Attch. 23 IBWC SBIWTP - Capital Improvement Plan (2025 - 2029).pdf
PDF 1 MB Posted
- Solicitation number
- FY26OMSBIWTP
About this file
This Capital Improvement Plan details proposed infrastructure upgrades for the South Bay International Wastewater Treatment Plant (SBIWTP) from 2025-2029, developed by Veolia. The comprehensive plan outlines multiple critical projects totaling approximately $125 million, focusing on rehabilitating aging infrastructure installed in 1996. Key projects include lift station rehabilitations ($15 million), secondary and aeration system upgrades ($15 million), headworks modernization ($10 million), SCADA server and system improvements ($2.2 million), and infrastructure enhancements for chemical storage, security, fire suppression, and laboratory facilities.
The plan addresses significant operational challenges caused by increased transboundary flows from Mexico, equipment wear, and outdated systems. Projects aim to improve operational efficiency, regulatory compliance, safety, and reliability across various plant systems, including canyon collectors, bar screens, valves, piping, electrical systems, and critical control infrastructure. Each proposed project includes detailed scopes of work, problem statements, recommended solutions, and estimated costs, with a strategic focus on preventing equipment failures, reducing maintenance expenses, and ensuring continuous, compliant wastewater treatment operations.
View the file
Other files
Show all 48
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
South Bay International Wastewater Treatment Plant
Capital Improvement Plan 2025 - 2029
Revision 0
San Diego, IBWC SBIWTP
Table of Contents
1. INTRODUCTION
2. PROPOSED PROJECTS INFORMATION
3. PROJECTS BY YEAR
2025 Summary of Proposed Capital Improvement Projects
4-6
2025 Proposed Capital Improvement Project Details
7-11
2026 Summary of Proposed Capital Improvement Projects
12-13
2026 Proposed Capital Improvement Project Details
14-20
2027-2029 Summary of Proposed Capital Improvement Projects
21-22
2027-2029 Proposed Capital Improvement Project Details
23-32
1. INTRODUCTION
This updated plan recommends proposed capital improvement projects for the South Bay International Wastewater Treatment Plant (SBIWTP) for 5 years over the course of 2025 through 2029, building upon the previous plan with the latest available information. These projects have been identified and prioritized, including development of the associated scope details and costs estimates, in complete cooperation between Veolia Operations & Maintenance (O&M) staff based at the South Bay International Wastewater Treatment Plant, Veolia Municipal Water Asset Management staff and the Veolia Capital Program Management (CPM) West Region team.
This recommended scope of work will directly support consistent operations of the overall facility, mitigate operational consequences of equipment failure and promote the necessary availability and reliability of the associated plant areas.
The International Boundary and Water Commission has successfully partnered with the Veolia CPM and O&M teams to complete emergency work from August 2023 to the current date. This cooperation is ongoing with projects that include 2021 Junction Box-1 Rehabilitation which collects transboundary flow from Tijuana Mexico, WAS/RAS and various pumps and motors replacements throughout the entirety of the facility, the USST 1 & 2 Rehabilitation, and Belt Filter Press Rehabilitation projects. Recently completed projects include the cleaning and rehabilitation of Primary Sedimentation Tanks 1-5, Hollister Lift Station repairs and the Influent Valve, Flow Meter, and Pipe Replacement Project.
2. PROPOSED PROJECTS INFORMATION
The plant systems and equipment listed for capital improvement projects have been selected due to a range of factors including process improvement and optimization opportunities, current asset condition / signs of wear and deterioration, expected and remaining useful life of assets, health / safety and environmental considerations, operational criticality and the consequences of failure.
For assets nearing the end of the expected useful life, investment at this stage will help minimize the risk of complete functional failure of the associated equipment and in-turn serve to better prevent the chance of major unplanned repairs and further mitigate against unwanted operational consequences.
For each year of the plan below, there is an initial Summary of Proposed Capital Improvement Projects table followed by a Proposed Capital Improvement Project Details section which provides detailed information and justifications regarding each individual project / component.
Estimated costs shown reflect the best available approximation at this time, considering all known factors as well as any budgetary quotes obtained, and are listed in present-day dollar figures. Some costs will be subject to change as the projects are further developed and associated equipment quotes are updated over time relative to the planned timing of the project. As funding for these proposed capital projects is approved, certain costs may also change based on further scope discovery during planning, design and during the construction bid submission process.
Method of Project Delivery Project management / execution by Veolia CPM Team in coordination with Veolia O&M Team.
3. PROJECTS BY YEAR
This section provides summary tables and subsequent project details pages for all proposed capital improvement projects which are grouped together by each year covered in the plan.
