Tentative-Layout-of-WESS-Equipment-in-Park-TPSS_22-Jan-2018-Addendum-5.pdf

PDF 626 KB Posted

Attached to
Traction Power Substation Rehabilitation Program – Contract 5 Broad, Loudon, Park and Castor Substations Project
Solicitation number
RFP 26-00105-AJEB
Issued by
Philadelphia County, Philadelphia City, Pennsylvania

About this file

This is a tentative equipment layout drawing (Addendum 5) for the Park Traction Power Substation Site prepared by Constellation/SEPTA dated January 17, 2018. The document consists of seven detailed basement-level floor plans showing the positioning of Wayside Energy Storage System (WESS) equipment at the Park substation, including high-speed circuit breakers, transition cells, master and slave converters, battery distribution systems, batteries, acquisition panels, concrete pads, AC/DC panels, overhead busbars, and SCADA/signal equipment locations across basement and first-floor areas. The drawings identify specific clearances required (columns to clear, drain clearance), existing equipment pads, concrete areas to be removed, and detailed power connection routing with color-coded cable paths (red for TPS+ power cable, black for TPS- power cable, purple for battery power cable) and equipment connections including RTU, Peco connections, HVAC power (240Vac), 125Vdc systems, SCADA controls, and E-STOP systems with notations distinguishing same-floor versus other-floor routing.

The layout drawings provide critical spatial planning information for contractors bidding on the Park substation rehabilitation component of SEPTA's larger four-substation project, showing the precise positioning of major electrical equipment including converters rated for 750VDC and 600VDC operations, battery systems, circuit protection devices, and control panels within the basement's confined space constraints. The plans specify dimensions (ranging from 1' to 15'0"), hatch locations, column clearances, and existing infrastructure that must be worked around during the phased rehabilitation while maintaining continuous traction power service, directly supporting the project's requirement to upgrade DC rectifier systems, protective relays, batteries, and SCADA systems as outlined in the main contract opportunity.

View the file

Other files

File Type Posted
Addendum-10-Contract-5-Substations-Step-1-8-25-26.pdf PDF
Addendum-9-Contract-5-Substations-Step-1-8-20-26.pdf PDF
Addendum-8-Contract-5-Substations-Step-1-8-10-26.pdf PDF
Addendum-7-DWG-7E-16563_28_color_a.pdf PDF
Addendum-7-REV1-Markups-11x17_SEPTA_CONTRACT-5_50_LOUDON.pdf PDF
Addendum-7-Contract-5-Substations_Rehab-Step-1-8-5-26.pdf PDF
Addendum-6-Contract-5-Substations-Step-1-7-6-26.pdf PDF
Managing-Asbestos-In-Place-Addendum-5.pdf PDF
SEPTA-Environmental-Report-combined-Addendum-5.pdf PDF
Broad-Roof-Replacement-100-DWG_Set-Addendum-5.pdf PDF
Management-of-Lead-Paint-in-SEPTA-Construction-Projects-Document-3001-Addendum-5.pdf PDF
Orange-Blue-Green-line-emerg.-lght-single-line-diag.-Addendum-5.pdf PDF
Park-Peco-Info-Addendum-5.pdf PDF
Market-PECO-fault-duty-letters-dc-TPSS-Addendum-5.pdf PDF
Broad-Peco-Info-Addendum-5.pdf PDF
Loudon-WESS-Details-REV3_signed-171108-Addendum-5.pdf PDF
PECO-fault-duty-letters-dc-TPSS-Addendum-5.pdf PDF
Addendum-5-Contract-5-Substations-Step-1-6-25-26.pdf PDF
SEPTA-Station-20-Sansom-Points-List-Addendum-5.pdf PDF
3004-ACM-Handling-Program-2023-Addendum-5.pdf PDF
DWG-7E-16563_28_color_a-Addendum-5.pdf PDF
Pre-Qualification-Meeting_-RFQ_-26-00105-AJEB-Substation-attendance-report-6-10-26.pdf PDF
Addendum-3-Contract-5-Substations-Step-1-6-10-26.pdf PDF
SIte-Visit-Attendance-Meeting-Power-Substation-Contract-5-6-11-26.pdf PDF
Addendum-4-Contract-5-Substations-Step-1-6-15-26.pdf PDF
Site-Visit-Attendance-Meeting-Substation-Contract-5-6-12-26.pdf PDF
Addendum-2-Contract-5-Substations-Step-1-6-4-26.pdf PDF
22x34-Loudon-Contract-5-Drawings-Addendum-3.pdf PDF
22x34-Broad-Street-Contract-5-Drawings-Addendum-3.pdf PDF
Attachment-2-11x17_SEPTA_CONTRACT-5_MARKET_50_BROAD-PARK-LOUDON-CASTOR-DRAWINGS-SET-3.pdf PDF
22x34-Castor-Contract-5-Drawings-Addendum-3.pdf PDF
Attachment-2-11x17_SEPTA_CONTRACT-5_MARKET_50_BROAD-PARK-LOUDON-CASTOR-DRAWINGS-SET-2.pdf PDF
Attachment-2-11x17_SEPTA_CONTRACT-5_MARKET_50_BROAD-PARK-LOUDON-CASTOR-DRAWINGS-SET-1.pdf PDF
22x34-General-Notes-Contract-5-Drawings-Addendum-3.pdf PDF
Addendum-1-Contract-5-Substations-Step-1-6-3-26.pdf PDF
22x34-Park-Contract-5-Drawings-Addendum-3.pdf PDF
JAL192590415-Substation-Rehab-Contract-5-Step-1.pdf PDF
ATTACHMENT-3-Form-330.pdf PDF
ATTACHMENT-2-SEPTA_CONTRACT-5_MARKET_50_BROAD-PARK-LOUDON-CASTOR-Drawings-SET-3.pdf PDF
JAL192590415-Invitation-to-Propose-2-Step-Process-Traction-Substation.pdf PDF
ATTACHMENT-4-Addendum-Acknowledgement-1.pdf PDF
ATTACHMENT-2-SEPTA_CONTRACT-5_MARKET_50_BROAD-PARK-LOUDON-CASTOR-Drawings-SET-1.pdf PDF
ATTACHMENT-1-SEPTA-Contract-5-Substations-50-Specifications.pdf PDF
Exhibit-FEDERAL-CONSTRUCTION-CONTRACT-STEP-2-CONTRACT-5-SUBSTATIONS.pdf PDF
ATTACHMENT-2-SEPTA_CONTRACT-5_MARKET_50_BROAD-PARK-LOUDON-CASTOR-Drawings-SET-2-1.pdf PDF
Show all 45

