This document outlines requirements for an Engineering Change Proposal (ECP) and Value Engineering Change Proposal (VECP) related to the Joint Light Tactical Vehicle (JLTV) Family of Vehicles program. It specifies the required content and supporting data for any ECPs or VECPs submitted under the contract, including detailed drawings, impacted documentation, test plans and results, cost analyses, and proposed changes clearly delineated. Additionally, it relates to the federal contract opportunity for the JLTV FoV Follow-On Production, with the Department of the Army Materiel Command TACOM Life Cycle Management Command seeking to competitively award a five-year contract with five one-year options. Interested parties must submit requests by specified dates to participate in an industry day event in February 2020 covering the program strategy and draft RFP, as well as scheduled one-on-one sessions and a static vehicle display to obtain feedback to inform the final solicitation requirements.
View the file
Other files
Show 40 more
Latest 50 of 167 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
UNCLASSIFIED
10/25/202114
UNCLASSIFIED JLTV - ECP/VECP
Draft Attachment 0120
Engineering Change Proposal & Value Engineering Change Proposal
October 2021
Distribution Statement A – Approved for Public Release; distribution unlimited
Draft Attachment 0120 Engineering Change Proposal
This contains the content and preparation instructions for the data product resulting from the work task specified in the contract.
Requirements
Reference Documents:
The applicable issue of any documents cited herein, including their approval dates and dates of any applicable amendments, notices, and revisions, shall be as specified in the contract.
Content:
Engineering Change Proposals (ECP) and VECPs shall be prepared in contractor format or by using the ECP form DD1692 found in: https://www.esd.whs.mil/Directives/forms/dd1500_1999/.
The contractor prepared ECPs/VECPs are required to use all fields applicable within the DD1692 Form.
Supporting Data:
In addition to the information required below, the ECP/VECP shall include supporting data as follows:
a. Full size drawings for all affected parts to include installation and interface drawings, and associated modeling data. The drawings shall clearly depict the "From/To" relationship of the change. Screen shots of the affected change will only be considered supplemental to the required full size drawings.
b. A consolidated list of all Contract Data Requirements Lists (CDRLs) impacted by the ECP/VECP.
c. Red line mark ups to Logistic Support Analysis (LSA) data and Logistics Product Data (LPD) CDRLs affected as a result of the ECP/VECP to include but not limited to: CDRL C004 - Logistics Product Data, LSAR 036 with PLISNs impacted, validated red-lines for CDRL C017 - Technical Publications to include, but not limited to, updates to Preventive Maintenance Checks and Services, Operation or Maintenance WPs, Repair Parts and Special Tools List or any other Technical Manual pages impacted by the ECP/VECP, validated CDRL C002 - Kit Installation Instructions (for inclusion in the TDP) and a summary of CDRL C057 - DMSMS Quarterly Status Report COAs. Final delivery of fully incorporated Logistics information via its associated CDRL shall occur no later than 30 days after ECP approval or the next scheduled CDRL deliverable impacted by the ECP/VECP whichever is later. Delivery for all Logistics CDRLs without regular delivery timelines (example “As Required/Needed” in Block 10. “Frequency”) will be delivered NLT 60 days after ECP/VECP approval.
d. Complete list of parts interchangeability factors (down to piece part level if item is repairable).
e. Updated or mark-ups/red-lines of affected Quality Assurance (QA) data.
f. Test data and analyses to justify and describe the change and to determine its total impact including assessments of changes to system operational deployment characteristics. A summary of any testing done to validate concepts or new technology to be employed in the proposed ECP/VECP shall be presented with the supporting data. All planned test activity and results shall be summarized using the Design Verification Plan and Report (DVP&R).
g. Detailed cost proposal data. When a life-cycle cost and/or operation and support cost model has been included in the contract, the ECP/VECP shall also include the costs expected to result from the implementation of the change into all future production and spare items procured for the program. Also for all projected operation and support costs for the total inventory of items by the Government.
h. Historical records that led to the proposed change. Examples: briefing charts, minutes, and work directive.
i. Updated or mark-ups/red-lines to:
Technical Data Package (Section 2.1.1.6) Attachment 0101 - JLTV Purchase Description Attachment 0108 - CSDR Plan CDRL B002 - Anti-Tampering Plan CDRL B008 - Interface Control Document (ICD) CDRL B009 - Software Version Description (SVD) CDRL B014 - Health Management System (HMS) Report CDRL B015 - Vehicle Network Configuration Package CDRL B016 - Routing Diagrams – Cabling, Wiring Harnesses and Plum CDRL B017 - Growth Margin Analysis CDRL B020 - Hazardous Materials Management Report (HMMR) CDRL B021 - Safety Assessment Report CDRL B023 - Human Engineering Systems Analysis Report (HESAR) CDRL B025 - Corrosion Prevention and Control Plan (CPCP) and Finish Specification Report CDRL B026 - Cybersecurity Artifact Package CDRL B029 - Cybersecurity Vulnerability Management Software Maintenance Plan