Traction Power Substation Rehabilitation Program – Contract 5 Broad, Loudon, Park and Castor Substations Project
Solicitation number
RFP 26-00105-AJEB
Issued by
Philadelphia County, Philadelphia City, Pennsylvania

About this file

Addendum No. 10 issued August 25, 2026, for SEPTA's Sealed Bid No. 26-00105-AJEB addresses the Traction Power Substation Rehabilitation Program Contract 5 covering Broad, Loudon, Park, and Castor Substations. The addendum maintains the proposal due date of Thursday, August 27, 2026, by 11:00 AM and must be acknowledged on Attachment 4: Addendum Acknowledgement Sheet or the bid may be deemed non-responsive. This addendum responds to three contractor questions (RFI 33-35) regarding delay compensation provisions, work suspension terms, and hazardous waste generator designation.

The addendum revises three critical contract provisions: (1) Section XI Part C now removes the "negligence" requirement for SEPTA-caused delays, allowing equitable adjustment in contract sum and time when the contractor is delayed by SEPTA, its agents, or other contractors under SEPTA's responsibility; (2) Section XI Part D revises suspension language to establish concrete thresholds—any single suspension exceeding 15 calendar days or cumulative suspensions exceeding 30 calendar days entitle the contractor to request equitable adjustment in contract sum for demonstrated cost increases including reasonable profit; (3) SEPTA confirms it is the waste generator for all hazardous materials including those covered in specifications 02080, 02081, 02082, 02083, 02084, and 02085 (beyond just specification 02205-3.03-A-6 for hazardous soils), will provide EPA ID if needed, and will revise all relevant specification sections accordingly, though the contractor remains responsible for removal and associated project costs.

View the file

Other files

File Type Posted
Addendum-9-Contract-5-Substations-Step-1-8-20-26.pdf PDF
Addendum-8-Contract-5-Substations-Step-1-8-10-26.pdf PDF
Addendum-7-DWG-7E-16563_28_color_a.pdf PDF
Addendum-7-REV1-Markups-11x17_SEPTA_CONTRACT-5_50_LOUDON.pdf PDF
Addendum-7-Contract-5-Substations_Rehab-Step-1-8-5-26.pdf PDF
Addendum-6-Contract-5-Substations-Step-1-7-6-26.pdf PDF
Managing-Asbestos-In-Place-Addendum-5.pdf PDF
SEPTA-Environmental-Report-combined-Addendum-5.pdf PDF
Broad-Roof-Replacement-100-DWG_Set-Addendum-5.pdf PDF
Management-of-Lead-Paint-in-SEPTA-Construction-Projects-Document-3001-Addendum-5.pdf PDF
Orange-Blue-Green-line-emerg.-lght-single-line-diag.-Addendum-5.pdf PDF
Park-Peco-Info-Addendum-5.pdf PDF
Market-PECO-fault-duty-letters-dc-TPSS-Addendum-5.pdf PDF
Broad-Peco-Info-Addendum-5.pdf PDF
Tentative-Layout-of-WESS-Equipment-in-Park-TPSS_22-Jan-2018-Addendum-5.pdf PDF
Loudon-WESS-Details-REV3_signed-171108-Addendum-5.pdf PDF
PECO-fault-duty-letters-dc-TPSS-Addendum-5.pdf PDF
Addendum-5-Contract-5-Substations-Step-1-6-25-26.pdf PDF
SEPTA-Station-20-Sansom-Points-List-Addendum-5.pdf PDF
3004-ACM-Handling-Program-2023-Addendum-5.pdf PDF
DWG-7E-16563_28_color_a-Addendum-5.pdf PDF
Pre-Qualification-Meeting_-RFQ_-26-00105-AJEB-Substation-attendance-report-6-10-26.pdf PDF
Addendum-3-Contract-5-Substations-Step-1-6-10-26.pdf PDF
SIte-Visit-Attendance-Meeting-Power-Substation-Contract-5-6-11-26.pdf PDF
Addendum-4-Contract-5-Substations-Step-1-6-15-26.pdf PDF
Site-Visit-Attendance-Meeting-Substation-Contract-5-6-12-26.pdf PDF
Addendum-2-Contract-5-Substations-Step-1-6-4-26.pdf PDF
22x34-Loudon-Contract-5-Drawings-Addendum-3.pdf PDF
22x34-Broad-Street-Contract-5-Drawings-Addendum-3.pdf PDF
Attachment-2-11x17_SEPTA_CONTRACT-5_MARKET_50_BROAD-PARK-LOUDON-CASTOR-DRAWINGS-SET-3.pdf PDF
22x34-Castor-Contract-5-Drawings-Addendum-3.pdf PDF
Attachment-2-11x17_SEPTA_CONTRACT-5_MARKET_50_BROAD-PARK-LOUDON-CASTOR-DRAWINGS-SET-2.pdf PDF
Attachment-2-11x17_SEPTA_CONTRACT-5_MARKET_50_BROAD-PARK-LOUDON-CASTOR-DRAWINGS-SET-1.pdf PDF
22x34-General-Notes-Contract-5-Drawings-Addendum-3.pdf PDF
Addendum-1-Contract-5-Substations-Step-1-6-3-26.pdf PDF
22x34-Park-Contract-5-Drawings-Addendum-3.pdf PDF
JAL192590415-Substation-Rehab-Contract-5-Step-1.pdf PDF
ATTACHMENT-3-Form-330.pdf PDF
ATTACHMENT-2-SEPTA_CONTRACT-5_MARKET_50_BROAD-PARK-LOUDON-CASTOR-Drawings-SET-3.pdf PDF
JAL192590415-Invitation-to-Propose-2-Step-Process-Traction-Substation.pdf PDF
ATTACHMENT-4-Addendum-Acknowledgement-1.pdf PDF
ATTACHMENT-2-SEPTA_CONTRACT-5_MARKET_50_BROAD-PARK-LOUDON-CASTOR-Drawings-SET-1.pdf PDF
ATTACHMENT-1-SEPTA-Contract-5-Substations-50-Specifications.pdf PDF
Exhibit-FEDERAL-CONSTRUCTION-CONTRACT-STEP-2-CONTRACT-5-SUBSTATIONS.pdf PDF
ATTACHMENT-2-SEPTA_CONTRACT-5_MARKET_50_BROAD-PARK-LOUDON-CASTOR-Drawings-SET-2-1.pdf PDF
Show all 45

