ATTACHMENT-1-SEPTA-Contract-5-Substations-50-Specifications.pdf

PDF 37 MB Posted

Attached to
Traction Power Substation Rehabilitation Program – Contract 5 Broad, Loudon, Park and Castor Substations Project
Solicitation number
RFP 26-00105-AJEB
Issued by
Philadelphia County, Philadelphia City, Pennsylvania

About this file

This is a technical specifications document for the Southeastern Pennsylvania Transportation Authority (SEPTA) Contract 5 Substations project, which encompasses rehabilitation work at four traction power substations: Broad, Loudon, Park, and Castor. The project involves comprehensive electrical infrastructure upgrades including replacement of 13.2kV switchgear, DC switchgear, rectifier transformers, silicon rectifiers, station batteries and chargers, protective relays, SCADA systems, fire protection systems, heating/ventilation/air conditioning systems, architectural improvements, and miscellaneous electrical work. The specifications detail work requirements for structure demolition, concrete restoration, masonry work, roofing modifications, mechanical systems installation, and electrical infrastructure upgrades across all four substations. Each substation has specific scope requirements with Broad Substation requiring extensive switchgear replacement and HVAC upgrades, Loudon Substation needing rectifier transformer and DC switchgear replacement, Park Substation requiring comprehensive electrical system modernization, and Castor Substation involving similar electrical infrastructure improvements along with building envelope repairs.

The specifications establish detailed technical requirements for equipment procurement and installation, including specific manufacturer requirements for major components such as ABB or approved equal for switchgear and transformers. The document includes comprehensive testing and commissioning requirements, quality assurance protocols, and coordination procedures with SEPTA operations to minimize service disruptions. Contractors must comply with SEPTA's standard specifications, National Electrical Code, NFPA standards, and other applicable codes and regulations. The work requires phased construction approaches to maintain continuous traction power service, with detailed outage coordination and temporary power arrangements. The specifications include requirements for shop drawings, product data submissions, warranty provisions, and as-built documentation upon project completion.

View the file

Other files

File Type Posted
Addendum-10-Contract-5-Substations-Step-1-8-25-26.pdf PDF
Addendum-9-Contract-5-Substations-Step-1-8-20-26.pdf PDF
Addendum-8-Contract-5-Substations-Step-1-8-10-26.pdf PDF
Addendum-7-DWG-7E-16563_28_color_a.pdf PDF
Addendum-7-REV1-Markups-11x17_SEPTA_CONTRACT-5_50_LOUDON.pdf PDF
Addendum-7-Contract-5-Substations_Rehab-Step-1-8-5-26.pdf PDF
Addendum-6-Contract-5-Substations-Step-1-7-6-26.pdf PDF
Managing-Asbestos-In-Place-Addendum-5.pdf PDF
SEPTA-Environmental-Report-combined-Addendum-5.pdf PDF
Broad-Roof-Replacement-100-DWG_Set-Addendum-5.pdf PDF
Management-of-Lead-Paint-in-SEPTA-Construction-Projects-Document-3001-Addendum-5.pdf PDF
Orange-Blue-Green-line-emerg.-lght-single-line-diag.-Addendum-5.pdf PDF
Park-Peco-Info-Addendum-5.pdf PDF
Market-PECO-fault-duty-letters-dc-TPSS-Addendum-5.pdf PDF
Broad-Peco-Info-Addendum-5.pdf PDF
Tentative-Layout-of-WESS-Equipment-in-Park-TPSS_22-Jan-2018-Addendum-5.pdf PDF
Loudon-WESS-Details-REV3_signed-171108-Addendum-5.pdf PDF
PECO-fault-duty-letters-dc-TPSS-Addendum-5.pdf PDF
Addendum-5-Contract-5-Substations-Step-1-6-25-26.pdf PDF
SEPTA-Station-20-Sansom-Points-List-Addendum-5.pdf PDF
3004-ACM-Handling-Program-2023-Addendum-5.pdf PDF
DWG-7E-16563_28_color_a-Addendum-5.pdf PDF
Pre-Qualification-Meeting_-RFQ_-26-00105-AJEB-Substation-attendance-report-6-10-26.pdf PDF
Addendum-3-Contract-5-Substations-Step-1-6-10-26.pdf PDF
SIte-Visit-Attendance-Meeting-Power-Substation-Contract-5-6-11-26.pdf PDF
Addendum-4-Contract-5-Substations-Step-1-6-15-26.pdf PDF
Site-Visit-Attendance-Meeting-Substation-Contract-5-6-12-26.pdf PDF
Addendum-2-Contract-5-Substations-Step-1-6-4-26.pdf PDF
22x34-Loudon-Contract-5-Drawings-Addendum-3.pdf PDF
22x34-Broad-Street-Contract-5-Drawings-Addendum-3.pdf PDF
Attachment-2-11x17_SEPTA_CONTRACT-5_MARKET_50_BROAD-PARK-LOUDON-CASTOR-DRAWINGS-SET-3.pdf PDF
22x34-Castor-Contract-5-Drawings-Addendum-3.pdf PDF
Attachment-2-11x17_SEPTA_CONTRACT-5_MARKET_50_BROAD-PARK-LOUDON-CASTOR-DRAWINGS-SET-2.pdf PDF
Attachment-2-11x17_SEPTA_CONTRACT-5_MARKET_50_BROAD-PARK-LOUDON-CASTOR-DRAWINGS-SET-1.pdf PDF
22x34-General-Notes-Contract-5-Drawings-Addendum-3.pdf PDF
Addendum-1-Contract-5-Substations-Step-1-6-3-26.pdf PDF
22x34-Park-Contract-5-Drawings-Addendum-3.pdf PDF
JAL192590415-Substation-Rehab-Contract-5-Step-1.pdf PDF
ATTACHMENT-3-Form-330.pdf PDF
ATTACHMENT-2-SEPTA_CONTRACT-5_MARKET_50_BROAD-PARK-LOUDON-CASTOR-Drawings-SET-3.pdf PDF
JAL192590415-Invitation-to-Propose-2-Step-Process-Traction-Substation.pdf PDF
ATTACHMENT-4-Addendum-Acknowledgement-1.pdf PDF
ATTACHMENT-2-SEPTA_CONTRACT-5_MARKET_50_BROAD-PARK-LOUDON-CASTOR-Drawings-SET-1.pdf PDF
Exhibit-FEDERAL-CONSTRUCTION-CONTRACT-STEP-2-CONTRACT-5-SUBSTATIONS.pdf PDF
ATTACHMENT-2-SEPTA_CONTRACT-5_MARKET_50_BROAD-PARK-LOUDON-CASTOR-Drawings-SET-2-1.pdf PDF
Show all 45

