Attachment 8 - CLIN Schedule.pdf

PDF 141 KB Posted

Attached to
F22 Consolidated Operations and Maintenance Hangar (COMH), Langley AFB
Solicitation number
W9123621R2003
Issued by

About this file

This document outlines a contract line item schedule for the construction of an F22 Consolidated Operations and Maintenance Hangar at Joint Base Langley-Eustis in Virginia. The base proposal includes construction of the hangar building, site work, and utility connections. There are ten bid options that can be exercised after award, including additions for audiovisual equipment, fixtures and furniture, airfield lighting, parking areas, electrical infrastructure, and disposal of unsatisfactory soils. Pricing is provided for the base work and each individual option. The Army Corps of Engineers is the contracting agency. The project completion period is 700 days unless the schedule reduction option is exercised.

View the file

Other files

File Type Posted
W9123621R2003_0016.pdf PDF
W9123621R2003_0015.pdf PDF
W9123621R2003_0014.pdf PDF
W9123621R2003_0013.pdf PDF
W9123621R2003_0012.pdf PDF
Attachment 8 - CLIN Schedule_REVISION 1 on 01.05.2022.pdf PDF
AMENDMENT 0011_21 DEC 21 - Drawings.pdf PDF
Amend 0011_23 09 23_Amended V2.pdf PDF
Amend 0011_07 61 14.00 20_Amended.pdf PDF
W9123621R2003_0011.pdf PDF
Attachment 16 - Construction Security Plan (CSP).pdf PDF
Attachment 17 - Installation Restoration Program (IRP) Background Chem Data.pdf PDF
COMH Amended Drawings_14 DEC 2021.pdf PDF
W9123621R2003_0010.pdf PDF
COMH Amended Specs_14 DEC 2021_Combined.pdf PDF
A.07.23 - Solicitation COMH W9123621R2003 0009.pdf PDF
W9123621R2003_0008.pdf PDF
COMH Tech Amendment 0007 - 01 57 13.00 22_Amended.pdf PDF
COMH Tech Amendment 0007 - AMENDMENT 19 NOV 21 - Drawings.pdf PDF
COMH Tech Amendment 0007 - 07 27 19.01_Amended.pdf PDF
A.07.24 SF30 - W9123621R2003 - 0007.pdf PDF
08 71 00_Amended 006.pdf PDF
W9123621R2003 Amendment 0006.pdf PDF
A.07.20 - Site Visit Sign-in Log - Dtd 20 Oct 2021_1Page.pdf PDF
A.07.24 SF30 - W9123621R2003 - 0005.pdf PDF
Attachment 12 - COMH_RTA_Design Drawings_Part 3 of 3_17MAR21.pdf PDF
Attachment 11 - COMH_RTA_Design Drawings_Part 2 of 3_17MAR21.pdf PDF
Attachment 13 - COMH_RTA_Specifications part 1 of 1_17MAR21.pdf PDF
Attachment 10 - COMH_RTA_Design Drawings_Part 1 of 3_17MAR21.pdf PDF
Attachment 15 - COMH - RTA SID_17MAR21.pdf PDF
Attachment 14 - COMH - RTA FFE_17MAR21.pdf PDF
A.07.24 SF30 - W9123621R2003 - 0004.pdf PDF
A.07.24 SF30 - W9123621R2003 - 0003.pdf PDF
A.07.24 SF30 - W9123621R2003 - 0002.pdf PDF
W9123621R2003 - 0001 - COMH.pdf PDF
Attachment 12 - COMH - Final Design Drawings Part 3 of 3.pdf PDF
Attachment 9 - Langley Environmental Management Special Conditions.pdf PDF
Attachment 3 - Past Performance Questionnaire.pdf PDF
Solicitation W9123621R2003 - COMH.pdf PDF
Attachment 7 - Small Business Participation Plan.pdf PDF
Attachment 13 - COMH Final Design Specifications Part 1 of 1.pdf PDF
Attachment 1 - Proposal Data Sheet.pdf PDF
Attachment 10 - COMH - Final Design Drawings Part 1 of 3.pdf PDF
Attachment 5 - Letter of Commitment Sample.pdf PDF
Attachment 6 - Small Business Subcontracting Record.pdf PDF
Attachment 4 - Telephone Interview Questionnaire (For Government Use Only).pdf PDF
Attachment 2 - Company Specialized Experience.pdf PDF
Attachment 11 - COMH - Final Design Drawings Part 2 of 3.pdf PDF
Show all 48