Summary of Proposed Capital Improvement Projects
Project Description Project Component Scope of Work Summary Asset
Install Date Estimated
Cost
Lift Station(s) Rehabilitation
Goat Canyon and Hollister Lift Station Rehabilitation
Complete replacement of Goat Canyon and Hollister Lift Stations
- Electrical Upgrades
- VFD Upgrades (Goat)
- Odor Scrubber Replacement
- Surge Tank Replacement
- Inlet MOV Replacement
- Generator Controls
Replacement
- Warrick probe for surge tank room
- Wetwell bubbler replacement
- Checks and Plug Valves
- Nuisance Pumps
1996 $15,000,000
SST & AST
Rehabilitation
Replacement of key equipment in the secondary process
SST & AST Rehabilitation
- Clean tanks
- Replace remaining large Imler mixers
- Secondary Skimming Pump
1A/1B
- AST/SST Tank Drain Pumps
- Replace diffusers
- Piping replacement for sprayers
- Replace drives
- Add water cannons
- New chains & flights
2008 $15,010,000
Install Date
Estimated Cost
- New I&C - actuators and air valves, DO probe addition to even number tanks
- Re-write PLC programming and HMI screens
- TSS meter for DAF and Primary (good for process control)
- Spare conduit and electrical installation
- Strainers
- Addition of Neuros Blowers
- SST underflow readings tied to
PLC
- 2 EQ Basin VFD’s
- BMCV 1&2 valve and actuator replacement
- Adding a 4th blower
- Soft start for remaining blowers
- AST and SST inlet isolating valves
- TWAS and WAS meters
- RAS valves and meters
Headworks Upgrades
Replacement of key components at Headworks
- VFD’s for 1, 3, 5, 6 & Soft Starts
- IPs 2 & 4 Soft Starts and VFDs
- Replace 6 plug and check valves
- Rotorks Upgrade
- Install H2S alarm
- Gates for Barscreen Influent and Effluent
- New electrical (on racks)
- New LCP
- Transformers
- Re landing IP faults to the PLC not the VFDs
- IP VFDs integrated into PLC programming and HMI
- Upgrade seal water sensor to individual pumps
- Bubbler replacement
- Requires bypass
$10,000,000
Install Date
Estimated Cost
Grit and Aeration Package
Replacement of key equipment in the grit removal process
- Three (3) grit classifiers
- Six (6) grit gallery pumps
- Six (6) grit pump VFD’s
- Two (2) primary channel air blowers
- Two (2) grit air blowers
- Replace piping in grit classifiers and grit gallery
- Short circuit arc flash study at
SBIWTP
- Rehab of diffusers in PIC and
PEC and cleaning
- Grit Chamber bypass
$7,300,000
SCADA
Server UPS
Replacement
- Floor mounted UPS replacement with extended batteries
- Manual bypass to isolate
- Integrated to HMI
- Recommend SCADA server upgrades
$2,200,000
Total Estimated Cost $49,510,000
Proposed Capital Improvement Project Details
Project Name Lift Station Rehabilitations
Project Description Goat Canyon and Hollister Lift Station Rehabilitations
Assets Included Goat Canyon Lift Station Hollister Lift Station
Asset Install Date 1996
Scope of Work
In kind replacements of Goat Canyon and Hollister Lift Stations including but not limited to:
- Surge tank replacements
- VFD upgrades
- Electrical upgrades
- Odor Scrubber Replacement
- Generator and Controls Replacement
- Wetwell bubbler replacement
- Pumps and bases
- Check and plug valves
- Nuisance pumps
- Sluice gates
- Roof replacements
Problem / Opportunity Goat Canyon and Hollister Lift Station have had failures from large amounts of silts and solids damaging pumps, motors and other necessary equipment needed to mitigate transboundary flows.
Recommended Solution/Basis of Recommendation
Rehabilitate, upgrade and install new equipment to include pumps, motors, generators, a new odor reduction facility, upgraded electrical and SCADA controls and new roof to protect installed critical assets.
Known failures, assessments, and tests conducted from O&M, CPM and contractors identified failures or the high potential for failure that could result in SSO’s through visual, operational, conductivity and other tests measuring the longevity and operational necessity of equipment.
Measurable Benefits This project will complement the SBIWTP by keeping it in environmental compliance, help increase the expected useful life of the equipment and properly mitigate future transboundary spills
Project Cost Estimate $15,000,000
Project Name AST & SST Rehabilitations
Project Description The AST and SST Rehabilitation Project involves the comprehensive cleaning and refurbishment upgrades of the facility's Aeration/Activated Sludge Tanks and Secondary Sedimentation Tanks.
Assets Included
TANK, SLUDGE, ACTIVATED AST1 - 7
DIFFUSERS, TANK, ACTIVATED SLUDGE AST1 - 7-DG
PUMP, MIXED LIQUOR, INTERMEDIATE IMLRP1 - 7
COLLECTOR, SECONDARY SLUDGE SSC1 - 13
DRIVE, SKIMMING, SECONDARY (ROTORK ACTUATOR) SSKS1-13
VALVE, SPRAY, SKIMMING, SECONDARY SSKSV1 - 13
PUMP, SECONDARY SKIMMINGS SSKP1A & SSKP1B
STRAINER, NPW2P, NORTH NPW-STR-N & SOUTH NPW-STR-S
BLOWER, AIR, PROCESS PAB1 - 3, ASTDP1, SSTDP1, ASTMX’s
Asset Install Date 2008
Scope of Work
Rehabilitate AST & SST Components:
- Clean tanks
- Replace large mixers
- Replace diffusers
- Piping replacement for sprayers
- Replace drives
- Add water cannons
- New chains & flights & shoes & sprockets & scum pipes
- New I&C
- Repair concrete
- Rehab to secondary skimming pump station
- Strainers
- Replace skimmings pumps
- Neuros blowers
Problem / Opportunity
The lifespan and operability of complex equipment is continuously compromised from large flows the SBIWTP receives. This critical project aims to extend the lifespan of these essential components by improving treatment efficiency, and will ensure compliance with current and future regulatory requirements.
Recommended Solution/Basis of Recommendation
Clean and rehabilitate SST/AST tanks and replace vital components to extend the lifespan of the equipment. Equipment failure due to large amounts of sediment damaging tanks and also due to age.
