in strategic phases, with the complete plant expansion targeted for completion by 2027. The initial phase of the plant’s expansion encompasses design development for the entire SBIWTP scope, while subsequent phases will implement rehabilitation efforts concurrent with the ongoing expansion work. 

During the expansion, the PDB team will work closely with the future SBIWTP Operator of this Contract to rehabilitate the plant while also expanding it. The USIBWC and PDB team aims to enhance the plant's treatment capacity from the current 25 MGD to 35 MGD by 2025, with a subsequent expansion to 60 MGD projected for completion by 2027. This will likely be done in incremental increases of, for example, 10 MGD or 20 MGD at a time, with a maximum potential capacity of 60 MGD. Throughout the incremental expansion period, the Operations and Maintenance contract will be adjusted as needed to accommodate the changing requirements and milestones of the Progressive Design-Build project. While the PDB project team will retain responsibility for all construction activities, modifications to this contract will undergo review and receive appropriate authorization when necessary. 

There will be a sixty (60) day phase in/outperiod. The Contract will consist of a Base Year from date of award 6March 30, 2027 plus four (4) one-year option periods.  This is anticipated to be an unrestricted procurement under the NAICS code 221320 (Sewage Treatment Facilities), the small business size standard is $50 million. 

List of Attachments: 

  1. SOM- Submittal Registry (aka deliverables) 
  2. Quality Assurance Surveillance Plan (QASP) 
  3. Required Performance Metrics (RPM) 
  4. NPDES Permit R9-2023-0009; 4A CDO-R9-2025-0139
  5. List of Permits 
  6. SBIWTP Asset Registry  
  7. SBIWTP Condition Assessment Report- January 2024 
  8. SBIWTP Asset Maintenance Schedule 
  9. SBIWTP Capital Project List- April 2024 
  10. Monthly Chemical Dosage from March 2024- March 2025, updated Sep-Oct 2025
  11. Canyon Collector Daily Inspection Template 
  12. NPDES Annual Biosolids Report 2024 
  13. SBIWTP O&M Manual 
  14. SBIWTP System Security Plan (Need to Request access through file share), updated 042020
  15. NIST SP 800-17r3 
  16. Plans/Drawings 
  17. Maps 
  18. NIST SP 199 
  19. SBIWTP Sequence of Operations (SOO) 
  20. Wage Determination (WD) 
  21. IBWC Spill and Transboundary Plan 2021
  22. USIBWC SDFO Org Chart 22A 2019 Contractor Org Chart
  23. IBWC SBIWTP Capital Improvement Plan 2025-2029
  24. 2025 2025 IBWC Risk Assessment Final
  25. 2025 Tijuana wastewater flow diagram
  26. Emergency Response Plan
  27. SBIWTP PDB O&M Contract PWS 2020
  28. SBIWTP PDB Expansion PWS section 01.31.83.01
  29. CUI_SBIWTP PDB Early Work Package 1C replacement in kind
  30. Temp_Capacity_Incr_BOD_TM8 (need to request access through file share)
  31. Temp_Capacity_Inc_OM_TM10 (need to request access through file share)
  32. Plant Flow Diagram_2025_Temp_increase 35 mgd (need to request through file share)
  33. Thickening & Dewatering Service (need to request through file share)
  34. 12 months O&M reports (need to request through file share)
  35. 12 months NPDES Reports (need to request through file share)
Update #9 ·

Amendment 005 corrects the Governemt's responce to Q&A #110 removing "Hard Copy and Electronic Copy: Both are required."

Corrected response: 

Page Size and Limits: Standard Page Size: 8.5" x 11", Maximum Length: Technical Proposal: 20 double-sided pages (or 40 single-sided), Qualifications Proposal (Phase One): 10 double-sided pages (or 20 single-sided); Exclusions from Page Count: Cover page, table of contents, resumes, client authorization letters, divider pages, and OSHA forms.11" x 17" Sheets: Allowed only for schedules or organizational charts. Counted as one 8.5" x 11" page toward the page limit. Font and Readability: Minimum Font Size: 10-point for body text. This does not apply to graphics, captions, tables, and charts. Legibility: Proposals must be clear, easy to read, and logically presented. Submission Format: Electronic Format: PDF only. Must be either a high-quality scan or a document produced directly to PDF. Page Numbering: All pages must be consecutively numbered, including tables and exhibits.

Amendment 004 incorporates the O&M PWS amended 16 December 2025 and updates the RFI. Both are added to the attachments of this solicitation. 

Amendment 003 Amendment 003 incorporates changes to the PWS, Q&A, adds attachments, and changes the due date of proposal to 16 January 2026. Question due date has passed but questions can still be submitted in accordance with instructions below, but the Contracting Officer has the discretion if an answer is warranted.  

Note - PWS added as attachment. Amendment 002 is adding updating Clauses and changing dates below:

Key Deadlines & Due Dates

Questions & Clarifications

•             Deadline to Submit Questions changed to 10:00 AM PST (11:00 AM MST), November 26, 2025

Proposal Submission

•             SharePoint Access Request Deadline changed to December 5, 2025, 12:00 PM MST

•             SharePoint Upload Window Opens changed to December 8, 2025

Solicitation Close

•             Solicitation Closing Date changed to December 22, 2025, 5:00 PM MT 

Questions shall be submitted via- SharePoint: request access to philip.johnson@ibwc.gov, seone.jones@ibwc.gov and suzette.smith@ibwc.gov, once access is requested you will receive confirmation. Each vendor must submit all solicitation and site visit questions in writing by 10:00 AM PST (11:00 AM MST) on November 17, 2025 referencing Solicitation No. 191BWC26R0001.

Only the individual who requested access will be granted permission to the vendor’s designated Q&A folder. Access links are unique and must not be shared or forwarded.

All questions must be uploaded directly to that folder, then an email notification must be sent to Philip.Johnson@ibwc.gov confirming submission.

Each question must identify the specific solicitation page or section it refers to.

File Naming Convention
File name must follow this format:
[YYYYMMDD]_[CompanyName]_191BWC26R0001_QA.docx
Example: 20251105_ABC_Engineering_191BWC26R0001_QA.docx

Submission Requirements
1. Upload one consolidated document per company.
2. Use Word or Excel format only.
3. Include page or section references for each question.
4. Do not include photos or unrelated attachments.
5. Questions will be answered publicly through the SAM.gov.

 

------------------------------------------------

Attachment 14 was revoked 

Amendment 001 - Changing Site Visit date to Friday, 7 November 2025

Current contract 191BWC20C0003 

INTRODUCTION

The United States Section of the International Boundary and Water Commission (USIBWC), has a requirement for contract for the operation and maintenance (O&M) of the South Bay International Wastewater Treatment Plant (SBIWTP) and facilities located in San Diego County, California.  Type of contract, Firm Fixed Priced, Cost Reimbursable, Hybrid, etc. to be determined.  

The Contractor shall provide, all labor, material, management (including bi-national participation with Mexico), and other resources required to perform full-service O&M of the SBIWTP and its conveyance system, plus Canyon Collectors, Pump Stations, and South Bay Land Outfall (SBLO). Full service operation and maintenance is defined as complete facility operation and maintenance, including but not limited to providing day-to-day contract management, planning, supervision, administration, personnel; plant influent and effluent sampling and laboratory testing; equipment operation, maintenance, servicing, repair and replacement; system monitoring and operation; data recording, markups of plant as built, management and reporting; quality control; capital improvements; vehicles and vehicle fleet management, operation, maintenance and repair; housekeeping; grounds maintenance; consumable supplies including chemicals, and other services related to the operation and maintenance of the SBIWTP.   

BACKGROUND  

The SBIWTP is a twenty-five (25) million gallon per day (MGD) wastewater treatment plant located at 2995 Clearwater Way, in San Diego, San Diego County, California, , north of the International Boundary, and near the intersections of Monument and Dairy Mart Roads.  Construction of the plant’s advanced primary treatment phase was completed in September 1997, and construction of the secondary treatment phase was completed in January 2011.  The plant is treating wastewater originating in Tijuana, Baja California, Mexico and the SBIWTP is operated under the authority of the United States Section, International Boundary and Water Commission (USIBWC).  An average of twenty five million gallons per day (25 MGD) of effluent is being discharged through the South Bay Ocean Outfall (SBOO), and is subject to the requirements of the National Pollutant Discharge Elimination System (NPDES) Permit, Permit Number CA0108928, Order Number R9-2023-0009; the California Regional Water Quality Control Board (CRWQCB) Monitoring and Reporting Program, Number: R9-2023-0009; and the California Ocean Plan.   

In 2024, USIBWC awarded a $600M contract for the design and construction of the rehabilitation and expansion of the SBIWTP. USIBWC awarded the contract to PCL Construction (PCL) of Long Beach, California. In turn, PCL selected Stantec Consulting Services, Inc. (Stantec), of San Diego, as the design firm. The project was awarded using the Progressive Design-Build (PDB) contract delivery method consistent with Government contracting practices and regulations. 

Expansion of Capacity 

According to USIBWC's timeline, the design process of the plant’s expansion will unfold in strategic phases, with the complete plant expansion targeted for completion by 2027. The initial phase of the plant’s expansion encompasses design development for the entire SBIWTP scope, while subsequent phases will implement rehabilitation efforts concurrent with the ongoing expansion work. 

During the expansion, the PDB team will work closely with the future SBIWTP Operator of this Contract to rehabilitate the plant while also expanding it. The USIBWC and PDB team aims to enhance the plant's treatment capacity from the current 25 MGD to 35 MGD by 2025, with a subsequent expansion to 60 MGD projected for completion by 2027. This will likely be done in incremental increases of, for example, 10 MGD or 20 MGD at a time, with a maximum potential capacity of 60 MGD. Throughout the incremental expansion period, the Operations and Maintenance contract will be adjusted as needed to accommodate the changing requirements and milestones of the Progressive Design-Build project. While the PDB project team will retain responsibility for all construction activities, modifications to this contract will undergo review and receive appropriate authorization when necessary. 

There will be a sixty (60) day phase in/outperiod. The Contract will consist of a Base Year from date of award 6March 30, 2027 plus four (4) one-year option periods.  This is anticipated to be an unrestricted procurement under the NAICS code 221320 (Sewage Treatment Facilities), the small business size standard is $50 million. 