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

F22 Consolidated Operations and Maintenance Hangar Joint Base Langley-Eustis (JBLE)

W91236-21-R-2003

Attachment 8 – CLIN Schedule

OFFEROR’S NAME:

CONTRACT LINE ITEM SCHEDULE

CLIN

Description

(QTY)

Unit

Unit Price

Amount

Base Proposal 0001 All work, labor, materials, and equipment required to the

Consolidated Operations and Maintenance Hangar (COMH), including all building related construction within the 5’ line, complete as prescribed in the construction documents excluding work described in CLIN 0002 – CLIN 0014.

Source of funding is MILCON.

(1)

JOB

0002 All work, labor, materials, and equipment required to construct the COMH site improvements, including all construction outside of the 5’ line, complete as prescribed in the construction documents excluding work described in CLIN 0001 and CLIN 0003 - CLIN 0014.

Source of funding is MILCON.

0003 All work, labor, materials, and equipment required to construct electrical service to the new COMH facility including transformer Q050A and medium voltage cabling to transformer by Dominion Energy, as indicated, complete as prescribed in the in the construction documents excluding work described in CLIN 0001 – CLIN 0002 and CLIN 0004 – CLIN 0014.

Source of funding is MILCON.

0004 All work, labor, materials, and equipment required to construct natural gas service to the new COMH facility by Virginia Natural Gas, including the distribution system to the new facility, the meter, the regulator and all connection fees, complete as prescribed in the in the construction documents excluding work described in CLIN 0001 – CLIN 0003 and CLIN 0005 - CLIN 0014.

Source of funding is MILCON.

Total Base

0005 Bid Option 1 All work, labor, materials, and equipment required to furnish and install Audio-Visual (AV) Equipment complete as prescribed in the construction documents excluding work described in CLIN 0001 – CLIN 0004 and CLIN 0006 - 0014.

Source of funding is NON-MILCON. Option to be exercised within 365 days of contract Notice To Proceed in accordance with FAR 52.217-7.

Source of funding is NON-MILCON

Unit

0006 BID OPTION 2

All work, labor, materials, and equipment required to furnish and install Fixtures, Furniture and Equipment (FF&E) complete as prescribed in the construction documents excluding work described in CLIN 0001 – CLIN 0005 and CLIN 0007 - CLIN 0014. Source of funding is NON-MILCON.

Option to be exercised within 365 days of contract Notice To Proceed in accordance with FAR 52.217-7.

Source of funding is NON-MILCON

0007 BID OPTION 3

All work, labor, materials, and equipment required to construct the High Mast Airfield Lighting, complete as prescribed in the construction documents excluding work described in CLIN 0001 – CLIN 0006 and CLIN 0008 – CLIN 0014. Source of funding is NON-MILCON. Option to be exercised within 180 days of contract Notice To Proceed in accordance with FAR 52.217-7.

Source of funding is NON-MILCON

0008 BID OPTION 4

Provide unit price for all work, labor, materials, and equipment required to provide the two (2) parking areas (ten

(10) diagonal automobile parking spaces) along Danforth Ave, excluding work described in CLIN 0001 – CLIN 0007 and CLIN 0009 - 0014. Source of funding is MILCON. Option to be exercised within 180 days of contract Notice To Proceed in accordance with FAR 52.217-7.

Source of funding is MILCON

0009 BID OPTION 5

All work, labor, materials, and equipment required to construct electrical infrastructure (concrete pads, manholes, ductwork, etc.) from and including EM85A to Switch Q050, complete as prescribed in the in the construction documents excluding work described CLIN 0001 – 0008 and CLIN 0010 – 0014. Option to be exercised within 180 days of contract Notice To Proceed in accordance with FAR 52.217-7.