Measurable Benefits
The rehabilitation will address structural issues, upgrade aeration systems, improve sludge collection mechanisms, and enhance overall operational efficiency. This project is crucial for maintaining the plant's treatment capacity and improving the quality of treated effluent.
Project Cost Estimate $15,010,000
Project Name Headworks Upgrades
Project Description The Headworks Upgrades Project involves comprehensive improvements to the initial treatment processes at the facility.
Assets Included
STRUCTURE/BUILDING, HW (HEADWORKS) 00100-HWE-BLDG
PIPING, PUMP, INFLUENT 00200-PG
SUBSTATION, TRANSFORMER, 12KV, HW 00240-SUBSTATION, A &
B
Asset Install Date 1996
Scope of Work
Upgrades to Mechanical & Electrical Components of Headworks:
- Reroute existing conduit systems overhead on a steel system
- Installation of (6) 30” motorized plug valves & (6) check valves
- Installation of course bubble diffusers
- Installation of (6) air relief valves
- Installation of (2) new 2000kva transformers
- Influent pump plug valves and controls upgrades
- Bypass the headworks facility to conduct work
Problem / Opportunity
The transformers noted are the main transformers for the headworks treatment process. Failure of these transformers would require the shutdown of critical processes and supplemental generators would need to be brought in to keep the plant running during repairs.
Flooding of the headworks in the past brought significant amounts of sediment and debris that has caused underground electrical conductivity issues and deterioration of wiring, as well as problems with the mechanical elements in the pump discharge piping (check valves, plug valves, air relief valves, etc.), which greatly complicates the operation of the systems.
Recommended Solution/Basis of Recommendation
Current condition / age (end of expected useful life) / lack of available parts
Measurable Benefits
The project will modernize existing equipment, implement new technologies, and improve overall system reliability and performance, alongside providing reliability and continuity of power to the facility, which will help address problems caused by increased flows and sediments.
Project Cost Estimate $10,000,000
Project Name Grit and Aeration Rehabilitation
Project Description Grit and Aeration Rehabilitation
Assets Included Hydrogritters, Grit VFD’s, Grit Pumps and Piping, Grit Blowers, Primary Channel Blowers, Short Circuit and Arc Flash Coordination Study
Asset Install Date 1996
Scope of Work
Rehabilitation of Grit Removal :
- 3 grit classifiers
- 6 grit gallery pumps
- 6 grit pump VFDs
- 2 primary channel air blowers
- 2 grit air blowers
- Piping in grit classifier and gallery
- Conduct a short circuit arc flash study.
Problem / Opportunity
The existing primary channel blowers #1 and #2, two (2) grit blowers and grit pumps have all failed due to excessive wear and tear from sand and debris in the influent flow. Tropical Storm Hilary exacerbated the vulnerabilities of an already at-risk treatment plant (due to plant age and repeated above-capacity flows), accelerating damage primarily through additional excessive flows and an influx of debris. Trash, sediment, and debris were carried by these excessive flows into the pumps, piping and tanks throughout the plant, and ultimately due to the excessive wear and tear, the blowers and pumps failed. These blowers and pumps are a key component of the treatment process. Replacement of these components (which are at or near the end of life) is essential to optimize the treatment process and prevent failures that could lead to permit violations.
Recommended Solution/Basis of Recommendation
Without prompt action, the treatment process will be severely compromised, jeopardizing the ability to meet permit requirements and exposing SBIWTP to the risk of violations. The replacement of these critical components is imperative for restoring the integrity of effluent wastewater treatment infrastructure at SBIWTP and maintaining compliance with regulatory standards for wastewater quality.
Moreover, the replacement of this equipment is a matter of paramount importance for safeguarding human health and safety. Failure to act swiftly will increase the risk of discharges. The rehabilitation and replacements are required to maintain safe and reliable operations of
SBIWTP.
Project Cost Estimate $7,300,000
Project Name SCADA Server UPS Replacement
The SCADA Server Uninterrupted Power Supply (UPS) Replacement Project is a critical infrastructure upgrade initiative focused on enhancing the reliability and resilience of the plant's control systems through modern uninterruptible power supply implementation and associated SCADA improvements.
Assets Included Various UPS and SCADA equipment replacement, with the addition of new assets to improve system functionality.
Asset Install Date 2008
Scope of Work
Upgrades to the New Floor-Mounted UPS System:
- Industrial-grade UPS units
- Extended battery backup capacity
- Manual bypass switching system
- Advanced monitoring capabilities
- Network integration features
- Temperature monitoring
- Remote management capability
SCADA Server Upgrades:
- Hardware modernization
- Operating system updates
- Security enhancements
- Virtualization capabilities
- Redundancy improvements
- Backup systems enhancement
Problem / Opportunity Aging equipment - Upgrade and modernize Hardware
Recommended Solution/Basis of
VRecommendation
This project increases system reliability by addressing the critical need for continuous power protection, replacing aging existing UPS infrastructure, enhancing backup power duration, and improving maintenance capabilities. Additional benefits include increased operational security through protection against power fluctuations, the reduced risk of data loss, enhanced system availability, and better disaster recovery capabilities. The project also modernizes monitoring capabilities, improves integration features, enhances management tools, and provides better efficiency ratings.