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SOUTHEASTERN PENNSYLVANIA

TRANSPORTATION AUTHORITY

CONTRACT SPECIFICATIONS

FOR

TRACTION POWER SUBSTATION

REHABILITATION

CONTRACT 5 – BROAD, LOUDON,

PARK, AND CASTOR SUBSTATIONS

Volume 1

APRIL 1, 2026

50% SUBMISSION

THIS PAGE NOT USED

April 1, 2026 SEPTA Substation Rehabilitation 50% Submission

Construction Contract No. 5 00110-1 Table of Contents

TABLE OF CONTENTS

DIVISION 01 — GENERAL REQUIREMENTS

01010 - Summary of Work 01025 - Measurement and Payment 01045 - Cutting and Patching 01050 - Field Engineering 01060 - Regulatory Requirements and Safety 01061 - Safety and Security Certification Requirements 01100 - Special Project Procedures 01200 - Project Progress Meetings 01300 - Submittals 01305 - Requests for Information 01380 - Construction Photographs 01400 - Quality Requirements 01410 - Inspection and Test Plans 01420 - Testing and Inspection Services 01452 - Contractor Quality Control - Traction Power Equipment 01500 - Construction Facilities and Temporary Controls 01505 - Mobilization and Demobilization 01510 - Maintenance, Support and Restoration of Existing Utility Facilities 01570 - Maintenance and Protection of Vehicles, Pedestrians and Passengers 01580 - Project Identification Signs 01590 - SEPTA Field Office 01600 - Materials and Equipment 01612 - Delivery, Storage and Handling - Traction Power Equipment 01700 - Contract Closeout 01710 - Final Cleaning 01720 - Project As-Built Documents 01752 - Spare Parts and Maintenance Materials - Traction Power Equipment 01810 - Commissioning of Systems 01820 - Demonstration and Training 01822 - Demonstration and Training - Traction Power Equipment 01830 - Operations and Maintenance Data 01832 - Operations and Maintenance Manuals - Traction Power Equipment

DIVISION 02 — SITE CONSTRUCTION

02070 - Selective Demolition 02080 - Hazardous Material Abatement 02081 - Asbestos Abatement 02082 - PCB Abatement 02083 - Heavy Metals Abatement 02084 - Petroleum Contaminated Material Abatement 02085 - Lead Paint Abatement 02205 - Impacted Soil Management 02209 - Geotextile Fabric 02220 - Excavation, Backfill and Compaction 02230 - Subbase 02270 - Erosion and Sedimentation Control 02520 - Bituminous Concrete Paving 02533 - Cement Concrete Sidewalk and Driveway Apron

Construction Contract No. 5 00110-2 Table of Contents

02724 - Manholes 02821 - Chain Link Fences and Gates 02822 - High Security Ornamental Fences and Gates

DIVISION 03 — CONCRETE

03100 - Concrete Forms 03200 - Concrete Reinforcement 03300 - Cast-In-Place Concrete 03600 - Grout 03710 - Remove Efflorescence From Concrete 03930 - Concrete Repair 03932 - Concrete Wall Repair

DIVISION 04 — MASONRY

04011 - Masonry Cleaning 04012 - Brick Masonry Repair 04014 - Stone Restoration 04200 - Unit Masonry 04212 - Terra Cotta Masonry 04270 - Glass Unit Masonry Assemblies 04720 - Cast Stone

DIVISION 05 — METALS

05090 - Metal Fasteners, Joining and Welding 05120 - Structural Steel 05310 - Steel Decking 05500 - Metal Fabrications 05511 - Metal Grating Stairs 05520 - Handrails and Railings 05610 - Miscellaneous Metals 05900 - Metal Restoration and Cleaning

DIVISION 06 — WOOD, PLASTICS, AND COMPOSITES

06105 - Miscellaneous Carpentry 06610 - Glass Fiber Fabrications

DIVISION 07 — THERMAL AND MOISTURE PROTECTION

07190 - Water Repellents 07210 - Building Insulation 07500 - Membrane Roofing 07590 - Preparation for Re-Roofing 07620 - Sheet Metal Flashing and Trim 07720 - Roof Accessories 07841 - Penetration Fire Stopping 07842 - Joint Fire Stopping 07900 - Joint Sealers

DIVISION 08 — DOORS AND WINDOWS

08110 - Metal Doors and Frames 08331 - Overhead Coiling Doors 08710 - Door Hardware 08800 - Glazing

DIVISION 09 — FINISHES

09662 - Electrically Insulated Floor Covering 09705 - Epoxy Resin Flooring

Construction Contract No. 5 00110-3 Table of Contents

09910 - Paints and Coatings 09960 - Painting of Steel 09965 - Graffiti Resistant Coatings

DIVISION 10 — SPECIALTIES

10140 - Identifying Devices 10200 - Louvers and Vents 10520 - Fire Protection Specialties 10800 - Toilet and Bath Accessories

DIVISION 13 — SPECIAL CONSTRUCTION

13700 - Intrusion Alarm System 13850 - Fire Alarm and Detection System

DIVISION 15 — MECHANICAL

15010 - Basic Mechanical Requirements 15050 - Basic Mechanical Materials and Methods 15060 - Hangers and Supports 15062 - Hangers and Supports for Plumbing Piping and Equipment 15075 - Mechanical Identification 15080 - Mechanical Insulation 15120 - Sleeves and Sleeve Seals 15130 - Pumps 15140 - Domestic Water Piping 15150 - Sanitary Waste and Vent Piping 15160 - Storm Drainage Piping 15165 - Storm Drainage Piping Specialties 15183 - Duct Insulation 15184 - Refrigerant Piping 15400 - Plumbing Fixtures and Equipment 15412 - Emergency Plumbing Fixtures 15700 - Heating, Ventilating and Air Conditioning Equipment 15794 - Electric Unit Heaters 15841 - Indoor Custom Air-Handling Units 15850 - Diffusers, Registers and Grilles 15857 - HVAC Gravity Ventilators 15890 - HVAC Ductwork 15935 - Building System Controls 15940 - Sequence of Operation 15950 - Testing, Adjusting and Balancing

DIVISION 16 — ELECTRICAL

16010 - Basic Electrical Requirements 16050 - Basic Electrical Materials and Methods 16060 - Grounding and Bonding 16070 - Hangers, Anchors and Supports 16075 - Electrical Identification 16120 - Conductors and Cables 16121 - Medium Voltage Cable 16122 - DC Traction Power Cable 16123 - Building Wire and Cable 16129 - Fiber Optic Cable 16130 - Raceways and Boxes 16131 - Bus Duct 16138 - Ductwork and Electrical Manholes and Handholes

