W9123621R2003 - 0001 - COMH.pdf
PDF 171 KB Posted
- Solicitation number
- W9123621R2003
About this file
This document contains a solicitation for construction services and amendments to the solicitation. Key details include:
-
The solicitation is for the construction of a six-bay high-bay consolidated operations and maintenance hangar to provide maintenance support for additional F-22A aircraft at Langley Air Force Base in Hampton, Virginia. The facility will include hangar bays, administration spaces, shops, storage, and supporting infrastructure. Site work will include demolishing an existing facility.
-
The project duration is 700 calendar days from notice to proceed unless option CLIN 0013 is exercised, which would reduce the completion date to 565 days. - Responses to Factors 1 and 2 are requested initially, with the design package to be provided via future amendment. - The solicitation was amended to include evaluator questions and responses relating to past performance evaluations and NIST cybersecurity requirements.
View the file
Other files
Show all 48
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.
15A. NAME AND TITLE OF SIGNER (Type or print)
30-105-04EXCEPTION TO SF 30
APPROVED BY OIRM 11-84
STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA
FAR (48 CFR) 53.243
Solicitation W9123621R2003 F22 Consolidated Operations and Maintenance Hanger (COMH), at Langley AFB in Hampton, VA is hereby amended as follow s:
1. All ProjNet questions and evaluations are added.
-- No further changes.
Contracting POC: Bryan Butler 757-201-7132 bryan.j.butler@usace.army.mil
1. CONTRACT ID CODE PAGE OF PAGES
J 1 3
16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)
16C. DATE SIGNED
BY 17-Feb-2021
16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR
(Signature of Contracting Officer)(Signature of person authorized to sign)
8. NAME AND ADDRESS OF CONTRACTOR (No., Street, County, State and Zip Code) X W9123621R2003
X 9B. DATED (SEE ITEM 11)
21-Jan-2021
10B. DATED (SEE ITEM 13)
9A. AMENDMENT OF SOLICITATION NO.
11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS
X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.
Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:
(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;
or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (If required)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.
IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.
A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE
CONTRACT ORDER NO. IN ITEM 10A.
B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).
C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:
D. OTHER (Specify type of modification and authority)
E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)
10A. MOD. OF CONTRACT/ORDER NO.
2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)
6. ISSUED BY
3. EFFECTIVE DATE
17-Feb-2021
CODE
USACE, NORFOLK DISTRICT OFFICE
CONTRACTING OFFICE
803 FRONT STREET
NORFOLK VA 23510-1011
W91236 7. ADMINISTERED BY (If other than item 6)
4. REQUISITION/PURCHASE REQ. NO.
CODE
See Item 6
FACILITY CODECODE
EMAIL:TEL:
W9123621R2003
SECTION SF 30 BLOCK 14 CONTINUATION PAGE
SUMMARY OF CHANGES
SECTION 00 10 00 - SOLICITATION
The following have been added by full text:
PROJNET INQUIRIES
PROJNET INQUIRIES The following Bidder Inquiry and subsequent corresponding Government Response are hereby incorporated:
Bidder Inquiry 9022481: Is the NIST SP 800-171 listed on page 12 of the solicitation a requirement for award for this project and if so what is the required level of assessment needed for the Prime Contractor?
Subcontractors?
Government Response to 9022481: Interim DFARS Rule 2019-D014 requires the inclusion of DFARS 252.204-7019 and 252.204-7020 in this contract and solicitation. However, the requirements contained in DFARS 252.204-7019 and 252.204-7020 are not applicable to this contract and the awardee will not be required to have posted an assessment on SPRS. We recommend that any additional questions regarding the requirements of these clauses be directed to the offerors' attorneys.
Bidder Inquiry 9040829: Is it acceptable to submit PPQ evaluations from previously submitted solicitations?
Government Response to 9040829: Yes, providing the PPQ evaluation previously submitted under another solicitation is acceptable, as long as it is in the specified format and is not included by reference.
Bidder Inquiry 9045709: RFP Section 00 21 16, paragraph 5.2.1 TAB B - FACTOR 1 – SPECIALIZED EXPERIENCE: Paragraph 5.2.1 indicates, "For a submitted project to be considered "Recent", it should be more than approximately 75% complete based on amount invoiced or turned over no more than ten (10) years preceding the issuance of this Solicitation." Given the unique, specialized nature of the anticipated F22 Consolidated Operations and Maintenance Hanger (COMH), at Langley AFB, and the relatively limited number of recently completed similar facilities, we respectfully request that the "Recent" timeframe adjust to "...turned over no more than twelve (12) years...".
Government Response to 9045709: The requirement remains unchanged.
Bidder Inquiry 9045736: The RFP states each volume's page parameter is to be set up using a "0" gutter parameter. Is a two-column layout acceptable?
Government Response to 9045736: There is no limitation on the number of columns. Formatting requirements identified in the solicitation still apply.
Bidder Inquiry 9054002: RFP Section 00 21 16, page 20 of 85, paragraph 1.6 states "The Government will not undertake to compare or conduct a selection decision until after all factors have been evaluated."
Prior to when the RTA design package becomes available via amendment, we respectfully request that the government issue evaluation notices to offerors exhibiting proposal weaknesses and deficiencies for Factor 1, Specialized Experience, and Factor 2, Past Performance.
W9123621R2003
Government Response to 9054002: In accordance with FAR Part 15.306, the Government does not intend to conduct discussions until all proposals are evaluated against all evaluation factors.
(End of Summary of Changes)