Measurable Benefits System Performance, Operational Improvements, Risk Reduction
Project Cost Estimate $2,200,000
Install Date Estimated
Cost
Plant Lighting Upgrade
(12) locations throughout the
SBIWTP
- Upgrade existing plant lighting with new LED lighting
1996 $6,000,000
Primary and Secondary
Non Pot Upgrades
Primary and Secondary Non Potable Water Systems
- New strainers
- New victaulics
- New plug and check valves
- Instrumentation, including flow meters
- SCADA upgrades
- Compressor Motors
- Compressor
- Pressure Vessel
1996/2006 $4,000,000
Odor Control Upgrades
Odor Control Scrubber Systems
- USST
- BFP/ Solids
Processing
- Headworks
- PST’s
- Chemical tank rehab
- Supply fans
- Exhaust fans
- Integrate odor reduction ancillary instrumentation to PLC programming and
HMI
- Control panel upgrades
1996 $7,500,000
PLC Migration
- Blowers
- Secondary Non
Pot
- Secondary PLC
- Upgrading PLC’s throughout plant
- Replace all aeration blower PLC’s
- Implement redundancy for secondary PLC
- Redundant network switches
- Non Pot - device level ring configuration
- Replace input/output cards within secondary
$1,000,000
Install Date
Estimated Cost
- Switchgear PLC replacement migration and have redundancy
- Coordination w/ CAT Hawthorne
- HMI screen integration
- Breaker readout device replacement(s) and integration
- Cathodic Protection
Effluent Flow Meter Replacement
- Replace 48” flow meter
- Control panel replacement
- Fiber loop around primary and secondary
- Canyon Collector meter re-route wiring
- Recycle flow meter - for drain and canyon flow coming in to facility
- Valve replacement
- Bypass needed
- Permanent Bypass
$6,750,000
MCC Buckets Upgrades
- MCC buckets for primary system
- Ground fault study
- Breaker coordination
$1,500,000
HVAC
Upgrades
- HVAC upgrades at MCC and control panels
- Increase efficiency for
HVAC
$5,000,000
Total Estimated Cost $28,500,000
Project Name Plant Lighting Upgrades Project Description The primary goal of this project is to upgrade and modernize the lighting systems throughout the wastewater treatment plant facility.
Assets Included
Bronze and Gray Light Poles, Headworks area, Primary Sedimentation Area, Secondary Sedimentation Area, Activated Sludge Area, Main Switchgear Maintenance Building, Daft EQ Gens Area, Solids Processing Area, Administration Building, Hollister Pump Station and Goat Canyon Pump Station.
Asset Install Date 1996
Scope of Work Provide and installation of new LED light fixtures, verification circuits feeding light fixtures involved and update panel schedules and as builts, verify integrity of existing wiring, verify light controls, Problem / Opportunity
Many of the plant's area lighting fixtures are 25 years old and failing and are not up to lighting standards. Masts and arms are made of steel and show serious corrosion. Lighting efficiency would be greatly improved with switching to LED fixtures and lamps. ROI on installation is expected to be less than 5 years based upon energy savings.
Recommended Solution/Basis of Recommendation
Install new lighting fixtures, circuits, and wiring. Lighting conditions create an unsafe work environment in addition to the degradation of fixtures and wiring throughout the plant.
Measurable Benefits Improved lighting upgrades would allow safe operation procedures and energy savings.
Project Cost Estimate $6,000,000
Project Name Primary and Secondary Non Potable Upgrades
The Primary and Secondary Non-Potable Piping Replacement Project involves the comprehensive replacement of aging and deteriorating non-potable water valves and piping, above and below ground for systems serving both the primary and secondary treatment areas.
Assets Included NPW Valves, NPW 01340-PG
Asset Install Date 1996
Scope of Work
The project will replace existing valves and piping, and install additional valves to provide isolation necessary for repair while allowing other plant processes to remain in operation. This work includes the replacement of new valves, victaulic couplings, strainers, instrumentation, and SCADA upgrades for the non-potable system.
Problem / Opportunity
Poor isolation valves necessitating repairs and causing routine maintenance difficulties. Valves are worn from age and normal operation. Replacement of the valves and piping would allow for repairs and maintenance to be completed more easily, maximizing operation throughout the SBIWTP and eliminating water runoff in emergency scenarios (e.g., line breaks and process failures).
Recommended Solution/Basis of Recommendation
This critical infrastructure upgrade aims to enhance system reliability, improve operational efficiency, and ensure the continued safe distribution of non-potable water throughout the facility.
Measurable Benefits
This upgrade will result in reduced maintenance costs, improved flow characteristics, and increased system longevity. Will allow for process isolation without affecting other critical operations when repairs are necessary.
Project Cost Estimate $4,000,000
Project Name Odor Control Upgrades Project Description Recondition Odor Control Scrubber Systems
Assets Included
SCRUBBER, ORHW 00355-ORSC1 - SCRUBBER, ORPST
00655-ORSC2 - SCRUBBER, TOWER 3, ORUSS 02255-ORSC3 -
SCRUBBER 4, ORSP 03705-ORSC4 - SCRUBBER 5, ORSP
03715-ORSC5
Asset Install Date 1996
Scope of Work The Odor Control Upgrade Project involves the comprehensive rehabilitation and improvement of the existing odor control system.
Problem / Opportunity
This critical project aims to address the calcification of the current media, replace the failing media support system, and upgrade the structural support to accommodate heavier media loads. Normal deposits of calcium from water hardness have caused the media to calcify, requiring it to be removed and replaced. The media support system is also starting to fail, as the media is heavier than the structural support loading design.
Recommended Solution/Basis of Recommendation
Current condition / age (end of expected useful life) / lack of available parts. The upgrades will enhance odor removal efficiency, improve system reliability, and ensure compliance with air quality regulations.