Construction Contract No. 5 00110-4 Table of Contents

16140 - Wiring Devices 16210 - Electric Utility Services 16230 - Generator Assemblies 16240 - Battery Equipment 16260 - Traction Power Rectifier 16271 - Auxiliary Power Transformers 16273 - Traction Power Rectifier Transformers 16274 - Transformer and Rectifier Unit 16290 - Protective Devices and Instrument Transformers 16300 - DC Remote Control Board 16315 - Dead Break Junction Equipment 16335 - Surge Protection 16340 - Medium Voltage Switchgear Assemblies (60 Hz) 16344 - DC Traction Power Switchgear Assemblies 16348 - Negative and Drainage Switchboard 16411 - Enclosed Switches 16412 - DC Enclosed Switch Cabinets 16413 - Enclosed Transfer Switches 16421 - Enclosed Motor Controllers 16440 - Panelboards 16460 - Low-Voltage Transformers 16500 - Lighting 16700 - Communications 16760 - Fiber Optic Network 16772 - CCTV System 16910 - Electrical Systems Control SCADA, Remote Terminal Unit - Including HMI 16920 - Stray Current Monitoring 16950 - Testing

Construction Contract No. 5 01010-1 Summary of Work

SECTION 01010

SUMMARY OF WORK

PART 1 - GENERAL

1.01 Description

A. The Design and Build Contract No. 5 consists of final design, rehabilitating and upgrading existing Traction Power Substations (TPSSs) located at Broad, Park and Loudon on the SEPTA Broad Street Subway line and Castor on the Route 59 Trackless Trolley of the City Transit Division (CTD). The Design-Build Contractor (Contractor) shall complete the final design and rehabilitate all equipment and installations at the facility, unless specifically noted otherwise.

1. At Broad, Park and Loudon field survey and provide final design for the replacement of DC remote control panels (cabinets).

B. Contractor should note that a new Safety & Security Certification requirement has been added. The Contractor shall complete all SSC requirements. This specification defines the requirements for implementing SEPTA’s Safety and Security Certification (SSC) Program to ensure that all safety and security critical project elements are properly identified, designed, constructed, tested, and verified prior to acceptance and operational use. The SSC process applies throughout design, construction, testing, and pre revenue phases and requires coordinated participation by the Design Consultant, Design Build Contractor, and SEPTA’s SSC Consultant through hazard and threat analyses, conformance checklists, verification activities, and formal certification. Completion of this process is mandatory to demonstrate compliance with applicable Federal, Commonwealth, and SEPTA requirements and to confirm project readiness for occupancy and revenue service.

C. The Contractor shall have proven experience in the traction power systems of railroads. The Contractor shall have design capability or subcontractor capabilities on the team to advance the design from 50% level to 100 % level and sign/seal the drawings, besides subcontractors of other disciplines such as civil/structural, mechanical, and other required trades to complete the rehabilitation of the TPSSs.

D. Initiate the rehabilitation work in the following order, unless approved by SEPTA otherwise:

1. Broad, first (only one station can be rehabilitated at a time)

2. Loudon, second

3. Park, third

4. Castor, fourth (independent of the three (3) TPSSs above)

E. The work shall be performed in close coordination with SEPTA and the utility and other trades working at the site.

F. The Contractor shall be responsible for the following administrative activities:

1. Creating and maintaining the Project schedule for all work.

2. Provision of Project identification signs (Refer to Section 01580).

Construction Contract No. 5 01010-2 Summary of Work

3. Furnishing and maintaining SEPTA field office (Refer to Section 01590), including associated utilities.

4. All snow removal, regular trash removal and cleaning from the Project sites.

G. Brief Description of SEPTA's Traction Electrification System:

1. SEPTA operates a comprehensive transportation system in the Philadelphia metropolitan area and suburbs. The CTD network of subway, light rail and electric trolleybus routes is an important part of SEPTA's service in the Philadelphia metropolitan area. The network includes the Broad Street Subway (BSS), the Market Frankford Subway elevated (MFSE), five (5) Subway Surface Trolley Lines, the Route 15 Historic Trolley (Girard Avenue and Richmond Streets), and the Routes 59, 66 and 75 Trackless Trolleys (electric trolleybuses).

2. Each TPSS has a unique electrical and physical layout.

3. The three (3) subway TPSSs to be rehabilitated as part of this Contract predominately provide power to the Broad Street Subway (BSS) and are located along this line at or near Mount Vernon Street, Loudon Street, and Cumberland Street. The BSS is third rail powered and was commissioned in 1928. The other TPSS to be rehabilitated as part of this Contract provides power to the Route 59 Trackless Trolley. The present Trackless Trolley routes were originally streetcar lines that were converted to electric trolleybus operation during the 1960's. The nominal system voltage of the CTD network is 700 V DC. The TPSS components vary in vintage from 1928 to present day technology. A Wayside Energy Storage System (WESS) allows for vehicle regenerative voltages up to

800 V DC.

4. Rehabilitation requires removal and replacement of essentially all existing equipment in a manner staged to prevent total outage, except at Castor TPSS. The Contractor shall field verify quantities of existing equipment to be removed. Remove abandoned equipment in quantities as field verified by the Contractor. Reflect the intent of having a full replacement of traction power equipment in the Contractor’s prepared final design for each site. Provide (furnish and install) quantities of equipment necessary for maintaining the current full operational functionality of the traction power system.

WESS equipment is not to be removed and replaced, but new positive and negative cables and connections to the new DC equipment shall be provided as part of this work, subject to approval by SEPTA.

5. Broad TPSS has dual 13.2 kV utility services and contains two (2) 3250 kVA rectifier transformers, rectifier anode AC buses, two (2) 3000 kW rectifiers, two (2) 8000 A DC cathode breakers, positive and negative DC buses, ten (10) 3000 A DC feeder circuit breakers and one (1) 3000 A DC transfer circuit breaker. The TPSS also houses one (1) 2000 kVA 13.2/4.8 kV transformer and five (5) 4.8 kV cable feeder circuit breakers.

There is also one (1) 400 kW diesel generator, one (1) 400 kW rectifier for the generator and five (5) 2000 A DC emergency cable feeder circuit breakers at this location. One (1) remote DC breaker room control panel and one (1) DC emergency cabinet shall also be removed and replaced. This TPSS is supervisory controlled and monitored, and supplies traction power for the BSS from stations Cecil B. Moore to City Hall, and also feeds the Broad-Ridge spur. This TPSS was originally commissioned in 1928 and is located at 1327 Mt. Vernon Street. In 1972, the diesel generator and its associated emergency equipment were added. Additionally, in 1979, the TPSS was partially modernized, at

Construction Contract No. 5 01010-3 Summary of Work which time the medium voltage AC switchgear (for 13.2 kV circuits) and rectifier/transformers were upgraded. The DC circuit breakers, however, remain as original. There is also a collection of “abandoned” (out-of-service) equipment (switchgear, transformer, etc.) in the TPSS room that will need to be dismantled and removed as part of this Contract.