List of Attachments: 

  1. SOM- Submittal Registry (aka deliverables) 
  2. Quality Assurance Surveillance Plan (QASP) 
  3. Required Performance Metrics (RPM) 
  4. NPDES Permit R9-2023-0009; 4A CDO-R9-2025-0139
  5. List of Permits 
  6. SBIWTP Asset Registry  
  7. SBIWTP Condition Assessment Report- January 2024 
  8. SBIWTP Asset Maintenance Schedule 
  9. SBIWTP Capital Project List- April 2024 
  10. Monthly Chemical Dosage from March 2024- March 2025, updated Sep-Oct 2025
  11. Canyon Collector Daily Inspection Template 
  12. NPDES Annual Biosolids Report 2024 
  13. SBIWTP O&M Manual 
  14. SBIWTP System Security Plan (Need to Request access through file share), updated 042020
  15. NIST SP 800-17r3 
  16. Plans/Drawings 
  17. Maps 
  18. NIST SP 199 
  19. SBIWTP Sequence of Operations (SOO) 
  20. Wage Determination (WD) 
  21. IBWC Spill and Transboundary Plan 2021
  22. USIBWC SDFO Org Chart 22A 2019 Contractor Org Chart
  23. IBWC SBIWTP Capital Improvement Plan 2025-2029
  24. 2025 2025 IBWC Risk Assessment Final
  25. 2025 Tijuana wastewater flow diagram
  26. Emergency Response Plan
  27. SBIWTP PDB O&M Contract PWS 2020
  28. SBIWTP PDB Expansion PWS section 01.31.83.01
  29. CUI_SBIWTP PDB Early Work Package 1C replacement in kind
  30. Temp_Capacity_Incr_BOD_TM8 (need to request access through file share)
  31. Temp_Capacity_Inc_OM_TM10 (need to request access through file share)
  32. Plant Flow Diagram_2025_Temp_increase 35 mgd (need to request through file share)
  33. Thickening & Dewatering Service (need to request through file share)
  34. 12 months O&M reports (need to request through file share)
  35. 12 months NPDES Reports (need to request through file share)
Update #8 ·

Amendment 004 incorporates the O&M PWS amended 16 December 2025 and updates the RFI. Both are added to the attachments of this solicitation. 

Amendment 003 Amendment 003 incorporates changes to the PWS, Q&A, adds attachments, and changes the due date of proposal to 16 January 2026. Question due date has passed but questions can still be submitted in accordance with instructions below, but the Contracting Officer has the discretion if an answer is warranted.  

Note - PWS added as attachment. Amendment 002 is adding updating Clauses and changing dates below:

Key Deadlines & Due Dates

Questions & Clarifications

•             Deadline to Submit Questions changed to 10:00 AM PST (11:00 AM MST), November 26, 2025

Proposal Submission

•             SharePoint Access Request Deadline changed to December 5, 2025, 12:00 PM MST

•             SharePoint Upload Window Opens changed to December 8, 2025

Solicitation Close

•             Solicitation Closing Date changed to December 22, 2025, 5:00 PM MT 

Questions shall be submitted via- SharePoint: request access to philip.johnson@ibwc.gov, seone.jones@ibwc.gov and suzette.smith@ibwc.gov, once access is requested you will receive confirmation. Each vendor must submit all solicitation and site visit questions in writing by 10:00 AM PST (11:00 AM MST) on November 17, 2025 referencing Solicitation No. 191BWC26R0001.

Only the individual who requested access will be granted permission to the vendor’s designated Q&A folder. Access links are unique and must not be shared or forwarded.

All questions must be uploaded directly to that folder, then an email notification must be sent to Philip.Johnson@ibwc.gov confirming submission.

Each question must identify the specific solicitation page or section it refers to.

File Naming Convention
File name must follow this format:
[YYYYMMDD]_[CompanyName]_191BWC26R0001_QA.docx
Example: 20251105_ABC_Engineering_191BWC26R0001_QA.docx

Submission Requirements
1. Upload one consolidated document per company.
2. Use Word or Excel format only.
3. Include page or section references for each question.
4. Do not include photos or unrelated attachments.
5. Questions will be answered publicly through the SAM.gov.

 

------------------------------------------------

Attachment 14 was revoked 

Amendment 001 - Changing Site Visit date to Friday, 7 November 2025

Current contract 191BWC20C0003 

INTRODUCTION

The United States Section of the International Boundary and Water Commission (USIBWC), has a requirement for contract for the operation and maintenance (O&M) of the South Bay International Wastewater Treatment Plant (SBIWTP) and facilities located in San Diego County, California.  Type of contract, Firm Fixed Priced, Cost Reimbursable, Hybrid, etc. to be determined.  

The Contractor shall provide, all labor, material, management (including bi-national participation with Mexico), and other resources required to perform full-service O&M of the SBIWTP and its conveyance system, plus Canyon Collectors, Pump Stations, and South Bay Land Outfall (SBLO). Full service operation and maintenance is defined as complete facility operation and maintenance, including but not limited to providing day-to-day contract management, planning, supervision, administration, personnel; plant influent and effluent sampling and laboratory testing; equipment operation, maintenance, servicing, repair and replacement; system monitoring and operation; data recording, markups of plant as built, management and reporting; quality control; capital improvements; vehicles and vehicle fleet management, operation, maintenance and repair; housekeeping; grounds maintenance; consumable supplies including chemicals, and other services related to the operation and maintenance of the SBIWTP.   

BACKGROUND  

The SBIWTP is a twenty-five (25) million gallon per day (MGD) wastewater treatment plant located at 2995 Clearwater Way, in San Diego, San Diego County, California, , north of the International Boundary, and near the intersections of Monument and Dairy Mart Roads.  Construction of the plant’s advanced primary treatment phase was completed in September 1997, and construction of the secondary treatment phase was completed in January 2011.  The plant is treating wastewater originating in Tijuana, Baja California, Mexico and the SBIWTP is operated under the authority of the United States Section, International Boundary and Water Commission (USIBWC).  An average of twenty five million gallons per day (25 MGD) of effluent is being discharged through the South Bay Ocean Outfall (SBOO), and is subject to the requirements of the National Pollutant Discharge Elimination System (NPDES) Permit, Permit Number CA0108928, Order Number R9-2023-0009; the California Regional Water Quality Control Board (CRWQCB) Monitoring and Reporting Program, Number: R9-2023-0009; and the California Ocean Plan.   

In 2024, USIBWC awarded a $600M contract for the design and construction of the rehabilitation and expansion of the SBIWTP. USIBWC awarded the contract to PCL Construction (PCL) of Long Beach, California. In turn, PCL selected Stantec Consulting Services, Inc. (Stantec), of San Diego, as the design firm. The project was awarded using the Progressive Design-Build (PDB) contract delivery method consistent with Government contracting practices and regulations. 

Expansion of Capacity 

According to USIBWC's timeline, the design process of the plant’s expansion will unfold in strategic phases, with the complete plant expansion targeted for completion by 2027. The initial phase of the plant’s expansion encompasses design development for the entire SBIWTP scope, while subsequent phases will implement rehabilitation efforts concurrent with the ongoing expansion work. 

During the expansion, the PDB team will work closely with the future SBIWTP Operator of this Contract to rehabilitate the plant while also expanding it. The USIBWC and PDB team aims to enhance the plant's treatment capacity from the current 25 MGD to 35 MGD by 2025, with a subsequent expansion to 60 MGD projected for completion by 2027. This will likely be done in incremental increases of, for example, 10 MGD or 20 MGD at a time, with a maximum potential capacity of 60 MGD. Throughout the incremental expansion period, the Operations and Maintenance contract will be adjusted as needed to accommodate the changing requirements and milestones of the Progressive Design-Build project. While the PDB project team will retain responsibility for all construction activities, modifications to this contract will undergo review and receive appropriate authorization when necessary. 

There will be a sixty (60) day phase in/outperiod. The Contract will consist of a Base Year from date of award 6March 30, 2027 plus four (4) one-year option periods.  This is anticipated to be an unrestricted procurement under the NAICS code 221320 (Sewage Treatment Facilities), the small business size standard is $50 million. 

List of Attachments: 

  1. SOM- Submittal Registry (aka deliverables) 
  2. Quality Assurance Surveillance Plan (QASP) 
  3. Required Performance Metrics (RPM) 
  4. NPDES Permit R9-2023-0009; 4A CDO-R9-2025-0139
  5. List of Permits 
  6. SBIWTP Asset Registry  
  7. SBIWTP Condition Assessment Report- January 2024 
  8. SBIWTP Asset Maintenance Schedule 
  9. SBIWTP Capital Project List- April 2024 
  10. Monthly Chemical Dosage from March 2024- March 2025, updated Sep-Oct 2025
  11. Canyon Collector Daily Inspection Template 
  12. NPDES Annual Biosolids Report 2024 
  13. SBIWTP O&M Manual 
  14. SBIWTP System Security Plan (Need to Request access through file share), updated 042020
  15. NIST SP 800-17r3 
  16. Plans/Drawings 
  17. Maps 
  18. NIST SP 199 
  19. SBIWTP Sequence of Operations (SOO) 
  20. Wage Determination (WD) 
  21. IBWC Spill and Transboundary Plan 2021
  22. USIBWC SDFO Org Chart 22A 2019 Contractor Org Chart
  23. IBWC SBIWTP Capital Improvement Plan 2025-2029
  24. 2025 2025 IBWC Risk Assessment Final
  25. 2025 Tijuana wastewater flow diagram
  26. Emergency Response Plan
  27. SBIWTP PDB O&M Contract PWS 2020
  28. SBIWTP PDB Expansion PWS section 01.31.83.01
  29. CUI_SBIWTP PDB Early Work Package 1C replacement in kind
  30. Temp_Capacity_Incr_BOD_TM8 (need to request access through file share)
  31. Temp_Capacity_Inc_OM_TM10 (need to request access through file share)
  32. Plant Flow Diagram_2025_Temp_increase 35 mgd (need to request through file share)
  33. Thickening & Dewatering Service (need to request through file share)
  34. 12 months O&M reports (need to request through file share)
  35. 12 months NPDES Reports (need to request through file share)
Update #7 ·

Amendment 003 Amendment 003 incorporates changes to the PWS, Q&A, adds attachments, and changes the due date of proposal to 16 January 2026. Question due date has passed but questions can still be submitted in accordance with instructions below, but the Contracting Officer has the discretion if an answer is warranted.  

Note - PWS added as attachment. Amendment 002 is adding updating Clauses and changing dates below:

Key Deadlines & Due Dates

Questions & Clarifications

•             Deadline to Submit Questions changed to 10:00 AM PST (11:00 AM MST), November 26, 2025

Proposal Submission

•             SharePoint Access Request Deadline changed to December 5, 2025, 12:00 PM MST

•             SharePoint Upload Window Opens changed to December 8, 2025

Solicitation Close

•             Solicitation Closing Date changed to December 22, 2025, 5:00 PM MT 

Questions shall be submitted via- SharePoint: request access to philip.johnson@ibwc.gov, seone.jones@ibwc.gov and suzette.smith@ibwc.gov, once access is requested you will receive confirmation. Each vendor must submit all solicitation and site visit questions in writing by 10:00 AM PST (11:00 AM MST) on November 17, 2025 referencing Solicitation No. 191BWC26R0001.

Only the individual who requested access will be granted permission to the vendor’s designated Q&A folder. Access links are unique and must not be shared or forwarded.

