Urgent repairs at SBIWTP to restore performance and add redundancy in process:
ACTION DESCRIPTION COST DATE
AWARDED NOTES
Repair Influent flow meter and associated piping and valves
Replace deteriorated Cement- Lined Ductile Iron (CLDI) piping and flow meter
$1,791,532 8/17/2021 Completed
Clean PSTs #1-4 Emergency Maintenance due to excess trash and sediment from excess inflows from MX
$1,782,473 7/28/2023 Completed
Repair Junction Box #1 Design and construction $5,793,110 8/10/2023 Complete by August 2025
Rehab PSTs #1-5 Emergency Maintenance due to trash and sediment from excess inflows from MX
$2,384,511 8/14/2023 Completed
USST Valves and Piping Replacement Rehab USST #1&2 $2,979,490 9/29/2023 Complete by Summer 2025
Backup Pumps & Motors For redundancy after TS Storm Hilary
$3,992,690 9/29/2023 Complete by December 2025
$197,543 8/9/2024 Modification for required electrical work
Clean Grit Chambers Emergency Maintenance due to trash and sediment from excess inflows from MX
$439,065 2/16/2024 Complete by May 2024
4 Backup Influent Pumps For redundancy after TS Storm Hilary $1,908,000 3/25/2024 Pumps on order
Complete by Summer 2025 Rehab Belt Filter Presses #1-4
Rapid deterioration caused by sand in sludge $4,668,046 5/10/2024 Complete by Summer 2025
Modifying for additional work
Hollister Street Pump Station Repairs
Clean out surge tanks filled with sediment and perform electrical repairs
$161,000 8/2/2024 Completed
Rehab Grit Facility Replace grit classifiers, gallery, Blowers, piping/valves and other components
$7,560,323 3/29/2025 Estimated completion October 2026
Replacement of Silva Drain and conveyance lines to
JB2
Replace collector structure and conveyance line to JB2, install 4 manholes
$637,012 4/21/2025 Estimated completion May
Rehab Hollister and Goats Pump Station
Replace Surge Arrestor system, Pumps, Odor Control, and electrical systems
TBD TBD Funding approved. Proposal expected the end of April
Total = $34,294,795
MOVING FORWARD – IBWC IS WORKING ON THE FOLLOWING KEY FRONTS
1. Continuation of urgent repairs for redundancy: Ongoing since 2023. Permit compliance achieved with completed urgent repairs in November 2024.
2. SBIWTP Expansion/Rehabilitation: Progressive design build awarded August 2024
3. Minute 328 – Ongoing monitoring progress of Mexico’s projects
4. Urgent action on Tijuana River Flows, including focus on PBCILA.