F22 Consolidated Operations and Maintenance Hangar (COMH), Langley AFB

Closed Solicitation Posted

This opportunity was awarded. See the award notice from , or the latest special notice from .

Solicitation number
W9123621R2003
Agency
Responses due
Set-aside
No set-aside

Opportunity facts

Place of performance
Langley AFB, Virginia 23665, United States

Notice details come from SAM.gov. Updated .

About this opportunity

This solicitation seeks design-build construction services for an F-22 Consolidated Operations and Maintenance Hangar at Joint Base Langley-Eustis in Virginia. The Department of the Army Corps of Engineers Engineering District Norfolk requires a six-bay hangar facility totaling 150,000 square feet to provide maintenance support for additional F-22A aircraft relocated from Tyndall Air Force Base. Responses will be evaluated based on specialized experience, past performance, small business participation, and price. The deadline for initial responses to evaluation Factors 1 and 2 was February 22, 2021, with full proposal requests issued through subsequent amendments.

The opportunity has no set-aside designation. The projected NAICS code is 237310 and PSC code is S206. The hangar must be completed within 700 calendar days of the notice to proceed, though an option could accelerate the schedule to 565 days. Site work will include fill, foundations, utilities and demolition of an existing 7,400 square meter facility at Joint Base Langley-Eustis. The total budget range is unspecified, though contract line items provide estimated values for individual scope components.

Notice text

18 versions

Update #18 · Latest ·

ONLY THOSE OFFERORS THAT SUBMITTED PROPOSAL RESPONSES TO FACTORS 1 AND 2 BY THE ORIGINAL RESPONSE DATE, ARE ALLOWED TO SUBMIT PROPOSALS FOR FACTORS 3 AND 4. REFER TO THE SOLICITATION AS AMENDED FOR FURTHER DETAILS.

01/21/2022 Amendment 0016 is issued to 1) provide revised specification; 2) correct a response to a projnet inquiry ID 9493801. This is the final amednment. The Government does not intend to issue any additional amendments. 

01/20/2022 Amendmnt 0015 is issued to 1) Extend the proposal due date to 28 Jan 2022 due to Government re-evaluation of concrete specifications; 2) to correct paragraph numbering throughout the solicitation; 3) correct reference to CLINs in the statutory cost limitation. Refer to SF30 for further details. One more amendment will be issued before the closing date. 

1/18/2022 Amendment 0014 is issued to extend the closing date to 21 January 2022 and to include the new wage determination.

01/12/2021 Amendment 0013 is issued to provide the following: 1) correction to the spec section 01 35 26; 2) Update Wage Determination. REFER TO ATTACHED SF30 for additional details. This is a the final amendment.

01/07/2021 Amendment 0012 is issued to provide the following: 1) extend prposal due date to 19 Jan 2022; 2) estimates for Dominion Virginia Power; 3) Delete a spec section 00 22 13.00 20, 4) revised Attachment 8 - CLIN Schedule; 5) Update solicitation CLINs to allign with Attachment 8; 6) Provide a response to an inquiry received; 7) Updates to clauses 52.217-7, 52.211-10 and 252.236-7001. REFER TO ATTACHED SF30 for additional details.

12/22/2021: Amendmnet 0011 is issued to provide the following: 1) technical changes to the drawings and specifications; 2) incorporate projnet responses into the solicitation.

Refer to SF30 and accomponying attachments for further details.

12/17/2021 Amendment 0010 is issued to provide the following:

1. Changes to drawings and specifications (Refer to Continuation page and attachments)

2. Wage Determination updated on 12 November 2021 (refer to continuation pages)
3. Provide Construction Security Plan (Refer to Attachment 16)
4. Provide Installation Restoration Program Background check document (Refer to Attachment 17)
5. Update Contract Specialist information
6. Proposal response date for Factors 3 and 4

Refer to SF30 and accomponaying attachmnents. Due date for responses to Factors 3 and 4 remains Jan 12, 2021 at 1400 EST. 

12/13/2021 - Amendment 0009 - The purpose of this amendment is to:
1.  Extend the period of proposal acceptance for Factors 1 and 2.
2.  Remove DFARS Clause 252.233-7999, Ensuring Adequate COVID-19 Safety Protocols for Federal Contractors (Deviation 2021-O0009)

12/06/2021 - Amendment 0008 to provide the following:
1. Change the submission approach to a bifurcated approach. Only Factors 1 and 2 are requested at this time.
2. Extend acceptance of Pre-Proposal Inquiries (PPIs).

11/24/2021 - Amendment 0007 - The purpose of Amendment 0007 is issued to provide the following: 
1. To amend the source selection procedures and remove Factor 3, Schedule, in its entirety. 
2. To provide changes to the technical documents. 
3. To provide revised drawings and specifications. 
4. To extend the solicitation response date.

11/9/2021  upload Amendment 0006.   To update specification Section 08 71 00 (see attachment 7 and the continuation sheet of the amendment)

10/26/2021 - Site Visit Sign-In Log Added to Attachments.

10/19/2021 Amendment 0005:  The purpose of this amendment is to:
1. To provide RTA drawings and specifications;
2. Incorporate additional contract clauses 252.204-7000 and 252.211-7003.
***RTA Drawings and specifications are uploaded as of 10/19/2021, a revised SF30 is pending due to system issues and will be posted once available.

Original Attachments:
Attachment 10 - COMH - Final Design Drawings Part 1 of 3.pdf
Attachment 11 - COMH - Final Design Drawings Part 2 of 3.pdf
Attachment 12 - COMH - Final Design Drawings Part 3 of 3.pdf
Attachment 13 - COMH Final Design Specifications Part 1 of 1.pdf

Replaced with:
Attachment 10 - COMH_RTA_Design Drawings_Part 1 of 3_17MAR21.pdf, dated 03/07/2021, 157 pages 
Attachment 11 - COMH_RTA_Design Drawings_Part 1 of 3_17MAR21, dated 03/07/2021, 161 pages 
Attachment 12 - COMH_RTA_Design Drawings_Part 3 of 3_17MAR21.pdf, dated 03/07/2021, 225 pages 
Attachment 13 - COMH_RTA_Specifications part 1 of 1_17MAR21, dated 03/07/2021, 2924 pages 
Attachment 14 - COMH - RTA FFE_17MAR21.pdf, dated 03/07/2021, 58 pages 
Attachment 15 - COMH - RTA SID_17MAR21, dated 03/07/2021, 32 pages

Amendment 0004 - The purpose of this amendment is to:
1. To update selection recency element under Factor 1;
2. Incorporate 252.233-7999 Ensuring Adequate COVID-19 Safety Protocols for Federal Contractors (Deviation 2021-O0009)

Amendment 0003. USACE has received authority to continue with the acquisition of this construction project. Due to the programmatic pause, this amendment permits new offerors to submit proposals in order to reasonably promote competition.  All offerors, including those that submitted proposals in response to the initial solicitation, are afforded equal consideration throughout the source selection process.

The purpose of this amendment is to provide the following: (See Continuation Page for Details)
1. To establish a new proposal due date; 
2. Extend the proposal validity for additional 180 days; 
3. Permit potential offerors who did not respond initially to submit a proposal in response to all factors;
4. Require the submission of all 5 factors.
5. Afford an opportunity for offerors to revise their proposal submission for Factors 1 and 2;
6. Afford an opportunity for offerors to withdraw their proposals; 
7. Provide proposal due date;
8. To update selection recency element under Factor 1 and 2;
9. To update wage determination;
10. Provide intent to include sole source items;
11. Provide update on door hardware schedule;
12. Provide site visit information.

Amendment 0002 -  Extends the period for acceptance of proposals for Technical Factors 1 and 2. - Amendment provided in posting Attachments.  No other changes.

Amendment 0001 - Provides responses to ProjNET questions - Amendment provided in posting Attachments.  No other changes.

This is the solicitation for F22 Consolidated Operations and Maintenance Hangar (COMH), Langley AFB, W9123621R2003.

Provide a six-bay high-bay consolidated operations and maintenance hangar to provide maintenance support for additional F-22A aircraft from Tyndall Air Force Base. Construction includes compacted fill above the 100-year flood plain, reinforced concrete foundations, concrete floor slab, structural steel frame with concrete masonry unit facade, and a standing seam metal roof. The facility will provide all necessary spaces to house hangar bays, staff administration, propulsion shop, ready room, break room, tools/parts support, aircraft maintenance equipment storage, wheel/tire shop, egress shop, restrooms/showers/lockers, and building systems support. The project includes all utilities, site improvements, pavements, detection/protection features, security enhancements, and other supporting work necessary to make a complete and useable facility. The facility must be able to withstand seismic and wind effects as prescribed in applicable codes and design guides. The project will demolish Facility 753 (7,400 Square Meters). Facilities will be designed as permanent construction in accordance with the DoD Unified Facilities Criteria 1-200-1, General Building Requirements. Sustainable principles and life-cycle cost-effective practices will be integrated into the design, development and construction of the project in accordance with Unified Facilities Criteria 1-200-02. This project will comply with Department of Defense minimum antiterrorism requirements in Unified Facilities Criteria 4-010-01. Air Conditioning: 150 Tons

The project duration is 700 calendar days from the notice to proceed, unless CLIN 0013 is exercised in which case the contract completion date will become 565 calendar days from notice to proceed.

Refer to the solicitation document for further details.

Update #17 ·

ONLY THOSE OFFERORS THAT SUBMITTED PROPOSAL RESPONSES TO FACTORS 1 AND 2 BY THE ORIGINAL RESPONSE DATE, ARE ALLOWED TO SUBMIT PROPOSALS FOR FACTORS 3 AND 4. REFER TO THE SOLICITATION AS AMENDED FOR FURTHER DETAILS.

01/20/2022 Amendmnt 0015 is issued to 1) Extend the proposal due date to 28 Jan 2022 due to Government re-evaluation of concrete specifications; 2) to correct paragraph numbering throughout the solicitation; 3) correct reference to CLINs in the statutory cost limitation. Refer to SF30 for further details. One more amendment will be issued before the closing date. 

1/18/2022 Amendment 0014 is issued to extend the closing date to 21 January 2022 and to include the new wage determination.

01/12/2021 Amendment 0013 is issued to provide the following: 1) correction to the spec section 01 35 26; 2) Update Wage Determination. REFER TO ATTACHED SF30 for additional details. This is a the final amendment.

01/07/2021 Amendment 0012 is issued to provide the following: 1) extend prposal due date to 19 Jan 2022; 2) estimates for Dominion Virginia Power; 3) Delete a spec section 00 22 13.00 20, 4) revised Attachment 8 - CLIN Schedule; 5) Update solicitation CLINs to allign with Attachment 8; 6) Provide a response to an inquiry received; 7) Updates to clauses 52.217-7, 52.211-10 and 252.236-7001. REFER TO ATTACHED SF30 for additional details.

12/22/2021: Amendmnet 0011 is issued to provide the following: 1) technical changes to the drawings and specifications; 2) incorporate projnet responses into the solicitation.

Refer to SF30 and accomponying attachments for further details.

12/17/2021 Amendment 0010 is issued to provide the following:

1. Changes to drawings and specifications (Refer to Continuation page and attachments)

2. Wage Determination updated on 12 November 2021 (refer to continuation pages)
3. Provide Construction Security Plan (Refer to Attachment 16)
4. Provide Installation Restoration Program Background check document (Refer to Attachment 17)
5. Update Contract Specialist information
6. Proposal response date for Factors 3 and 4

Refer to SF30 and accomponaying attachmnents. Due date for responses to Factors 3 and 4 remains Jan 12, 2021 at 1400 EST. 

12/13/2021 - Amendment 0009 - The purpose of this amendment is to:
1.  Extend the period of proposal acceptance for Factors 1 and 2.
2.  Remove DFARS Clause 252.233-7999, Ensuring Adequate COVID-19 Safety Protocols for Federal Contractors (Deviation 2021-O0009)

12/06/2021 - Amendment 0008 to provide the following:
1. Change the submission approach to a bifurcated approach. Only Factors 1 and 2 are requested at this time.
2. Extend acceptance of Pre-Proposal Inquiries (PPIs).

