DRAFT Attachment 0137 - Design Review Checklist.xlsx

XLSX spreadsheet 28 KB Posted

Attached to
Joint Light Tactical Vehicle (JLTV) Family of Vehicles (FoV) Follow-On
Solicitation number
W56HZV-20-R-0072
Issued by

About this file

This document contains a draft design review checklist for the Joint Light Tactical Vehicle (JLTV) program and information on an upcoming industry day event.

The draft design review checklist outlines criteria and exit requirements for an Initial Design Review and Final Design Review of the JLTV. It includes requirements for participation and deliverables, as well as review criteria covering technical specifications, systems engineering, manufacturing and quality. The industry day event will provide an overview of the JLTV follow-on production contract strategy and make the technical data package and first draft RFP available. It will include presentations on February 24th and one-on-one sessions and a static vehicle display with the JLTV on February 25th. Interested parties are required to submit a base access request form by February 14th to attend.

View the file

Other files

File Type Posted
220121_JLTV-FoV_Prod_DRAFT-RFP_QAs_(Distribution_A).pdf PDF
JLTV FOC - Industry Day for DRAFT RFP3.pptx PPTX presentation
2021 SANG Vetting Form A2 Static Display.xlsx XLSX spreadsheet
DRAFT Attachment 0107 - Project Expenditure Report(3).xlsx XLSX spreadsheet
DRAFT Attachment 0151 - EDFP Data Righs.pdf PDF
DRAFT Attachment 0144 - Data Requirements Form for Acquisition Requirement Package (ARP).pdf PDF
DRAFT Attachment 0142 - Table A-VII (DMWR_NMWR Requirements Matrix)(3).docx DOCX document
DRAFT Attachment 0179 - Small Business Participation Cert.pdf PDF
DRAFT Attachment 0173 - Production Process Site Visit Plan.docx DOCX document
DRAFT Attachment 0122 - JLTV FoV Master Task List.xlsx XLSX spreadsheet
DRAFT Attachment 0117 - HMMR Format Example.xlsx XLSX spreadsheet
DRAFT Attachment 0126 - Design Verification Plan and Report (DVPR).xlsx XLSX spreadsheet
DRAFT Attachment 0177 - Small Business Participation Factor WB.xlsx XLSX spreadsheet
DRAFT Attachment 0148 - CDRS Search.pdf PDF
DRAFT Attachment 0113 - M and S Input Data Sheets.xlsx XLSX spreadsheet
DRAFT Attachment 0172 -Technology Enhancement TDP Proposal.xlsx XLSX spreadsheet
DRAFT Attachment 0118 - Hazard Tracking Log(3).xls XLS spreadsheet
Draft Section E - Inspection and Acceptance(3).docx DOCX document
DRAFT Attachment 0159 - Welding Standards(3).doc DOC document
DRAFT Attachment 0119 - Exceptions to Hazardous Materials Requirements(3).doc DOC document
DRAFT Attachment 0127 - GFP_GFI List.XLSX XLSX spreadsheet
DRAFT Attachment 0125 - Windchill User Guide.pdf PDF
DRAFT Attachment 0149 - LLRC Proposal Format.DOC DOC document
DRAFT Attachment 0116 - Risk Management Scoring Criteria Template.xlsx XLSX spreadsheet
DRAFT Attachment 0120 - ECP and VECP.docx DOCX document
DRAFT Attachment 0133 - New Equipment Training(3).pdf PDF
DRAFT Attachment 0178 - Small Business Participation Factor WB Instructions.docx DOCX document
DRAFT Attachment 0176 - Production Process Attribute Rating Criteria.xlsx XLSX spreadsheet
Draft Section C - SOW(3).docx DOCX document
DRAFT Attachment 0121 - Request for Variance (RFV).docx DOCX document
DRAFT Attachment 0134 - Deprocessing Checklist(3).docx DOCX document
DRAFT Attachment 0106 - STA Form 7114-2.pdf PDF
DRAFT Attachment 0132 - STS Phase 1 WD Process List(3).xlsx XLSX spreadsheet
DRAFT Attachment 0115 - SIL Configuration and Verification Audit (SCAVA).docx DOCX document
Draft Section H - Special Contract Requirements(3).docx DOCX document
DRAFT Attachment 0147 - ATPD 2232 Engines - Preparation for Shipment and Storage.pdf PDF
DRAFT Attachment 0153 - Pre-TRR Checklist(3).docx DOCX document
DRAFT Attachment 0123 - TDP Option Selection Worksheet.docx DOCX document
Draft Section L - Instr., Conditions, and Notices(3).docx DOCX document
DRAFT Attachment 0128 - Supplier RFI Form(3).xlsx XLSX spreadsheet
DRAFT Attachment 0146 - Incoming Transaction Format(3).docx DOCX document
DRAFT Attachment 0163 - JLTV Special Characteristics(3).docx DOCX document
DRAFT Attachment 0168 - DCAA Preaward Survey of Prospective Contractor Accounting System Checklist.pdf PDF
DRAFT Attachment 0143 - Provisioning Requirements Statement(3).pdf PDF
DRAFT Attachment 0145 - Packaging Data Products(3).docx DOCX document
DRAFT Attachment 0152 - Provisioning Requirements LSA-036.xlsx XLSX spreadsheet
DRAFT Attachment 0164 - JLTV PPAP Requirements(3).docx DOCX document
DRAFT Attachment 0135 - FMECA Requirements.pdf PDF
DRAFT Attachment 0174 - Assertion of Restrictions.xlsx XLSX spreadsheet
DRAFT Attachment 0111 - FPVI Requirements List.xlsx XLSX spreadsheet
Show 40 more