Measurable Benefits The upgrades will enhance odor removal efficiency, improve system reliability, and ensure compliance with air quality regulations.
Project Cost Estimate $7,500,000
Project Name PLC Migration
Project Description
The PLC Migration Project involves upgrading the existing Programmable Logic Controller (PLC) system to a modern, more efficient control system. This project aims to enhance the plant's operational efficiency, reliability, and compliance with current industry standards and regulations.
Assets Included Headworks PLC, PST PLC, GCPS PLC, HPS PLC, BFP PLC, GEN PLC, PEB PLC, PERC PLC, Solids Processing PLC, Lime Stabilization PLC, Plant Control Center PLC, Odor Reduction PLC
Asset Install Date
Scope of Work
Blowers, Secondary Non Pot, Secondary PLC:
- Upgrading PLC’s throughout plant
- Replace all aeration blower PLC’s
- Secondary Non Pot - redundant PLC configuration
- Implement redundancy for secondary PLC
- Redundant network switches
- Non Pot - device level ring configuration
- Replace input/output cards within secondary
- Switchgear PLC replacement migration and have redundancy
- Coordination w/ CAT Hawthorne
- HMI screen integration
- Breaker readout device replacement(s) and integration
- Cathodic protection
Problem/Opportunity
This project focuses on modernizing the plant's control system infrastructure, enhancing operational efficiency and process control, improving system reliability and reducing downtime, facilitating better data management and reporting, ensuring compatibility with current and future plant equipment, and providing a platform for future expansion and upgrades.
Recommended Solution/Basis of Recommendation
The existing PLC infrastructure, which has been in operation for years, is approaching the end of its useful life and is becoming increasingly difficult to maintain due to obsolete components and limited vendor support. This modernization effort will replace outdated PLCs with state-of-the-art control systems, ensuring the plant's continued optimal performance and preparedness for future technological advancements.
Measurable Benefits
The project will replace outdated PLC hardware and software with a state-of-the-art system that offers improved processing power, expanded memory, enhanced communication capabilities, and better integration with other plant systems. This upgrade will result in more precise control of plant operations, improved data collection and analysis, and increased system reliability.
Project Cost Estimate $1,000,000
Project Name Effluent Flow Meter Replacement
The Effluent Flow Meter Replacement Project involves the removal of the existing 48" effluent flow meter and installation of a new, state-of-the-art 48" flow meter.
Assets Included METER, FLOW, MAGNETIC, 48", PLANT EFFLUENT 01506-FLOW-PE
Asset Install Date 1996
Scope of Work
- Planning and Design
- Procurement of new flow meter
- Scheduling temporary bypass for replacement
- Removal of old flow meter
- Installation of new flow meter
- Installing bypass on effluent line
- Calibration and testing
- Integration with SCADA or other monitoring systems
Problem / Opportunity This critical upgrade aims to enhance the accuracy and reliability of effluent flow measurements, ensuring optimal plant performance and regulatory compliance.
Recommended Solution/ Basis of Recommendation
Installing a new flow meter and permanent bypass piping will allow for repair and replacement opportunities without disrupting flow.
Measurable Benefits
The replacement of the existing clamp on effluent flowmeter with a magnetic flowmeter will allow for improved accuracy in effluent flow measurement reporting, better monitoring and control of plant operations, compliance with regulatory and environmental requirements, and potential energy savings with more efficient equipment. Installation of a permanent bypass will allow for maintenance on the effluent meter without the need to install a temporary bypass.
Project Cost Estimate $6,750,000
Project Name MCC Bucket Upgrades
The MCC (Motor Control Center) Bucket Upgrades Project is a comprehensive electrical system improvement initiative focusing on modernizing critical electrical infrastructure for the primary treatment system while ensuring proper protection coordination and safety compliance through detailed electrical studies.
Assets Included Various MCC equipment throughout the facility.
Asset Install Date 1996
Scope of Work
- MCC buckets for primary system
- Ground fault study
- Breaker coordination
Problem / Opportunity Upgrades will modernize and enhance system operations.
Recommended Solution/Basis of Recommendation
This project would increase the system reliability as the aging MCC infrastructure requires modernization. The plant has a need for improved operational reliability as the current equipment is approaching the end of useful life. The project would help the plant meet safety compliance standards by: meeting current electrical codes, ensuring proper protection coordination, implementing modern safety features, and reducing arc flash hazards. This would improve operational efficiency by: improving monitoring capabilities, enhancing maintenance access, providing a better system protection. There will also be risk mitigation by: reducing the risk of electrical failures, enhancing personnel safety, improving equipment protection, and providing better system documentation.
Measurable Benefits Current condition / age (end of expected useful life) / lack of available parts
Project Cost Estimate $1,500,000
Project Name HVAC Upgrades
The HVAC Upgrades Project involves upgrading and modernizing the Heating, Ventilation, and Air Conditioning (HVAC) systems at the
SBIWTP.
Assets Included HVAC upgrades in spaces that currently utilize A/C
Asset Install Date 1996
Scope of Work
- Conduct a comprehensive assessment of existing HVAC systems throughout the plant
- Implement upgrades to HVAC systems in office buildings, Motor Control Center (MCC) buildings, and control panels
Problem / Opportunity The current HVAC infrastructure is outdated and inefficient, exposing existing equipment to excessive heating of the equipment and electrical components.
Recommended Solution/Basis of Recommendation
This project will significantly enhance the working environment for staff and protect vital equipment, contributing to the overall efficiency and effectiveness of the wastewater treatment plant operations.