6. Park TPSS has dual 13.2 kV utility services and includes two (2) 3250 kVA rectifier transformers, rectifier anode AC buses, two (2) 3000 kW rectifiers, two (2) 8000 A DC cathode breakers, positive and negative DC buses, eight (8) 3000 A DC feeder circuit breakers, one (1) 3000A DC transfer circuit breaker, six (6) 2000A DC circuit breakers and two (2) 1600 A DC emergency cable feeder circuit breakers. This TPSS also houses one (1) 2000 kVA, 13.2/4.8 kV transformer and six (6) 4.8 kV cable feeder circuit breakers. One (1) remote DC breaker room control panel and one (1) DC emergency cabinet shall also be removed and replaced. This TPSS is supervisory controlled and monitored and provides traction power for the BSS from stations Cecil B. Moore to Allegheny. The TPSS, originally commissioned in 1928, is located at 2440 N. Park Street.

In 1980 the TPSS was partially modernized, at which time the medium voltage AC switchgear (for 13.2 kV and 4.8 kV circuits) and rectifier/transformers were upgraded. In 1992, the 13.2/4.8 kV transformer was replaced. The DC circuit breakers at this location are the originally installed equipment. Recently, between 2017 and 2018 SEPTA installed WESS equipment in this TPSS.

7. Loudon TPSS has dual 13.2 kV utility services and includes two (2) 3250 kVA rectifier transformers, rectifier anode AC buses, two (2) 3000 kW rectifiers, two (2) 8000 A DC cathode breakers, positive and negative DC buses, four (4) 4000 A DC feeder circuit breakers, four (4) 3000A DC circuit breakers, one (1) 3000A DC transfer circuit breaker, five (5) 2000 A DC feeder circuit breakers, and two (2) 1600 A DC emergency cable feeder circuit breakers. This TPSS also houses one (1) 2000 kVA, 13.2/4.8 kV transformer and six (6) 4800 V cable feeder circuit breakers. One (1) remote DC breaker room control panel and one (1) DC emergency cabinet shall also be removed and replaced.

This TPSS is supervisory controlled and monitored, and supplies traction power for the BSS from Hunting Park to Olney Station, and also feeds a significant portion of Trackless Trolley Route 75. The TPSS was originally commissioned in 1928 and is located at 1410 W. Loudon Street. In 1979 the TPSS was partially modernized at which time the medium voltage AC switchgear (for 13.2 kV and 4.8 kV circuits) and rectifier/transformers were upgraded. In 1990, four (4) of the eight (8) DC feeder circuit breakers were replaced, and in 2007 the 13.2/4.8 kV transformer was replaced. Recently, in 2012, the rectifier transformers were also replaced. The DC circuit breakers, however, remain as original.

Recently between 2017 and 2018, SEPTA installed WESS equipment in this TPSS.

8. Castor TPSS has one (1) 13.2 kV incoming utility service, one (1) 1130 kVA rectifier transformer, rectifier anode AC bus, one (1) 1000 kW rectifier, a 4000 A DC cathode breaker, positive and negative DC buses, and three (3) 2000 A DC feeder circuit breakers (one (1) is a transfer bus circuit breaker). This TPSS is supervisory controlled and monitored and provides power to the northern end of the Route 59 Trackless Trolley (electric trolleybus). The TPSS was commissioned in 1950, and included a PCB oil-filled rectifier transformer, live frame mercury-arc rectifier, and open style DC circuit breakers in a single floor brick building that is located on the Route 59 terminus loop. In 1995, the

Construction Contract No. 5 01010-4 Summary of Work transformer was retro-filled and reclassified as non-PCB. The obsolete mercury-arc rectifier was also replaced with an open frame solid-state rectifier.

9. Rehabilitation of the Castor TPSS will allow SEPTA to provide a reliable Route 59 Trackless Trolley system power supply for many years to come.

10. SEPTA engaged with another contractor to replace the roof at Broad TPSS, which was completed in April 2019. Refer to Article 1.02/L for details of the relevant reference drawings for the roof replacement project.

H. The Contract is intended to rehabilitate the TPSSs to a like new state. All equipment, components, installations, Supervisory Control and Data Acquisition (SCADA), lighting, auxiliary power systems, conductors, and cables, unless expressly stated otherwise, shall be replaced with new equipment and components where indicated on the Contract Documents.

I. The work generally consists of, but is not necessarily limited to, the following:

1. Completion of the 50% design to 100% level:

a. Completing the 50% design supplied with the Contract Drawings and Specifications to a 100% level.

b. Signing and sealing the drawings, reports and specifications.

c. Perform a Lead/Asbestos/PCB survey prior to commencement of work. All testing is to be coordinated through SEPTA System Safety Department.

2. Site Demolition and Clearing for each TPSS in Construction Contract No. 5:

a. Clearing and grubbing including removal and disposal of debris and abandoned equipment.

b. Selective demolition of pipes, conduits, duct banks, manholes, fuel tanks and metal cases.

c. Recycle scrap metal.

d. Test, then dispose of as hazardous waste scrap material, storage tank and contaminated soil.

e. Asbestos abatement.

3. Site Fencing for Castor TPSS in Construction Contract No. 5:

a. Construct new chain link fencing around building and equipment yard including swinging gate.

b. Replace the existing chain linked security gate at Park TPSS.

c. Replace the iron fence in the alley at Park and Loudon TPSSs.

4. Site Utilities for each TPSS in Construction Contract No. 5:

a. Protect in place site utilities as indicated on the Contract Drawings.

5. Grading, Storm Water System and Sedimentation Control for each TPSS in Construction Contract No. 5:

a. Grade at site in accordance with the Contract Drawings.

b. Provide sedimentation control to include filter fabric, filter bags for inlet protection, storm protection.

6. Equipment Yard Pads for Castor TPSS in Construction Contract No. 5:

a. Construct new electrical and non-electrical equipment pads as indicated on the Contract Drawings.

Construction Contract No. 5 01010-5 Summary of Work

7. Cast-In-Place Concrete Foundations for Castor TPSS in Construction Contract No. 5:

a. Construct foundations for outdoor electrical equipment as indicated on the Contract Drawings.

8. Control Systems for each TPSS in Construction Contract No. 5:

a. Demolish existing concrete equipment pads and refinish floor.

b. Relocate existing batteries and other auxiliary power supply equipment to facilitate the work.

c. New Protection and Control Panels:

1) Installation of new protection and control panels.