All questions must be uploaded directly to that folder, then an email notification must be sent to Philip.Johnson@ibwc.gov confirming submission.

Each question must identify the specific solicitation page or section it refers to.

File Naming Convention
File name must follow this format:
[YYYYMMDD]_[CompanyName]_191BWC26R0001_QA.docx
Example: 20251105_ABC_Engineering_191BWC26R0001_QA.docx

Submission Requirements
1. Upload one consolidated document per company.
2. Use Word or Excel format only.
3. Include page or section references for each question.
4. Do not include photos or unrelated attachments.
5. Questions will be answered publicly through the SAM.gov.

 

------------------------------------------------

Attachment 14 was revoked 

Amendment 001 - Changing Site Visit date to Friday, 7 November 2025

Current contract 191BWC20C0003 

INTRODUCTION

The United States Section of the International Boundary and Water Commission (USIBWC), has a requirement for contract for the operation and maintenance (O&M) of the South Bay International Wastewater Treatment Plant (SBIWTP) and facilities located in San Diego County, California.  Type of contract, Firm Fixed Priced, Cost Reimbursable, Hybrid, etc. to be determined.  

The Contractor shall provide, all labor, material, management (including bi-national participation with Mexico), and other resources required to perform full-service O&M of the SBIWTP and its conveyance system, plus Canyon Collectors, Pump Stations, and South Bay Land Outfall (SBLO). Full service operation and maintenance is defined as complete facility operation and maintenance, including but not limited to providing day-to-day contract management, planning, supervision, administration, personnel; plant influent and effluent sampling and laboratory testing; equipment operation, maintenance, servicing, repair and replacement; system monitoring and operation; data recording, markups of plant as built, management and reporting; quality control; capital improvements; vehicles and vehicle fleet management, operation, maintenance and repair; housekeeping; grounds maintenance; consumable supplies including chemicals, and other services related to the operation and maintenance of the SBIWTP.   

BACKGROUND  

The SBIWTP is a twenty-five (25) million gallon per day (MGD) wastewater treatment plant located at 2995 Clearwater Way, in San Diego, San Diego County, California, , north of the International Boundary, and near the intersections of Monument and Dairy Mart Roads.  Construction of the plant’s advanced primary treatment phase was completed in September 1997, and construction of the secondary treatment phase was completed in January 2011.  The plant is treating wastewater originating in Tijuana, Baja California, Mexico and the SBIWTP is operated under the authority of the United States Section, International Boundary and Water Commission (USIBWC).  An average of twenty five million gallons per day (25 MGD) of effluent is being discharged through the South Bay Ocean Outfall (SBOO), and is subject to the requirements of the National Pollutant Discharge Elimination System (NPDES) Permit, Permit Number CA0108928, Order Number R9-2023-0009; the California Regional Water Quality Control Board (CRWQCB) Monitoring and Reporting Program, Number: R9-2023-0009; and the California Ocean Plan.   

In 2024, USIBWC awarded a $600M contract for the design and construction of the rehabilitation and expansion of the SBIWTP. USIBWC awarded the contract to PCL Construction (PCL) of Long Beach, California. In turn, PCL selected Stantec Consulting Services, Inc. (Stantec), of San Diego, as the design firm. The project was awarded using the Progressive Design-Build (PDB) contract delivery method consistent with Government contracting practices and regulations. 

Expansion of Capacity 

According to USIBWC's timeline, the design process of the plant’s expansion will unfold in strategic phases, with the complete plant expansion targeted for completion by 2027. The initial phase of the plant’s expansion encompasses design development for the entire SBIWTP scope, while subsequent phases will implement rehabilitation efforts concurrent with the ongoing expansion work. 

During the expansion, the PDB team will work closely with the future SBIWTP Operator of this Contract to rehabilitate the plant while also expanding it. The USIBWC and PDB team aims to enhance the plant's treatment capacity from the current 25 MGD to 35 MGD by 2025, with a subsequent expansion to 60 MGD projected for completion by 2027. This will likely be done in incremental increases of, for example, 10 MGD or 20 MGD at a time, with a maximum potential capacity of 60 MGD. Throughout the incremental expansion period, the Operations and Maintenance contract will be adjusted as needed to accommodate the changing requirements and milestones of the Progressive Design-Build project. While the PDB project team will retain responsibility for all construction activities, modifications to this contract will undergo review and receive appropriate authorization when necessary. 

There will be a sixty (60) day phase in/outperiod. The Contract will consist of a Base Year from date of award 6March 30, 2027 plus four (4) one-year option periods.  This is anticipated to be an unrestricted procurement under the NAICS code 221320 (Sewage Treatment Facilities), the small business size standard is $50 million. 

List of Attachments: 

  1. SOM- Submittal Registry (aka deliverables) 
  2. Quality Assurance Surveillance Plan (QASP) 
  3. Required Performance Metrics (RPM) 
  4. NPDES Permit R9-2023-0009; 4A CDO-R9-2025-0139
  5. List of Permits 
  6. SBIWTP Asset Registry  
  7. SBIWTP Condition Assessment Report- January 2024 
  8. SBIWTP Asset Maintenance Schedule 
  9. SBIWTP Capital Project List- April 2024 
  10. Monthly Chemical Dosage from March 2024- March 2025, updated Sep-Oct 2025
  11. Canyon Collector Daily Inspection Template 
  12. NPDES Annual Biosolids Report 2024 
  13. SBIWTP O&M Manual 
  14. SBIWTP System Security Plan (Need to Request access through file share), updated 042020
  15. NIST SP 800-17r3 
  16. Plans/Drawings 
  17. Maps 
  18. NIST SP 199 
  19. SBIWTP Sequence of Operations (SOO) 
  20. Wage Determination (WD) 
  21. IBWC Spill and Transboundary Plan 2021
  22. USIBWC SDFO Org Chart 22A 2019 Contractor Org Chart
  23. IBWC SBIWTP Capital Improvement Plan 2025-2029
  24. 2025 2025 IBWC Risk Assessment Final
  25. 2025 Tijuana wastewater flow diagram
  26. Emergency Response Plan
  27. SBIWTP PDB O&M Contract PWS 2020
  28. SBIWTP PDB Expansion PWS section 01.31.83.01
  29. CUI_SBIWTP PDB Early Work Package 1C replacement in kind
  30. Temp_Capacity_Incr_BOD_TM8 (need to request access through file share)
  31. Temp_Capacity_Inc_OM_TM10 (need to request access through file share)
  32. Plant Flow Diagram_2025_Temp_increase 35 mgd (need to request through file share)
  33. Thickening & Dewatering Service (need to request through file share)
  34. 12 months O&M reports (need to request through file share)
  35. 12 months NPDES Reports (need to request through file share)
Update #6 ·

Note - PWS added as attachment. Amendment 002 is adding updating Clauses and changing dates below:

Key Deadlines & Due Dates

Questions & Clarifications

•             Deadline to Submit Questions changed to 10:00 AM PST (11:00 AM MST), November 26, 2025

Proposal Submission

•             SharePoint Access Request Deadline changed to December 5, 2025, 12:00 PM MST

•             SharePoint Upload Window Opens changed to December 8, 2025

Solicitation Close

•             Solicitation Closing Date changed to December 22, 2025, 5:00 PM MT 

Questions shall be submitted via- SharePoint: request access to philip.johnson@ibwc.gov, seone.jones@ibwc.gov and suzette.smith@ibwc.gov, once access is requested you will receive confirmation. Each vendor must submit all solicitation and site visit questions in writing by 10:00 AM PST (11:00 AM MST) on November 17, 2025 referencing Solicitation No. 191BWC26R0001.

Only the individual who requested access will be granted permission to the vendor’s designated Q&A folder. Access links are unique and must not be shared or forwarded.

All questions must be uploaded directly to that folder, then an email notification must be sent to Philip.Johnson@ibwc.gov confirming submission.

Each question must identify the specific solicitation page or section it refers to.

File Naming Convention
File name must follow this format:
[YYYYMMDD]_[CompanyName]_191BWC26R0001_QA.docx
Example: 20251105_ABC_Engineering_191BWC26R0001_QA.docx

Submission Requirements
1. Upload one consolidated document per company.
2. Use Word or Excel format only.
3. Include page or section references for each question.
4. Do not include photos or unrelated attachments.
5. Questions will be answered publicly through the SAM.gov.

 

------------------------------------------------

Attachment 14 was revoked 

Amendment 001 - Changing Site Visit date to Friday, 7 November 2025

Current contract 191BWC20C0003 

INTRODUCTION

The United States Section of the International Boundary and Water Commission (USIBWC), has a requirement for contract for the operation and maintenance (O&M) of the South Bay International Wastewater Treatment Plant (SBIWTP) and facilities located in San Diego County, California.  Type of contract, Firm Fixed Priced, Cost Reimbursable, Hybrid, etc. to be determined.  

The Contractor shall provide, all labor, material, management (including bi-national participation with Mexico), and other resources required to perform full-service O&M of the SBIWTP and its conveyance system, plus Canyon Collectors, Pump Stations, and South Bay Land Outfall (SBLO). Full service operation and maintenance is defined as complete facility operation and maintenance, including but not limited to providing day-to-day contract management, planning, supervision, administration, personnel; plant influent and effluent sampling and laboratory testing; equipment operation, maintenance, servicing, repair and replacement; system monitoring and operation; data recording, markups of plant as built, management and reporting; quality control; capital improvements; vehicles and vehicle fleet management, operation, maintenance and repair; housekeeping; grounds maintenance; consumable supplies including chemicals, and other services related to the operation and maintenance of the SBIWTP.   

BACKGROUND  

The SBIWTP is a twenty-five (25) million gallon per day (MGD) wastewater treatment plant located at 2995 Clearwater Way, in San Diego, San Diego County, California, , north of the International Boundary, and near the intersections of Monument and Dairy Mart Roads.  Construction of the plant’s advanced primary treatment phase was completed in September 1997, and construction of the secondary treatment phase was completed in January 2011.  The plant is treating wastewater originating in Tijuana, Baja California, Mexico and the SBIWTP is operated under the authority of the United States Section, International Boundary and Water Commission (USIBWC).  An average of twenty five million gallons per day (25 MGD) of effluent is being discharged through the South Bay Ocean Outfall (SBOO), and is subject to the requirements of the National Pollutant Discharge Elimination System (NPDES) Permit, Permit Number CA0108928, Order Number R9-2023-0009; the California Regional Water Quality Control Board (CRWQCB) Monitoring and Reporting Program, Number: R9-2023-0009; and the California Ocean Plan.   

In 2024, USIBWC awarded a $600M contract for the design and construction of the rehabilitation and expansion of the SBIWTP. USIBWC awarded the contract to PCL Construction (PCL) of Long Beach, California. In turn, PCL selected Stantec Consulting Services, Inc. (Stantec), of San Diego, as the design firm. The project was awarded using the Progressive Design-Build (PDB) contract delivery method consistent with Government contracting practices and regulations. 