11/24/2021 - Amendment 0007 - The purpose of Amendment 0007 is issued to provide the following: 
1. To amend the source selection procedures and remove Factor 3, Schedule, in its entirety. 
2. To provide changes to the technical documents. 
3. To provide revised drawings and specifications. 
4. To extend the solicitation response date.

11/9/2021  upload Amendment 0006.   To update specification Section 08 71 00 (see attachment 7 and the continuation sheet of the amendment)

10/26/2021 - Site Visit Sign-In Log Added to Attachments.

10/19/2021 Amendment 0005:  The purpose of this amendment is to:
1. To provide RTA drawings and specifications;
2. Incorporate additional contract clauses 252.204-7000 and 252.211-7003.
***RTA Drawings and specifications are uploaded as of 10/19/2021, a revised SF30 is pending due to system issues and will be posted once available.

Original Attachments:
Attachment 10 - COMH - Final Design Drawings Part 1 of 3.pdf
Attachment 11 - COMH - Final Design Drawings Part 2 of 3.pdf
Attachment 12 - COMH - Final Design Drawings Part 3 of 3.pdf
Attachment 13 - COMH Final Design Specifications Part 1 of 1.pdf

Replaced with:
Attachment 10 - COMH_RTA_Design Drawings_Part 1 of 3_17MAR21.pdf, dated 03/07/2021, 157 pages 
Attachment 11 - COMH_RTA_Design Drawings_Part 1 of 3_17MAR21, dated 03/07/2021, 161 pages 
Attachment 12 - COMH_RTA_Design Drawings_Part 3 of 3_17MAR21.pdf, dated 03/07/2021, 225 pages 
Attachment 13 - COMH_RTA_Specifications part 1 of 1_17MAR21, dated 03/07/2021, 2924 pages 
Attachment 14 - COMH - RTA FFE_17MAR21.pdf, dated 03/07/2021, 58 pages 
Attachment 15 - COMH - RTA SID_17MAR21, dated 03/07/2021, 32 pages

Amendment 0004 - The purpose of this amendment is to:
1. To update selection recency element under Factor 1;
2. Incorporate 252.233-7999 Ensuring Adequate COVID-19 Safety Protocols for Federal Contractors (Deviation 2021-O0009)

Amendment 0003. USACE has received authority to continue with the acquisition of this construction project. Due to the programmatic pause, this amendment permits new offerors to submit proposals in order to reasonably promote competition.  All offerors, including those that submitted proposals in response to the initial solicitation, are afforded equal consideration throughout the source selection process.

The purpose of this amendment is to provide the following: (See Continuation Page for Details)
1. To establish a new proposal due date; 
2. Extend the proposal validity for additional 180 days; 
3. Permit potential offerors who did not respond initially to submit a proposal in response to all factors;
4. Require the submission of all 5 factors.
5. Afford an opportunity for offerors to revise their proposal submission for Factors 1 and 2;
6. Afford an opportunity for offerors to withdraw their proposals; 
7. Provide proposal due date;
8. To update selection recency element under Factor 1 and 2;
9. To update wage determination;
10. Provide intent to include sole source items;
11. Provide update on door hardware schedule;
12. Provide site visit information.

Amendment 0002 -  Extends the period for acceptance of proposals for Technical Factors 1 and 2. - Amendment provided in posting Attachments.  No other changes.

Amendment 0001 - Provides responses to ProjNET questions - Amendment provided in posting Attachments.  No other changes.

This is the solicitation for F22 Consolidated Operations and Maintenance Hangar (COMH), Langley AFB, W9123621R2003.

Provide a six-bay high-bay consolidated operations and maintenance hangar to provide maintenance support for additional F-22A aircraft from Tyndall Air Force Base. Construction includes compacted fill above the 100-year flood plain, reinforced concrete foundations, concrete floor slab, structural steel frame with concrete masonry unit facade, and a standing seam metal roof. The facility will provide all necessary spaces to house hangar bays, staff administration, propulsion shop, ready room, break room, tools/parts support, aircraft maintenance equipment storage, wheel/tire shop, egress shop, restrooms/showers/lockers, and building systems support. The project includes all utilities, site improvements, pavements, detection/protection features, security enhancements, and other supporting work necessary to make a complete and useable facility. The facility must be able to withstand seismic and wind effects as prescribed in applicable codes and design guides. The project will demolish Facility 753 (7,400 Square Meters). Facilities will be designed as permanent construction in accordance with the DoD Unified Facilities Criteria 1-200-1, General Building Requirements. Sustainable principles and life-cycle cost-effective practices will be integrated into the design, development and construction of the project in accordance with Unified Facilities Criteria 1-200-02. This project will comply with Department of Defense minimum antiterrorism requirements in Unified Facilities Criteria 4-010-01. Air Conditioning: 150 Tons

The project duration is 700 calendar days from the notice to proceed, unless CLIN 0013 is exercised in which case the contract completion date will become 565 calendar days from notice to proceed.

Refer to the solicitation document for further details.

Update #16 ·

ONLY THOSE OFFERORS THAT SUBMITTED PROPOSAL RESPONSES TO FACTORS 1 AND 2 BY THE ORIGINAL RESPONSE DATE, ARE ALLOWED TO SUBMIT PROPOSALS FOR FACTORS 3 AND 4. REFER TO THE SOLICITATION AS AMENDED FOR FURTHER DETAILS.

1/18/2022 Amendment 0014 is issued to extend the closing date to 21 January 2022 and to include the new wage determination.

01/12/2021 Amendment 0013 is issued to provide the following: 1) correction to the spec section 01 35 26; 2) Update Wage Determination. REFER TO ATTACHED SF30 for additional details. This is a the final amendment.

01/07/2021 Amendment 0012 is issued to provide the following: 1) extend prposal due date to 19 Jan 2022; 2) estimates for Dominion Virginia Power; 3) Delete a spec section 00 22 13.00 20, 4) revised Attachment 8 - CLIN Schedule; 5) Update solicitation CLINs to allign with Attachment 8; 6) Provide a response to an inquiry received; 7) Updates to clauses 52.217-7, 52.211-10 and 252.236-7001. REFER TO ATTACHED SF30 for additional details.

12/22/2021: Amendmnet 0011 is issued to provide the following: 1) technical changes to the drawings and specifications; 2) incorporate projnet responses into the solicitation.

Refer to SF30 and accomponying attachments for further details.

12/17/2021 Amendment 0010 is issued to provide the following:

1. Changes to drawings and specifications (Refer to Continuation page and attachments)

2. Wage Determination updated on 12 November 2021 (refer to continuation pages)
3. Provide Construction Security Plan (Refer to Attachment 16)
4. Provide Installation Restoration Program Background check document (Refer to Attachment 17)
5. Update Contract Specialist information
6. Proposal response date for Factors 3 and 4

Refer to SF30 and accomponaying attachmnents. Due date for responses to Factors 3 and 4 remains Jan 12, 2021 at 1400 EST. 

12/13/2021 - Amendment 0009 - The purpose of this amendment is to:
1.  Extend the period of proposal acceptance for Factors 1 and 2.
2.  Remove DFARS Clause 252.233-7999, Ensuring Adequate COVID-19 Safety Protocols for Federal Contractors (Deviation 2021-O0009)

12/06/2021 - Amendment 0008 to provide the following:
1. Change the submission approach to a bifurcated approach. Only Factors 1 and 2 are requested at this time.
2. Extend acceptance of Pre-Proposal Inquiries (PPIs).

11/24/2021 - Amendment 0007 - The purpose of Amendment 0007 is issued to provide the following: 
1. To amend the source selection procedures and remove Factor 3, Schedule, in its entirety. 
2. To provide changes to the technical documents. 
3. To provide revised drawings and specifications. 
4. To extend the solicitation response date.

11/9/2021  upload Amendment 0006.   To update specification Section 08 71 00 (see attachment 7 and the continuation sheet of the amendment)

10/26/2021 - Site Visit Sign-In Log Added to Attachments.

10/19/2021 Amendment 0005:  The purpose of this amendment is to:
1. To provide RTA drawings and specifications;
2. Incorporate additional contract clauses 252.204-7000 and 252.211-7003.
***RTA Drawings and specifications are uploaded as of 10/19/2021, a revised SF30 is pending due to system issues and will be posted once available.

Original Attachments:
Attachment 10 - COMH - Final Design Drawings Part 1 of 3.pdf
Attachment 11 - COMH - Final Design Drawings Part 2 of 3.pdf
Attachment 12 - COMH - Final Design Drawings Part 3 of 3.pdf
Attachment 13 - COMH Final Design Specifications Part 1 of 1.pdf

Replaced with:
Attachment 10 - COMH_RTA_Design Drawings_Part 1 of 3_17MAR21.pdf, dated 03/07/2021, 157 pages 
Attachment 11 - COMH_RTA_Design Drawings_Part 1 of 3_17MAR21, dated 03/07/2021, 161 pages 
Attachment 12 - COMH_RTA_Design Drawings_Part 3 of 3_17MAR21.pdf, dated 03/07/2021, 225 pages 
Attachment 13 - COMH_RTA_Specifications part 1 of 1_17MAR21, dated 03/07/2021, 2924 pages 
Attachment 14 - COMH - RTA FFE_17MAR21.pdf, dated 03/07/2021, 58 pages 
Attachment 15 - COMH - RTA SID_17MAR21, dated 03/07/2021, 32 pages

Amendment 0004 - The purpose of this amendment is to:
1. To update selection recency element under Factor 1;
2. Incorporate 252.233-7999 Ensuring Adequate COVID-19 Safety Protocols for Federal Contractors (Deviation 2021-O0009)

Amendment 0003. USACE has received authority to continue with the acquisition of this construction project. Due to the programmatic pause, this amendment permits new offerors to submit proposals in order to reasonably promote competition.  All offerors, including those that submitted proposals in response to the initial solicitation, are afforded equal consideration throughout the source selection process.

The purpose of this amendment is to provide the following: (See Continuation Page for Details)
1. To establish a new proposal due date; 
2. Extend the proposal validity for additional 180 days; 
3. Permit potential offerors who did not respond initially to submit a proposal in response to all factors;
4. Require the submission of all 5 factors.
5. Afford an opportunity for offerors to revise their proposal submission for Factors 1 and 2;
6. Afford an opportunity for offerors to withdraw their proposals; 
7. Provide proposal due date;
8. To update selection recency element under Factor 1 and 2;
9. To update wage determination;
10. Provide intent to include sole source items;
11. Provide update on door hardware schedule;
12. Provide site visit information.

Amendment 0002 -  Extends the period for acceptance of proposals for Technical Factors 1 and 2. - Amendment provided in posting Attachments.  No other changes.

Amendment 0001 - Provides responses to ProjNET questions - Amendment provided in posting Attachments.  No other changes.

This is the solicitation for F22 Consolidated Operations and Maintenance Hangar (COMH), Langley AFB, W9123621R2003.

Provide a six-bay high-bay consolidated operations and maintenance hangar to provide maintenance support for additional F-22A aircraft from Tyndall Air Force Base. Construction includes compacted fill above the 100-year flood plain, reinforced concrete foundations, concrete floor slab, structural steel frame with concrete masonry unit facade, and a standing seam metal roof. The facility will provide all necessary spaces to house hangar bays, staff administration, propulsion shop, ready room, break room, tools/parts support, aircraft maintenance equipment storage, wheel/tire shop, egress shop, restrooms/showers/lockers, and building systems support. The project includes all utilities, site improvements, pavements, detection/protection features, security enhancements, and other supporting work necessary to make a complete and useable facility. The facility must be able to withstand seismic and wind effects as prescribed in applicable codes and design guides. The project will demolish Facility 753 (7,400 Square Meters). Facilities will be designed as permanent construction in accordance with the DoD Unified Facilities Criteria 1-200-1, General Building Requirements. Sustainable principles and life-cycle cost-effective practices will be integrated into the design, development and construction of the project in accordance with Unified Facilities Criteria 1-200-02. This project will comply with Department of Defense minimum antiterrorism requirements in Unified Facilities Criteria 4-010-01. Air Conditioning: 150 Tons

The project duration is 700 calendar days from the notice to proceed, unless CLIN 0013 is exercised in which case the contract completion date will become 565 calendar days from notice to proceed.