2) Decommission and remove existing control panels after commissioning of all new equipment.

3) Installation of cable trays and cable ladder.

9. Structural Repairs to Existing Masonry Walls for each TPSS in Construction Contract No.

5:

a. Remove vegetation from wall joints.

b. Remove efflorescence from wall face.

c. Repair spalled areas.

d. Seal concrete.

e. Refinish/repair masonry walls and brick fence posts.

f. Repair roof system.

10. Work that will bring each TPSS in Construction Contract No. 5 into compliance with all relevant codes, regulations, standards, etc.:

a. Caging of access ladders.

b. Signage.

c. Add doors and stairs.

11. Mechanical and HVAC System for each TPSS in Construction Contract No. 5:

a. Energy recovery ventilator units.

b. Electric unit heater.

c. Heat Pump.

d. Exhaust fan in battery room.

e. Air conditioning split system for battery room.

f. Louvers with dampers.

g. Emergency eye wash in battery room.

h. HVAC unit.

i. Electrical controls and sensors.

j. Power connections, conductors in raceways and supports.

12. Architectural System for each TPSS in Construction Contract No. 5:

a. Seal openings.

b. Replace windows and doors.

c. Replace roll-up doors as indicated on the Contract Drawings.

13. Auxiliary power system, to include all cabling and AC power panel to receive power from existing PECO supply for each TPSS in Construction Contract No. 5.

Construction Contract No. 5 01010-6 Summary of Work

a. TPSS Battery System (136 V DC System):

1) Install new batteries. Relocate, temporarily if required, existing batteries to facilitate the work in the control room.

2) Install new battery chargers.

3) Install new battery transfer panel.

4) Install new dropping resistors.

5) Remove existing battery system and dispose per SEPTA instructions.

b. New 136 V DC power panel.

c. AC power panel to provide power for lighting and new equipment.

d. Auxiliary power conduits, boxes, and conductors.

e. Disconnect switches.

f. Receptacles.

g. Auxiliary transformer(s).

h. Bonding and grounding.

i. New outdoor cable raceway systems as required.

14. Lighting for each TPSS in Construction Contract No. 5:

a. Site lighting to suit new equipment arrangement.

b. Indoor lighting.

15. Fire Alarm and Intrusion Detection for each TPSS in Construction Contract No. 5:

a. Fire alarm system.

b. Intrusion detection system, including CCTV system.

c. Controls in interface with HVAC for shut down.

16. Communication and SCADA System for each TPSS in Construction Contract No. 5:

a. Provide Remote Terminal Unit (RTU) with integrated TPSS gateway computer.

b. SCADA conduits or cable trays and cables for indication and control circuits.

c. TPSS controls and sensors.

d. Existing servers A, B and C located at 1234 Market Street to be replaced prior to any new RTU installation for this Contract. Provide labor required for testing.

e. Replacing the communication cable from the TPSS termination cabinet to the nearest outdoor junction box/manhole.

17. Traction Power and SEPTA emergency AC and DC power systems equipment, for each TPSS in Construction Contract No. 5, to include incoming medium voltage supply, 15 kV AC switchgear (for 13.2 kV circuits), traction transformer rectifiers sets, auxiliary and signal power transformers, 15 kV AC switchgear (for 4.8 kV circuits), 1000 V DC switchgear, traction return system, auxiliary power supply network, traction power and return cables, rail return bus, return cables including, but not limited to, the following (as indicated on the Contract Drawings):

a. 15 kV AC Incoming/Feeder Circuit Breakers:

1) Seven (7) at Broad TPSS.

2) Seven (7) at Park TPSS.

3) Eight (8) at Loudon TPSS.

4) Three (3) at Castor TPSS.

Construction Contract No. 5 01010-7 Summary of Work

b. One (1) 15 kV AC tie circuit breaker at Broad, Park and Loudon TPSSs.

c. 4.8 KV AC Circuit Breakers (15 kV Rated):

5) Nine (9) at Broad TPSS.

6) Six (6) at Park TPSS.

7) Five (5) at Loudon TPSS.

d. 1000 V DC Circuit Breakers with a Withdrawable Direct Acting Trip Element:

1) Two (2) cathode breakers at each of Broad, Park, and Loudon TPSSs. One (1) cathode breaker at Castor TPSS.

2) Ten (10) feeder breakers at Broad, Nine (9) feeder breakers At Park, eleven (11) feeder breakers at Loudon, and two (2) feeder breakers at Castor TPSS.

3) Three station service breakers each at Park and Loudon TPSS and five (5) station service breakers at Broad TPSS.

e. Two (2) 4 MVA transformer rectifier sets at Broad, Park and Loudon TPSSs.

f. One (1) 1 MVA transformer rectifier set at Castor TPSS.

g. One (1) 2 MVA lighting power transformers (13.2 kV/4.8 kV) at Broad, Park and Loudon TPSSs.

h. Two (2) 150 kVA auxiliary transformers (13.2 kV/120-208 V) at Broad, Park and Loudon TPSSs.

i. One (1) 45 kVA auxiliary transformer (13.2 kV/120-208 V) at Castor TPSS.

j. Potential and current transformers (PTs, CTs).

k. 500 kW diesel generator set at Broad TPSS.

l. 500 kW rectifier at Broad TPSS.

m. 1000 V DC Withdrawable Circuit Breakers:

1) Five (5) in Broad TPSS.

2) Six (6) in Park TPSS.

3) Four (4) in Loudon TPSS.

n. Manual disconnect switches.

o. DC current shunts.

p. Surge arresters.

q. AC and DC circuit breaker test cabinets.

r. Renewal of all high voltage buses, wires, connections, insulators, conduit, etc.

s. Replace existing return rail/ground busses, install new return rail/ground busses, and return rail cables from the TPSSs to the nearest manhole. Coordinate replacement with SEPTA.

t. Ground grid with ground buses and connections to the equipment and perimeter fencing.

Install new ground grid and associated conductors to supplement and/or replace the existing ground grid and all equipment connections. This shall include return circuit connections in the areas affected by the new and existing equipment.

18. Recover redundant assets and return to SEPTA (spares/asset value) for each TPSS in Construction Contract No. 5.

19. Demolition, Removal and Disposal of Equipment:

a. SEPTA will remove parts from existing circuit breakers before removal of existing circuit breakers from the Project site. Coordinate with SEPTA for the details and schedule. The Contractor is responsible for removal and disposal of all asbestos containing materials (arc chutes, transite panels, wiring, etc.).

