TE_10_AdverseWeatherPlan.docx
DOCX document 53 KB Posted
- Attached to
- DRAFT Solicitation for Base Operations and Maintenance Services, Fort Huachuca, Arizona 20231115
- Solicitation number
- W9124A23R0005
About this file
This document outlines an adverse weather plan for Fort Huachuca in Arizona. It establishes responsibilities and procedures for responding to adverse weather conditions including snow, ice, flooding, high winds, and other events that could impact safety or operations. The Operations and Maintenance contractor is responsible for providing equipment like graders, dump trucks, and sand and responding within 30 minutes of notification to address road conditions and other weather-related issues as directed by the Contracting Officer's Representative. Primary duties of the contractor include maintaining safe primary and secondary roads on base and coordinating response efforts with military police and other groups. The related federal contract opportunity is a draft pre-solicitation for base operations and maintenance services at Fort Huachuca set to be awarded in 2023, conducted by the Department of the Army Materiel Command Army Contracting Command at Aberdeen Proving Ground.
View the file
Other files
Show 40 more
Latest 50 of 90 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Base Operations (BASOPS) Performance Work Statement Technical Exhibit 10 – Adverse Weather Plan
DIRECTORATE OF PUBLIC WORKS ADVERSE WEATHER PLAN
1. PURPOSE: To establish responsibilities and procedures pertaining to adverse weather conditions.
2. SCOPE: This procedure is applicable to adverse weather conditions on Fort Huachuca to ensure response by the operations and maintenance (O&M) contractor as directed by the Contracting Officer’s Representative (COR). Adverse weather conditions are those conditions which may create hazardous conditions on roadways and airfield runways, interrupt the military and civilian work force mission, cause utility failures, create safety problems, and impair security operations. Such adverse weather conditions would include one or more of the following, but not limited to:
One inch of snow accumulated on roads Ice covered roads Flooded roadways Freezing rain High sustaining winds (50 mph or higher)
3. RESPONSIBILITIES: Chief, Operations and Maintenance Branch, will provide overall direction and technical management of contract preparation and inspection. The COR will serve as the Directorate of Public Works’s (DPW) liaison with the Contracting Officer and ensure that the contract contains adequate description and requirements for all actions pertaining to contractor response to adverse weather conditions and will certify contractor’s performance for payment.
a. The designated Quality Assurance Evaluator (QAE) will serve as technical expert (depending on which contractor shop is responding) and will be responsible for inspections. The O&M contractor will be responsible for management expertise, experienced personnel, and all operations pertaining to performing adverse weather condition contractual requirements.
b. Designated QAE for each functional areas is identified below.
| FUNCTONAL AREA |
| QAE |
| PHONE NUMBER |
| RADIO CALL SIGN |
Roads and Grounds
| 533-1443 |
| 22E |
Electric
| 533-5158 |
| 22H |
Carpentry
| 533-8514 |
| 22M |
HVAC
| 533-5158 |
| 22H |
Plumbing
| 533-8514 |
| 22M |
UNITED STATES ARMY GARRISON FORT HUACHUCA, ARIZONA
INTERNAL PROCEDURE
ATZS-ISU PAGE 1 OF 3
April 2016 280-7
c. Service Support. The following equipment and materials shall be available for immediate use by the O&M contractor.
a. Three road graders
b. Two dump trucks equipped with hydraulic sling spreaders.
c. One front-end loader.
d. Sufficient sand for spreading on primary and secondary roads on the Installation.
4. PROCEDURES:
a. During Duty Hours:
(1) If weather conditions deteriorate during the duty day, the COR or appropriate QAE will notify the O&M contractor of what procedures are to take place to ensure safety to all post occupants. This possibly could consist of ensuring contractor is prepared to spread sand in the event roads become unsafe due to ice or snow on roads.
(2) The Chief, Operations and Maintenance Branch, will report to the Director, Public Works , and the Battle Captain, Incident Operations Center, of what procedures have been put in place to ensure safety to all post occupants.
(3) The Chief, Operations and Maintenance Branch, or designated representative will coordinate with the Military Police of what procedures have been established; for example, spreading of sand, barricades, etc.
b. After or Prior to Duty Hours:
(1) The Military Police will notify the designated duty lead for the O&M contractor when adverse weather conditions render post roads unsafe for vehicular traffic or other adverse weather conditions affecting post utilities or post and family housing facilities.
(2) The designated duty lead shall notify contractor personnel required to respond to emergency conditions. The on-call duty lead shall then notify the appropriate QAE depending on the type of emergency weather conditions.
c. The O&M contractor shall respond within 30 minutes of notification and provide direction and work operations in accordance with their approved plan.
UNITED STATES ARMY GARRISON FORT HUACHUCA, ARIZONA
INTERNAL PROCEDURE
ATZS-ISU PAGE 2 OF 3
April 2016 280-7
d. The appropriate QAE will monitor contractor performance and provide information to his supervisory chain.
e. The list below identifies primary and secondary roads/avenues and roads/avenues identified for shut down (shut downs per Military Police only) Contractor shall maintain roads in accordance with their approved plan.
f. Primary Roads: Secondary Roads:
| Winrow Ave Squire Ave Irwin St Hatfield St Hunt Rd Arizona St Christy Ave Allison Rd |
| Carter St Smith Ave Cushing St Cibeque St Canelo Rd Grierson Ave Boyd Ave |
Hungerford Ave Mizner Ave Johnson Rd Butler Rd Backer Rd Brainard Rd
Encl
Map
Director, Public Works