Refer to the solicitation document for further details.

Update #15 ·

ONLY THOSE OFFERORS THAT SUBMITTED PROPOSAL RESPONSES TO FACTORS 1 AND 2 BY THE ORIGINAL RESPONSE DATE, ARE ALLOWED TO SUBMIT PROPOSALS FOR FACTORS 3 AND 4. REFER TO THE SOLICITATION AS AMENDED FOR FURTHER DETAILS.

01/12/2021 Amendment 0013 is issued to provide the following: 1) correction to the spec section 01 35 26; 2) Update Wage Determination. REFER TO ATTACHED SF30 for additional details. This is a the final amendment.

01/07/2021 Amendment 0012 is issued to provide the following: 1) extend prposal due date to 19 Jan 2022; 2) estimates for Dominion Virginia Power; 3) Delete a spec section 00 22 13.00 20, 4) revised Attachment 8 - CLIN Schedule; 5) Update solicitation CLINs to allign with Attachment 8; 6) Provide a response to an inquiry received; 7) Updates to clauses 52.217-7, 52.211-10 and 252.236-7001. REFER TO ATTACHED SF30 for additional details.

12/22/2021: Amendmnet 0011 is issued to provide the following: 1) technical changes to the drawings and specifications; 2) incorporate projnet responses into the solicitation.

Refer to SF30 and accomponying attachments for further details.

12/17/2021 Amendment 0010 is issued to provide the following:

1. Changes to drawings and specifications (Refer to Continuation page and attachments)

2. Wage Determination updated on 12 November 2021 (refer to continuation pages)
3. Provide Construction Security Plan (Refer to Attachment 16)
4. Provide Installation Restoration Program Background check document (Refer to Attachment 17)
5. Update Contract Specialist information
6. Proposal response date for Factors 3 and 4

Refer to SF30 and accomponaying attachmnents. Due date for responses to Factors 3 and 4 remains Jan 12, 2021 at 1400 EST. 

12/13/2021 - Amendment 0009 - The purpose of this amendment is to:
1.  Extend the period of proposal acceptance for Factors 1 and 2.
2.  Remove DFARS Clause 252.233-7999, Ensuring Adequate COVID-19 Safety Protocols for Federal Contractors (Deviation 2021-O0009)

12/06/2021 - Amendment 0008 to provide the following:
1. Change the submission approach to a bifurcated approach. Only Factors 1 and 2 are requested at this time.
2. Extend acceptance of Pre-Proposal Inquiries (PPIs).

11/24/2021 - Amendment 0007 - The purpose of Amendment 0007 is issued to provide the following: 
1. To amend the source selection procedures and remove Factor 3, Schedule, in its entirety. 
2. To provide changes to the technical documents. 
3. To provide revised drawings and specifications. 
4. To extend the solicitation response date.

11/9/2021  upload Amendment 0006.   To update specification Section 08 71 00 (see attachment 7 and the continuation sheet of the amendment)

10/26/2021 - Site Visit Sign-In Log Added to Attachments.

10/19/2021 Amendment 0005:  The purpose of this amendment is to:
1. To provide RTA drawings and specifications;
2. Incorporate additional contract clauses 252.204-7000 and 252.211-7003.
***RTA Drawings and specifications are uploaded as of 10/19/2021, a revised SF30 is pending due to system issues and will be posted once available.

Original Attachments:
Attachment 10 - COMH - Final Design Drawings Part 1 of 3.pdf
Attachment 11 - COMH - Final Design Drawings Part 2 of 3.pdf
Attachment 12 - COMH - Final Design Drawings Part 3 of 3.pdf
Attachment 13 - COMH Final Design Specifications Part 1 of 1.pdf

Replaced with:
Attachment 10 - COMH_RTA_Design Drawings_Part 1 of 3_17MAR21.pdf, dated 03/07/2021, 157 pages 
Attachment 11 - COMH_RTA_Design Drawings_Part 1 of 3_17MAR21, dated 03/07/2021, 161 pages 
Attachment 12 - COMH_RTA_Design Drawings_Part 3 of 3_17MAR21.pdf, dated 03/07/2021, 225 pages 
Attachment 13 - COMH_RTA_Specifications part 1 of 1_17MAR21, dated 03/07/2021, 2924 pages 
Attachment 14 - COMH - RTA FFE_17MAR21.pdf, dated 03/07/2021, 58 pages 
Attachment 15 - COMH - RTA SID_17MAR21, dated 03/07/2021, 32 pages

Amendment 0004 - The purpose of this amendment is to:
1. To update selection recency element under Factor 1;
2. Incorporate 252.233-7999 Ensuring Adequate COVID-19 Safety Protocols for Federal Contractors (Deviation 2021-O0009)

Amendment 0003. USACE has received authority to continue with the acquisition of this construction project. Due to the programmatic pause, this amendment permits new offerors to submit proposals in order to reasonably promote competition.  All offerors, including those that submitted proposals in response to the initial solicitation, are afforded equal consideration throughout the source selection process.

The purpose of this amendment is to provide the following: (See Continuation Page for Details)
1. To establish a new proposal due date; 
2. Extend the proposal validity for additional 180 days; 
3. Permit potential offerors who did not respond initially to submit a proposal in response to all factors;
4. Require the submission of all 5 factors.
5. Afford an opportunity for offerors to revise their proposal submission for Factors 1 and 2;
6. Afford an opportunity for offerors to withdraw their proposals; 
7. Provide proposal due date;
8. To update selection recency element under Factor 1 and 2;
9. To update wage determination;
10. Provide intent to include sole source items;
11. Provide update on door hardware schedule;
12. Provide site visit information.

Amendment 0002 -  Extends the period for acceptance of proposals for Technical Factors 1 and 2. - Amendment provided in posting Attachments.  No other changes.

Amendment 0001 - Provides responses to ProjNET questions - Amendment provided in posting Attachments.  No other changes.

This is the solicitation for F22 Consolidated Operations and Maintenance Hangar (COMH), Langley AFB, W9123621R2003.

Provide a six-bay high-bay consolidated operations and maintenance hangar to provide maintenance support for additional F-22A aircraft from Tyndall Air Force Base. Construction includes compacted fill above the 100-year flood plain, reinforced concrete foundations, concrete floor slab, structural steel frame with concrete masonry unit facade, and a standing seam metal roof. The facility will provide all necessary spaces to house hangar bays, staff administration, propulsion shop, ready room, break room, tools/parts support, aircraft maintenance equipment storage, wheel/tire shop, egress shop, restrooms/showers/lockers, and building systems support. The project includes all utilities, site improvements, pavements, detection/protection features, security enhancements, and other supporting work necessary to make a complete and useable facility. The facility must be able to withstand seismic and wind effects as prescribed in applicable codes and design guides. The project will demolish Facility 753 (7,400 Square Meters). Facilities will be designed as permanent construction in accordance with the DoD Unified Facilities Criteria 1-200-1, General Building Requirements. Sustainable principles and life-cycle cost-effective practices will be integrated into the design, development and construction of the project in accordance with Unified Facilities Criteria 1-200-02. This project will comply with Department of Defense minimum antiterrorism requirements in Unified Facilities Criteria 4-010-01. Air Conditioning: 150 Tons

The project duration is 700 calendar days from the notice to proceed, unless CLIN 0013 is exercised in which case the contract completion date will become 565 calendar days from notice to proceed.

Refer to the solicitation document for further details.

Update #14 ·

ONLY THOSE OFFERORS THAT SUBMITTED PROPOSAL RESPONSES TO FACTORS 1 AND 2 BY THE ORIGINAL RESPONSE DATE, ARE ALLOWED TO SUBMIT PROPOSALS FOR FACTORS 3 AND 4. REFER TO THE SOLICITATION AS AMENDED FOR FURTHER DETAILS.

01/07/2021 Amendment 0012 is issued to provide the following: 1) extend prposal due date to 19 Jan 2022; 2) estimates for Dominion Virginia Power; 3) Delete a spec section 00 22 13.00 20, 4) revised Attachment 8 - CLIN Schedule; 5) Update solicitation CLINs to allign with Attachment 8; 6) Provide a response to an inquiry received; 7) Updates to clauses 52.217-7, 52.211-10 and 252.236-7001. REFER TO ATTACHED SF30 for additional details.

12/22/2021: Amendmnet 0011 is issued to provide the following: 1) technical changes to the drawings and specifications; 2) incorporate projnet responses into the solicitation.

Refer to SF30 and accomponying attachments for further details.

12/17/2021 Amendment 0010 is issued to provide the following:

1. Changes to drawings and specifications (Refer to Continuation page and attachments)

2. Wage Determination updated on 12 November 2021 (refer to continuation pages)
3. Provide Construction Security Plan (Refer to Attachment 16)
4. Provide Installation Restoration Program Background check document (Refer to Attachment 17)
5. Update Contract Specialist information
6. Proposal response date for Factors 3 and 4

Refer to SF30 and accomponaying attachmnents. Due date for responses to Factors 3 and 4 remains Jan 12, 2021 at 1400 EST. 

12/13/2021 - Amendment 0009 - The purpose of this amendment is to:
1.  Extend the period of proposal acceptance for Factors 1 and 2.
2.  Remove DFARS Clause 252.233-7999, Ensuring Adequate COVID-19 Safety Protocols for Federal Contractors (Deviation 2021-O0009)

12/06/2021 - Amendment 0008 to provide the following:
1. Change the submission approach to a bifurcated approach. Only Factors 1 and 2 are requested at this time.
2. Extend acceptance of Pre-Proposal Inquiries (PPIs).

11/24/2021 - Amendment 0007 - The purpose of Amendment 0007 is issued to provide the following: 
1. To amend the source selection procedures and remove Factor 3, Schedule, in its entirety. 
2. To provide changes to the technical documents. 
3. To provide revised drawings and specifications. 
4. To extend the solicitation response date.

11/9/2021  upload Amendment 0006.   To update specification Section 08 71 00 (see attachment 7 and the continuation sheet of the amendment)

10/26/2021 - Site Visit Sign-In Log Added to Attachments.

10/19/2021 Amendment 0005:  The purpose of this amendment is to:
1. To provide RTA drawings and specifications;
2. Incorporate additional contract clauses 252.204-7000 and 252.211-7003.
***RTA Drawings and specifications are uploaded as of 10/19/2021, a revised SF30 is pending due to system issues and will be posted once available.

Original Attachments:
Attachment 10 - COMH - Final Design Drawings Part 1 of 3.pdf
Attachment 11 - COMH - Final Design Drawings Part 2 of 3.pdf
Attachment 12 - COMH - Final Design Drawings Part 3 of 3.pdf
Attachment 13 - COMH Final Design Specifications Part 1 of 1.pdf

Replaced with:
Attachment 10 - COMH_RTA_Design Drawings_Part 1 of 3_17MAR21.pdf, dated 03/07/2021, 157 pages 
Attachment 11 - COMH_RTA_Design Drawings_Part 1 of 3_17MAR21, dated 03/07/2021, 161 pages 
Attachment 12 - COMH_RTA_Design Drawings_Part 3 of 3_17MAR21.pdf, dated 03/07/2021, 225 pages 
Attachment 13 - COMH_RTA_Specifications part 1 of 1_17MAR21, dated 03/07/2021, 2924 pages 
Attachment 14 - COMH - RTA FFE_17MAR21.pdf, dated 03/07/2021, 58 pages 
Attachment 15 - COMH - RTA SID_17MAR21, dated 03/07/2021, 32 pages

Amendment 0004 - The purpose of this amendment is to:
1. To update selection recency element under Factor 1;
2. Incorporate 252.233-7999 Ensuring Adequate COVID-19 Safety Protocols for Federal Contractors (Deviation 2021-O0009)

Amendment 0003. USACE has received authority to continue with the acquisition of this construction project. Due to the programmatic pause, this amendment permits new offerors to submit proposals in order to reasonably promote competition.  All offerors, including those that submitted proposals in response to the initial solicitation, are afforded equal consideration throughout the source selection process.

