Addendum-1-Contract-5-Substations-Step-1-6-3-26.pdf

PDF 208 KB Posted

Attached to
Traction Power Substation Rehabilitation Program – Contract 5 Broad, Loudon, Park and Castor Substations Project
Solicitation number
RFP 26-00105-AJEB
Issued by
Philadelphia County, Philadelphia City, Pennsylvania

About this file

This is Addendum No. 1 to SEPTA's (Southeastern Pennsylvania Transportation Authority) Sealed Bid No. 26-00105-AJEB for the Traction Power Substation Rehabilitation Program – Contract 5 covering Broad, Loudon, Park, and Castor Substations Project, issued June 3, 2026. The addendum confirms that the proposal due date remains unchanged at Wednesday, July 15, 2026 by 11:00 AM. Bidders must acknowledge Addendum No. 1 by inserting the date within Attachment 4: Addendum Acknowledgement Sheet of the bid package, or their proposal may be deemed non-responsive. Any inquiries regarding this bid must be directed to Justin Benante, Sr. Contract Administrator in the Procurement & Supply Chain Management Department at (215) 580-7022.

The addendum contains no changes to general provisions, specifications, drawings, or attachments, but provides clarifications through a questions and answers section. Regarding protective clothing requirements for site access, all garments must meet NFPA 70E 2024 guidelines with dual-rated protective clothing (AR and FR) compliant with NFPA 2112 for flame resistance and arc-rated per NFPA 70E/ASTM F1506. The required PPE category is Category 2 with an Arc Rating of 8, and work boots must have EH (Electrical Hazard) marking. The questions and answers issued with this addendum are incorporated by reference and made part of the project's Terms and Conditions.

View the file

Other files

File Type Posted
Addendum-10-Contract-5-Substations-Step-1-8-25-26.pdf PDF
Addendum-9-Contract-5-Substations-Step-1-8-20-26.pdf PDF
Addendum-8-Contract-5-Substations-Step-1-8-10-26.pdf PDF
Addendum-7-DWG-7E-16563_28_color_a.pdf PDF
Addendum-7-REV1-Markups-11x17_SEPTA_CONTRACT-5_50_LOUDON.pdf PDF
Addendum-7-Contract-5-Substations_Rehab-Step-1-8-5-26.pdf PDF
Addendum-6-Contract-5-Substations-Step-1-7-6-26.pdf PDF
Managing-Asbestos-In-Place-Addendum-5.pdf PDF
SEPTA-Environmental-Report-combined-Addendum-5.pdf PDF
Broad-Roof-Replacement-100-DWG_Set-Addendum-5.pdf PDF
Management-of-Lead-Paint-in-SEPTA-Construction-Projects-Document-3001-Addendum-5.pdf PDF
Orange-Blue-Green-line-emerg.-lght-single-line-diag.-Addendum-5.pdf PDF
Park-Peco-Info-Addendum-5.pdf PDF
Market-PECO-fault-duty-letters-dc-TPSS-Addendum-5.pdf PDF
Broad-Peco-Info-Addendum-5.pdf PDF
Tentative-Layout-of-WESS-Equipment-in-Park-TPSS_22-Jan-2018-Addendum-5.pdf PDF
Loudon-WESS-Details-REV3_signed-171108-Addendum-5.pdf PDF
PECO-fault-duty-letters-dc-TPSS-Addendum-5.pdf PDF
Addendum-5-Contract-5-Substations-Step-1-6-25-26.pdf PDF
SEPTA-Station-20-Sansom-Points-List-Addendum-5.pdf PDF
3004-ACM-Handling-Program-2023-Addendum-5.pdf PDF
DWG-7E-16563_28_color_a-Addendum-5.pdf PDF
Pre-Qualification-Meeting_-RFQ_-26-00105-AJEB-Substation-attendance-report-6-10-26.pdf PDF
Addendum-3-Contract-5-Substations-Step-1-6-10-26.pdf PDF
SIte-Visit-Attendance-Meeting-Power-Substation-Contract-5-6-11-26.pdf PDF
Addendum-4-Contract-5-Substations-Step-1-6-15-26.pdf PDF
Site-Visit-Attendance-Meeting-Substation-Contract-5-6-12-26.pdf PDF
Addendum-2-Contract-5-Substations-Step-1-6-4-26.pdf PDF
22x34-Loudon-Contract-5-Drawings-Addendum-3.pdf PDF
22x34-Broad-Street-Contract-5-Drawings-Addendum-3.pdf PDF
Attachment-2-11x17_SEPTA_CONTRACT-5_MARKET_50_BROAD-PARK-LOUDON-CASTOR-DRAWINGS-SET-3.pdf PDF
22x34-Castor-Contract-5-Drawings-Addendum-3.pdf PDF
Attachment-2-11x17_SEPTA_CONTRACT-5_MARKET_50_BROAD-PARK-LOUDON-CASTOR-DRAWINGS-SET-2.pdf PDF
Attachment-2-11x17_SEPTA_CONTRACT-5_MARKET_50_BROAD-PARK-LOUDON-CASTOR-DRAWINGS-SET-1.pdf PDF
22x34-General-Notes-Contract-5-Drawings-Addendum-3.pdf PDF
22x34-Park-Contract-5-Drawings-Addendum-3.pdf PDF
JAL192590415-Substation-Rehab-Contract-5-Step-1.pdf PDF
ATTACHMENT-3-Form-330.pdf PDF
ATTACHMENT-2-SEPTA_CONTRACT-5_MARKET_50_BROAD-PARK-LOUDON-CASTOR-Drawings-SET-3.pdf PDF
JAL192590415-Invitation-to-Propose-2-Step-Process-Traction-Substation.pdf PDF
ATTACHMENT-4-Addendum-Acknowledgement-1.pdf PDF
ATTACHMENT-2-SEPTA_CONTRACT-5_MARKET_50_BROAD-PARK-LOUDON-CASTOR-Drawings-SET-1.pdf PDF
ATTACHMENT-1-SEPTA-Contract-5-Substations-50-Specifications.pdf PDF
Exhibit-FEDERAL-CONSTRUCTION-CONTRACT-STEP-2-CONTRACT-5-SUBSTATIONS.pdf PDF
ATTACHMENT-2-SEPTA_CONTRACT-5_MARKET_50_BROAD-PARK-LOUDON-CASTOR-Drawings-SET-2-1.pdf PDF
Show all 45

