DRAFT Attachment 0132 - STS Phase 1 WD Process List(3).xlsx
XLSX spreadsheet 50 KB Posted
- Solicitation number
- W56HZV-20-R-0072
About this file
This document outlines the process for issuing a work directive under the Joint Light Tactical Vehicle (JLTV) Family of Vehicles program. Key steps in the process include:
-
An Assistant Program Manager, engineer, or logistician delivers a draft contract scope, signed funding request, independent cost estimate, and target award date to initiate the process.
-
A core integrated product team reviews the request and finalizes funding determination, statement of work, and target award date. Proposal preparation hours are then sent to original equipment manufacturers.
-
If needed, government and contractor representatives bilaterally concur on the statement of work. Then the request for proposals is released with a 10 day proposal development period.
-
Proposals are delivered and undergo a technical evaluation and pricing analysis. Negotiations are conducted and award documentation is prepared over a period of approximately 68 days from start to contract award.
View the file
Other files
Show 40 more
Latest 50 of 167 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Cover
UNCLASSIFIED
| Draft Attachment 0132 |
| Systems Technical Support (STS) Phase I Work Directive (WD) Process List |
October 2021
Distribution Statement A – Approved for Public Release; distribution unlimited
(*Distribution Statement A only applies when form is not filled in.
Once filled check the JLTV Security Class Guide for proper distribution statement/markings)
UNCLASSIFIED
&G
STS Phase 1 Process Rev 9
| STS Work Directive Process Checklist (WD Concept to Contract Award) | |||
| Step # | Step Description | # of Business Days to complete | |
| (68 Days) | Completed (ü) | Date | Step in Process Category |
| 1 | APM/Engineer/Logistician delivers the following which is considered the "procurement package" in a folder on SharePoint to the STS Core IPT Review Team: |
- Draft contract scope language for the STS WD
- Signed Request To Issue Funds (RTIF) Form
- Independent Government Cost Estimate (IGCE)
- Requested Target Award Date (TAD)
| (Note: Release to the STS Core IPT using email template). | 1 | Baseline Start of WD Step | |
| 2 | The following will take place during the STS Core IPT Review: |
- STS WD # assigned
- APM/SME work with the PCO/PA to jointly determine achievable TAD
- SOW reviewed by IPT (comments/changes input, adjudication, etc) (opportunity for input across JPO)
- Funding determination (R&D or Procurement, Army, USMC, or joint) shall be established by the budget office during this time
- WD begins to be monitored on tracker
- Cabinet built in PCF by contracting (post TAD determination)
| - APM/Engineer/Logistician shall submit a request to both acquisition and contracting for 100 proposal preparation hours to be sent to OEM for SOW review and proposal preparation. | 8 | Baseline Start of WD Step | |||
| 3 | Upon STS Core IPT approval contracting sends 100 proposal preparation hours to OEM for SOW review and proposal preparation. | 2 | Days to RFP Release Step | ||
| 4 | If determined to be necessary by the APM, the APM/Engineer/Logistician shall collaborate with their contractor counterparts to reach bi-lateral concurrence on the SOW language. This step ends when bi-lateral concurrence on the SOW is reached between the Government and Contractor or the APM determines that the SOW should be released for RFP. | 10 | Days to RFP Release Step | ||
| 5 | Upon receiving SI Leadership concurrence to release the RFP. APM sends SOW to PA to release the RFP to the contractor. | ||||
| (Note: This is the step at which procurement drives award timeline) | 2 | Days to RFP Release Step | |||
| 6 | Contractor acknowledges RFP receipt and the 10 day proposal development process starts. | 10 | Days to Tech Eval and Pricing Step | ||
| 7 | Contractor delivers proposal to the Government (i.e. contracting department) | 1 | Days to Tech Eval and Pricing Step | ||
| 8 | Contract Specialist routes proposal documents in Parallel to APM/SME and the pricing team chief. Pricing team creates tech evaluation template to assist APM/SME in completing the technical evaluation. | ||||
| (Note: Pricing team cannot complete cost/price analysis until the technical evaluation is complete) | 3 | Days to Tech Eval and Pricing Step | |||
| 9 | APM/Engineer/Logistician delivers technical evaluation to pricing team in order for pricing report to be completed. | 5 | Days to Tech Eval and Pricing Step | ||
| 10 | Cost/price Analysis Memorandum (CAM) is completed and delivered to contracting in order to initiate contract negotiations. | ||||
| (Note: If applicable (depending on $ Value) a business clearance memo and legal review and certified cost/pricing data may be required which would increase timeline) | 5 | Days to Tech Eval and Pricing Step | |||
| 11 | Contract negotiations is conducted with contracting, pricing, and the contractor. | 10 | Days to complete negotiations | ||
| 12 | Upon final negotiated agreement, contracting prepares the award documentation and acquisition requests funding from budget office. | 8 | Days for WD Award | ||
| 13 | The contract modification and WD are routed in parallel to the BMO and Contractor for bi-lateral concurrence and signature to award WD | 3 | Days for WD Award | ||
| 14 | Government awards work directive to the contractor | 68 |
| Acronyms | Role of APM | |
| APM | Assistant Program Manager | Role of OEM |
| BMO | Business Management Office | Role of Contracting/Pricing |
| CAM | Cost/price Analysis Memorandum | |
| IGCE | Independent Government Cost Estimate | |
| IPT | Integrated Product Team | |
| JPO | Joint Program Office | |
| OEM | Original Equipment Manufacturer | |
| PA | Procurement Analyst | |
| PCF | Paperless Contract Files | |
| PCO | Procuring Contracting Officer | |
| R&D | Research & Development | |
| RFP | Request For Proposal | |
| RTIF | Request To Issue Funds | |
| SI | Systems Integration | |
| SME | Subject Matter Expert | |
| SOW | Statement of Work | |
| STS | System Technical Support | |
| TAD | Target Award Date | |
| USMC | United States Marine Corps | |
| WD | Work Directive |
&G image1.png