Construction Contract No. 5 01010-8 Summary of Work

b. All transformer-rectifier sets.

c. All 13.2 kV and 4.8 kV switchgear.

d. All auxiliary transformers and lighting and power transformers.

e. All DC circuit breakers.

f. Generator set at Broad TPSS and all its attachments including active and abandoned fuel tanks.

g. 400 kW rectifier at Broad TPSS.

h. All DC emergency cabinets.

i. All DC remote control boards.

j. All local supervisory, SCADA termination and SCADA cabinets.

k. All rectifier isolation switches.

l. All normal and emergency circuit breakers and control cabinets.

m. All emergency DC lineups.

n. All DC circuit breaker control boards.

o. All PTs, CTs, disconnect switches.

p. 125 V DC batteries, battery charger rectifiers.

q. All 600 V DC lighting and heating equipment.

r. All abandoned 4800 V AC signal power equipment.

20. Testing, commissioning, training, and placing into revenue service of all components and equipment to make a complete operating system; followed by post commissioning testing.

21. Final Design, procurement of materials, manufacture, factory testing, delivery and storage of components and materials, installation, all field testing, commissioning and bringing into revenue service all components necessary for implementation of full and correct operation of the TPSSs.

22. Perform all work based on the Contract Documents. The Contractor shall develop the final design drawings and specifications for review and approval by SEPTA. Construction work shall not be commenced until SEPTA has approved the final design drawings and specifications.

23. Verify and update all design requirements prior to commencement of detailed/final design.

24. The TPSS functionality will remain as exists today, except for the changes as specified in the Contract Drawings.

25. Test all hazardous material prior to starting any work.

26. Abatement or remediation of contaminated or hazardous materials.

27. Verification of existing conditions including utilities.

28. Final construction plans for all TPSS work including temporary structures, signed and sealed by an Engineer licensed in the Commonwealth of Pennsylvania.

29. Final construction specifications for all TPSS work including temporary structures, signed and sealed by an Engineer licensed in the Commonwealth of Pennsylvania.

Construction Contract No. 5 01010-9 Summary of Work

30. All permits required to perform Contract work from municipal Authority Having Jurisdiction of the work site.

31. Work plans that are fully coordinated with the SEPTA Project Manager.

32. Support SEPTA public involvement initiative with technical information and presentation graphics.

33. Provide temporary power.

34. As-built drawings in AutoCAD and PDF format.

J. Complexity of the Contract:

1. The traction power work included in this Contract is complex and requires a high degree of coordination between the Contractor, suppliers, subcontractors, and SEPTA.

Therefore, the Contractor shall schedule the work to minimize the requirement for outages. Also, the Contractor shall coordinate the repair and rehabilitation work between all subcontractors to ensure minimal requirement of outages.

2. It is expected that the traction power equipment will be procured from multiple manufacturers. The Contractor is required to ensure that all components and equipment meet the requirements of the Contract and are compatible with each other for integration of the equipment into a single operable system. Services of a full time experienced and licensed Electrical Engineer in the Commonwealth of Pennsylvania are essential to accomplish this.

3. The current control of each TPSS is by a supervisory and remote control system using interposing relays and hardwired and/or fiber optic cable connection to SEPTA’s SCADA system. The proposed control of each TPSS shall be by a supervisory and remote control system using microprocessor-based control relays and hard wired and/or fiber optic cable connection to SEPTA's SCADA system. The microprocessor relays shall be connected to a SCADA RTU which shall communicate with the SCADA system. However, the TPSS shall remain functional via local control in the event of failure of any component or components of the supervisory and remote control system. The relays shall be able to be interrogated via an integral Human Machine Interface (HMI).

4. Multiple levels of testing shall be required, including design and production tests at the manufacturer's plants, and commissioning and post-energization testing at the site.

K. Traction Power Limit of Work:

1. The limit of the work shall be all the traction power electrical equipment within the boundary of the traction power compound. It also includes replacement of positive feeder and rail return cables and communications cables from the TPSS to the nearest manhole.

2. PECO feeder cables within the TPSS and out to the property line or point of common coupling.

1.02 Related Sections

A. Drawings and general provisions of the Contract, including General and Supplementary Provisions and other Division 1 Specification Sections, apply to this Section.

B. Agreement.

Construction Contract No. 5 01010-10 Summary of Work

C. Section 01025 – Measurement and Payment

D. Section 01060 – Regulatory Requirements and Safety

E. Section 01300 – Submittals

F. Section 01400 – Quality Requirements

G. Section 01500 – Construction Facilities and Temporary Controls

H. Section 01580 – Project Identification Signs

I. Section 01590 – SEPTA Field Office

J. Section 16010 – Basic Electrical Requirements

K. Section 16060 – Grounding and Bonding

L. Preliminary Drawings:

1. Preliminary drawings demonstrate viability of proposed design solutions and are provided to convey the scope of the SEPTA Substation Project. The Contractor shall adopt the scope and solutions defined by the preliminary drawings as a basis for final design and construction.

M. Performance Specifications:

1. Project performance specifications identify the general requirements, products, execution, and quality control measures that shall be adopted while constructing or procuring materials. These performance specifications must be integral to the final design plans, and adhered to as the Contractor acquires manufactured products, materials, or construction services. The Contractor is encouraged to use and refine the project performance specifications to develop final technical specifications for construction, provided the final technical specifications preserve the fundamental framework and work result of each performance specification as approved by SEPTA.

N. Reference Documents:

1. Reference documents that were obtained or developed in conjunction with these Contract Documents are provided as general background information. The reference documents have no contractual basis for design and construction. The Contractor must validate the accuracy of applicable reference documents before using this information to develop designs or construction plans. Table 01010-1 is a list of the reference documents.

Table 01010-1 Reference Documents

Reference File Name Brief Description

Broad Substation Roof Replacement Plans

Plans for Broad TPSS roof replacement project

SEPTA 630VDC Emergency Lighting and Power Cable – Single Line Diagram

Orange, Blue, and Green Line Subways, City Transit Division - 630V DC Emergency Lighting & Power Cable, Emergency Power Generation, Electrical Single Line Diagram – 600 V DC Emergency Distribution Existing Conditions

Construction Contract No. 5 01010-11 Summary of Work

DWG 7E-16563 M.F.S.E./B.S.S./Ridge Ave. Spur - 4800V.A.C. Power & Lighting Cable Loading - Single Line Diagram - Electrical

Environmental Investigation Report Environmental Assessment of 17 TPSS/SWS sites

Loudon WESS Details-Rev3_signed 171108

WESS equipment and cable layout Rev 3 by Constellation / SEPTA

Management of Lead Paint in SEPTA Construction Projects Document #3001

SEPTA standard method report

3004 Asbestos Control and Handling Program 2023

SEPTA standard method report

PECO fault duty letters - dc TPSS 2016 PECO letters - Contracts 4 & 5 locations

SEPTA Station 20 Sansom Points List SEPTA standard template for master station

Tentative layout of WESS Equipment in Park TPSS_22-Jan-2018

Tentative layout, final as built plans to be available only after April 2018

Park PECO Info PECO Conduit Map near Park TPSS

Broad PECO Info PECO Conduit Map near Broad TPSS

O. Permit Matrix (attached to this Section):

1. The Permit Matrix summarizes the various permits that may be required for the Substation Rehabilitation project. This matrix identifies the type of permit, reviewing agency, municipality or city, and the entity responsible for obtaining each permit.