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

June 3, 2026

Dear Sir/Madam:

Attached is Addendum No.1 for SEPTA's Sealed Bid No. 26-00105-AJEB Traction Power Substation Rehabilitation Program – Contract 5 Broad, Loudon, Park and Castor Substations Project. The Proposal Due Date remains unchanged on Wednesday, July 15, 2026 by 11AM.

Any inquiries regarding this bid must be directed to Justin Benante of the Procurement and Supply Chain Management Department at (215) 580-7022.

Sincerely, Justin Benante

Justin Benante Sr. Contract Administrator Procurement & Supply Chain Management Dept.

Addendum #1 June 3, 2026

SEALED BID No. 26-00105-AJEB

Traction Power Substation Rehabilitation Program – Contract 5 Broad, Loudon, Park and Castor Substations Project

ADDENDUM No. 1

To All Bidders:

The following constitutes Addendum No. 1 to SEPTA's Sealed Bid No. 26-00105-AJEB Traction Power Substation Rehabilitation Program – Contract 5 Broad, Loudon, Park and Castor Substations Project. Addendum No. 1 must be acknowledged by inserting the date on the Addenda Response form. Failure to do so may render a bidder's proposal as non-responsive. Addendum No. 1 must be acknowledged by inserting the date of the Addendum within Attachment 4: ADDENDUM ACKNOWLEDGEMENT SHEET of the Bid Package. Failure to do so may render a bidder's proposal as non-responsive.

Questions and Answers issued with this Addendum No. 1 are hereby incorporated by reference and made part of the Terms and Conditions of this project

A. General

1. N/A

B. Specifications, C. Drawings & Attachments

D. Questions & Answers

Please see answers in RED below:

Can SEPTA please clarify:

1. What level of protective clothing is required for site access? SEPTA stated that "FR Clothing" was required. Please confirm if this must be: All garments will meet NFPA 70E 2024 guidelines.

a. NFPA 2112 Flame-Resistant (FR) compliant clothing

b. AR (arc-rated in accordance with NFPA 70E / ASTM F1506)

c. dual-rated protective clothing (AR and FR)

2. If arc resistance is required, what NFPA 70E PPE category of arc rating is required? Category 2, Arc Rating 8

3. If there is an ankle height and/or EH marking requirement for the work boots? EH Marking is required

1 | P ag e

SEALED BID No. 26-00105-AJEB
A. General
B. Specifications,
C. Drawings & Attachments
D. Questions & Answers