Measurable Benefits
This project will directly result in improved indoor air quality and comfort for staff in office buildings, enhanced protection and optimal operating conditions for sensitive electrical equipment in MCC buildings, increased energy efficiency and reduced operating costs, extended lifespan of critical plant equipment through better environmental control, and the improved overall functionality and reliability of the wastewater treatment plant.
Project Cost Estimate $2,000,000
2027-2029
Install Date Estimated
Cost
WWTP
Storage Facility
Addition of a storage facility onsite to house equipment, spare parts, materials, etc.
- Addition of storage facility New asset $2,605,000
Interior Condition Assessment and Repairs of USST’s
Condition assessment and corresponding repairs of mechanical equipment inside the USSTs plus possible concrete repairs and structural bracing.
- Interior and exterior coatings
- Piping & Valves
- Instrumentation upgrades
- Concrete repairs
- Struvite removal from feed lines
1996 $3,125,000
Ocean Outfall
- Anti Intrusion Structure Rehab
Assessment of the outfall and the corresponding mechanical elements.
- Replacement of 4 air vacs
- Bubbler system replacement
- Valve replacement
1996 TBD
Bar Screen & Conveyors Replacement
Screening equipment (automatic and manual) at headworks to be upgraded to modern standards.
- Screens and compactors
- Installation
- Engineering/SCADA
- Conveyors
1996 $6,500,000
Canyon Collector Rehabilitation & Upgrades
Upgrades to the canyon collector infrastructure to improve operations and maintenance of the facilities.
- Valving on three gravity collectors
- Expand containment
- Sediment basin upgrades
- 2nd collector box to both
Goat and Hollister
- Drying beds w/ decant capabilities
1996 $12,000,000
Chemical Tank Rehabilitation
Improvements to chemical storage infrastructure, including diesel tanks, to improve site safety and efficiency of chemical use in the Plant. The project includes the
- Rerun poly bulk storage tanks electrical
- Primary polymer addition pumps
- Demolition of ferric pumps
- Polymer tanks
1996 $2,500,000
Install Date
Estimated Cost corresponding electrical work.
- Polymer pumps replacement for solid processing
- Truck loading scales
- Diesel storage tanks (3) and containment area (double tank capacity)
- Containment sump pumps
Security & Fire Suppression Assessment
Assessment and improvements to fire suppression systems to enhance site safety
- Door replacements
- Garage door replacements
- Fire panel upgrade
- Communicate with fire dept
- New heat and smoke detectors
- Strobe lighting
- SCADA server fire suppression upgrades (Heptafluoropropane)
1996 $3,000,000
Onsite Laboratory Upgrades
Upgrade the existing onsite laboratory, to bring the infrastructure and equipment to modern standards.
- Upgrade existing lab infrastructure to protect the lab from dust and other outdoor elements
1996 $1,500,000
Total Estimated Cost ~$32,230,000
2027-2029
Project Name WWTP Storage Facility
The Wastewater Treatment Plant Storage Facility Project involves the design and construction of a new, purpose-built storage facility to house equipment and materials essential for plant operations. This project aims to address current storage inadequacies, enhance operational efficiency, improve safety, and ensure better preservation of valuable assets.
Assets Included No storage is existing (New asset)
Asset Install Date N/A
Scope of Work
- Construction of a secure, weather resistant building
- Implementation of organized storage systems for various equipment and materials
- Installation of proper lighting, ventilation, and climate control systems
- Integration of safety features and hazardous material handling areas
- Development of an inventory management system
Problem / Opportunity
The current lack of adequate storage facilities heightens the risk of inefficient operations, equipment deterioration, inventory problems, increased maintenance costs, space constraints, and safety hazards.
Building a new storage facility presents an opportunity to address these issues.
Recommended Solution/Basis of Recommendation
The new facility will centralize storage, project assets from environmental damage, improve inventory control, and create a safer working environment. The project is expected to result in long-term cost-savings, increased operational efficiency, and better compliance with safety and environmental regulations.
Project Cost Estimate $2,605,000
Project Name Interior Condition Assessment and Repairs on USST 1&2
Project Description
The project involves conducting a comprehensive interior condition assessment of the Unstabilized Sludge Storage Tanks (USSTs).
Following the assessment, necessary repairs will be identified and executed to ensure the continued efficient operation and longevity of these critical components of the wastewater treatment system.
Assets Included
TANK, SLUDGE, UNSTABILIZED (USST) - USST1, USST2
PIPING, MIXING, SLUDGE, USST SMP-PG
VALVES, MIXING, SLUDGE, USST SMP-VG
PUMP, MIXING, SLUDGE, USST - SMP1A, 1B, 1C
PUMP, MIXING, SLUDGE, USST - SMP2A, 2B, 2C
Asset Install Date 1996
Scope of Work
- Assessment of the existing infrastructure.
- Replacement of piping
- Replacement of valves
- Replacement of pumps
- Reconditioning and coating
Problem / Opportunity
The tanks currently experience poor valve isolation for cleaning and operational needs. The condition of the piping is poor and has extensive struvite build up that needs to be removed. The interior coatings of the pipe and tank walls have worn down from the excess material and normal wear introduced into the tank. Tank inspections show the coating on interior walls and piping is in poor condition. Addressing these issues would provide adequate isolation as needed, proper conveyance of material through piping and safeguard the USST tanks from further deterioration.
Recommended Solution/Basis of Recommendation
Replace valves, pumps, and piping. Rehabilitate and recoat tanks.
Deteriorating pipe and valve conditions. Initial visual inspection of interior condition of USST tank.