The purpose of this amendment is to provide the following: (See Continuation Page for Details)
1. To establish a new proposal due date; 
2. Extend the proposal validity for additional 180 days; 
3. Permit potential offerors who did not respond initially to submit a proposal in response to all factors;
4. Require the submission of all 5 factors.
5. Afford an opportunity for offerors to revise their proposal submission for Factors 1 and 2;
6. Afford an opportunity for offerors to withdraw their proposals; 
7. Provide proposal due date;
8. To update selection recency element under Factor 1 and 2;
9. To update wage determination;
10. Provide intent to include sole source items;
11. Provide update on door hardware schedule;
12. Provide site visit information.

Amendment 0002 -  Extends the period for acceptance of proposals for Technical Factors 1 and 2. - Amendment provided in posting Attachments.  No other changes.

Amendment 0001 - Provides responses to ProjNET questions - Amendment provided in posting Attachments.  No other changes.

This is the solicitation for F22 Consolidated Operations and Maintenance Hangar (COMH), Langley AFB, W9123621R2003.

Provide a six-bay high-bay consolidated operations and maintenance hangar to provide maintenance support for additional F-22A aircraft from Tyndall Air Force Base. Construction includes compacted fill above the 100-year flood plain, reinforced concrete foundations, concrete floor slab, structural steel frame with concrete masonry unit facade, and a standing seam metal roof. The facility will provide all necessary spaces to house hangar bays, staff administration, propulsion shop, ready room, break room, tools/parts support, aircraft maintenance equipment storage, wheel/tire shop, egress shop, restrooms/showers/lockers, and building systems support. The project includes all utilities, site improvements, pavements, detection/protection features, security enhancements, and other supporting work necessary to make a complete and useable facility. The facility must be able to withstand seismic and wind effects as prescribed in applicable codes and design guides. The project will demolish Facility 753 (7,400 Square Meters). Facilities will be designed as permanent construction in accordance with the DoD Unified Facilities Criteria 1-200-1, General Building Requirements. Sustainable principles and life-cycle cost-effective practices will be integrated into the design, development and construction of the project in accordance with Unified Facilities Criteria 1-200-02. This project will comply with Department of Defense minimum antiterrorism requirements in Unified Facilities Criteria 4-010-01. Air Conditioning: 150 Tons

The project duration is 700 calendar days from the notice to proceed, unless CLIN 0013 is exercised in which case the contract completion date will become 565 calendar days from notice to proceed.

Refer to the solicitation document for further details.

Update #13 ·

ONLY THOSE OFFERORS THAT SUBMITTED PROPOSAL RESPONSES TO FACTORS 1 AND 2 BY THE ORIGINAL RESPONSE DATE, ARE ALLOWED TO SUBMIT PROPOSALS FOR FACTORS 3 AND 4. REFER TO THE SOLICITATION AS AMENDED FOR FURTHER DETAILS.

12/22/2021: Amendmnet 0011 is issued to provide the following: 1) technical changes to the drawings and specifications; 2) incorporate projnet responses into the solicitation.

Refer to SF30 and accomponying attachments for further details.

12/17/2021 Amendment 0010 is issued to provide the following:

1. Changes to drawings and specifications (Refer to Continuation page and attachments)

2. Wage Determination updated on 12 November 2021 (refer to continuation pages)
3. Provide Construction Security Plan (Refer to Attachment 16)
4. Provide Installation Restoration Program Background check document (Refer to Attachment 17)
5. Update Contract Specialist information
6. Proposal response date for Factors 3 and 4

Refer to SF30 and accomponaying attachmnents. Due date for responses to Factors 3 and 4 remains Jan 12, 2021 at 1400 EST. 

12/13/2021 - Amendment 0009 - The purpose of this amendment is to:
1.  Extend the period of proposal acceptance for Factors 1 and 2.
2.  Remove DFARS Clause 252.233-7999, Ensuring Adequate COVID-19 Safety Protocols for Federal Contractors (Deviation 2021-O0009)

12/06/2021 - Amendment 0008 to provide the following:
1. Change the submission approach to a bifurcated approach. Only Factors 1 and 2 are requested at this time.
2. Extend acceptance of Pre-Proposal Inquiries (PPIs).

11/24/2021 - Amendment 0007 - The purpose of Amendment 0007 is issued to provide the following: 
1. To amend the source selection procedures and remove Factor 3, Schedule, in its entirety. 
2. To provide changes to the technical documents. 
3. To provide revised drawings and specifications. 
4. To extend the solicitation response date.

11/9/2021  upload Amendment 0006.   To update specification Section 08 71 00 (see attachment 7 and the continuation sheet of the amendment)

10/26/2021 - Site Visit Sign-In Log Added to Attachments.

10/19/2021 Amendment 0005:  The purpose of this amendment is to:
1. To provide RTA drawings and specifications;
2. Incorporate additional contract clauses 252.204-7000 and 252.211-7003.
***RTA Drawings and specifications are uploaded as of 10/19/2021, a revised SF30 is pending due to system issues and will be posted once available.

Original Attachments:
Attachment 10 - COMH - Final Design Drawings Part 1 of 3.pdf
Attachment 11 - COMH - Final Design Drawings Part 2 of 3.pdf
Attachment 12 - COMH - Final Design Drawings Part 3 of 3.pdf
Attachment 13 - COMH Final Design Specifications Part 1 of 1.pdf

Replaced with:
Attachment 10 - COMH_RTA_Design Drawings_Part 1 of 3_17MAR21.pdf, dated 03/07/2021, 157 pages 
Attachment 11 - COMH_RTA_Design Drawings_Part 1 of 3_17MAR21, dated 03/07/2021, 161 pages 
Attachment 12 - COMH_RTA_Design Drawings_Part 3 of 3_17MAR21.pdf, dated 03/07/2021, 225 pages 
Attachment 13 - COMH_RTA_Specifications part 1 of 1_17MAR21, dated 03/07/2021, 2924 pages 
Attachment 14 - COMH - RTA FFE_17MAR21.pdf, dated 03/07/2021, 58 pages 
Attachment 15 - COMH - RTA SID_17MAR21, dated 03/07/2021, 32 pages

Amendment 0004 - The purpose of this amendment is to:
1. To update selection recency element under Factor 1;
2. Incorporate 252.233-7999 Ensuring Adequate COVID-19 Safety Protocols for Federal Contractors (Deviation 2021-O0009)

Amendment 0003. USACE has received authority to continue with the acquisition of this construction project. Due to the programmatic pause, this amendment permits new offerors to submit proposals in order to reasonably promote competition.  All offerors, including those that submitted proposals in response to the initial solicitation, are afforded equal consideration throughout the source selection process.

The purpose of this amendment is to provide the following: (See Continuation Page for Details)
1. To establish a new proposal due date; 
2. Extend the proposal validity for additional 180 days; 
3. Permit potential offerors who did not respond initially to submit a proposal in response to all factors;
4. Require the submission of all 5 factors.
5. Afford an opportunity for offerors to revise their proposal submission for Factors 1 and 2;
6. Afford an opportunity for offerors to withdraw their proposals; 
7. Provide proposal due date;
8. To update selection recency element under Factor 1 and 2;
9. To update wage determination;
10. Provide intent to include sole source items;
11. Provide update on door hardware schedule;
12. Provide site visit information.

Amendment 0002 -  Extends the period for acceptance of proposals for Technical Factors 1 and 2. - Amendment provided in posting Attachments.  No other changes.

Amendment 0001 - Provides responses to ProjNET questions - Amendment provided in posting Attachments.  No other changes.

This is the solicitation for F22 Consolidated Operations and Maintenance Hangar (COMH), Langley AFB, W9123621R2003.

Provide a six-bay high-bay consolidated operations and maintenance hangar to provide maintenance support for additional F-22A aircraft from Tyndall Air Force Base. Construction includes compacted fill above the 100-year flood plain, reinforced concrete foundations, concrete floor slab, structural steel frame with concrete masonry unit facade, and a standing seam metal roof. The facility will provide all necessary spaces to house hangar bays, staff administration, propulsion shop, ready room, break room, tools/parts support, aircraft maintenance equipment storage, wheel/tire shop, egress shop, restrooms/showers/lockers, and building systems support. The project includes all utilities, site improvements, pavements, detection/protection features, security enhancements, and other supporting work necessary to make a complete and useable facility. The facility must be able to withstand seismic and wind effects as prescribed in applicable codes and design guides. The project will demolish Facility 753 (7,400 Square Meters). Facilities will be designed as permanent construction in accordance with the DoD Unified Facilities Criteria 1-200-1, General Building Requirements. Sustainable principles and life-cycle cost-effective practices will be integrated into the design, development and construction of the project in accordance with Unified Facilities Criteria 1-200-02. This project will comply with Department of Defense minimum antiterrorism requirements in Unified Facilities Criteria 4-010-01. Air Conditioning: 150 Tons

The project duration is 700 calendar days from the notice to proceed, unless CLIN 0013 is exercised in which case the contract completion date will become 565 calendar days from notice to proceed.

Refer to the solicitation document for further details.

Update #12 ·

12/17/2021 Amendment 0010 is issued to provide the following:

1. Changes to drawings and specifications (Refer to Continuation page and attachments)

2. Wage Determination updated on 12 November 2021 (refer to continuation pages)
3. Provide Construction Security Plan (Refer to Attachment 16)
4. Provide Installation Restoration Program Background check document (Refer to Attachment 17)
5. Update Contract Specialist information
6. Proposal response date for Factors 3 and 4

Refer to SF30 and accomponaying attachmnents. Due date for responses to Factors 3 and 4 remains Jan 12, 2021 at 1400 EST. 

12/13/2021 - Amendment 0009 - The purpose of this amendment is to:
1.  Extend the period of proposal acceptance for Factors 1 and 2.
2.  Remove DFARS Clause 252.233-7999, Ensuring Adequate COVID-19 Safety Protocols for Federal Contractors (Deviation 2021-O0009)

12/06/2021 - Amendment 0008 to provide the following:
1. Change the submission approach to a bifurcated approach. Only Factors 1 and 2 are requested at this time.
2. Extend acceptance of Pre-Proposal Inquiries (PPIs).

11/24/2021 - Amendment 0007 - The purpose of Amendment 0007 is issued to provide the following: 
1. To amend the source selection procedures and remove Factor 3, Schedule, in its entirety. 
2. To provide changes to the technical documents. 
3. To provide revised drawings and specifications. 
4. To extend the solicitation response date.

11/9/2021  upload Amendment 0006.   To update specification Section 08 71 00 (see attachment 7 and the continuation sheet of the amendment)

10/26/2021 - Site Visit Sign-In Log Added to Attachments.

10/19/2021 Amendment 0005:  The purpose of this amendment is to:
1. To provide RTA drawings and specifications;
2. Incorporate additional contract clauses 252.204-7000 and 252.211-7003.
***RTA Drawings and specifications are uploaded as of 10/19/2021, a revised SF30 is pending due to system issues and will be posted once available.

Original Attachments:
Attachment 10 - COMH - Final Design Drawings Part 1 of 3.pdf
Attachment 11 - COMH - Final Design Drawings Part 2 of 3.pdf
Attachment 12 - COMH - Final Design Drawings Part 3 of 3.pdf
Attachment 13 - COMH Final Design Specifications Part 1 of 1.pdf

Replaced with:
Attachment 10 - COMH_RTA_Design Drawings_Part 1 of 3_17MAR21.pdf, dated 03/07/2021, 157 pages 
Attachment 11 - COMH_RTA_Design Drawings_Part 1 of 3_17MAR21, dated 03/07/2021, 161 pages 
Attachment 12 - COMH_RTA_Design Drawings_Part 3 of 3_17MAR21.pdf, dated 03/07/2021, 225 pages 
Attachment 13 - COMH_RTA_Specifications part 1 of 1_17MAR21, dated 03/07/2021, 2924 pages 
Attachment 14 - COMH - RTA FFE_17MAR21.pdf, dated 03/07/2021, 58 pages 
Attachment 15 - COMH - RTA SID_17MAR21, dated 03/07/2021, 32 pages

Amendment 0004 - The purpose of this amendment is to:
1. To update selection recency element under Factor 1;
2. Incorporate 252.233-7999 Ensuring Adequate COVID-19 Safety Protocols for Federal Contractors (Deviation 2021-O0009)

Amendment 0003. USACE has received authority to continue with the acquisition of this construction project. Due to the programmatic pause, this amendment permits new offerors to submit proposals in order to reasonably promote competition.  All offerors, including those that submitted proposals in response to the initial solicitation, are afforded equal consideration throughout the source selection process.