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

August 25, 2026

Dear Sir/Madam:

Attached is Addendum No. 10 for SEPTA's Sealed Bid No. 26-00105-AJEB Traction Power Substation Rehabilitation Program – Contract 5 Broad, Loudon, Park and Castor Substations Project. The Proposal Due Date remains unchanged on Thursday, August 27, 2026, by 11AM.

Any inquiries regarding this bid must be directed to Justin Benante of the Procurement and Supply Chain Management Department at (215) 580-7022.

Sincerely, Justin Benante

Justin Benante Sr. Contract Administrator Procurement & Supply Chain Management Dept.

Addendum #10 August 25, 2026

SEALED BID No. 26-00105-AJEB

Traction Power Substation Rehabilitation Program – Contract 5 Broad, Loudon, Park and Castor Substations Project

ADDENDUM No. 10 To All Bidders:

The following constitutes Addendum No.10 to SEPTA's Sealed Bid No. 26-00105-AJEB Traction Power Substation Rehabilitation Program – Contract 5 Broad, Loudon, Park and Castor Substations Project. Addendum No. 10 must be acknowledged by inserting the date on the Addenda Response form. Failure to do so may render a bidder's proposal as non-responsive. Addendum No. 10 must be acknowledged by inserting the date of the Addendum within Attachment 4: ADDENDUM ACKNOWLEDGEMENT SHEET of the Bid Package. Failure to do so may render a bidder's proposal as non-responsive.

Questions and Answers issued with this Addendum No. 10 are hereby incorporated by reference and made part of the Terms and Conditions of this project.

A. General

1. N/A

B. Specifications, C. Drawings & Attachments

D . Ques t ions & Answers

Please see answers be low in RED.