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Constellation / SEPTA Park

Park Site Layout

2018/01/17 3ACD611142E0041-rev2 as built 1

Park Basement – Concrete

Hatch

X

X

X

32 41

5’ 8”

2018/01/17 3ACD611142E0041-rev2 2 3’

X

1’

1’

Column to clear

X

15’0”

Existing equipment concrete pad

3’

Drain clearance required

X

76 85 109 concrete pad

X concrete to remove

Park Basement – Equipment Positioning

Hatch

X

X

X

32 41 76 85

Remote Acq panel

3’7” 3’7”

2’ 2”

2018/01/17 3ACD611142E0041-rev2 3 3’ location for the 240V AC panel

X

1’

1’

Column to clear

X

3’7” 3’7”15’0” 3’7”

Existing equipment concrete pad

3’ location for the DC panel

Orange HSCB & transition cab Blue Converters Purple Battery distribution Red Batteries Gray Acquisition panel Green AC panel Black DC panel

1 High Speed Circuit Breaker 2 Transition Cell 3 Master Converter 4 Slave Converter 5 Battery Distribution 6 Batteries 7 Acquisition panel 8 concrete pad

9 X Concrete to remove

6 6 6

Drain clearance required

X

5’7”

Park Basement – Power Connections

Hatch

X

X

X

32 41 76 85

TPS – overhead busbar

TPS+ connection to overhead busbar

2018/01/17 3ACD611142E0041-rev2 4

XX

Red line TPS+ power cable Black Line TPS- power cable Purple Batteries power cable Solid/dotted Same Floor/Other Floor

1 32 4 5 76 8 19 1

Park Basement – SCADA & signal equipment location

Hatch

X

X

X

32 41 76 85

Rect.1 1st fl.

RTU

1st fl

Rect.2 1st fl.

Pe co

1st fl

2018/01/17 3ACD611142E0041-rev2 5

Red Network

Green Peco connection

Black 240Vac for Hvac

Orange 125Vdc

Brown SCADA

Gray E-STOP

Solid/dotted Same Floor/Other Floor

1 76 132 32

XXXX

Hatch

X

X

X

32 41 76 85

Rect.1 1st fl.

RTU

1st fl

Rect.2 1st fl.

Pe co

1st fl

2018/01/17 3ACD611142E0041-rev2 6

Red Network

Green Peco connection

Black 240Vac for Hvac

Orange 125Vdc

Brown SCADA

Gray E-STOP

Solid/dotted Same Floor/Other Floor

X

8 1

Hatch

X

X

X

32 41 76 85

Rect.1 1st fl.

RTU

1st fl

Rect.2 1st fl.

Pe co

1st fl

2018/01/17 3ACD611142E0041-rev2 7

Red Network

Green Peco connection

Black 240Vac for Hvac

Orange 125Vdc

Brown SCADA

Gray E-STOP

Solid/dotted Same Floor/Other Floor

X

8 1