Measurable Benefits
The project will provide an extended lifespan of the piping, valves, and tanks, improved structural integrity, enhanced operational efficiency, reduced maintenance costs, increased treatment capacity, decreased chemical usage, improved regulatory compliance, and increased system reliability in the face of current flows and sediment entering the plant.
Project Cost Estimate $3,125,000
Project Name South Bay Land Outfall - Anti-Intrusion Structure Assessment
Project Description
The SBLO (South Bay Land Outfall) / Anti-Intrusion Structure Assessment project involves a comprehensive evaluation of the existing ocean outfall system and its associated anti-intrusion structure at
SBIWTP.
Assets Included
STRUCTURE, ANTI-INTRUSION 01541-BLDG-AIS
DISK, RUPTURE, 42", STRUCTURE, ANTI-INTRUSION
01541-RUPTURE_DISK
GATE, FLAP, 36", STRUCTURE, ANTI-INTRUSION 01541-FGATE-AIS
PANEL, BUBBLER, STRUCTURE, ANTI-INTRUSION
01541-AIS-BUBBLER
VALVE, AIR, COMB., STRUCTURE, ANTI-INTRUSION - SAV-AIS-1 & 2
Asset Install Date 1996
Scope of Work
- Assessment of the existing infrastructure
- Replacement of 4 air vacs
- bubbler system replacement
- valve replacement 12ME
Problem / Opportunity Assess existing infrastructure and address any deficiencies it may have in order to maintain continuous operation of the facility, ensure compliance and environmental protection, as well as public health.
Recommended Solution/Basis of Recommendation
This critical assessment aims to determine the current condition, performance, and integrity of the outfall system, identify any potential issues or risks, and provide recommendations for maintenance, repairs, or upgrades
Measurable Benefits Risk mitigation associated with the existing infrastructure.
Project Cost Estimate TBD
Project Name Bar Screen and Conveyor Replacement
The Bar Screen and Conveyor Replacement Project involves the removal of the existing bar screen system and installation of a new, more efficient screening system at the plant’s Headworks. It also involves the rehabilitation of the conveyor system for the solids processing system.
Assets Included SCREEN, BAR, MECHANICAL, HW -SCN1, SCN2, SCN3
Asset Install Date 1996
Scope of Work
- Screens and compactors
- Installation
- Design and engineering
Problem / Opportunity
Barscreens and conveyance systems are excessively worn from the lack of source control at the JB-1 structure. Without source control at the gate, large debris and aggregate continuously break and wear equipment causing damage and disruption to plant processes. The project will replace outdated screening equipment with a modern, automated system better able to handle the plant's current and projected future flows and the associated rags, debris and sediment.
This upgrade will result in improved capture of screenings, reduced maintenance requirements, and increased operational reliability.
Recommended Solution/Basis of Recommendation
Replacement of barscreens, compactors and conveyance systems from abnormal flow and debris, and lack of source control.
Measurable Benefits This critical upgrade aims to improve the removal of large debris and inorganic materials from the incoming wastewater stream, protecting downstream equipment and enhancing overall treatment efficiency.
Project Cost Estimate $6,500,000
Project Name Canyon and Collector Rehabilitation Upgrades
Wastewater entering the system through the Canyon Collectors increasingly contains high amounts of solids from Mexico, which has made cleaning the collectors very difficult and has caused damage to the downstream equipment in the pump stations. Therefore, it is recommended to redesign the Canyon collectors to allow effective and efficient cleaning while protecting the equipment downstream.
Assets Included All Canyon Collectors
Asset Install Date 1996
Scope of Work
Redesign of the collector canyons with the goal of facilitating cleaning, being able to isolate and manage flows and protecting downstream equipment. Ideas may include, but are not limited to:
- Valving and piping on the gravity collectors
- Expand and modify containment for isolation and better cleaning
- Sediment basin upgrades
- 2nd collector box to both Goat and Hollister
- Drying beds w/ decant capabilities
Problem / Opportunity
The design of almost 30 years ago is no longer effective for the current conditions, especially due to the amount of sediment, trash, solids and unregulated, increased flow of the raw sewage and storm water. The main opportunities are to protect the equipment downstream and to upgrade the collectors’ capacity through expansion of the existing containment and additional collector boxes.
Recommended Solution/Basis of Recommendation
It is recommended to select for the delivery method a progressive design-built project, in which different alternatives are presented, and in conjunction with operations, the best option is selected, with the idea of protecting the downstream equipment and facilitating the cleaning of the collectors. Expanding collectors and sediment boxes will allow the collection facilities to accommodate the increase in flows.
Measurable Benefits
Cleaning and servicing of the collectors will be more effective, so there will be savings in personnel, use of equipment, etc.
Improvement times will be shorter, which will facilitate permit compliance.
Downstream equipment will suffer less wear and tear, so there will be less downtime, fewer failures and corrections, and less exposure to catastrophic failures that lead to spills.
Project Cost Estimate $12,000,000
Project Name Chemical Tank Rehabilitation
The Chemical Tank Rehabilitation Project is a comprehensive infrastructure upgrade initiative focused on modernizing and improving the chemical storage and delivery systems at the wastewater treatment plant.