Expansion of Capacity 

According to USIBWC's timeline, the design process of the plant’s expansion will unfold in strategic phases, with the complete plant expansion targeted for completion by 2027. The initial phase of the plant’s expansion encompasses design development for the entire SBIWTP scope, while subsequent phases will implement rehabilitation efforts concurrent with the ongoing expansion work. 

During the expansion, the PDB team will work closely with the future SBIWTP Operator of this Contract to rehabilitate the plant while also expanding it. The USIBWC and PDB team aims to enhance the plant's treatment capacity from the current 25 MGD to 35 MGD by 2025, with a subsequent expansion to 60 MGD projected for completion by 2027. This will likely be done in incremental increases of, for example, 10 MGD or 20 MGD at a time, with a maximum potential capacity of 60 MGD. Throughout the incremental expansion period, the Operations and Maintenance contract will be adjusted as needed to accommodate the changing requirements and milestones of the Progressive Design-Build project. While the PDB project team will retain responsibility for all construction activities, modifications to this contract will undergo review and receive appropriate authorization when necessary. 

There will be a sixty (60) day phase in/outperiod. The Contract will consist of a Base Year from date of award 6March 30, 2027 plus four (4) one-year option periods.  This is anticipated to be an unrestricted procurement under the NAICS code 221320 (Sewage Treatment Facilities), the small business size standard is $50 million. 

An Industry day/s is anticipaited to be held at the South Bay International Wastewater Treatment Plant the week of 11 August 2025 to provide industry an opertunity to provide feedback during the market research phase. Those attending need contract Philip (Phil) Johnson @ philip.johnson@ibwc.gov by 31 July 2025. 

The solicitation is expected to be posted on or about September 2025 (this is a target date which may slip or change; if the solicitation is not posted on Federal Business Opportunities by 01 October 2025 to that is because the solicitation is not available for posting).  

Draft PWS and Attachments (attached) 

PWS attached  

List of Attachments: 

  1. SOM- Submittal Registry (aka deliverables) 

  1. Quality Assurance Surveillance Plan (QASP) 

  1. Required Performance Metrics (RPM) 

  1. NPDES Permit R9-2023-0009 

  1. List of Permits 

  1. SBIWTP Asset Registry  

  1. SBIWTP Condition Assessment Report- January 2024 

  1. SBIWTP Asset Maintenance Schedule 

  1. SBIWTP Capital Project List- April 2024 

  1. Monthly Chemical Dosage from March 2024- March 2025 

  1. Canyon Collector Daily Inspection Template 

  1. NPDES Annual Biosolids Report 2024 

  1. SBIWTP O&M Manual 

  1. SBIWTP System Security Plan 

  1. NIST SP 800-17r3 

  1. Plans/Drawings 

  1. Maps 

  1. NIST SP 199 

  1. SBIWTP Sequence of Operations (SOO) 

  1. Wage Determination (WD) 

  1. Request for Information (RFI) Tracker 

REQUEST FOR FEEDBACK:

The information gathered from the sources sought, industry day/s, and these questions may be used as market research to assist the Government in determining and shaping various aspects of the acquisition process. This includes, but is not limited to, the development of solicitation documents, source selection criteria, contract type, Performance Work Statement (PWS), Quality Assurance Surveillance Plan (QASP), and other acquisition-related documents. The responses provided will help the Government understand industry capabilities, identify potential risks, and develop strategies to ensure successful project execution. Your participation and input are greatly appreciated.

Cost:

  • What are the potential cost drivers for operating and maintaining the South Bay International Wastewater Treatment Plant (SBIWTP)?
  • How will costs be affected during the temporary facility's increase to 35MGD and the permanent expansion to 50-60MGD? How can these cost risks be managed and mitigated?
  • What strategies can be used to manage and mitigate unexpected costs associated with operating and maintaining the plant? How would these strategies change during the increase in temporary capacity from 25MGD to 35MGD and eventually to 50-60MGD?
  • What measures can be implemented to help potential contractors manage and mitigate unexpected costs associated with operating and maintaining the plant?

Technical:

  • What technical challenges do you anticipate in operating and maintaining the plant? What strategies could be used to manage and mitigate these risks?
  • What technical challenges do you anticipate during the temporary facility's increase to 35MGD and the permanent expansion to 50-60MGD?
  • Can you share your experience with similar projects and the lessons learned that could be applied to this project?
  • Are there any other technical risks that are unique to the O&M services for the SBIWTP?

Performance:

  • What performance metrics would you use to measure the success of the operation and maintenance of the plant?
  • How would you ensure that your projects meet performance standards?
  • What are the key resources required to perform these services for a project of this size and complexity?
  • What other performance risks do you see that may be unique to the O&M services for the SBIWTP?

Schedule:

  • What are the key milestones and timelines for the phase-in period? How will you ensure an effective transition?
  • How would you manage any delays or disruptions that may occur during the performance? What contingency plans would you have in place to address these issues?
  • What strategies could you implement to ensure the timely completion of tasks/projects?
  • What other schedule risks do you see as unique to the O&M services for the SBIWTP?

Additional Feedback Requested:

  • Clarity and completeness of PWS and attachments
  • Feasibility of the requirements
  • Suggestions for improvements
  • Feedback on the contract type (FFP plus Cost Reimbursement, or FFP only). Please provide a recommendation on the most suitable type of contract for this requirement.
  • Risks and drawbacks
  • Can your company extend services to the NIWTP in Nogales, AZ? If so, please explain.
  • Contractor’s experience working with FAR and Government contracts that would be considered the same or similar in size, scope, and complexity
  • Contractor’s experience in WWTP within the last 5-7 years
  • Would your company intend to form a Joint Venture, partnership, LLC, or subcontract portions of work to satisfy the requirements listed in this Sources Sought?
  • Will the majority of the work be subcontracted?
  • Experience working internationally
  • Experience working with sediment and waste removal
  • Experience with Supervisory Control and Data Acquisition (SCADA) systems for WWTP
Update #5 ·

Note - PWS added as attachment. Amendment 002 is adding updating Clauses and changing dates below:

Key Deadlines & Due Dates

Questions & Clarifications

•             Deadline to Submit Questions changed to 10:00 AM PST (11:00 AM MST), November 26, 2025

Proposal Submission

•             SharePoint Access Request Deadline changed to December 5, 2025, 12:00 PM MST

•             SharePoint Upload Window Opens changed to December 8, 2025

Solicitation Close

•             Solicitation Closing Date changed to December 22, 2025, 5:00 PM MT 

Questions shall be submitted via- SharePoint: request access to philip.johnson@ibwc.gov, once access is requested you will receive confirmation. Each vendor must submit all solicitation and site visit questions in writing by 10:00 AM PST (11:00 AM MST) on November 17, 2025 referencing Solicitation No. 191BWC26R0001.

Only the individual who requested access will be granted permission to the vendor’s designated Q&A folder. Access links are unique and must not be shared or forwarded.

All questions must be uploaded directly to that folder, then an email notification must be sent to Philip.Johnson@ibwc.gov confirming submission.

Each question must identify the specific solicitation page or section it refers to.

File Naming Convention
File name must follow this format:
[YYYYMMDD]_[CompanyName]_191BWC26R0001_QA.docx
Example: 20251105_ABC_Engineering_191BWC26R0001_QA.docx

Submission Requirements
1. Upload one consolidated document per company.
2. Use Word or Excel format only.
3. Include page or section references for each question.
4. Do not include photos or unrelated attachments.
5. Questions will be answered publicly through the SAM.gov.

 

------------------------------------------------

Attachment 14 was revoked 

Amendment 001 - Changing Site Visit date to Friday, 7 November 2025

Current contract 191BWC20C0003 

INTRODUCTION

The United States Section of the International Boundary and Water Commission (USIBWC), has a requirement for contract for the operation and maintenance (O&M) of the South Bay International Wastewater Treatment Plant (SBIWTP) and facilities located in San Diego County, California.  Type of contract, Firm Fixed Priced, Cost Reimbursable, Hybrid, etc. to be determined.  

The Contractor shall provide, all labor, material, management (including bi-national participation with Mexico), and other resources required to perform full-service O&M of the SBIWTP and its conveyance system, plus Canyon Collectors, Pump Stations, and South Bay Land Outfall (SBLO). Full service operation and maintenance is defined as complete facility operation and maintenance, including but not limited to providing day-to-day contract management, planning, supervision, administration, personnel; plant influent and effluent sampling and laboratory testing; equipment operation, maintenance, servicing, repair and replacement; system monitoring and operation; data recording, markups of plant as built, management and reporting; quality control; capital improvements; vehicles and vehicle fleet management, operation, maintenance and repair; housekeeping; grounds maintenance; consumable supplies including chemicals, and other services related to the operation and maintenance of the SBIWTP.   

BACKGROUND  

The SBIWTP is a twenty-five (25) million gallon per day (MGD) wastewater treatment plant located at 2995 Clearwater Way, in San Diego, San Diego County, California, , north of the International Boundary, and near the intersections of Monument and Dairy Mart Roads.  Construction of the plant’s advanced primary treatment phase was completed in September 1997, and construction of the secondary treatment phase was completed in January 2011.  The plant is treating wastewater originating in Tijuana, Baja California, Mexico and the SBIWTP is operated under the authority of the United States Section, International Boundary and Water Commission (USIBWC).  An average of twenty five million gallons per day (25 MGD) of effluent is being discharged through the South Bay Ocean Outfall (SBOO), and is subject to the requirements of the National Pollutant Discharge Elimination System (NPDES) Permit, Permit Number CA0108928, Order Number R9-2023-0009; the California Regional Water Quality Control Board (CRWQCB) Monitoring and Reporting Program, Number: R9-2023-0009; and the California Ocean Plan.   

In 2024, USIBWC awarded a $600M contract for the design and construction of the rehabilitation and expansion of the SBIWTP. USIBWC awarded the contract to PCL Construction (PCL) of Long Beach, California. In turn, PCL selected Stantec Consulting Services, Inc. (Stantec), of San Diego, as the design firm. The project was awarded using the Progressive Design-Build (PDB) contract delivery method consistent with Government contracting practices and regulations. 

Expansion of Capacity 

According to USIBWC's timeline, the design process of the plant’s expansion will unfold in strategic phases, with the complete plant expansion targeted for completion by 2027. The initial phase of the plant’s expansion encompasses design development for the entire SBIWTP scope, while subsequent phases will implement rehabilitation efforts concurrent with the ongoing expansion work. 

During the expansion, the PDB team will work closely with the future SBIWTP Operator of this Contract to rehabilitate the plant while also expanding it. The USIBWC and PDB team aims to enhance the plant's treatment capacity from the current 25 MGD to 35 MGD by 2025, with a subsequent expansion to 60 MGD projected for completion by 2027. This will likely be done in incremental increases of, for example, 10 MGD or 20 MGD at a time, with a maximum potential capacity of 60 MGD. Throughout the incremental expansion period, the Operations and Maintenance contract will be adjusted as needed to accommodate the changing requirements and milestones of the Progressive Design-Build project. While the PDB project team will retain responsibility for all construction activities, modifications to this contract will undergo review and receive appropriate authorization when necessary. 