Source of funding is MILCON.

0010 BID OPTION 6

All work, labor, materials, and equipment required to construct electrical service from and including EM85A to and including connection to Switch Q050 by Dominion Energy, complete as prescribed in the in the construction documents excluding work described CLIN 0001 – 0009 and CLIN 0011 – 0014. Option to be exercised within 180 days of contract Notice To Proceed in accordance with FAR 52.217-7.

Source of funding is MILCON.

Unit

0011 BID OPTION 7

All work, labor, materials, and equipment required to dispose any other-than-clean soil complete as prescribed in the construction documents, including but not limited to specification section 01 57 19 Temporary Environmental Controls 01 57 19 ATTACHMENT JBLE-Langley Environmental Special Conditions para 1.1.2.2, excluding work described in CLIN 0001 – CLIN 0010 and CLIN 0012 – CLIN 0014.

Source of funding is MILCON. Option to be exercised within 365 days of contract Notice To Proceed in accordance with

FAR 52.217-7.

For bidding purposes Offeror shall assume a total quantity of 250 CY.

Source of funding is MILCON

(250)

CY

0012 BID OPTION 8

equipment required to dispose unsatisfactory subgrade soils due to failure of proof roll testing and replace with aggregate base complete as prescribed in the construction documents, excluding work described in CLIN 0001 – 0011 and CLIN 0013 - 0014. Source of funding is MILCON. Option to be exercised within 365 days of contract Notice To Proceed in accordance with FAR 52.217-7.

For bidding purposes Offeror shall assume 500 cy.

Unit Price for each cubic yard (CY)

Source of funding is MILCON

(500)

0013 BID OPTION 9

equipment required to decrease contract completion date by 135 calendar days, excluding work described in CLIN 0001– CLIN 0012 and CLIN 0014. Source of funding is MILCON.

Option to be exercised upon initial award in accordance with

FAR 52.217-7.

Source of funding is MILCON

0014 BID OPTION 10

Provide unit price for all work, labor, materials, and equipment required to dispose and replace any unsatisfactory soils which have been removed as uncontrolled fill yet do not meet the requirements for Structural Fill, complete as prescribed in the construction documents, excluding work described in CLIN 0001 - 0013. Source of funding is MILCON. Option to be exercised within 365 days of contract Notice To Proceed in accordance with FAR 52.217-7.

For bidding purposes Offeror shall assume 310 cy.

Unit Price for each cubic yard (cy).

Source of funding is MILCON

(310)

TOTAL BASE AMOUNT

(CLINS 0001, 0002, 0003, 0004)

TOTAL NON-MILCON OPTIONS

(CLINS 0005, 0006, 0007)

TOTAL MILCON OPTIONS

(CLINS 0008, 0009, 0010, 0011, 0012, 0013, 0014)

TOTAL (BASE PLUS OPTIONS)

NOTES FOR CONTRACT LINE ITEM (CLIN) SCHEDULE

NOTE NO. 1. To better facilitate the receipt and proposal process, all modifications to proposals are to be submitted on copies of the latest Contract Line Item (CLIN) schedules as published in the solicitation or the latest amendment thereto. In lieu of indicating additions/deductions to line items, all Offerors should state their revised prices for each item.

NOTE NO. 2. Offerors must insert a price on all numbered items including unit prices and options of the CLIN Schedule.

Failure to do so may result in the offer being unacceptable.

NOTE NO. 3. The Offeror’s Base Bid and all Options will be evaluated. In accordance with 52.217-5, Evaluation of Options, the Government will evaluate offers for award purposes by adding the total price for all options to the total price for the basic requirement. Evaluation of options will not obligate the Government to exercise the option(s).

NOTE NO. 4. In accordance with FAR Part 15.306, exchanges with offerors after receipt of proposals may be held to resolve ambiguities in the proposal such as errors or mistakes in addition and multiplication.

Attachment 8 – CLIN Schedule