Assets Included Chemical Facilities
Asset Install Date 1996
Scope of Work
Polymer System Upgrades:
- Installation of new poly bulk storage tanks with modern safety features
- Replacement of primary polymer addition pumps
- New polymer tanks and pumps for solids processing
- Electrical system reconfigurations for improved reliability
Ferric System Modifications:
- Demolition of existing ferric pumps
- Implementation of updated chemical delivery systems
Chemical Management Infrastructure:
- Installation of new truck loading scales for accurate chemical deliveries
- Upgrade of three diesel storage tanks with modern containment systems
- Construction of enhanced containment area
- Installation of new containment sump pumps
Problem / Opportunity
The existing chemical storage systems are old, unreliable and not very efficient, a situation that has been exacerbated by the high flows received at the plant, which has required an increased consumption of chemicals, well above what was projected by the design capacity of the facility.
Recommended Solution/Basis of Recommendation
Infrastructure Reliability:
- Aging chemical storage and delivery systems require modernization
- Current infrastructure approaching end of useful life
- Need for improved operational reliability and safety
Regulatory Compliance:
- Meeting current environmental regulations for chemical storage
- Ensuring proper containment systems for hazardous materials
- Compliance with updated safety standards
Operational Efficiency:
- Improved chemical delivery and management systems
- Enhanced monitoring and control capabilities
- Better inventory management through accurate scaling
Risk Mitigation:
- Reduced risk of chemical spills or leaks
- Enhanced containment capabilities
- Improved emergency response systems
Measurable Benefits
Operational Improvements:
- Reduction in chemical handling time
- Improvement in dosing accuracy
- Reduction in maintenance requirements
- Increase in system reliability
Safety Enhancements:
- Compliance with current containment regulations
- Reduction in potential spill risks
- Improvement in chemical handling safety
Cost Savings:
- Reduction in chemical waste
- Improvement in chemical usage efficiency
- Decrease in maintenance costs
- Reduction in emergency repair needs
Environmental Benefits:
- Improvement in spill prevention capability
- Containment capacity for worst-case scenarios
- Reduction in environmental incident risk
Process Control:
- Improvement in dosing accuracy
- Better inventory management
- Reduction in chemical delivery issues
Project Cost Estimate $3,500,000
Project Name Security and Fire Suppression Assessment
The Security and Fire Suppression Assessment Project is a comprehensive safety upgrade initiative focusing on modernizing fire detection, suppression, and security systems.
Assets Included Various locations to include the addition of modern equipment
Asset Install Date 1996
Scope of Work
Physical Security Upgrades:
Replacement of aging garage doors to enhance facility security:
- Implementation of modern access control systems Fire Detection System Modernization:
- Installation of new heat and smoke detectors throughout the facility
- Integration of advanced strobe lighting systems for visual alerts
- Upgrade of the main fire control panel with current technology
Emergency Response Enhancement:
- Implementation of improved communication protocols with local fire department
- Integration of emergency response systems with facility operations Critical Infrastructure Protection:
- Installation of specialized Heptafluoropropane fire suppression system for SCADA server rooms
- Protection of vital operational control systems and data
Problem / Opportunity The existing equipment is outdated and unreliable. It is essential to upgrade and install new assets to maximize safety and security and to allow continuous operations.
Recommended Solution/Basis of Recommendation
Risk Management:
- Current systems may be outdated or insufficient for modern safety standards
- Critical SCADA infrastructure requires specialized protection
- Need for enhanced emergency response capabilities
Regulatory Compliance:
- Meeting updated fire safety codes and regulations
- Ensuring alignment with insurance requirements
- Maintaining compliance with industrial safety standards
Asset Protection:
- Safeguarding critical operational infrastructure
- Protecting valuable equipment and facilities
- Preserving essential operational data and control systems
Personnel Safety:
- Improving emergency detection and response times
- Enhancing evacuation capabilities
- Ensuring proper protection of staff during incidents
Measurable Benefits
Safety Improvements:
- Reduction in emergency response time
- Coverage of critical areas with modern detection systems
- Improvement in early detection capability
Asset Protection:
- Protection rate for critical SCADA infrastructure
- Reduction in potential damage from fire incidents
- Improvement in security breach prevention
Operational Benefits:
- Reduction in insurance premiums
- Reduction in false alarm incidents
- Improvement in emergency response coordination
Long-term Value:
- Extended life expectancy of critical systems
- Reduced maintenance costs through modern equipment
- Enhanced facility resilience and business continuity
Compliance and Documentation:
- Alignment with current fire safety regulations
- Improved documentation and tracking of safety systems
- Enhanced audit trail for safety and security incidents
Project Cost Estimate $3,000,000
Project Name Onsite Laboratory Upgrades
The Laboratory Infrastructure Upgrade Project aims to enhance the existing laboratory facilities at the wastewater treatment plant by implementing comprehensive protective measures against environmental contaminants, particularly dust and outdoor elements.
Assets Included Existing laboratory
Asset Install Date 1996
Scope of Work
- Installation of advanced air filtration systems
- Upgrading sealing mechanisms for doors and windows
- Implementation of positive pressure ventilation systems
- Modernization of workspace containment solutions
- Enhancement of sample storage and handling areas
Problem / Opportunity
This reduces the risk of sample contamination, which leads to fewer re-runs on tests. The new lab provides better environmental control which leads to more reliable instrument performance and improved working conditions for laboratory personnel.
Recommended Solution/Basis of Recommendation
Installation of a new laboratory with state of the art equipment will allow for a more workable space and will reduce the risk of contaminating samples.
Measurable Benefits The benefits of this project include increased laboratory quality assurance, regulatory compliance, and operational efficiency.
Project Cost Estimate $1,500,000
1.INTRODUCTION
2.PROPOSED PROJECTS INFORMATION
3.PROJECTS BY YEAR