1.03 Quality Assurance and Quality Control

A. The Contractor will assume responsibility for executing a Quality Assurance/Quality Control (QA/QC) program. The QA/QC program’s basic form will be specified in the Contractor’s Quality Control Plan (QCP) as submitted under Section 01400 and will include the tests and inspections called for in the technical sections of the Specifications. The Contractor shall be responsible for requiring all subcontractors and suppliers to adhere to the Contractor’s QA/QC program and participate in quality assurance activities.

B. If a Project is governed by ‘Buy America’ requirements, SEPTA will require documentation to confirm the country of origin of all applicable products and materials. The Contractor is responsible for communicating ‘Buy America’ requirements to subcontractors and suppliers.

The lack of sufficient documentation may be grounds for rejecting a product or material.

C. Quality activities will be documented by the Contractor. SEPTA may audit the Contractor’s QA/QC activities. The Contractor will make the subcontractor’s applicable documentation available to SEPTA.

D. The Contractor and subcontractors are required to cooperate fully with testing and inspection activities carried out by SEPTA and its agents. The Contractor will provide the SEPTA Project Manager with adequate (as determined by the SEPTA Project Manager) notification for all activities which require testing and/or inspection. For all inspections and testing required by code, work may not proceed until this testing and inspection has been completed.

E. Once a product or material has been accepted through the submittal process, no substitution of this material or product will be allowed without resubmitting it following the

Construction Contract No. 5 01010-12 Summary of Work provisions of Section 01300. SEPTA reserves the right to require removal of any non-reviewed material and product.

1.04 Contractor Responsibilities

A. The Contractor shall furnish all materials, tools, equipment, supervision, administration, and transportation, and perform all labor and services necessary to furnish, deliver, construct, install, connect and/or interconnect and test as required to complete all work described in the Specifications and indicated in the Contract Drawings.

B. The Contractor is solely responsible for ensuring the methods and equipment required to transport the new and existing equipment into and out of the working site location will cause the least amount of impact to SEPTA Operations and/or local residences and/or businesses. The Contractor shall develop and submit the delivery/transportation plans and procedures for SEPTA approval.

C. The Contractor is responsible for securing and paying for all necessary permits and approvals required to complete the work. No work may commence on site without securing and paying for the necessary approvals including but not limited to:

1. Permits and utility connection fees.

2. Temporary power.

3. Governmental fees.

4. Licenses.

5. Inspections.

6. Any local taxes.

D. SEPTA PMIS (Project Management Information System):

1. SEPTA has a PMIS in place used for tracking Key Performance Indicators (KPI) through integrated reporting and dashboards populating capital projects with ‘real time’ information essential for performance tracking and benchmarking which are essential to achieving SEPTA’s project management goals.

2. SEPTA shall make access available, to the Contractor, to SEPTA’s PMIS for the Contractor’s use to exchange Project information as required throughout the life of the Project at no additional cost to the Contractor. User access licenses are not required for the Contractor’s use of SEPTA’s PMIS. The SEPTA Project Manager shall create user accounts with appropriate permissions for the Contractor’s use throughout the life of the Project.

3. The Contractor is required to coordinate with the SEPTA Project Manager regarding hands-on training for Contractor Project employees on the SEPTA PMIS program (i.e., e- Builder). SEPTA will not compensate the Contractor or their personnel for any formal and/or informal training of the Contractor’s staff on the SEPTA PMIS.

4. The Contractor shall submit all Project information/communications through SEPTA’s current PMIS. Document distribution to Project members shall be accomplished both within the PMIS system and via email as appropriate. Project document distribution to parties outside of the Project communication system shall be accomplished by secure email of outgoing documents and attachments, readable by a standard email client.

Construction Contract No. 5 01010-13 Summary of Work

E. SEPTA Notification:

1. Give written notices necessary for, and incidental to, the due and lawful prosecution of the work.

2. Provide fourteen (14) day notification to SEPTA for all construction work which requires observation, testing and/or inspection.

3. Notify the SEPTA Project Manager at least fourteen (14) days in advance of the date the individual construction stages or elements will be fully complete and ready for inspection.

4. Notify the SEPTA Project Manager at least fourteen (14) days in advance of the date the entire work will be substantially complete and ready for inspection.

5. Notify the SEPTA Project Manager at least fourteen (14) days in advance of the date the entire work will be substantially complete and ready for inspection.

F. Utility Notification:

1. Known existing utilities may be indicated on the Contract Drawings but the Contractor may not interpret this information as either complete or accurate. Regardless of the existing utilities shown on the Contract Drawings, the Contractor must identify and verify the location of all existing utilities; prior to working; by following applicable regulations and procedures such as contacting the PA One Call system and asking SEPTA personnel to identify utilities at the site.

2. The Contractor shall determine ownership of all utilities and notify utility owners prior to intended work start date. Deliver a copy of this notice to the SEPTA Project Manager within eight (8) hours of the submittal of the notification.

3. Verify location of existing utilities prior to working in or adjacent to areas containing existing utilities.

a. Notify SEPTA as specified on the Contract Drawings prior to intended start work date in an area in which other SEPTA infrastructure may be located.

G. Protection and Repair of the Work and Adjacent Property:

1. Prior to commencement of work, the Contractor and the SEPTA Project Manager shall examine the site and document the condition of all areas not intended to be changed by the Project. Depending on the scope of work, this may include features such as sidewalks, driveways, roadways, and adjacent facilities.

2. The Contractor must repair any damage to property caused, directly or indirectly, by the actions of the Contractor to the satisfaction of the SEPTA Project Manager (and property Owner if the damage is to property not owned by SEPTA) at no cost to SEPTA.

3. Until final acceptance of the work by SEPTA, the Contractor shall be responsible for maintaining the executed work in its finished condition as determined by the SEPTA Project Manager. All work shall be restored to its finished condition prior to final acceptance at no expense to SEPTA.