The purpose of this amendment is to provide the following: (See Continuation Page for Details)
1. To establish a new proposal due date; 
2. Extend the proposal validity for additional 180 days; 
3. Permit potential offerors who did not respond initially to submit a proposal in response to all factors;
4. Require the submission of all 5 factors.
5. Afford an opportunity for offerors to revise their proposal submission for Factors 1 and 2;
6. Afford an opportunity for offerors to withdraw their proposals; 
7. Provide proposal due date;
8. To update selection recency element under Factor 1 and 2;
9. To update wage determination;
10. Provide intent to include sole source items;
11. Provide update on door hardware schedule;
12. Provide site visit information.

Amendment 0002 -  Extends the period for acceptance of proposals for Technical Factors 1 and 2. - Amendment provided in posting Attachments.  No other changes.

Amendment 0001 - Provides responses to ProjNET questions - Amendment provided in posting Attachments.  No other changes.

This is the solicitation for F22 Consolidated Operations and Maintenance Hangar (COMH), Langley AFB, W9123621R2003.

Provide a six-bay high-bay consolidated operations and maintenance hangar to provide maintenance support for additional F-22A aircraft from Tyndall Air Force Base. Construction includes compacted fill above the 100-year flood plain, reinforced concrete foundations, concrete floor slab, structural steel frame with concrete masonry unit facade, and a standing seam metal roof. The facility will provide all necessary spaces to house hangar bays, staff administration, propulsion shop, ready room, break room, tools/parts support, aircraft maintenance equipment storage, wheel/tire shop, egress shop, restrooms/showers/lockers, and building systems support. The project includes all utilities, site improvements, pavements, detection/protection features, security enhancements, and other supporting work necessary to make a complete and useable facility. The facility must be able to withstand seismic and wind effects as prescribed in applicable codes and design guides. The project will demolish Facility 753 (7,400 Square Meters). Facilities will be designed as permanent construction in accordance with the DoD Unified Facilities Criteria 1-200-1, General Building Requirements. Sustainable principles and life-cycle cost-effective practices will be integrated into the design, development and construction of the project in accordance with Unified Facilities Criteria 1-200-02. This project will comply with Department of Defense minimum antiterrorism requirements in Unified Facilities Criteria 4-010-01. Air Conditioning: 150 Tons

The project duration is 700 calendar days from the notice to proceed, unless CLIN 0013 is exercised in which case the contract completion date will become 565 calendar days from notice to proceed.

Refer to the solicitation document for further details.

Update #11 ·

12/13/2021 - Amendment 0009 - The purpose of this amendment is to:
1.  Extend the period of proposal acceptance for Factors 1 and 2.
2.  Remove DFARS Clause 252.233-7999, Ensuring Adequate COVID-19 Safety Protocols for Federal Contractors (Deviation 2021-O0009)

12/06/2021 - Amendment 0008 to provide the following:
1. Change the submission approach to a bifurcated approach. Only Factors 1 and 2 are requested at this time.
2. Extend acceptance of Pre-Proposal Inquiries (PPIs).

11/24/2021 - Amendment 0007 - The purpose of Amendment 0007 is issued to provide the following: 
1. To amend the source selection procedures and remove Factor 3, Schedule, in its entirety. 
2. To provide changes to the technical documents. 
3. To provide revised drawings and specifications. 
4. To extend the solicitation response date.

11/9/2021  upload Amendment 0006.   To update specification Section 08 71 00 (see attachment 7 and the continuation sheet of the amendment)

10/26/2021 - Site Visit Sign-In Log Added to Attachments.

10/19/2021 Amendment 0005:  The purpose of this amendment is to:
1. To provide RTA drawings and specifications;
2. Incorporate additional contract clauses 252.204-7000 and 252.211-7003.
***RTA Drawings and specifications are uploaded as of 10/19/2021, a revised SF30 is pending due to system issues and will be posted once available.

Original Attachments:
Attachment 10 - COMH - Final Design Drawings Part 1 of 3.pdf
Attachment 11 - COMH - Final Design Drawings Part 2 of 3.pdf
Attachment 12 - COMH - Final Design Drawings Part 3 of 3.pdf
Attachment 13 - COMH Final Design Specifications Part 1 of 1.pdf

Replaced with:
Attachment 10 - COMH_RTA_Design Drawings_Part 1 of 3_17MAR21.pdf, dated 03/07/2021, 157 pages 
Attachment 11 - COMH_RTA_Design Drawings_Part 1 of 3_17MAR21, dated 03/07/2021, 161 pages 
Attachment 12 - COMH_RTA_Design Drawings_Part 3 of 3_17MAR21.pdf, dated 03/07/2021, 225 pages 
Attachment 13 - COMH_RTA_Specifications part 1 of 1_17MAR21, dated 03/07/2021, 2924 pages 
Attachment 14 - COMH - RTA FFE_17MAR21.pdf, dated 03/07/2021, 58 pages 
Attachment 15 - COMH - RTA SID_17MAR21, dated 03/07/2021, 32 pages

Amendment 0004 - The purpose of this amendment is to:
1. To update selection recency element under Factor 1;
2. Incorporate 252.233-7999 Ensuring Adequate COVID-19 Safety Protocols for Federal Contractors (Deviation 2021-O0009)

Amendment 0003. USACE has received authority to continue with the acquisition of this construction project. Due to the programmatic pause, this amendment permits new offerors to submit proposals in order to reasonably promote competition.  All offerors, including those that submitted proposals in response to the initial solicitation, are afforded equal consideration throughout the source selection process.

The purpose of this amendment is to provide the following: (See Continuation Page for Details)
1. To establish a new proposal due date; 
2. Extend the proposal validity for additional 180 days; 
3. Permit potential offerors who did not respond initially to submit a proposal in response to all factors;
4. Require the submission of all 5 factors.
5. Afford an opportunity for offerors to revise their proposal submission for Factors 1 and 2;
6. Afford an opportunity for offerors to withdraw their proposals; 
7. Provide proposal due date;
8. To update selection recency element under Factor 1 and 2;
9. To update wage determination;
10. Provide intent to include sole source items;
11. Provide update on door hardware schedule;
12. Provide site visit information.

Amendment 0002 -  Extends the period for acceptance of proposals for Technical Factors 1 and 2. - Amendment provided in posting Attachments.  No other changes.

Amendment 0001 - Provides responses to ProjNET questions - Amendment provided in posting Attachments.  No other changes.

This is the solicitation for F22 Consolidated Operations and Maintenance Hangar (COMH), Langley AFB, W9123621R2003.

Provide a six-bay high-bay consolidated operations and maintenance hangar to provide maintenance support for additional F-22A aircraft from Tyndall Air Force Base. Construction includes compacted fill above the 100-year flood plain, reinforced concrete foundations, concrete floor slab, structural steel frame with concrete masonry unit facade, and a standing seam metal roof. The facility will provide all necessary spaces to house hangar bays, staff administration, propulsion shop, ready room, break room, tools/parts support, aircraft maintenance equipment storage, wheel/tire shop, egress shop, restrooms/showers/lockers, and building systems support. The project includes all utilities, site improvements, pavements, detection/protection features, security enhancements, and other supporting work necessary to make a complete and useable facility. The facility must be able to withstand seismic and wind effects as prescribed in applicable codes and design guides. The project will demolish Facility 753 (7,400 Square Meters). Facilities will be designed as permanent construction in accordance with the DoD Unified Facilities Criteria 1-200-1, General Building Requirements. Sustainable principles and life-cycle cost-effective practices will be integrated into the design, development and construction of the project in accordance with Unified Facilities Criteria 1-200-02. This project will comply with Department of Defense minimum antiterrorism requirements in Unified Facilities Criteria 4-010-01. Air Conditioning: 150 Tons

The project duration is 700 calendar days from the notice to proceed, unless CLIN 0013 is exercised in which case the contract completion date will become 565 calendar days from notice to proceed.

Refer to the solicitation document for further details.

Update #10 ·

12/06/2021 - Amendment 0008 to provide the following:

1. Change the submission approach to a bifurcated approach. Only Factors 1 and 2 are requested at this time.

2. Extend acceptance of Pre-Proposal Inquiries (PPIs).

11/24/2021 - Amendment 0007 - The purpose of Amendment 0007 is issued to provide the following: 
1. To amend the source selection procedures and remove Factor 3, Schedule, in its entirety. 
2. To provide changes to the technical documents. 
3. To provide revised drawings and specifications. 
4. To extend the solicitation response date.

11/9/2021  upload Amendment 0006.   To update specification Section 08 71 00 (see attachment 7 and the continuation sheet of the amendment)

10/26/2021 - Site Visit Sign-In Log Added to Attachments.

10/19/2021 Amendment 0005:  The purpose of this amendment is to:
1. To provide RTA drawings and specifications;
2. Incorporate additional contract clauses 252.204-7000 and 252.211-7003.
***RTA Drawings and specifications are uploaded as of 10/19/2021, a revised SF30 is pending due to system issues and will be posted once available.

Original Attachments:
Attachment 10 - COMH - Final Design Drawings Part 1 of 3.pdf
Attachment 11 - COMH - Final Design Drawings Part 2 of 3.pdf
Attachment 12 - COMH - Final Design Drawings Part 3 of 3.pdf
Attachment 13 - COMH Final Design Specifications Part 1 of 1.pdf

Replaced with:
Attachment 10 - COMH_RTA_Design Drawings_Part 1 of 3_17MAR21.pdf, dated 03/07/2021, 157 pages 
Attachment 11 - COMH_RTA_Design Drawings_Part 1 of 3_17MAR21, dated 03/07/2021, 161 pages 
Attachment 12 - COMH_RTA_Design Drawings_Part 3 of 3_17MAR21.pdf, dated 03/07/2021, 225 pages 
Attachment 13 - COMH_RTA_Specifications part 1 of 1_17MAR21, dated 03/07/2021, 2924 pages 
Attachment 14 - COMH - RTA FFE_17MAR21.pdf, dated 03/07/2021, 58 pages 
Attachment 15 - COMH - RTA SID_17MAR21, dated 03/07/2021, 32 pages

Amendment 0004 - The purpose of this amendment is to:
1. To update selection recency element under Factor 1;
2. Incorporate 252.233-7999 Ensuring Adequate COVID-19 Safety Protocols for Federal Contractors (Deviation 2021-O0009)

Amendment 0003. USACE has received authority to continue with the acquisition of this construction project. Due to the programmatic pause, this amendment permits new offerors to submit proposals in order to reasonably promote competition.  All offerors, including those that submitted proposals in response to the initial solicitation, are afforded equal consideration throughout the source selection process.

The purpose of this amendment is to provide the following: (See Continuation Page for Details)
1. To establish a new proposal due date; 
2. Extend the proposal validity for additional 180 days; 
3. Permit potential offerors who did not respond initially to submit a proposal in response to all factors;
4. Require the submission of all 5 factors.
5. Afford an opportunity for offerors to revise their proposal submission for Factors 1 and 2;
6. Afford an opportunity for offerors to withdraw their proposals; 
7. Provide proposal due date;
8. To update selection recency element under Factor 1 and 2;
9. To update wage determination;
10. Provide intent to include sole source items;
11. Provide update on door hardware schedule;
12. Provide site visit information.

Amendment 0002 -  Extends the period for acceptance of proposals for Technical Factors 1 and 2. - Amendment provided in posting Attachments.  No other changes.