Latest 50 of 167 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Title

UNCLASSIFIED

Draft Attachment 0137

Design Review Checklist

October 2021

Distribution Statement A – Approved for Public Release; distribution unlimited
UNCLASSIFIED

Criteria

UNCLASSIFIED

EventObjectiveContract Ref.
Initial Design Review (IDR)Completed
Initial Design Review PreparationsCompleted
P1Participation/AdministrationMet
P2Indentured Bill of MaterialsDelivered
P3Performance Specification Compliance AnalysisDelivered
P4RAM Management PlanUpdated
P5Quality Management SystemDelivered
P6DFMEA and PFMEADelivered
P7DVP&RDelivered
P8Agenda and Read‐Ahead PackagesFinalized
Requirements ReviewCompleted
R1Purchase Description Complinace PlanReviewed
R2SOW SE SectionUnderstood
R3SOW Safety & Environmental SectionUnderstood
R4Quality and TestUnderstood
R5Quality, Test and Engineering CDRL reviewUnderstood
R6Contractor Integrated Master Schedule (design, test, quality)Reviewed
R7Risk review (technical - performance, quality, test and manufacturing)Established
R8SOW Configuration Management PlanUnderstood
Systems Engineering ReviewCompleted
SE1Systems Engineering Management PlanReviewed
SE2Indentured Bill of MaterialsReviewed
SE3Initial Design Drawing Package - Government Unique ComponentsReviewed
SE4M&S Strategy / Initial M&S ResultsReviewed
SE5Software DesignReviewed
SE6Initial Design of Major Systems and SubsystemsReviewed
SE7RAM Management PlanReviewed
SE8Initial Design Safety Analysis - ride quality, seating, restraints, roll protetionReviewed
SE9Transportability ReportUnderstood
SE10Corrosion Prevention and Control PlanUnderstood
SE11Hazardous Materials Management ProgramUnderstood
Manufacturing, Quality & Test ReviewCompleted
M1Contractor Verification Test StrategyUnderstood
M2Manufacturing Development StrategyUnderstood
M3Long Lead Item ApproachUnderstood
M4Quality Management SystemReviewed
M5DVP&RReviewed
M6DFMEA and PFMEAReviewed
Initial Design Review ExitCompleted
E1All technical criteria reviewed and feasible, action plan established for risk driversMet
E2Initial P-Spec ReportInitiated
E3Conditional Closure by Chairs Subject to Action Item ClosureApproved
E4Action ItemsUnderstood
E5MinutesApproved
Final Design Review (FDR)Completed
Final Design Review PreparationsCompleted
FD_P1Participation/AdministrationMet
FD_P2Indentured Bill of MaterialsDelivered
FD_P3Performance Specification Compliance AnalysisDelivered
FD_P4RAM Management PlanDelivered
FD_P5Quality Management PlanDelivered
FD_P6DFMEA and PFMEADelivered
FD_P7Transportability ReportDelivered
FD_P8Corrosion Prevention and Control PlanDelivered
FD_P9Hazardous Materials Management ProgramDelivered