33 . Your r esponse to RFI 11 rev ises Sec t ion XI Par t C to " I f t he Con t rac to r i s un reasonably de layed by the neg l igence o f SEPTA, i t s agen ts o r r ep resen ta t i ves , o r ano the r con t rac to r fo r whom SEPTA i s r e spons ib l e , t he Con t rac to r shal l be en t i t l ed t o an equ i t ab l e ad jus tment in t he Con t rac t Sum and Cont rac t T ime in acco rdance wi th t he T ime Impac t Analys i s l anguage in Sect ion XI C 4 o f the cont rac t . " We have two i ssues wi th th i s l anguage :

- The requ i rement tha t fo r any de l ay to be compensable , i t mus t be t he r esu l t o f SEPTA’s negl igence i s no t acceptab le , a s i t would p rec lude re imbursemen t fo r a lmos t a l l poss ib le causes o f de l ay due to SEPTA. P l ease r emove the words “ the negl igence o f” f rom the sen t ence .

- The requ i remen t t ha t t he con t rac to r be un reasonab ly delayed be fo re del ays a re compensable i s p rob lemat i c , as SEPTA and the cont rac to r wi l l have ve ry d i f fe ren t op in ions as t o wha t i s un reasonable . Wi thout a quant i f i ab l e de f in i t ion fo r "un reasonably" i t i s imposs ib l e to quan t i fy t he i nd iv idual and cumula t ive du ra t i on o f de l ays caused by SEPTA that a cont rac to r cou ld be exposed to wi thou t e l ig ib i l i t y fo r add i t i ona l compensat ion . Scope tha t canno t be quan t i f i ed cannot be p r i ced . P l ease r ev i se t h i s l anguage to de l e t e t he word "unreasonab ly" o r p rov ide a de f in i t i on wh ich quant i f i e s the ind iv idua l and cumula t ive du ra t ion o f de l ays e l ig ib l e fo r compensat ion .

I f t he Con t rac to r i s de l ayed by the neg l igence o f SEPTA, i t s agent s o r r ep resenta t i ves , o r anothe r cont rac to r fo r whom SEPTA i s r e spons ib l e , t he Con t rac to r shal l be en t i t l ed to an equ i t ab l e ad jus tment in the Cont rac t Sum and Con t rac t Time in acco rdance wi th t he T ime Impac t Ana lys i s l anguage in Sec t ion XI C4 o f t he cont rac t .

34 . Your r esponse t o RFI 12 rev i ses Sec t ion XI Par t D to " I f t he du ra t ion o f suspended

Work i s fo r an un reasonab le pe r iod o f t ime, an ad jus tmen t wi l l be made to t he Con t rac t Sum in acco rdance wi th the T ime Impac t Analys i s l anguage in Sect ion XI C 4 o f the cont rac t fo r any inc rease i n t he cos t o f pe r formance ( i nc luding p ro f i t ) caused by such Suspens ion and th i s Cont rac t shal l be mod i f i ed acco rd ingly i n wr i t i ng ." Again , wi thout a quant i f i ab l e de f in i t i on fo r "un reasonab le , " i t i s imposs ib l e t o quan t i fy t he du ra t ion o f SEPTA-di rec t ed suspens ions t ha t the con t rac to r mus t accommodate wi thou t add i t ional compensa t ion . Scope tha t canno t be quan t i f i ed cannot be p r i ced . P l ease r ev ise t h i s l anguage in one o f two ways : (1 ) de l e t e the word "unreasonable” , o r (2 ) de l e t e t he word "unreasonable” and a l so p rov ide t he cumula t ive t h reshold du ra t ion o f SEPTA-d i rec t ed suspens ions t ha t would enab le fu r the r days o f suspens ion to be e l i g ib l e fo r compensa t ion .

The l anguage has been rev ised to the fo l lowing:

Suspens ions o f Work The Cont rac tor shal l suspend the progres s o f t he Work , o r any pa r t t he reof , fo r t he opera t i ona l neces s i t y o r convenience o f SEPTA whenever i t shal l be r equi red by wr i t t en o rder o f t he P ro j ec t Manager or Contract Admini s tra tor (au thorized SEPTA Representa t ive ) . Such suspens ions shal l be fo r such reasonab le per iods o f t ime as the au tho r i zed SEPTA Represen ta t ive may o rder ; p rov ided tha t , i n t he even t o f such suspens ion (s ) o f t he p rogress o f Work o r any par t the reo f , the Comple t ion Date o f the Work so suspended o r de l ayed by such suspens ion (s ) shal l be ex t ended by SEPTA fo r a pe r iod equival en t to the t ime los t by reason o f such suspens ion (s ) .

