This is an amendment to a solicitation for construction of a consolidated operations and maintenance hangar at Langley Air Force Base. The amendment updates door hardware specifications and environmental control requirements. It also modifies drawings and specifications references. The project involves construction of a six-bay hangar to provide maintenance support for additional F-22 aircraft. The 58,000 square foot facility will house maintenance bays, administration, shops, storage, and support spaces. Site work will include fill, foundations, paving and utilities. Design will comply with DoD facility criteria for construction, sustainability, and antiterrorism. The projected duration is 700 days unless a option for an accelerated 565 day schedule is exercised. Only Factor 1 and 2 responses are requested at this time in response to the bifurcated solicitation.
View the file
Other files
Show all 48
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
Modification is issued to update section 08 71 00 Door hardw are and Applendix to 08 71 00:
. Please see the continuation sheet for additional information and the new attachment number 7
1. CONTRACT ID CODE PAGE OF PAGES
J 1 4
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 09-Nov-2021
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W9123621R2003
X 9B. DATED (SEE ITEM 11)
21-Jan-2021
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN
REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
09-Nov-2021
CODE
USACE NORFOLK DISTRICT OFFICE
CONTRACTING OFFICE
803 FRONT STREET
NORFOLK VA 23510-1011
W91236 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W9123621R2003
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)
The following have been added by full text:
AMENDMENT 6
PROJECT TABLE OF CONTENT
Delete section 08 71 00 Door hardware and Appendix to 08 71 00: Hardware List. Add section “08 71 00 Door Hardware 02/16 Amendment #0006 and Appendix to 08 71 00: Hardware Sets” (Attachment 7)
SECTION 01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS
Section 1.8 Licenses and Permits In subparagraph ‘a’ add “approvals and ….. and are included in the Appendix to this specification:”
After sub paragraph ‘a’ add: (1) Virginia Department of Environmental Quality (DEQ) has approved the combined Stormwater Management and Erosion & Sediment Control Plan.”
After sub paragraph ‘b’ add: “(Updates to the Air Emissions Permit. Provide information required in paragraph 3.5 below.
For permits or approvals obtained by the Government, whether or not required by the permit or approval, the Contractor is responsible for conforming to all permit requirements and performing all quality control inspections of the work in progress, and to submit notifications and certifications to the applicable regulatory agency via the Contracting Officer.”
SECTION 08 33 23 OVERHEAD COILING DOORS –
Section 2.2.1.1 In first sentence add “exterior and” Delete second paragraph.
SECTION 08 33 23 OVERHEAD COILING DOORS –
Section 2.2.1.5 After paragraph add “In addition to endlocks, exterior doors which are more than 16 feet wide or which have a design wind load of more than 20 pounds per square foot, must have windlocks of manufacturer's standard design. Windlocks must prevent curtain from leaving guide because of deflection from wind press.
SECTION 08 33 23 OVERHEAD COILING DOORS
Section 2.2.6.1 After this paragraph add the following:
“2.2.6.2 Stainless Steel Type 304, No. 4 Finish”
SECTION 00 70 00 - CONDITIONS OF THE CONTRACT
The following have been modified:
252.236-7001 CONTRACT DRAWINGS AND SPECIFICATIONS (AUG 2000)
(a) The Government will provide to the Contractor, without charge, one set of contract drawings and specifications, except publications incorporated into the technical provisions by reference, in electronic or paper media as chosen by the Contracting Officer.
(b) The Contractor shall--
(1) Check all drawings furnished immediately upon receipt;
(2) Compare all drawings and verify the figures before laying out the work;
(3) Promptly notify the Contracting Officer of any discrepancies;
(4) Be responsible for any errors that might have been avoided by complying with this paragraph (b); and
(5) Reproduce and print contract drawings and specifications as needed.
(c) In general--
(1) Large-scale drawings shall govern small-scale drawings; and
(2) The Contractor shall follow figures marked on drawings in preference to scale measurements.
(d) Omissions from the drawings or specifications or the misdescription of details of work that are manifestly necessary to carry out the intent of the drawings and specifications, or that are customarily performed, shall not relieve the Contractor from performing such omitted or misdescribed details of the work. The Contractor shall perform such details as if fully and correctly set forth and described in the drawings and specifications.
(e) The work shall conform to the specifications and the contract drawings identified on the following index of drawings:
Drawings and Specifications
1) COMH – Final Design Drawings Part 1 of 3.pdf, dated 01/04/2021, 154 pages
2) COMH – Final Design Drawings Part 2 of 3.pdf, dated 01/04/2021, 158 pages
3) COMH – Final Design Drawings Part 3 of 3.pdf, dated 01/04/2021, 222 pages
4) COMH – Final Design Specifications Part 1 of 1.pdf, dated 01/04/2021, 2900 pages
1) COMH_RTA_Design Drawings_Part 1 of 3_17MAR21.pdf, dated 03/07/2021, 157 pages
2) COMH_RTA_Design Drawings_Part 1 of 3_17MAR21, dated 03/07/2021, 161 pages
3) COMH_RTA_Design Drawings_Part 3 of 3_17MAR21.pdf, dated 03/07/2021, 225 pages
4) COMH_RTA_Specifications part 1 of 1_17MAR21, dated 03/07/2021, 2924 pages
5) COMH - RTA FFE_17MAR21.pdf, dated 03/07/2021, 58 pages
6) COMH - RTA SID_17MAR21, dated 03/07/2021, 32 pages
7) COMH – Section 08 71 00 Door Hardware 02/16 Amendment #0006 24 pages
(End of clause)