There will be a sixty (60) day phase in/outperiod. The Contract will consist of a Base Year from date of award 6March 30, 2027 plus four (4) one-year option periods.  This is anticipated to be an unrestricted procurement under the NAICS code 221320 (Sewage Treatment Facilities), the small business size standard is $50 million. 

An Industry day/s is anticipaited to be held at the South Bay International Wastewater Treatment Plant the week of 11 August 2025 to provide industry an opertunity to provide feedback during the market research phase. Those attending need contract Philip (Phil) Johnson @ philip.johnson@ibwc.gov by 31 July 2025. 

The solicitation is expected to be posted on or about September 2025 (this is a target date which may slip or change; if the solicitation is not posted on Federal Business Opportunities by 01 October 2025 to that is because the solicitation is not available for posting).  

Draft PWS and Attachments (attached) 

PWS attached  

List of Attachments: 

  1. SOM- Submittal Registry (aka deliverables) 

  1. Quality Assurance Surveillance Plan (QASP) 

  1. Required Performance Metrics (RPM) 

  1. NPDES Permit R9-2023-0009 

  1. List of Permits 

  1. SBIWTP Asset Registry  

  1. SBIWTP Condition Assessment Report- January 2024 

  1. SBIWTP Asset Maintenance Schedule 

  1. SBIWTP Capital Project List- April 2024 

  1. Monthly Chemical Dosage from March 2024- March 2025 

  1. Canyon Collector Daily Inspection Template 

  1. NPDES Annual Biosolids Report 2024 

  1. SBIWTP O&M Manual 

  1. SBIWTP System Security Plan 

  1. NIST SP 800-17r3 

  1. Plans/Drawings 

  1. Maps 

  1. NIST SP 199 

  1. SBIWTP Sequence of Operations (SOO) 

  1. Wage Determination (WD) 

  1. Request for Information (RFI) Tracker 

REQUEST FOR FEEDBACK:

The information gathered from the sources sought, industry day/s, and these questions may be used as market research to assist the Government in determining and shaping various aspects of the acquisition process. This includes, but is not limited to, the development of solicitation documents, source selection criteria, contract type, Performance Work Statement (PWS), Quality Assurance Surveillance Plan (QASP), and other acquisition-related documents. The responses provided will help the Government understand industry capabilities, identify potential risks, and develop strategies to ensure successful project execution. Your participation and input are greatly appreciated.

Cost:

  • What are the potential cost drivers for operating and maintaining the South Bay International Wastewater Treatment Plant (SBIWTP)?
  • How will costs be affected during the temporary facility's increase to 35MGD and the permanent expansion to 50-60MGD? How can these cost risks be managed and mitigated?
  • What strategies can be used to manage and mitigate unexpected costs associated with operating and maintaining the plant? How would these strategies change during the increase in temporary capacity from 25MGD to 35MGD and eventually to 50-60MGD?
  • What measures can be implemented to help potential contractors manage and mitigate unexpected costs associated with operating and maintaining the plant?

Technical:

  • What technical challenges do you anticipate in operating and maintaining the plant? What strategies could be used to manage and mitigate these risks?
  • What technical challenges do you anticipate during the temporary facility's increase to 35MGD and the permanent expansion to 50-60MGD?
  • Can you share your experience with similar projects and the lessons learned that could be applied to this project?
  • Are there any other technical risks that are unique to the O&M services for the SBIWTP?

Performance:

  • What performance metrics would you use to measure the success of the operation and maintenance of the plant?
  • How would you ensure that your projects meet performance standards?
  • What are the key resources required to perform these services for a project of this size and complexity?
  • What other performance risks do you see that may be unique to the O&M services for the SBIWTP?

Schedule:

  • What are the key milestones and timelines for the phase-in period? How will you ensure an effective transition?
  • How would you manage any delays or disruptions that may occur during the performance? What contingency plans would you have in place to address these issues?
  • What strategies could you implement to ensure the timely completion of tasks/projects?
  • What other schedule risks do you see as unique to the O&M services for the SBIWTP?

Additional Feedback Requested:

  • Clarity and completeness of PWS and attachments
  • Feasibility of the requirements
  • Suggestions for improvements
  • Feedback on the contract type (FFP plus Cost Reimbursement, or FFP only). Please provide a recommendation on the most suitable type of contract for this requirement.
  • Risks and drawbacks
  • Can your company extend services to the NIWTP in Nogales, AZ? If so, please explain.
  • Contractor’s experience working with FAR and Government contracts that would be considered the same or similar in size, scope, and complexity
  • Contractor’s experience in WWTP within the last 5-7 years
  • Would your company intend to form a Joint Venture, partnership, LLC, or subcontract portions of work to satisfy the requirements listed in this Sources Sought?
  • Will the majority of the work be subcontracted?
  • Experience working internationally
  • Experience working with sediment and waste removal
  • Experience with Supervisory Control and Data Acquisition (SCADA) systems for WWTP
Update #4 ·

Attachment 14 was revoved 

Amendment 001 - Changing Site Visit date to Friday, 7 November 2025

Current contract 191BWC20C0003 

INTRODUCTION

The United States Section of the International Boundary and Water Commission (USIBWC), has a requirement for contract for the operation and maintenance (O&M) of the South Bay International Wastewater Treatment Plant (SBIWTP) and facilities located in San Diego County, California.  Type of contract, Firm Fixed Priced, Cost Reimbursable, Hybrid, etc. to be determined.  

The Contractor shall provide, all labor, material, management (including bi-national participation with Mexico), and other resources required to perform full-service O&M of the SBIWTP and its conveyance system, plus Canyon Collectors, Pump Stations, and South Bay Land Outfall (SBLO). Full service operation and maintenance is defined as complete facility operation and maintenance, including but not limited to providing day-to-day contract management, planning, supervision, administration, personnel; plant influent and effluent sampling and laboratory testing; equipment operation, maintenance, servicing, repair and replacement; system monitoring and operation; data recording, markups of plant as built, management and reporting; quality control; capital improvements; vehicles and vehicle fleet management, operation, maintenance and repair; housekeeping; grounds maintenance; consumable supplies including chemicals, and other services related to the operation and maintenance of the SBIWTP.   

BACKGROUND  

The SBIWTP is a twenty-five (25) million gallon per day (MGD) wastewater treatment plant located at 2995 Clearwater Way, in San Diego, San Diego County, California, , north of the International Boundary, and near the intersections of Monument and Dairy Mart Roads.  Construction of the plant’s advanced primary treatment phase was completed in September 1997, and construction of the secondary treatment phase was completed in January 2011.  The plant is treating wastewater originating in Tijuana, Baja California, Mexico and the SBIWTP is operated under the authority of the United States Section, International Boundary and Water Commission (USIBWC).  An average of twenty five million gallons per day (25 MGD) of effluent is being discharged through the South Bay Ocean Outfall (SBOO), and is subject to the requirements of the National Pollutant Discharge Elimination System (NPDES) Permit, Permit Number CA0108928, Order Number R9-2023-0009; the California Regional Water Quality Control Board (CRWQCB) Monitoring and Reporting Program, Number: R9-2023-0009; and the California Ocean Plan.   

In 2024, USIBWC awarded a $600M contract for the design and construction of the rehabilitation and expansion of the SBIWTP. USIBWC awarded the contract to PCL Construction (PCL) of Long Beach, California. In turn, PCL selected Stantec Consulting Services, Inc. (Stantec), of San Diego, as the design firm. The project was awarded using the Progressive Design-Build (PDB) contract delivery method consistent with Government contracting practices and regulations. 

Expansion of Capacity 

According to USIBWC's timeline, the design process of the plant’s expansion will unfold in strategic phases, with the complete plant expansion targeted for completion by 2027. The initial phase of the plant’s expansion encompasses design development for the entire SBIWTP scope, while subsequent phases will implement rehabilitation efforts concurrent with the ongoing expansion work. 

During the expansion, the PDB team will work closely with the future SBIWTP Operator of this Contract to rehabilitate the plant while also expanding it. The USIBWC and PDB team aims to enhance the plant's treatment capacity from the current 25 MGD to 35 MGD by 2025, with a subsequent expansion to 60 MGD projected for completion by 2027. This will likely be done in incremental increases of, for example, 10 MGD or 20 MGD at a time, with a maximum potential capacity of 60 MGD. Throughout the incremental expansion period, the Operations and Maintenance contract will be adjusted as needed to accommodate the changing requirements and milestones of the Progressive Design-Build project. While the PDB project team will retain responsibility for all construction activities, modifications to this contract will undergo review and receive appropriate authorization when necessary. 

There will be a sixty (60) day phase in/outperiod. The Contract will consist of a Base Year from date of award 6March 30, 2027 plus four (4) one-year option periods.  This is anticipated to be an unrestricted procurement under the NAICS code 221320 (Sewage Treatment Facilities), the small business size standard is $50 million. 

An Industry day/s is anticipaited to be held at the South Bay International Wastewater Treatment Plant the week of 11 August 2025 to provide industry an opertunity to provide feedback during the market research phase. Those attending need contract Philip (Phil) Johnson @ philip.johnson@ibwc.gov by 31 July 2025. 

The solicitation is expected to be posted on or about September 2025 (this is a target date which may slip or change; if the solicitation is not posted on Federal Business Opportunities by 01 October 2025 to that is because the solicitation is not available for posting).  

Draft PWS and Attachments (attached) 

PWS attached  

List of Attachments: 

  1. SOM- Submittal Registry (aka deliverables) 

  1. Quality Assurance Surveillance Plan (QASP) 

  1. Required Performance Metrics (RPM) 

  1. NPDES Permit R9-2023-0009 

  1. List of Permits 

  1. SBIWTP Asset Registry  

  1. SBIWTP Condition Assessment Report- January 2024 

  1. SBIWTP Asset Maintenance Schedule 

  1. SBIWTP Capital Project List- April 2024 

  1. Monthly Chemical Dosage from March 2024- March 2025 

  1. Canyon Collector Daily Inspection Template 

  1. NPDES Annual Biosolids Report 2024 

  1. SBIWTP O&M Manual 

  1. SBIWTP System Security Plan 

  1. NIST SP 800-17r3 

  1. Plans/Drawings 

  1. Maps 

  1. NIST SP 199 

  1. SBIWTP Sequence of Operations (SOO) 

  1. Wage Determination (WD) 

  1. Request for Information (RFI) Tracker 

REQUEST FOR FEEDBACK:

The information gathered from the sources sought, industry day/s, and these questions may be used as market research to assist the Government in determining and shaping various aspects of the acquisition process. This includes, but is not limited to, the development of solicitation documents, source selection criteria, contract type, Performance Work Statement (PWS), Quality Assurance Surveillance Plan (QASP), and other acquisition-related documents. The responses provided will help the Government understand industry capabilities, identify potential risks, and develop strategies to ensure successful project execution. Your participation and input are greatly appreciated.

