This amendment to a solicitation and the related federal contract opportunity provide details for a construction project. The U.S. Army Corps of Engineers, Norfolk District, issued Amendment 0016 to Solicitation W9123621R2003 to revise the concrete specification and response to a question regarding locating a batching and mixing plant. Offerors must provide a six-bay high-bay consolidated operations and maintenance hangar at Langley Air Force Base to support additional F-22A aircraft from Tyndall AFB. The project scope includes site work, foundations, structural steel frame, utilities and pavements to construct a 150-ton air conditioned facility. The period of performance is 700 days from notice to proceed, with an option to reduce to 565 days if CLIN 0013 is exercised. This bifurcated solicitation requests responses to Factors 1 and 2 initially.

View the file

Other files

File Type Posted
W9123621R2003_0015.pdf PDF
W9123621R2003_0014.pdf PDF
W9123621R2003_0013.pdf PDF
W9123621R2003_0012.pdf PDF
Attachment 8 - CLIN Schedule_REVISION 1 on 01.05.2022.pdf PDF
AMENDMENT 0011_21 DEC 21 - Drawings.pdf PDF
Amend 0011_23 09 23_Amended V2.pdf PDF
Amend 0011_07 61 14.00 20_Amended.pdf PDF
W9123621R2003_0011.pdf PDF
Attachment 16 - Construction Security Plan (CSP).pdf PDF
Attachment 17 - Installation Restoration Program (IRP) Background Chem Data.pdf PDF
COMH Amended Drawings_14 DEC 2021.pdf PDF
W9123621R2003_0010.pdf PDF
COMH Amended Specs_14 DEC 2021_Combined.pdf PDF
A.07.23 - Solicitation COMH W9123621R2003 0009.pdf PDF
W9123621R2003_0008.pdf PDF
COMH Tech Amendment 0007 - 01 57 13.00 22_Amended.pdf PDF
COMH Tech Amendment 0007 - AMENDMENT 19 NOV 21 - Drawings.pdf PDF
COMH Tech Amendment 0007 - 07 27 19.01_Amended.pdf PDF
A.07.24 SF30 - W9123621R2003 - 0007.pdf PDF
08 71 00_Amended 006.pdf PDF
W9123621R2003 Amendment 0006.pdf PDF
A.07.20 - Site Visit Sign-in Log - Dtd 20 Oct 2021_1Page.pdf PDF
A.07.24 SF30 - W9123621R2003 - 0005.pdf PDF
Attachment 12 - COMH_RTA_Design Drawings_Part 3 of 3_17MAR21.pdf PDF
Attachment 11 - COMH_RTA_Design Drawings_Part 2 of 3_17MAR21.pdf PDF
Attachment 13 - COMH_RTA_Specifications part 1 of 1_17MAR21.pdf PDF
Attachment 10 - COMH_RTA_Design Drawings_Part 1 of 3_17MAR21.pdf PDF
Attachment 15 - COMH - RTA SID_17MAR21.pdf PDF
Attachment 14 - COMH - RTA FFE_17MAR21.pdf PDF
A.07.24 SF30 - W9123621R2003 - 0004.pdf PDF
A.07.24 SF30 - W9123621R2003 - 0003.pdf PDF
A.07.24 SF30 - W9123621R2003 - 0002.pdf PDF
W9123621R2003 - 0001 - COMH.pdf PDF
Attachment 12 - COMH - Final Design Drawings Part 3 of 3.pdf PDF
Attachment 9 - Langley Environmental Management Special Conditions.pdf PDF
Attachment 8 - CLIN Schedule.pdf PDF
Attachment 3 - Past Performance Questionnaire.pdf PDF
Solicitation W9123621R2003 - COMH.pdf PDF
Attachment 7 - Small Business Participation Plan.pdf PDF
Attachment 13 - COMH Final Design Specifications Part 1 of 1.pdf PDF
Attachment 1 - Proposal Data Sheet.pdf PDF
Attachment 10 - COMH - Final Design Drawings Part 1 of 3.pdf PDF
Attachment 5 - Letter of Commitment Sample.pdf PDF
Attachment 6 - Small Business Subcontracting Record.pdf PDF
Attachment 4 - Telephone Interview Questionnaire (For Government Use Only).pdf PDF
Attachment 2 - Company Specialized Experience.pdf PDF
Attachment 11 - COMH - Final Design Drawings Part 2 of 3.pdf PDF
Show all 48

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

Amendment 0016 is issued to provide the follow ing:

1. A revision to the concrete specification. Please see continuation page.

2. A revised response to a ProjNet question. Please see continuation page.

Contracting POC: Axel Doody 757-201-7712 Axel.F.Doody@usace.army.mil

1. CONTRACT ID CODE PAGE OF PAGES

1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 21-Jan-2022

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X W9123621R2003

X 9B. DATED (SEE ITEM 11)

21-Jan-2021

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer is extended, X is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

21-Jan-2022

CODE

USACE NORFOLK DISTRICT OFFICE

CONTRACTING OFFICE

803 FRONT STREET

NORFOLK VA 23510-1011

W91236 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

W9123621R2003

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

AMENDMENT 0016

Amendment 0016 is issued to provide the following:

1. SPECIFICATION SECTION 32 13 14.13 CONCRETE PAVING FOR AIRFIELDS AND OTHER

HEAVY DUTY PAVEMENTS

2.11.1.1 Location

Delete “Locate the batching and mixing plant off Government premises no more than 15 minutes haul time from the placing site. ”

Add “Locate the batching and mixing plant off Government premises. The use of an offsite ready mixed concrete facility will be considered acceptable as long as the Contractor can reliably meet all related requirements for concrete placement identified herein.”

3.4.2 Transporting and Transfer - Spreading Operations

Delete “ Operate non-agitating equipment only on smooth roads and for haul time less than 15 minutes.”

Add “ Operate non-agitating equipment only on smooth roads.”

2. ProjNet Inquiry ID 9493801 The requirement in Specification 32 13 14.13 for locating a batching and mixing plant off Government premises no more than 15 minutes haul time from the placing site (paragraph 2.11.1.1) is not practical and, in fact may not be possible. Please confirm that this requirement will be relaxed or deleted.

GOVERNMENT RESPONSE

Delete “Offerors shall locate the batching and mixing plant off Government premises no more than 15 minutes haul time from the placing site or as approved by the Contracting Officer. Refer to technical changes provided by amendment 0010.”

Add “The requirement for haul time of 15 minutes is removed. Instead, locate the batching and mixing plant off Government premises. The use of an offsite ready mixed concrete facility will be considered acceptable as long as the Contractor can reliably meet all related requirements for concrete placement identified in the specifications. Refer to technical changes provided by Amendment 0016.”

(End of Summary of Changes)