H. Support of Existing Structures and Right of Way:

1. Existing structures, adjacent to the Project work area, must be supported adequately utilizing underpinning, shoring and other temporary stabilization measures. A plan to

Construction Contract No. 5 01010-14 Summary of Work execute this temporary support and stabilization must be approved by the SEPTA Project Manager prior to any excavation commencing. At the discretion of the SEPTA Project Manager, the Contractor may be required to have this plan prepared and sealed by the Professional Engineer licensed in the Commonwealth of Pennsylvania.

2. Under no circumstances shall excavation in the vicinity of track and right of way occur without the prior approval of the SEPTA Project Manager.

I. Until final acceptance of the work by SEPTA, the Contractor shall have the charge and care thereof and shall take every reasonable precaution against injury or damage to any part thereof by the action of the elements, theft, vandalism, or from any other cause, whether arising from the execution or from the non-execution of the work. The Contractor shall rebuild, repair, restore, and make good, to the satisfaction of the SEPTA Project Manager, all damages to any portion of the work occasioned by any of the above causes before final acceptance and shall bear the expense thereof at no cost to SEPTA. The Contractor shall coordinate with the utility regarding outages required.

J. Contractor's Field Staff:

1. The Contractor shall have a full-fledged design firm on its team to advance the 50% level design to 100% and sign/seal the drawings. The design team shall have architects and design engineers, licensed in Commonwealth of Pennsylvania, of all disciplines. The Design team shall also have specialty designers for the studies specified in the Contract Documents. The key personnel are described hereunder:

a. Project Manager:

1) The Contractor shall designate a Project Manager. The work of the Project Manager includes oversight and coordination of the entire Contract, including mobilization, final design, procurement, construction, testing & commissioning, quality assurance, and safety.

2) The Project Manager shall serve as SEPTA's single point of contact for all contractual issues.

3) The Project Manager shall coordinate prosecution of the work with each sub-contractor, public utilities, government bodies, PECO, PADOT, SEPTA Operations and other contractors. The Project Manager shall implement means and methods to eliminate or minimize possible delays in the work caused by conflicts with utilities or other outside agencies or jurisdictions.

b. Design Manager:

1) The Contractor shall designate a Design Manager. The Design Manager shall be responsible for completing all facets of final design including document research, surveys, field verification, final design, quality assurance, shop drawings, and as-builts.

2) The Design Manager shall facilitate coordination between designers, subconsultants, utility companies, agencies having jurisdiction, suppliers, constructors, SEPTA, and any other entity that impacts the work.

3) The Design Manager shall enforce quality standards and safety procedures.

4) The Design Manager should have a direct line of communication with the Project Manager and the Superintendent.

5) The Design Manager shall be a licensed Engineer in the Commonwealth of Pennsylvania.

c. Environmental Engineer:

1) The Contractor shall designate an Environmental Engineer. The work of the Environmental Engineer shall include site investigations, sampling, and administration of

Construction Contract No. 5 01010-15 Summary of Work laboratory analyses, data interpretation, and developing remediation recommendations for construction.

2) The Environmental Engineer shall coordinate with designers, agencies having jurisdiction, SEPTA, and any other entities that have authority over environmental practice.

3) The Environmental Engineer shall monitor construction activities for compliance with specified remediation plans.

4) The Environmental Engineer shall be licensed Engineer in the Commonwealth of Pennsylvania.

d. Traction Power Lead Engineer:

1) The Contractor shall designate a Traction Power Lead Engineer. The Traction Power Lead Engineer shall be responsible for completing final design of all TPSS power equipment and supply systems. Duties include comprehensive design coordination with interfacing disciplines.

2) The Traction Power Lead Engineer will coordinate with Contractor vendors, PECO, SEPTA, and providers of SEPTA supplied equipment.

3) The Traction Power Lead Engineer shall perform or supervise checking of shop drawings and prepare of as-built drawings.

4) The Traction Power Lead Engineer shall inspect delivered equipment for conformance to procurement specifications.

5) The Traction Power Lead Engineer shall monitor construction for conformance to final construction plans.

6) The Traction Power Lead Engineer shall monitor and coordinate testing & commissioning activities.

7) The Traction Power Lead Engineer shall be a licensed Engineer in the Commonwealth of Pennsylvania.

e. Superintendent:

1) The Contractor shall designate a Superintendent. The Superintendent shall have demonstrated competency in the work of this Project. The Superintendent shall be responsible for all aspects of construction including coordination with the final designer, suppliers, permitting agencies, agencies having jurisdiction, SEPTA, and any other entity that has legitimate activity within the limits of work.

2) The Superintendent shall be a full-time employee and shall be assigned exclusively to this Contract. Contract employees are not permitted.

3) The Superintendent shall coordinate the TPSS outages with sub- contractors and SEPTA.

4) The Superintendent shall maintain a detailed critical path method construction schedule, and a comprehensive activity log. The Superintendent shall attend recurring progress meetings with SEPTA and SEPTA's representatives.

5) The Superintendent should have a direct line of communication with the Project Manager and the Design Manager.

6) The Superintendent shall enforce construction quality standards and safety procedures.

f. Traction Power Integrator/Designer:

1) The Contractor shall provide the services of a Traction Power Integrator (TPI) who shall be responsible for complete traction power system integration. He shall coordinate the shop drawings and supplies from the suppliers of transformers, 15 kV AC circuit breakers, transformer rectifiers, DC circuit breakers, disconnect switches, cables, control circuits, and surge arresters to ensure full compatibility with each other, proper location of the conduits to suit the equipment, relay selection and setting of the relays.

Construction Contract No. 5 01010-16 Summary of Work

2) The TPI shall be a Professional Engineer licensed in the Commonwealth of Pennsylvania.

3) The TPI shall be responsible for:

a) Coordinating and integrating the design of all disciplines into a single system.

b) Ensuring that there are no conflicts between the various equipment and subsystems especially in regard to functionality and layout.

c) Coordination of various studies, selection of protective relays and their settings.

d) Review and signing of the shop drawings before submitting to SEPTA for review.

e) Coordinating the construction activities in each stage of construction to minimize the requirement of power outage.

f) Coordinating matching of equipment various suppliers for working on the medium voltage and low voltage supply.

g) Coordinate and work with PECO for work related to the utility supply and make service applications and submittals.

h) Coordinating the testing of various subsystems and complete system.

i) The TPI shall be a registered Engineer in the Commonwealth of Pennsylvania.

g. Quality Control Manager:

1) The Contractor shall assign a Quality Control Manager for the duration of the work.

2) The Quality Control Manager shall be responsible for developing, implementing, and enforcing project-wide quality control procedures for all design and construction activities.

3) Refer to Section 01400 for a definition of the responsibilities of this position.

h. Safety Officer:

1) The Contractor shall assign a designated on-site Safety Officer.

2) The presence of the Safety Officer at…