Cost:

  • What are the potential cost drivers for operating and maintaining the South Bay International Wastewater Treatment Plant (SBIWTP)?
  • How will costs be affected during the temporary facility's increase to 35MGD and the permanent expansion to 50-60MGD? How can these cost risks be managed and mitigated?
  • What strategies can be used to manage and mitigate unexpected costs associated with operating and maintaining the plant? How would these strategies change during the increase in temporary capacity from 25MGD to 35MGD and eventually to 50-60MGD?
  • What measures can be implemented to help potential contractors manage and mitigate unexpected costs associated with operating and maintaining the plant?

Technical:

  • What technical challenges do you anticipate in operating and maintaining the plant? What strategies could be used to manage and mitigate these risks?
  • What technical challenges do you anticipate during the temporary facility's increase to 35MGD and the permanent expansion to 50-60MGD?
  • Can you share your experience with similar projects and the lessons learned that could be applied to this project?
  • Are there any other technical risks that are unique to the O&M services for the SBIWTP?

Performance:

  • What performance metrics would you use to measure the success of the operation and maintenance of the plant?
  • How would you ensure that your projects meet performance standards?
  • What are the key resources required to perform these services for a project of this size and complexity?
  • What other performance risks do you see that may be unique to the O&M services for the SBIWTP?

Schedule:

  • What are the key milestones and timelines for the phase-in period? How will you ensure an effective transition?
  • How would you manage any delays or disruptions that may occur during the performance? What contingency plans would you have in place to address these issues?
  • What strategies could you implement to ensure the timely completion of tasks/projects?
  • What other schedule risks do you see as unique to the O&M services for the SBIWTP?

Additional Feedback Requested:

  • Clarity and completeness of PWS and attachments
  • Feasibility of the requirements
  • Suggestions for improvements
  • Feedback on the contract type (FFP plus Cost Reimbursement, or FFP only). Please provide a recommendation on the most suitable type of contract for this requirement.
  • Risks and drawbacks
  • Can your company extend services to the NIWTP in Nogales, AZ? If so, please explain.
  • Contractor’s experience working with FAR and Government contracts that would be considered the same or similar in size, scope, and complexity
  • Contractor’s experience in WWTP within the last 5-7 years
  • Would your company intend to form a Joint Venture, partnership, LLC, or subcontract portions of work to satisfy the requirements listed in this Sources Sought?
  • Will the majority of the work be subcontracted?
  • Experience working internationally
  • Experience working with sediment and waste removal
  • Experience with Supervisory Control and Data Acquisition (SCADA) systems for WWTP
Update #3 ·

Amendment 001 - Changing Site Visit date to Friday, 7 November 2025

Current contract 191BWC20C0003 

INTRODUCTION

The United States Section of the International Boundary and Water Commission (USIBWC), has a requirement for contract for the operation and maintenance (O&M) of the South Bay International Wastewater Treatment Plant (SBIWTP) and facilities located in San Diego County, California.  Type of contract, Firm Fixed Priced, Cost Reimbursable, Hybrid, etc. to be determined.  

The Contractor shall provide, all labor, material, management (including bi-national participation with Mexico), and other resources required to perform full-service O&M of the SBIWTP and its conveyance system, plus Canyon Collectors, Pump Stations, and South Bay Land Outfall (SBLO). Full service operation and maintenance is defined as complete facility operation and maintenance, including but not limited to providing day-to-day contract management, planning, supervision, administration, personnel; plant influent and effluent sampling and laboratory testing; equipment operation, maintenance, servicing, repair and replacement; system monitoring and operation; data recording, markups of plant as built, management and reporting; quality control; capital improvements; vehicles and vehicle fleet management, operation, maintenance and repair; housekeeping; grounds maintenance; consumable supplies including chemicals, and other services related to the operation and maintenance of the SBIWTP.   

BACKGROUND  

The SBIWTP is a twenty-five (25) million gallon per day (MGD) wastewater treatment plant located at 2995 Clearwater Way, in San Diego, San Diego County, California, , north of the International Boundary, and near the intersections of Monument and Dairy Mart Roads.  Construction of the plant’s advanced primary treatment phase was completed in September 1997, and construction of the secondary treatment phase was completed in January 2011.  The plant is treating wastewater originating in Tijuana, Baja California, Mexico and the SBIWTP is operated under the authority of the United States Section, International Boundary and Water Commission (USIBWC).  An average of twenty five million gallons per day (25 MGD) of effluent is being discharged through the South Bay Ocean Outfall (SBOO), and is subject to the requirements of the National Pollutant Discharge Elimination System (NPDES) Permit, Permit Number CA0108928, Order Number R9-2023-0009; the California Regional Water Quality Control Board (CRWQCB) Monitoring and Reporting Program, Number: R9-2023-0009; and the California Ocean Plan.   

In 2024, USIBWC awarded a $600M contract for the design and construction of the rehabilitation and expansion of the SBIWTP. USIBWC awarded the contract to PCL Construction (PCL) of Long Beach, California. In turn, PCL selected Stantec Consulting Services, Inc. (Stantec), of San Diego, as the design firm. The project was awarded using the Progressive Design-Build (PDB) contract delivery method consistent with Government contracting practices and regulations. 

Expansion of Capacity 

According to USIBWC's timeline, the design process of the plant’s expansion will unfold in strategic phases, with the complete plant expansion targeted for completion by 2027. The initial phase of the plant’s expansion encompasses design development for the entire SBIWTP scope, while subsequent phases will implement rehabilitation efforts concurrent with the ongoing expansion work. 

During the expansion, the PDB team will work closely with the future SBIWTP Operator of this Contract to rehabilitate the plant while also expanding it. The USIBWC and PDB team aims to enhance the plant's treatment capacity from the current 25 MGD to 35 MGD by 2025, with a subsequent expansion to 60 MGD projected for completion by 2027. This will likely be done in incremental increases of, for example, 10 MGD or 20 MGD at a time, with a maximum potential capacity of 60 MGD. Throughout the incremental expansion period, the Operations and Maintenance contract will be adjusted as needed to accommodate the changing requirements and milestones of the Progressive Design-Build project. While the PDB project team will retain responsibility for all construction activities, modifications to this contract will undergo review and receive appropriate authorization when necessary. 

There will be a sixty (60) day phase in/outperiod. The Contract will consist of a Base Year from date of award 6March 30, 2027 plus four (4) one-year option periods.  This is anticipated to be an unrestricted procurement under the NAICS code 221320 (Sewage Treatment Facilities), the small business size standard is $50 million. 

An Industry day/s is anticipaited to be held at the South Bay International Wastewater Treatment Plant the week of 11 August 2025 to provide industry an opertunity to provide feedback during the market research phase. Those attending need contract Philip (Phil) Johnson @ philip.johnson@ibwc.gov by 31 July 2025. 

The solicitation is expected to be posted on or about September 2025 (this is a target date which may slip or change; if the solicitation is not posted on Federal Business Opportunities by 01 October 2025 to that is because the solicitation is not available for posting).  

Draft PWS and Attachments (attached) 

PWS attached  

List of Attachments: 

  1. SOM- Submittal Registry (aka deliverables) 

  1. Quality Assurance Surveillance Plan (QASP) 

  1. Required Performance Metrics (RPM) 

  1. NPDES Permit R9-2023-0009 

  1. List of Permits 

  1. SBIWTP Asset Registry  

  1. SBIWTP Condition Assessment Report- January 2024 

  1. SBIWTP Asset Maintenance Schedule 

  1. SBIWTP Capital Project List- April 2024 

  1. Monthly Chemical Dosage from March 2024- March 2025 

  1. Canyon Collector Daily Inspection Template 

  1. NPDES Annual Biosolids Report 2024 

  1. SBIWTP O&M Manual 

  1. SBIWTP System Security Plan 

  1. NIST SP 800-17r3 

  1. Plans/Drawings 

  1. Maps 

  1. NIST SP 199 

  1. SBIWTP Sequence of Operations (SOO) 

  1. Wage Determination (WD) 

  1. Request for Information (RFI) Tracker 

REQUEST FOR FEEDBACK:

The information gathered from the sources sought, industry day/s, and these questions may be used as market research to assist the Government in determining and shaping various aspects of the acquisition process. This includes, but is not limited to, the development of solicitation documents, source selection criteria, contract type, Performance Work Statement (PWS), Quality Assurance Surveillance Plan (QASP), and other acquisition-related documents. The responses provided will help the Government understand industry capabilities, identify potential risks, and develop strategies to ensure successful project execution. Your participation and input are greatly appreciated.

Cost:

  • What are the potential cost drivers for operating and maintaining the South Bay International Wastewater Treatment Plant (SBIWTP)?
  • How will costs be affected during the temporary facility's increase to 35MGD and the permanent expansion to 50-60MGD? How can these cost risks be managed and mitigated?
  • What strategies can be used to manage and mitigate unexpected costs associated with operating and maintaining the plant? How would these strategies change during the increase in temporary capacity from 25MGD to 35MGD and eventually to 50-60MGD?
  • What measures can be implemented to help potential contractors manage and mitigate unexpected costs associated with operating and maintaining the plant?

Technical:

  • What technical challenges do you anticipate in operating and maintaining the plant? What strategies could be used to manage and mitigate these risks?
  • What technical challenges do you anticipate during the temporary facility's increase to 35MGD and the permanent expansion to 50-60MGD?
  • Can you share your experience with similar projects and the lessons learned that could be applied to this project?
  • Are there any other technical risks that are unique to the O&M services for the SBIWTP?

Performance:

  • What performance metrics would you use to measure the success of the operation and maintenance of the plant?
  • How would you ensure that your projects meet performance standards?
  • What are the key resources required to perform these services for a project of this size and complexity?
  • What other performance risks do you see that may be unique to the O&M services for the SBIWTP?

Schedule:

  • What are the key milestones and timelines for the phase-in period? How will you ensure an effective transition?
  • How would you manage any delays or disruptions that may occur during the performance? What contingency plans would you have in place to address these issues?
  • What strategies could you implement to ensure the timely completion of tasks/projects?
  • What other schedule risks do you see as unique to the O&M services for the SBIWTP?