Amendment 0001 - Provides responses to ProjNET questions - Amendment provided in posting Attachments.  No other changes.

This is the solicitation for F22 Consolidated Operations and Maintenance Hangar (COMH), Langley AFB, W9123621R2003.

Provide a six-bay high-bay consolidated operations and maintenance hangar to provide maintenance support for additional F-22A aircraft from Tyndall Air Force Base. Construction includes compacted fill above the 100-year flood plain, reinforced concrete foundations, concrete floor slab, structural steel frame with concrete masonry unit facade, and a standing seam metal roof. The facility will provide all necessary spaces to house hangar bays, staff administration, propulsion shop, ready room, break room, tools/parts support, aircraft maintenance equipment storage, wheel/tire shop, egress shop, restrooms/showers/lockers, and building systems support. The project includes all utilities, site improvements, pavements, detection/protection features, security enhancements, and other supporting work necessary to make a complete and useable facility. The facility must be able to withstand seismic and wind effects as prescribed in applicable codes and design guides. The project will demolish Facility 753 (7,400 Square Meters). Facilities will be designed as permanent construction in accordance with the DoD Unified Facilities Criteria 1-200-1, General Building Requirements. Sustainable principles and life-cycle cost-effective practices will be integrated into the design, development and construction of the project in accordance with Unified Facilities Criteria 1-200-02. This project will comply with Department of Defense minimum antiterrorism requirements in Unified Facilities Criteria 4-010-01. Air Conditioning: 150 Tons

The project duration is 700 calendar days from the notice to proceed, unless CLIN 0013 is exercised in which case the contract completion date will become 565 calendar days from notice to proceed.

Refer to the solicitation document for further details.

Update #9 ·

11/24/2021 - Amendment 0007 - The purpose of Amendment 0007 is issued to provide the following: 
1. To amend the source selection procedures and remove Factor 3, Schedule, in its entirety. 
2. To provide changes to the technical documents. 
3. To provide revised drawings and specifications. 
4. To extend the solicitation response date.

11/9/2021  upload Amendment 0006.   To update specification Section 08 71 00 (see attachment 7 and the continuation sheet of the amendment)

10/26/2021 - Site Visit Sign-In Log Added to Attachments.

10/19/2021 Amendment 0005:  The purpose of this amendment is to:
1. To provide RTA drawings and specifications;
2. Incorporate additional contract clauses 252.204-7000 and 252.211-7003.
***RTA Drawings and specifications are uploaded as of 10/19/2021, a revised SF30 is pending due to system issues and will be posted once available.

Original Attachments:
Attachment 10 - COMH - Final Design Drawings Part 1 of 3.pdf
Attachment 11 - COMH - Final Design Drawings Part 2 of 3.pdf
Attachment 12 - COMH - Final Design Drawings Part 3 of 3.pdf
Attachment 13 - COMH Final Design Specifications Part 1 of 1.pdf

Replaced with:
Attachment 10 - COMH_RTA_Design Drawings_Part 1 of 3_17MAR21.pdf, dated 03/07/2021, 157 pages 
Attachment 11 - COMH_RTA_Design Drawings_Part 1 of 3_17MAR21, dated 03/07/2021, 161 pages 
Attachment 12 - COMH_RTA_Design Drawings_Part 3 of 3_17MAR21.pdf, dated 03/07/2021, 225 pages 
Attachment 13 - COMH_RTA_Specifications part 1 of 1_17MAR21, dated 03/07/2021, 2924 pages 
Attachment 14 - COMH - RTA FFE_17MAR21.pdf, dated 03/07/2021, 58 pages 
Attachment 15 - COMH - RTA SID_17MAR21, dated 03/07/2021, 32 pages

Amendment 0004 - The purpose of this amendment is to:
1. To update selection recency element under Factor 1;
2. Incorporate 252.233-7999 Ensuring Adequate COVID-19 Safety Protocols for Federal Contractors (Deviation 2021-O0009)

Amendment 0003. USACE has received authority to continue with the acquisition of this construction project. Due to the programmatic pause, this amendment permits new offerors to submit proposals in order to reasonably promote competition.  All offerors, including those that submitted proposals in response to the initial solicitation, are afforded equal consideration throughout the source selection process.

The purpose of this amendment is to provide the following: (See Continuation Page for Details)
1. To establish a new proposal due date; 
2. Extend the proposal validity for additional 180 days; 
3. Permit potential offerors who did not respond initially to submit a proposal in response to all factors;
4. Require the submission of all 5 factors.
5. Afford an opportunity for offerors to revise their proposal submission for Factors 1 and 2;
6. Afford an opportunity for offerors to withdraw their proposals; 
7. Provide proposal due date;
8. To update selection recency element under Factor 1 and 2;
9. To update wage determination;
10. Provide intent to include sole source items;
11. Provide update on door hardware schedule;
12. Provide site visit information.

Amendment 0002 -  Extends the period for acceptance of proposals for Technical Factors 1 and 2. - Amendment provided in posting Attachments.  No other changes.

Amendment 0001 - Provides responses to ProjNET questions - Amendment provided in posting Attachments.  No other changes.

This is the solicitation for F22 Consolidated Operations and Maintenance Hangar (COMH), Langley AFB, W9123621R2003.

Provide a six-bay high-bay consolidated operations and maintenance hangar to provide maintenance support for additional F-22A aircraft from Tyndall Air Force Base. Construction includes compacted fill above the 100-year flood plain, reinforced concrete foundations, concrete floor slab, structural steel frame with concrete masonry unit facade, and a standing seam metal roof. The facility will provide all necessary spaces to house hangar bays, staff administration, propulsion shop, ready room, break room, tools/parts support, aircraft maintenance equipment storage, wheel/tire shop, egress shop, restrooms/showers/lockers, and building systems support. The project includes all utilities, site improvements, pavements, detection/protection features, security enhancements, and other supporting work necessary to make a complete and useable facility. The facility must be able to withstand seismic and wind effects as prescribed in applicable codes and design guides. The project will demolish Facility 753 (7,400 Square Meters). Facilities will be designed as permanent construction in accordance with the DoD Unified Facilities Criteria 1-200-1, General Building Requirements. Sustainable principles and life-cycle cost-effective practices will be integrated into the design, development and construction of the project in accordance with Unified Facilities Criteria 1-200-02. This project will comply with Department of Defense minimum antiterrorism requirements in Unified Facilities Criteria 4-010-01. Air Conditioning: 150 Tons

The project duration is 700 calendar days from the notice to proceed, unless CLIN 0013 is exercised in which case the contract completion date will become 565 calendar days from notice to proceed.

Refer to the solicitation document for further details.

Update #8 ·

11/9/2021  upload Amendment 0006.   To update specification Section 08 71 00 (see attachment 7 and the continuation sheet of the amendment)

10/26/2021 - Site Visit Sign-In Log Added to Attachments.

10/19/2021 Amendment 0005:  The purpose of this amendment is to:
1. To provide RTA drawings and specifications;
2. Incorporate additional contract clauses 252.204-7000 and 252.211-7003.
***RTA Drawings and specifications are uploaded as of 10/19/2021, a revised SF30 is pending due to system issues and will be posted once available.

Original Attachments:
Attachment 10 - COMH - Final Design Drawings Part 1 of 3.pdf
Attachment 11 - COMH - Final Design Drawings Part 2 of 3.pdf
Attachment 12 - COMH - Final Design Drawings Part 3 of 3.pdf
Attachment 13 - COMH Final Design Specifications Part 1 of 1.pdf

Replaced with:
Attachment 10 - COMH_RTA_Design Drawings_Part 1 of 3_17MAR21.pdf, dated 03/07/2021, 157 pages 
Attachment 11 - COMH_RTA_Design Drawings_Part 1 of 3_17MAR21, dated 03/07/2021, 161 pages 
Attachment 12 - COMH_RTA_Design Drawings_Part 3 of 3_17MAR21.pdf, dated 03/07/2021, 225 pages 
Attachment 13 - COMH_RTA_Specifications part 1 of 1_17MAR21, dated 03/07/2021, 2924 pages 
Attachment 14 - COMH - RTA FFE_17MAR21.pdf, dated 03/07/2021, 58 pages 
Attachment 15 - COMH - RTA SID_17MAR21, dated 03/07/2021, 32 pages

Amendment 0004 - The purpose of this amendment is to:
1. To update selection recency element under Factor 1;
2. Incorporate 252.233-7999 Ensuring Adequate COVID-19 Safety Protocols for Federal Contractors (Deviation 2021-O0009)

Amendment 0003. USACE has received authority to continue with the acquisition of this construction project. Due to the programmatic pause, this amendment permits new offerors to submit proposals in order to reasonably promote competition.  All offerors, including those that submitted proposals in response to the initial solicitation, are afforded equal consideration throughout the source selection process.

The purpose of this amendment is to provide the following: (See Continuation Page for Details)
1. To establish a new proposal due date; 
2. Extend the proposal validity for additional 180 days; 
3. Permit potential offerors who did not respond initially to submit a proposal in response to all factors;
4. Require the submission of all 5 factors.
5. Afford an opportunity for offerors to revise their proposal submission for Factors 1 and 2;
6. Afford an opportunity for offerors to withdraw their proposals; 
7. Provide proposal due date;
8. To update selection recency element under Factor 1 and 2;
9. To update wage determination;
10. Provide intent to include sole source items;
11. Provide update on door hardware schedule;
12. Provide site visit information.

Amendment 0002 -  Extends the period for acceptance of proposals for Technical Factors 1 and 2. - Amendment provided in posting Attachments.  No other changes.

Amendment 0001 - Provides responses to ProjNET questions - Amendment provided in posting Attachments.  No other changes.

This is the solicitation for F22 Consolidated Operations and Maintenance Hangar (COMH), Langley AFB, W9123621R2003.

Provide a six-bay high-bay consolidated operations and maintenance hangar to provide maintenance support for additional F-22A aircraft from Tyndall Air Force Base. Construction includes compacted fill above the 100-year flood plain, reinforced concrete foundations, concrete floor slab, structural steel frame with concrete masonry unit facade, and a standing seam metal roof. The facility will provide all necessary spaces to house hangar bays, staff administration, propulsion shop, ready room, break room, tools/parts support, aircraft maintenance equipment storage, wheel/tire shop, egress shop, restrooms/showers/lockers, and building systems support. The project includes all utilities, site improvements, pavements, detection/protection features, security enhancements, and other supporting work necessary to make a complete and useable facility. The facility must be able to withstand seismic and wind effects as prescribed in applicable codes and design guides. The project will demolish Facility 753 (7,400 Square Meters). Facilities will be designed as permanent construction in accordance with the DoD Unified Facilities Criteria 1-200-1, General Building Requirements. Sustainable principles and life-cycle cost-effective practices will be integrated into the design, development and construction of the project in accordance with Unified Facilities Criteria 1-200-02. This project will comply with Department of Defense minimum antiterrorism requirements in Unified Facilities Criteria 4-010-01. Air Conditioning: 150 Tons

The project duration is 700 calendar days from the notice to proceed, unless CLIN 0013 is exercised in which case the contract completion date will become 565 calendar days from notice to proceed.

Refer to the solicitation document for further details.

Update #7 ·

10/26/2021 - Site Visit Sign-In Log Added to Attachments.

10/19/2021 Amendment 0005:  The purpose of this amendment is to:
1. To provide RTA drawings and specifications;
2. Incorporate additional contract clauses 252.204-7000 and 252.211-7003.
***RTA Drawings and specifications are uploaded as of 10/19/2021, a revised SF30 is pending due to system issues and will be posted once available.