I f any s ing le suspens ion d irec ted by the au thor ized SEPTA Representat ive exceeds f i f t een (15 ) ca l endar days or , i f mul t ip l e d i rec ted suspens ions cum ulat ively exceed th i r ty (30 ) ca lendar days , the Contractor m ay submi t a reques t for an equi table ad jus tm ent to the Contract Sum in accordance wi th the T im e Impact Ana lys i s requirem ents s e t for th in Sect ion XI .C.4 o f the Contract .

To the ex ten t the Contractor dem onstra tes an increase in the cos t o f per form ance resu l t ing from such suspens ion , including reasonable prof i t where perm i t ted under the Contract , the Contract Sum shal l be ad jus ted by wr i t ten m odi f i ca t ion o f the Contract .

Such o rder f rom an authorized SEPTA Representa t ive sha l l no t o the rwi se modi fy , o r inva l ida t e i n any way, any o f the o the r p rov i s ions o f t he Cont rac t .

35 . Spec 02205-3 .03 -A-6 fo r haza rdous so i l s s t a t es "SEPTA shal l be l i s t ed in the d i sposal document s as t he was t e genera to r" . Speci f i ca t i on sec t ions 02080 , 02081, 02082 , 02083 , 02084 , and 02085 fo r o the r haza rdous mate r i a l types do not s t a t e "SEPTA shal l be l i s t ed in the d i sposal documen ts a s the was t e genera to r" . I t mus t be c l ea r i n the Con t rac t t ha t SEPTA i s the was t e genera to r o f a l l haza rdous ma te r i a l t ypes . P lease immedia t e ly conf i rm that SEPTA i s t he "was t e genera to r" o f a l l haza rdous mate r i a l s . Al so , p r io r to the p r i c ing phase o f th i s b id , p l ease add th i s l anguage to specs 02080 , 02081, 02082 , 02083 , 02084, and 02085 to c l a r i fy t ha t SEPTA i s the was t e genera to r o f a l l haza rdous mate r i a l t ypes .

Yes SEPTA i s the was t e genera to r and wi l l supply an EPA ID i f needed fo r t he was t e . Al l o f t he Spec i f i ca t i on sec t ions l i s t ed above wi l l be r ev i sed to r e f l ec t th i s .

The cont rac to r wi l l be r espons ib l e fo r r emova l and cos t as soci a t ed wi th t he p ro j ec t fo r a l l was t e .

ADDENDUM No. 10
B. Specifications,
C. Drawings & Attachments
D. Questions & Answers
Please see answers below in RED.
33. Your response to RFI 11 revises Section XI Part C to "If the Contractor is unreasonably delayed by the negligence of SEPTA, its agents or representatives, or another contractor for whom SEPTA is responsible, the Contractor shall be enti...
- The requirement that for any delay to be compensable, it must be the result of SEPTA’s negligence is not acceptable, as it would preclude reimbursement for almost all possible causes of delay due to SEPTA. Please remove the words “th...
If the Contractor is delayed by the negligence of SEPTA, its agents or representatives, or another contractor for whom SEPTA is responsible, the Contractor shall be entitled to an equitable adjustment in the Contract Sum and Cont...
34. Your response to RFI 12 revises Section XI Part D to "If the duration of suspended Work is for an unreasonable period of time, an adjustment will be made to the Contract Sum in accordance with the Time Impact Analysis language in Secti...
The language has been revised to the following:
Suspensions of Work
The Contractor shall suspend the progress of the Work, or any part thereof, for the operational necessity or convenience of SEPTA whenever it shall be required by written order of the Project Manager or Contract Administrator (authori...
Such order from an authorized SEPTA Representative shall not otherwise modify, or invalidate in any way, any of the other provisions of the Contract.
35. Spec 02205-3.03-A-6 for hazardous soils states "SEPTA shall be listed in the disposal documents as the waste generator". Specification sections 02080, 02081, 02082, 02083, 02084, and 02085 for other hazardous material types do not stat...
Yes SEPTA is the waste generator and will supply an EPA ID if needed for the waste. All of the Specification sections listed above will be revised to reflect this. The contractor will be responsible for removal and cost associated with th...