Additional Feedback Requested:

  • Clarity and completeness of PWS and attachments
  • Feasibility of the requirements
  • Suggestions for improvements
  • Feedback on the contract type (FFP plus Cost Reimbursement, or FFP only). Please provide a recommendation on the most suitable type of contract for this requirement.
  • Risks and drawbacks
  • Can your company extend services to the NIWTP in Nogales, AZ? If so, please explain.
  • Contractor’s experience working with FAR and Government contracts that would be considered the same or similar in size, scope, and complexity
  • Contractor’s experience in WWTP within the last 5-7 years
  • Would your company intend to form a Joint Venture, partnership, LLC, or subcontract portions of work to satisfy the requirements listed in this Sources Sought?
  • Will the majority of the work be subcontracted?
  • Experience working internationally
  • Experience working with sediment and waste removal
  • Experience with Supervisory Control and Data Acquisition (SCADA) systems for WWTP
Update #2 ·

Current contract 191BWC20C0003 

INTRODUCTION

The United States Section of the International Boundary and Water Commission (USIBWC), has a requirement for contract for the operation and maintenance (O&M) of the South Bay International Wastewater Treatment Plant (SBIWTP) and facilities located in San Diego County, California.  Type of contract, Firm Fixed Priced, Cost Reimbursable, Hybrid, etc. to be determined.  

The Contractor shall provide, all labor, material, management (including bi-national participation with Mexico), and other resources required to perform full-service O&M of the SBIWTP and its conveyance system, plus Canyon Collectors, Pump Stations, and South Bay Land Outfall (SBLO). Full service operation and maintenance is defined as complete facility operation and maintenance, including but not limited to providing day-to-day contract management, planning, supervision, administration, personnel; plant influent and effluent sampling and laboratory testing; equipment operation, maintenance, servicing, repair and replacement; system monitoring and operation; data recording, markups of plant as built, management and reporting; quality control; capital improvements; vehicles and vehicle fleet management, operation, maintenance and repair; housekeeping; grounds maintenance; consumable supplies including chemicals, and other services related to the operation and maintenance of the SBIWTP.   

BACKGROUND  

The SBIWTP is a twenty-five (25) million gallon per day (MGD) wastewater treatment plant located at 2995 Clearwater Way, in San Diego, San Diego County, California, , north of the International Boundary, and near the intersections of Monument and Dairy Mart Roads.  Construction of the plant’s advanced primary treatment phase was completed in September 1997, and construction of the secondary treatment phase was completed in January 2011.  The plant is treating wastewater originating in Tijuana, Baja California, Mexico and the SBIWTP is operated under the authority of the United States Section, International Boundary and Water Commission (USIBWC).  An average of twenty five million gallons per day (25 MGD) of effluent is being discharged through the South Bay Ocean Outfall (SBOO), and is subject to the requirements of the National Pollutant Discharge Elimination System (NPDES) Permit, Permit Number CA0108928, Order Number R9-2023-0009; the California Regional Water Quality Control Board (CRWQCB) Monitoring and Reporting Program, Number: R9-2023-0009; and the California Ocean Plan.   

In 2024, USIBWC awarded a $600M contract for the design and construction of the rehabilitation and expansion of the SBIWTP. USIBWC awarded the contract to PCL Construction (PCL) of Long Beach, California. In turn, PCL selected Stantec Consulting Services, Inc. (Stantec), of San Diego, as the design firm. The project was awarded using the Progressive Design-Build (PDB) contract delivery method consistent with Government contracting practices and regulations. 

Expansion of Capacity 

According to USIBWC's timeline, the design process of the plant’s expansion will unfold in strategic phases, with the complete plant expansion targeted for completion by 2027. The initial phase of the plant’s expansion encompasses design development for the entire SBIWTP scope, while subsequent phases will implement rehabilitation efforts concurrent with the ongoing expansion work. 

During the expansion, the PDB team will work closely with the future SBIWTP Operator of this Contract to rehabilitate the plant while also expanding it. The USIBWC and PDB team aims to enhance the plant's treatment capacity from the current 25 MGD to 35 MGD by 2025, with a subsequent expansion to 60 MGD projected for completion by 2027. This will likely be done in incremental increases of, for example, 10 MGD or 20 MGD at a time, with a maximum potential capacity of 60 MGD. Throughout the incremental expansion period, the Operations and Maintenance contract will be adjusted as needed to accommodate the changing requirements and milestones of the Progressive Design-Build project. While the PDB project team will retain responsibility for all construction activities, modifications to this contract will undergo review and receive appropriate authorization when necessary. 

There will be a sixty (60) day phase in/outperiod. The Contract will consist of a Base Year from date of award 6March 30, 2027 plus four (4) one-year option periods.  This is anticipated to be an unrestricted procurement under the NAICS code 221320 (Sewage Treatment Facilities), the small business size standard is $50 million. 

An Industry day/s is anticipaited to be held at the South Bay International Wastewater Treatment Plant the week of 11 August 2025 to provide industry an opertunity to provide feedback during the market research phase. Those attending need contract Philip (Phil) Johnson @ philip.johnson@ibwc.gov by 31 July 2025. 

The solicitation is expected to be posted on or about September 2025 (this is a target date which may slip or change; if the solicitation is not posted on Federal Business Opportunities by 01 October 2025 to that is because the solicitation is not available for posting).  

Draft PWS and Attachments (attached) 

PWS attached  

List of Attachments: 

  1. SOM- Submittal Registry (aka deliverables) 

  1. Quality Assurance Surveillance Plan (QASP) 

  1. Required Performance Metrics (RPM) 

  1. NPDES Permit R9-2023-0009 

  1. List of Permits 

  1. SBIWTP Asset Registry  

  1. SBIWTP Condition Assessment Report- January 2024 

  1. SBIWTP Asset Maintenance Schedule 

  1. SBIWTP Capital Project List- April 2024 

  1. Monthly Chemical Dosage from March 2024- March 2025 

  1. Canyon Collector Daily Inspection Template 

  1. NPDES Annual Biosolids Report 2024 

  1. SBIWTP O&M Manual 

  1. SBIWTP System Security Plan 

  1. NIST SP 800-17r3 

  1. Plans/Drawings 

  1. Maps 

  1. NIST SP 199 

  1. SBIWTP Sequence of Operations (SOO) 

  1. Wage Determination (WD) 

  1. Request for Information (RFI) Tracker 

REQUEST FOR FEEDBACK:

The information gathered from the sources sought, industry day/s, and these questions may be used as market research to assist the Government in determining and shaping various aspects of the acquisition process. This includes, but is not limited to, the development of solicitation documents, source selection criteria, contract type, Performance Work Statement (PWS), Quality Assurance Surveillance Plan (QASP), and other acquisition-related documents. The responses provided will help the Government understand industry capabilities, identify potential risks, and develop strategies to ensure successful project execution. Your participation and input are greatly appreciated.

Cost:

  • What are the potential cost drivers for operating and maintaining the South Bay International Wastewater Treatment Plant (SBIWTP)?
  • How will costs be affected during the temporary facility's increase to 35MGD and the permanent expansion to 50-60MGD? How can these cost risks be managed and mitigated?
  • What strategies can be used to manage and mitigate unexpected costs associated with operating and maintaining the plant? How would these strategies change during the increase in temporary capacity from 25MGD to 35MGD and eventually to 50-60MGD?
  • What measures can be implemented to help potential contractors manage and mitigate unexpected costs associated with operating and maintaining the plant?

Technical:

  • What technical challenges do you anticipate in operating and maintaining the plant? What strategies could be used to manage and mitigate these risks?
  • What technical challenges do you anticipate during the temporary facility's increase to 35MGD and the permanent expansion to 50-60MGD?
  • Can you share your experience with similar projects and the lessons learned that could be applied to this project?
  • Are there any other technical risks that are unique to the O&M services for the SBIWTP?

Performance:

  • What performance metrics would you use to measure the success of the operation and maintenance of the plant?
  • How would you ensure that your projects meet performance standards?
  • What are the key resources required to perform these services for a project of this size and complexity?
  • What other performance risks do you see that may be unique to the O&M services for the SBIWTP?

Schedule:

  • What are the key milestones and timelines for the phase-in period? How will you ensure an effective transition?
  • How would you manage any delays or disruptions that may occur during the performance? What contingency plans would you have in place to address these issues?
  • What strategies could you implement to ensure the timely completion of tasks/projects?
  • What other schedule risks do you see as unique to the O&M services for the SBIWTP?

Additional Feedback Requested:

  • Clarity and completeness of PWS and attachments
  • Feasibility of the requirements
  • Suggestions for improvements
  • Feedback on the contract type (FFP plus Cost Reimbursement, or FFP only). Please provide a recommendation on the most suitable type of contract for this requirement.
  • Risks and drawbacks
  • Can your company extend services to the NIWTP in Nogales, AZ? If so, please explain.
  • Contractor’s experience working with FAR and Government contracts that would be considered the same or similar in size, scope, and complexity
  • Contractor’s experience in WWTP within the last 5-7 years
  • Would your company intend to form a Joint Venture, partnership, LLC, or subcontract portions of work to satisfy the requirements listed in this Sources Sought?
  • Will the majority of the work be subcontracted?
  • Experience working internationally
  • Experience working with sediment and waste removal
  • Experience with Supervisory Control and Data Acquisition (SCADA) systems for WWTP
Update #1 ·

INTRODUCTION

The United States Section of the International Boundary and Water Commission (USIBWC), has a requirement for contract for the operation and maintenance (O&M) of the South Bay International Wastewater Treatment Plant (SBIWTP) and facilities located in San Diego County, California.  Type of contract, Firm Fixed Priced, Cost Reimbursable, Hybrid, etc. to be determined.  

The Contractor shall provide, all labor, material, management (including bi-national participation with Mexico), and other resources required to perform full-service O&M of the SBIWTP and its conveyance system, plus Canyon Collectors, Pump Stations, and South Bay Land Outfall (SBLO). Full service operation and maintenance is defined as complete facility operation and maintenance, including but not limited to providing day-to-day contract management, planning, supervision, administration, personnel; plant influent and effluent sampling and laboratory testing; equipment operation, maintenance, servicing, repair and replacement; system monitoring and operation; data recording, markups of plant as built, management and reporting; quality control; capital improvements; vehicles and vehicle fleet management, operation, maintenance and repair; housekeeping; grounds maintenance; consumable supplies including chemicals, and other services related to the operation and maintenance of the SBIWTP.   

BACKGROUND  

The SBIWTP is a twenty-five (25) million gallon per day (MGD) wastewater treatment plant located at 2995 Clearwater Way, in San Diego, San Diego County, California, , north of the International Boundary, and near the intersections of Monument and Dairy Mart Roads.  Construction of the plant’s advanced primary treatment phase was completed in September 1997, and construction of the secondary treatment phase was completed in January 2011.  The plant is treating wastewater originating in Tijuana, Baja California, Mexico and the SBIWTP is operated under the authority of the United States Section, International Boundary and Water Commission (USIBWC).  An average of twenty five million gallons per day (25 MGD) of effluent is being discharged through the South Bay Ocean Outfall (SBOO), and is subject to the requirements of the National Pollutant Discharge Elimination System (NPDES) Permit, Permit Number CA0108928, Order Number R9-2023-0009; the California Regional Water Quality Control Board (CRWQCB) Monitoring and Reporting Program, Number: R9-2023-0009; and the California Ocean Plan.   