Original Attachments:
Attachment 10 - COMH - Final Design Drawings Part 1 of 3.pdf
Attachment 11 - COMH - Final Design Drawings Part 2 of 3.pdf
Attachment 12 - COMH - Final Design Drawings Part 3 of 3.pdf
Attachment 13 - COMH Final Design Specifications Part 1 of 1.pdf

Replaced with:
Attachment 10 - COMH_RTA_Design Drawings_Part 1 of 3_17MAR21.pdf, dated 03/07/2021, 157 pages 
Attachment 11 - COMH_RTA_Design Drawings_Part 1 of 3_17MAR21, dated 03/07/2021, 161 pages 
Attachment 12 - COMH_RTA_Design Drawings_Part 3 of 3_17MAR21.pdf, dated 03/07/2021, 225 pages 
Attachment 13 - COMH_RTA_Specifications part 1 of 1_17MAR21, dated 03/07/2021, 2924 pages 
Attachment 14 - COMH - RTA FFE_17MAR21.pdf, dated 03/07/2021, 58 pages 
Attachment 15 - COMH - RTA SID_17MAR21, dated 03/07/2021, 32 pages

Amendment 0004 - The purpose of this amendment is to:
1. To update selection recency element under Factor 1;
2. Incorporate 252.233-7999 Ensuring Adequate COVID-19 Safety Protocols for Federal Contractors (Deviation 2021-O0009)

Amendment 0003. USACE has received authority to continue with the acquisition of this construction project. Due to the programmatic pause, this amendment permits new offerors to submit proposals in order to reasonably promote competition.  All offerors, including those that submitted proposals in response to the initial solicitation, are afforded equal consideration throughout the source selection process.

The purpose of this amendment is to provide the following: (See Continuation Page for Details)
1. To establish a new proposal due date; 
2. Extend the proposal validity for additional 180 days; 
3. Permit potential offerors who did not respond initially to submit a proposal in response to all factors;
4. Require the submission of all 5 factors.
5. Afford an opportunity for offerors to revise their proposal submission for Factors 1 and 2;
6. Afford an opportunity for offerors to withdraw their proposals; 
7. Provide proposal due date;
8. To update selection recency element under Factor 1 and 2;
9. To update wage determination;
10. Provide intent to include sole source items;
11. Provide update on door hardware schedule;
12. Provide site visit information.

Amendment 0002 -  Extends the period for acceptance of proposals for Technical Factors 1 and 2. - Amendment provided in posting Attachments.  No other changes.

Amendment 0001 - Provides responses to ProjNET questions - Amendment provided in posting Attachments.  No other changes.

This is the solicitation for F22 Consolidated Operations and Maintenance Hangar (COMH), Langley AFB, W9123621R2003.

Provide a six-bay high-bay consolidated operations and maintenance hangar to provide maintenance support for additional F-22A aircraft from Tyndall Air Force Base. Construction includes compacted fill above the 100-year flood plain, reinforced concrete foundations, concrete floor slab, structural steel frame with concrete masonry unit facade, and a standing seam metal roof. The facility will provide all necessary spaces to house hangar bays, staff administration, propulsion shop, ready room, break room, tools/parts support, aircraft maintenance equipment storage, wheel/tire shop, egress shop, restrooms/showers/lockers, and building systems support. The project includes all utilities, site improvements, pavements, detection/protection features, security enhancements, and other supporting work necessary to make a complete and useable facility. The facility must be able to withstand seismic and wind effects as prescribed in applicable codes and design guides. The project will demolish Facility 753 (7,400 Square Meters). Facilities will be designed as permanent construction in accordance with the DoD Unified Facilities Criteria 1-200-1, General Building Requirements. Sustainable principles and life-cycle cost-effective practices will be integrated into the design, development and construction of the project in accordance with Unified Facilities Criteria 1-200-02. This project will comply with Department of Defense minimum antiterrorism requirements in Unified Facilities Criteria 4-010-01. Air Conditioning: 150 Tons

The project duration is 700 calendar days from the notice to proceed, unless CLIN 0013 is exercised in which case the contract completion date will become 565 calendar days from notice to proceed.

Refer to the solicitation document for further details.

Update #6 ·

10/19/2021 Amendment 0005:  The purpose of this amendment is to:
1. To provide RTA drawings and specifications;
2. Incorporate additional contract clauses 252.204-7000 and 252.211-7003.
***RTA Drawings and specifications are uploaded as of 10/19/2021, a revised SF30 is pending due to system issues and will be posted once available.

Original Attachments:
Attachment 10 - COMH - Final Design Drawings Part 1 of 3.pdf
Attachment 11 - COMH - Final Design Drawings Part 2 of 3.pdf
Attachment 12 - COMH - Final Design Drawings Part 3 of 3.pdf
Attachment 13 - COMH Final Design Specifications Part 1 of 1.pdf

Replaced with:
Attachment 10 - COMH_RTA_Design Drawings_Part 1 of 3_17MAR21.pdf, dated 03/07/2021, 157 pages 
Attachment 11 - COMH_RTA_Design Drawings_Part 1 of 3_17MAR21, dated 03/07/2021, 161 pages 
Attachment 12 - COMH_RTA_Design Drawings_Part 3 of 3_17MAR21.pdf, dated 03/07/2021, 225 pages 
Attachment 13 - COMH_RTA_Specifications part 1 of 1_17MAR21, dated 03/07/2021, 2924 pages 
Attachment 14 - COMH - RTA FFE_17MAR21.pdf, dated 03/07/2021, 58 pages 
Attachment 15 - COMH - RTA SID_17MAR21, dated 03/07/2021, 32 pages

Amendment 0004 - The purpose of this amendment is to:
1. To update selection recency element under Factor 1;
2. Incorporate 252.233-7999 Ensuring Adequate COVID-19 Safety Protocols for Federal Contractors (Deviation 2021-O0009)

Amendment 0003. USACE has received authority to continue with the acquisition of this construction project. Due to the programmatic pause, this amendment permits new offerors to submit proposals in order to reasonably promote competition.  All offerors, including those that submitted proposals in response to the initial solicitation, are afforded equal consideration throughout the source selection process.

The purpose of this amendment is to provide the following: (See Continuation Page for Details)
1. To establish a new proposal due date; 
2. Extend the proposal validity for additional 180 days; 
3. Permit potential offerors who did not respond initially to submit a proposal in response to all factors;
4. Require the submission of all 5 factors.
5. Afford an opportunity for offerors to revise their proposal submission for Factors 1 and 2;
6. Afford an opportunity for offerors to withdraw their proposals; 
7. Provide proposal due date;
8. To update selection recency element under Factor 1 and 2;
9. To update wage determination;
10. Provide intent to include sole source items;
11. Provide update on door hardware schedule;
12. Provide site visit information.

Amendment 0002 -  Extends the period for acceptance of proposals for Technical Factors 1 and 2. - Amendment provided in posting Attachments.  No other changes.

Amendment 0001 - Provides responses to ProjNET questions - Amendment provided in posting Attachments.  No other changes.

This is the solicitation for F22 Consolidated Operations and Maintenance Hangar (COMH), Langley AFB, W9123621R2003.

Provide a six-bay high-bay consolidated operations and maintenance hangar to provide maintenance support for additional F-22A aircraft from Tyndall Air Force Base. Construction includes compacted fill above the 100-year flood plain, reinforced concrete foundations, concrete floor slab, structural steel frame with concrete masonry unit facade, and a standing seam metal roof. The facility will provide all necessary spaces to house hangar bays, staff administration, propulsion shop, ready room, break room, tools/parts support, aircraft maintenance equipment storage, wheel/tire shop, egress shop, restrooms/showers/lockers, and building systems support. The project includes all utilities, site improvements, pavements, detection/protection features, security enhancements, and other supporting work necessary to make a complete and useable facility. The facility must be able to withstand seismic and wind effects as prescribed in applicable codes and design guides. The project will demolish Facility 753 (7,400 Square Meters). Facilities will be designed as permanent construction in accordance with the DoD Unified Facilities Criteria 1-200-1, General Building Requirements. Sustainable principles and life-cycle cost-effective practices will be integrated into the design, development and construction of the project in accordance with Unified Facilities Criteria 1-200-02. This project will comply with Department of Defense minimum antiterrorism requirements in Unified Facilities Criteria 4-010-01. Air Conditioning: 150 Tons

The project duration is 700 calendar days from the notice to proceed, unless CLIN 0013 is exercised in which case the contract completion date will become 565 calendar days from notice to proceed.

Refer to the solicitation document for further details.

Update #5 ·

Amendment 0004 - The purpose of this amendment is to:
1. To update selection recency element under Factor 1;
2. Incorporate 252.233-7999 Ensuring Adequate COVID-19 Safety Protocols for Federal Contractors (Deviation 2021-O0009)

Amendment 0003. USACE has received authority to continue with the acquisition of this construction project. Due to the programmatic pause, this amendment permits new offerors to submit proposals in order to reasonably promote competition.  All offerors, including those that submitted proposals in response to the initial solicitation, are afforded equal consideration throughout the source selection process.

The purpose of this amendment is to provide the following: (See Continuation Page for Details)
1. To establish a new proposal due date; 
2. Extend the proposal validity for additional 180 days; 
3. Permit potential offerors who did not respond initially to submit a proposal in response to all factors;
4. Require the submission of all 5 factors.
5. Afford an opportunity for offerors to revise their proposal submission for Factors 1 and 2;
6. Afford an opportunity for offerors to withdraw their proposals; 
7. Provide proposal due date;
8. To update selection recency element under Factor 1 and 2;
9. To update wage determination;
10. Provide intent to include sole source items;
11. Provide update on door hardware schedule;
12. Provide site visit information.

Amendment 0002 -  Extends the period for acceptance of proposals for Technical Factors 1 and 2. - Amendment provided in posting Attachments.  No other changes.

Amendment 0001 - Provides responses to ProjNET questions - Amendment provided in posting Attachments.  No other changes.

This is the solicitation for F22 Consolidated Operations and Maintenance Hangar (COMH), Langley AFB, W9123621R2003.

Provide a six-bay high-bay consolidated operations and maintenance hangar to provide maintenance support for additional F-22A aircraft from Tyndall Air Force Base. Construction includes compacted fill above the 100-year flood plain, reinforced concrete foundations, concrete floor slab, structural steel frame with concrete masonry unit facade, and a standing seam metal roof. The facility will provide all necessary spaces to house hangar bays, staff administration, propulsion shop, ready room, break room, tools/parts support, aircraft maintenance equipment storage, wheel/tire shop, egress shop, restrooms/showers/lockers, and building systems support. The project includes all utilities, site improvements, pavements, detection/protection features, security enhancements, and other supporting work necessary to make a complete and useable facility. The facility must be able to withstand seismic and wind effects as prescribed in applicable codes and design guides. The project will demolish Facility 753 (7,400 Square Meters). Facilities will be designed as permanent construction in accordance with the DoD Unified Facilities Criteria 1-200-1, General Building Requirements. Sustainable principles and life-cycle cost-effective practices will be integrated into the design, development and construction of the project in accordance with Unified Facilities Criteria 1-200-02. This project will comply with Department of Defense minimum antiterrorism requirements in Unified Facilities Criteria 4-010-01. Air Conditioning: 150 Tons

The project duration is 700 calendar days from the notice to proceed, unless CLIN 0013 is exercised in which case the contract completion date will become 565 calendar days from notice to proceed.

Refer to the solicitation document for further details.

Update #4 ·

Amendment 0003. USACE has received authority to continue with the acquisition of this construction project. Due to the programmatic pause, this amendment permits new offerors to submit proposals in order to reasonably promote competition.  All offerors, including those that submitted proposals in response to the initial solicitation, are afforded equal consideration throughout the source selection process.

The purpose of this amendment is to provide the following: (See Continuation Page for Details)
1. To establish a new proposal due date; 
2. Extend the proposal validity for additional 180 days; 
3. Permit potential offerors who did not respond initially to submit a proposal in response to all factors;
4. Require the submission of all 5 factors.
5. Afford an opportunity for offerors to revise their proposal submission for Factors 1 and 2;
6. Afford an opportunity for offerors to withdraw their proposals; 
7. Provide proposal due date;
8. To update selection recency element under Factor 1 and 2;
9. To update wage determination;
10. Provide intent to include sole source items;
11. Provide update on door hardware schedule;
12. Provide site visit information.

Amendment 0002 -  Extends the period for acceptance of proposals for Technical Factors 1 and 2. - Amendment provided in posting Attachments.  No other changes.