FD_P10Safety AssementDelivered
FD_P11DVP&RDelivered
FD_P12Draft ECP DevelopmentDelivered
FD_P13Agenda and Read‐Ahead PackagesFinalized
Technical Program ReviewCompleted
FD_T1Integrated Master ScheduleReviewed
FD_T2Risk TrackingReviewed
FD_T3Systems Engineering Management PlanReviewed
Systems Engineering ReviewCompleted
FD_SE1PD Compliance ReviewCompleted
FD_SE2Design Drawing Package - Government Unique ComponentsReviewed
FD_SE3Detailed Design of Major SubsystemsReviewed
FD_SE4M&S Final ResultsReviewed
FD_SE5Software DesignReviewed
FD_SE6RAM Management PlanReviewed
FD_SE7Transportability ReportReviewed
FD_SE8System Safety Assessment, Human Factors and SARReviewed
FD_SE9Systems Engineering Management PlanUpdated
FD_SE10Corrosion Prevention and Control PlanReviewed
FD_SE11Hazardous Materials Management ProgramReviewed
Manufactuirng, Quality & Test ReviewCompleted
FD_M1Contractor Verification Test StrategyReviewed
FD_M2Manufacturing Readiness StrategyReviewed
FD_M3Long Lead Item ApproachReviewed
FD_M4Quality Management SystemCompleted
FD_M5DVP&RReviewed
FD_M5DFMEA and PFMEACompleted
Final Design Review ExitCompleted
FD_E1FDR Meeting ConductedCompleted
FD_E2Final P-Spec ReportApproved
FD_E3Conditional Closure by Chairs Subject to Action Item ClosureApproved
FD_E4DVP&RCompleted
FD_E5ECPsApproved
FD_E6Action ItemsUnderstood
FD_E7MinutesApproved
UNCLASSIFIED

Verbs

UNCLASSIFIED
VerbsExit Criteria Description for Design Review Events
ApprovedThe subject Document has been submitted and APPROVED by the Government
CompletedThe subject item has been prepared, reviewed and has been deemed acceptable by the Government as satisfying contract requirements in their entirety.
DeliveredThe subject DELIVERABLE has been submitted to the Government and the information presented at the event.
EstablishedThe subject item has been started or created and set in place in a manner consistent with its intended use (e.g., procedures, baselines established)
FinalizedThe subject DELIVERABLE has been finalized in its entirety (with no expectation of updates at future events) and ACCEPTED by the Government.
InitiatedThe first submission of the subject DELIVERABLE has been completed in its entirety and ACCEPTED by the Government.
MetThe subject criteria has been accomplished.
ReviewedThe subject item has been examined critically, presented at the event, and no issues were identified.
UnderstoodThe subject item has been discussed between the Contractor and Government and the two parties have a mutual agreement.
UpdatedThe subject DELIVERABLE has been revised based on later information, adjustments have been incorporated, and ACCEPTED by the Government.