In 2024, USIBWC awarded a $600M contract for the design and construction of the rehabilitation and expansion of the SBIWTP. USIBWC awarded the contract to PCL Construction (PCL) of Long Beach, California. In turn, PCL selected Stantec Consulting Services, Inc. (Stantec), of San Diego, as the design firm. The project was awarded using the Progressive Design-Build (PDB) contract delivery method consistent with Government contracting practices and regulations. 

Expansion of Capacity 

According to USIBWC's timeline, the design process of the plant’s expansion will unfold in strategic phases, with the complete plant expansion targeted for completion by 2027. The initial phase of the plant’s expansion encompasses design development for the entire SBIWTP scope, while subsequent phases will implement rehabilitation efforts concurrent with the ongoing expansion work. 

During the expansion, the PDB team will work closely with the future SBIWTP Operator of this Contract to rehabilitate the plant while also expanding it. The USIBWC and PDB team aims to enhance the plant's treatment capacity from the current 25 MGD to 35 MGD by 2025, with a subsequent expansion to 60 MGD projected for completion by 2027. This will likely be done in incremental increases of, for example, 10 MGD or 20 MGD at a time, with a maximum potential capacity of 60 MGD. Throughout the incremental expansion period, the Operations and Maintenance contract will be adjusted as needed to accommodate the changing requirements and milestones of the Progressive Design-Build project. While the PDB project team will retain responsibility for all construction activities, modifications to this contract will undergo review and receive appropriate authorization when necessary. 

There will be a sixty (60) day phase in/outperiod. The Contract will consist of a Base Year from date of award 6March 30, 2027 plus four (4) one-year option periods.  This is anticipated to be an unrestricted procurement under the NAICS code 221320 (Sewage Treatment Facilities), the small business size standard is $50 million. 

An Industry day/s is anticipaited to be held at the South Bay International Wastewater Treatment Plant the week of 11 August 2025 to provide industry an opertunity to provide feedback during the market research phase. Those attending need contract Philip (Phil) Johnson @ philip.johnson@ibwc.gov by 31 July 2025. 

The solicitation is expected to be posted on or about September 2025 (this is a target date which may slip or change; if the solicitation is not posted on Federal Business Opportunities by 01 October 2025 to that is because the solicitation is not available for posting).  

Draft PWS and Attachments (attached) 

PWS attached  

List of Attachments: 

  1. SOM- Submittal Registry (aka deliverables) 

  1. Quality Assurance Surveillance Plan (QASP) 

  1. Required Performance Metrics (RPM) 

  1. NPDES Permit R9-2023-0009 

  1. List of Permits 

  1. SBIWTP Asset Registry  

  1. SBIWTP Condition Assessment Report- January 2024 

  1. SBIWTP Asset Maintenance Schedule 

  1. SBIWTP Capital Project List- April 2024 

  1. Monthly Chemical Dosage from March 2024- March 2025 

  1. Canyon Collector Daily Inspection Template 

  1. NPDES Annual Biosolids Report 2024 

  1. SBIWTP O&M Manual 

  1. SBIWTP System Security Plan 

  1. NIST SP 800-17r3 

  1. Plans/Drawings 

  1. Maps 

  1. NIST SP 199 

  1. SBIWTP Sequence of Operations (SOO) 

  1. Wage Determination (WD) 

  1. Request for Information (RFI) Tracker 

REQUEST FOR FEEDBACK:

The information gathered from the sources sought, industry day/s, and these questions may be used as market research to assist the Government in determining and shaping various aspects of the acquisition process. This includes, but is not limited to, the development of solicitation documents, source selection criteria, contract type, Performance Work Statement (PWS), Quality Assurance Surveillance Plan (QASP), and other acquisition-related documents. The responses provided will help the Government understand industry capabilities, identify potential risks, and develop strategies to ensure successful project execution. Your participation and input are greatly appreciated.

Cost:

  • What are the potential cost drivers for operating and maintaining the South Bay International Wastewater Treatment Plant (SBIWTP)?
  • How will costs be affected during the temporary facility's increase to 35MGD and the permanent expansion to 50-60MGD? How can these cost risks be managed and mitigated?
  • What strategies can be used to manage and mitigate unexpected costs associated with operating and maintaining the plant? How would these strategies change during the increase in temporary capacity from 25MGD to 35MGD and eventually to 50-60MGD?
  • What measures can be implemented to help potential contractors manage and mitigate unexpected costs associated with operating and maintaining the plant?

Technical:

  • What technical challenges do you anticipate in operating and maintaining the plant? What strategies could be used to manage and mitigate these risks?
  • What technical challenges do you anticipate during the temporary facility's increase to 35MGD and the permanent expansion to 50-60MGD?
  • Can you share your experience with similar projects and the lessons learned that could be applied to this project?
  • Are there any other technical risks that are unique to the O&M services for the SBIWTP?

Performance:

  • What performance metrics would you use to measure the success of the operation and maintenance of the plant?
  • How would you ensure that your projects meet performance standards?
  • What are the key resources required to perform these services for a project of this size and complexity?
  • What other performance risks do you see that may be unique to the O&M services for the SBIWTP?

Schedule:

  • What are the key milestones and timelines for the phase-in period? How will you ensure an effective transition?
  • How would you manage any delays or disruptions that may occur during the performance? What contingency plans would you have in place to address these issues?
  • What strategies could you implement to ensure the timely completion of tasks/projects?
  • What other schedule risks do you see as unique to the O&M services for the SBIWTP?

Additional Feedback Requested:

  • Clarity and completeness of PWS and attachments
  • Feasibility of the requirements
  • Suggestions for improvements
  • Feedback on the contract type (FFP plus Cost Reimbursement, or FFP only). Please provide a recommendation on the most suitable type of contract for this requirement.
  • Risks and drawbacks
  • Can your company extend services to the NIWTP in Nogales, AZ? If so, please explain.
  • Contractor’s experience working with FAR and Government contracts that would be considered the same or similar in size, scope, and complexity
  • Contractor’s experience in WWTP within the last 5-7 years
  • Would your company intend to form a Joint Venture, partnership, LLC, or subcontract portions of work to satisfy the requirements listed in this Sources Sought?
  • Will the majority of the work be subcontracted?
  • Experience working internationally
  • Experience working with sediment and waste removal
  • Experience with Supervisory Control and Data Acquisition (SCADA) systems for WWTP

Files

File Type Posted
191BWC26R0001 0008.pdf PDF
191BWC26R0001 0007.pdf PDF
191BWC26R0001 0006.pdf PDF
191BWC26R0001 0005.pdf PDF
FY26 SBIWTP OM PWS_Amended 16 Dec 2025 (2).pdf PDF
191BWC26R0001 0004.pdf PDF
Request For Information_ Final for Solicitation Posting (1).xlsx XLSX spreadsheet
Attch. 20 Wage Determinations CA202100001CA20240001 07.26.2024.pdf PDF
191BWC26R0001 0003.pdf PDF
Site Visit SB Exp-ENG 11.7.2025_rev.pptx PPTX presentation
Attch. 29 CUI_SBIWTP PDB Early Work Package 1C Replace in Kind.pdf PDF
Attch. 28 SBIWTP PDB Expansion SOW Section 01.31.83.01.pdf PDF
Attch. 26 Emergency Response Plan.pdf PDF
Attch. 25 Tijuana wastewater flow diagram Oct 2025.pdf PDF
Attch. 24 2025 IBWC Risk Assessment Final.pdf PDF
Attch. 21 IBWC Spill and Transboundary Plan 2021.pdf PDF
FY26 SBIWTP OM PWS_Amended 16 Dec 2025.pdf PDF
Attch. 27 SBIWTP OM Contract PWS 2020.pdf PDF
Attch. 23 IBWC SBIWTP - Capital Improvement Plan (2025 - 2029).pdf PDF
Attch. 22A 2019 Contractor OrgChart.pdf PDF
Request For Information_ Final for Solicitation Posting.xlsx XLSX spreadsheet
Attch. 22 USIBWC SDFO Org Chart.pdf PDF
Attch. 14 SBIWTP SSP 042020.pdf PDF
Attch. 10 Updated September October 2025 Chemical Dosage.pdf PDF
Attch. 04A CDO-R9-2025-0139.pdf PDF
FY26 SBIWTP OM PWS_Final.pdf PDF
191BWC26R0001 002.pdf PDF
191BWC26R0001 0001.pdf PDF
191BWC26R0001 OM Services SBIWTP.pdf PDF
Attch. 19 SOO_V2_06192018.pdf PDF
Attch. 20 Wage Determinations CA20240001 07.26.2024.pdf PDF
Attch. 10 Monthly Chemical Dosage March 2024 to March 2025.pdf PDF
Attch. 08 IBWC SBIWTP - Asset Maintenance Schedule.xlsx XLSX spreadsheet
Attch. 06 IBWC SBIWTP Asset Registry 2024.xlsx XLSX spreadsheet
Attch. 11 Canyon Collector Daily Inspection template- MAR 2025.xlsx XLSX spreadsheet
Attch. 13 SBIWTP O&M Manual.pdf PDF
Attch. 04 NPDES Permit Order R9-2023-0009.pdf PDF
Attch. 14 SBIWTP SSP 042020.pdf PDF
Attch. 01 SOM SUBMITTAL REGISTER SBIWTP O&M 2026.xlsx XLSX spreadsheet
Attch. 03 RPM- Table 2026.xlsx XLSX spreadsheet
Attch. 17 SBIWTP Map.pdf PDF
Attch. 15 NIST.SP.800-171r3.pdf PDF
Attch. 07 Condition Assessment Report Jan 2024.pdf PDF
Attch. 05 List-of-Permits.docx DOCX document
Attch. 02 FY26 SBIWTP O&M QASP.doc DOC document
Attch. 12 2024 NPDES ANNUAL BIOSOLIDS.pdf PDF
Attch. 16 Plans Drawings.docx DOCX document
Attch. 18 NIST.FIPS.199.pdf PDF
Attch. 09 SBIWTP Capital Project List as of April 2025.pdf PDF
Show all 49

Notice history

Notice Type Posted
Operation & Maintenance of the South Bay Wastewater Treatment Plant Latest special notice Special Notice
Operation & Maintenance of the South Bay Wastewater Treatment Plant Pre-Solicitation
Operation & Maintenance of the South Bay Wastewater Treatment Plant Special Notice
This notice Original Pre-Solicitation

Similar open opportunities

Opportunity Agency Set-aside Responses due
Operations and Maintenance (O&M) Services for the SBIWTP San Ysidro, California 92173, United States · NAICS 221320 International Boundary and Water Commission U.S.-Mexico No set-aside
Waste Water Treatment Plant Services Praia da Vitoria Azores 9760- Portugal · NAICS 221320 Air Forces Europe and Africa No set-aside

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity

GovTribe for Federal Contractors