Amendment 0001 - Provides responses to ProjNET questions - Amendment provided in posting Attachments.  No other changes.

This is the solicitation for F22 Consolidated Operations and Maintenance Hangar (COMH), Langley AFB, W9123621R2003.

Provide a six-bay high-bay consolidated operations and maintenance hangar to provide maintenance support for additional F-22A aircraft from Tyndall Air Force Base. Construction includes compacted fill above the 100-year flood plain, reinforced concrete foundations, concrete floor slab, structural steel frame with concrete masonry unit facade, and a standing seam metal roof. The facility will provide all necessary spaces to house hangar bays, staff administration, propulsion shop, ready room, break room, tools/parts support, aircraft maintenance equipment storage, wheel/tire shop, egress shop, restrooms/showers/lockers, and building systems support. The project includes all utilities, site improvements, pavements, detection/protection features, security enhancements, and other supporting work necessary to make a complete and useable facility. The facility must be able to withstand seismic and wind effects as prescribed in applicable codes and design guides. The project will demolish Facility 753 (7,400 Square Meters). Facilities will be designed as permanent construction in accordance with the DoD Unified Facilities Criteria 1-200-1, General Building Requirements. Sustainable principles and life-cycle cost-effective practices will be integrated into the design, development and construction of the project in accordance with Unified Facilities Criteria 1-200-02. This project will comply with Department of Defense minimum antiterrorism requirements in Unified Facilities Criteria 4-010-01. Air Conditioning: 150 Tons

The project duration is 700 calendar days from the notice to proceed, unless CLIN 0013 is exercised in which case the contract completion date will become 565 calendar days from notice to proceed.

Refer to the solicitation document for further details.

Update #3 ·

Amendment 0002 -  Extends the period for acceptance of proposals for Technical Factors 1 and 2. - Amendment provided in posting Attachments.  No other changes.

Amendment 0001 - Provides responses to ProjNET questions - Amendment provided in posting Attachments.  No other changes.

This is the solicitation for F22 Consolidated Operations and Maintenance Hangar (COMH), Langley AFB, W9123621R2003.

Provide a six-bay high-bay consolidated operations and maintenance hangar to provide maintenance support for additional F-22A aircraft from Tyndall Air Force Base. Construction includes compacted fill above the 100-year flood plain, reinforced concrete foundations, concrete floor slab, structural steel frame with concrete masonry unit facade, and a standing seam metal roof. The facility will provide all necessary spaces to house hangar bays, staff administration, propulsion shop, ready room, break room, tools/parts support, aircraft maintenance equipment storage, wheel/tire shop, egress shop, restrooms/showers/lockers, and building systems support. The project includes all utilities, site improvements, pavements, detection/protection features, security enhancements, and other supporting work necessary to make a complete and useable facility. The facility must be able to withstand seismic and wind effects as prescribed in applicable codes and design guides. The project will demolish Facility 753 (7,400 Square Meters). Facilities will be designed as permanent construction in accordance with the DoD Unified Facilities Criteria 1-200-1, General Building Requirements. Sustainable principles and life-cycle cost-effective practices will be integrated into the design, development and construction of the project in accordance with Unified Facilities Criteria 1-200-02. This project will comply with Department of Defense minimum antiterrorism requirements in Unified Facilities Criteria 4-010-01. Air Conditioning: 150 Tons

The project duration is 700 calendar days from the notice to proceed, unless CLIN 0013 is exercised in which case the contract completion date will become 565 calendar days from notice to proceed.

This is a bifurcated solicitation. Only Factors 1 and 2 responses are requsted at this time.

Refer to the solicitation document for further details.

Update #2 ·

Amendment 0001 - Provides responses to ProjNET questions - Amendment provided in posting Attachments.  No other changes.

This is the solicitation for F22 Consolidated Operations and Maintenance Hangar (COMH), Langley AFB, W9123621R2003.

Provide a six-bay high-bay consolidated operations and maintenance hangar to provide maintenance support for additional F-22A aircraft from Tyndall Air Force Base. Construction includes compacted fill above the 100-year flood plain, reinforced concrete foundations, concrete floor slab, structural steel frame with concrete masonry unit facade, and a standing seam metal roof. The facility will provide all necessary spaces to house hangar bays, staff administration, propulsion shop, ready room, break room, tools/parts support, aircraft maintenance equipment storage, wheel/tire shop, egress shop, restrooms/showers/lockers, and building systems support. The project includes all utilities, site improvements, pavements, detection/protection features, security enhancements, and other supporting work necessary to make a complete and useable facility. The facility must be able to withstand seismic and wind effects as prescribed in applicable codes and design guides. The project will demolish Facility 753 (7,400 Square Meters). Facilities will be designed as permanent construction in accordance with the DoD Unified Facilities Criteria 1-200-1, General Building Requirements. Sustainable principles and life-cycle cost-effective practices will be integrated into the design, development and construction of the project in accordance with Unified Facilities Criteria 1-200-02. This project will comply with Department of Defense minimum antiterrorism requirements in Unified Facilities Criteria 4-010-01. Air Conditioning: 150 Tons

The project duration is 700 calendar days from the notice to proceed, unless CLIN 0013 is exercised in which case the contract completion date will become 565 calendar days from notice to proceed.

This is a bifurcated solicitation. Only Factors 1 and 2 responses are requsted at this time.

Refer to the solicitation document for further details.

Update #1 ·

This is the solicitation for F22 Consolidated Operations and Maintenance Hangar (COMH), Langley AFB, W9123621R2003.

Provide a six-bay high-bay consolidated operations and maintenance hangar to provide maintenance support for additional F-22A aircraft from Tyndall Air Force Base. Construction includes compacted fill above the 100-year flood plain, reinforced concrete foundations, concrete floor slab, structural steel frame with concrete masonry unit facade, and a standing seam metal roof. The facility will provide all necessary spaces to house hangar bays, staff administration, propulsion shop, ready room, break room, tools/parts support, aircraft maintenance equipment storage, wheel/tire shop, egress shop, restrooms/showers/lockers, and building systems support. The project includes all utilities, site improvements, pavements, detection/protection features, security enhancements, and other supporting work necessary to make a complete and useable facility. The facility must be able to withstand seismic and wind effects as prescribed in applicable codes and design guides. The project will demolish Facility 753 (7,400 Square Meters). Facilities will be designed as permanent construction in accordance with the DoD Unified Facilities Criteria 1-200-1, General Building Requirements. Sustainable principles and life-cycle cost-effective practices will be integrated into the design, development and construction of the project in accordance with Unified Facilities Criteria 1-200-02. This project will comply with Department of Defense minimum antiterrorism requirements in Unified Facilities Criteria 4-010-01. Air Conditioning: 150 Tons

The project duration is 700 calendar days from the notice to proceed, unless CLIN 0013 is exercised in which case the contract completion date will become 565 calendar days from notice to proceed.

This is a bifurcated solicitation. Only Factors 1 and 2 responses are requsted at this time.

Refer to the solicitation document for further details.

Files

File Type Posted
W9123621R2003_0016.pdf PDF
W9123621R2003_0015.pdf PDF
W9123621R2003_0014.pdf PDF
W9123621R2003_0013.pdf PDF
W9123621R2003_0012.pdf PDF
Attachment 8 - CLIN Schedule_REVISION 1 on 01.05.2022.pdf PDF
Amend 0011_07 61 14.00 20_Amended.pdf PDF
AMENDMENT 0011_21 DEC 21 - Drawings.pdf PDF
Amend 0011_23 09 23_Amended V2.pdf PDF
W9123621R2003_0011.pdf PDF
Attachment 16 - Construction Security Plan (CSP).pdf PDF
COMH Amended Drawings_14 DEC 2021.pdf PDF
Attachment 17 - Installation Restoration Program (IRP) Background Chem Data.pdf PDF
COMH Amended Specs_14 DEC 2021_Combined.pdf PDF
W9123621R2003_0010.pdf PDF
A.07.23 - Solicitation COMH W9123621R2003 0009.pdf PDF
W9123621R2003_0008.pdf PDF
COMH Tech Amendment 0007 - 07 27 19.01_Amended.pdf PDF
COMH Tech Amendment 0007 - AMENDMENT 19 NOV 21 - Drawings.pdf PDF
COMH Tech Amendment 0007 - 01 57 13.00 22_Amended.pdf PDF
A.07.24 SF30 - W9123621R2003 - 0007.pdf PDF
08 71 00_Amended 006.pdf PDF
W9123621R2003 Amendment 0006.pdf PDF
A.07.20 - Site Visit Sign-in Log - Dtd 20 Oct 2021_1Page.pdf PDF
A.07.24 SF30 - W9123621R2003 - 0005.pdf PDF
Attachment 10 - COMH_RTA_Design Drawings_Part 1 of 3_17MAR21.pdf PDF
Attachment 13 - COMH_RTA_Specifications part 1 of 1_17MAR21.pdf PDF
Attachment 11 - COMH_RTA_Design Drawings_Part 2 of 3_17MAR21.pdf PDF
Attachment 15 - COMH - RTA SID_17MAR21.pdf PDF
Attachment 14 - COMH - RTA FFE_17MAR21.pdf PDF
Attachment 12 - COMH_RTA_Design Drawings_Part 3 of 3_17MAR21.pdf PDF
A.07.24 SF30 - W9123621R2003 - 0004.pdf PDF
A.07.24 SF30 - W9123621R2003 - 0003.pdf PDF
A.07.24 SF30 - W9123621R2003 - 0002.pdf PDF
W9123621R2003 - 0001 - COMH.pdf PDF
Attachment 7 - Small Business Participation Plan.pdf PDF
Attachment 5 - Letter of Commitment Sample.pdf PDF
Solicitation W9123621R2003 - COMH.pdf PDF
Attachment 13 - COMH Final Design Specifications Part 1 of 1.pdf PDF
Attachment 12 - COMH - Final Design Drawings Part 3 of 3.pdf PDF
Attachment 9 - Langley Environmental Management Special Conditions.pdf PDF
Attachment 6 - Small Business Subcontracting Record.pdf PDF
Attachment 10 - COMH - Final Design Drawings Part 1 of 3.pdf PDF
Attachment 8 - CLIN Schedule.pdf PDF
Attachment 3 - Past Performance Questionnaire.pdf PDF
Attachment 1 - Proposal Data Sheet.pdf PDF
Attachment 11 - COMH - Final Design Drawings Part 2 of 3.pdf PDF
Attachment 4 - Telephone Interview Questionnaire (For Government Use Only).pdf PDF
Attachment 2 - Company Specialized Experience.pdf PDF
Show all 49

Notice history

Notice Type Posted
F22 Consolidated Operations and Maintenance Hangar (COMH), Langley AFB Award Award Notice
F22 Consolidated Operations and Maintenance Hangar (COMH), Langley AFB Latest special notice Special Notice
This notice Solicitation
F22 Consolidated Operations and Maintenance Hangar (COMH), Langley AFB Original Pre-Solicitation

Similar open opportunities

Opportunity Agency Set-aside Responses due
F-35 Composite Repair and Training Facility / F-35 Maintenance Facility, Hill Air Force Base, Utah Hill Air Force Base, Utah, United States · NAICS 236210 ENDIST Sacramento No set-aside
P1050 maintenance hangar at NAS JRB fort worth, TX. Fort Worth, Texas, United States · NAICS 236220 Naval Facilities Engineering Command No set-aside
REQUEST FOR INFORMATION (RFI) / MARKET RESEARCH NOTICE RELATED TO SEVERAL UPCOMING PROJECTS at WRIGHT-PATTERSON AFB, OHIO Wright Patterson AFB, Ohio 45433, United States · NAICS 236220 ENDIST Louisville No set-aside
RWP - Test Site 2 (TS2) Improvements & Modernization, Aerospace Vehicle Survivability Facility (AVSF) Wright Patterson AFB, Ohio, United States · NAICS 236220 Air Force Test Center No set-aside

On GovTribe

Work this opportunity

  • Track it in your pipeline
  • Find teaming partners
  • Similar opportunities
  • Ask GovTribe AI about this opportunity