- N4008525R2639 DESIGN-BID-BUILD P-222: MQ-25 AIRCRAFT LAYDOWN FACILITIES, NAVAL STATION NORFOLK, NORFOLK, VA
- Solicitation number
- N4008525R2639
About this file
Solicitation Summary
This is a Request for Proposal (RFP) for design-bid-build construction services issued by the Naval Facilities Engineering Command (NAVFAC) Mid-Atlantic for Project P222: MQ-25 Aircraft Laydown Facilities at Naval Station Norfolk, Virginia. The solicitation number is N4008525R2639, issued January 26, 2026, with proposals due March 12, 2026 at 2:00 PM ET. The Government intends to award a firm-fixed-price construction contract with an estimated magnitude between $100 million and $250 million. Contract performance shall commence within 15 calendar days of award and be completed within 1,017 calendar days (approximately 2.8 years). The NAICS code is 236220 (Building Construction) with a small business size standard of $45 million. This is an unrestricted full and open competition solicitation.
The scope of work encompasses three primary components: (A) construction of a two-story annex to support the existing Building LP48 high bay hangar facility, featuring reinforced concrete masonry walls with maintenance shops, secured storage, Unmanned Carrier Aviation Mission Control System spaces, and weapons training facilities; (B) construction of a Ground Based Detection and Avoidance radar tower with electrical and fiber optic infrastructure connected to the Air Traffic Control tower; and (C) renovation of existing LP48 hangar with multiple one-story additions for tool room, battery charging, and RCS Shelter/Command functions, including repair of a vertical lift fabric door. The project includes environmental mitigation addressing historical airfield contamination, site preparation, utility work, grading, paving with low-impact development stormwater management, security fencing expansion, and landscape improvements, with emphasis on energy efficiency and life cycle cost optimization. Contractors must meet corporate experience requirements of $75 million minimum final construction cost on comparable projects completed within seven years; furnish performance and payment bonds equal to 100 percent of contract value; comply with Davis-Bacon wage determinations; and maintain safety management systems with demonstrated DART and TCR rates. Award will be based on best value considering technical factors (corporate experience, management approach/schedule, safety, and small business utilization equally weighted at approximately 25% each) and past performance (25%), with price evaluation at approximately 25% relative importance.
View the file
Other files
Show 40 more
Latest 50 of 56 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
(See ).
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair) IMPORTANT - The "offer" section on the reverse must be fully completed by offeror.
9. FOR
INFORMATION CALL:
NOTE: In sealed bid solicitations "offer" and "offeror" mean "bid and "bidder".
SOLICITATION
1. SOLICITATION NUMBER
5. REQUISITION/PURCHASE REQUEST NUMBER
CODE
6. PROJECT NUMBER
8. ADDRESS OFFER TO
4. CONTRACT NUMBER
7. ISSUED BY
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying number, date)
11. The contractor shall begin performance within
12a. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If "YES", indicate within how many calendar days after award in Item 12b.)
13. ADDITIONAL SOLICITATION REQUIREMENTS:
a. Sealed offers in original and
b. An offer guarantee
c. All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
d. Offers providing less than
STANDARD FORM 1442 (REV. 12/2022)
Prescribed by GSA - FAR (48 CFR) 53.236-1(d) calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
is, is not required.
local time containing offers shall be marked to show the offeror's name and address, the solicitation number, and the date and time offers are due.
(date). If this is a sealed bid solicitation, offers will be publicly opened at that time. Sealed envelopes copies to perform the work required are due at the place specified in Item 8 by (hour) award, YES NO notice to proceed. This performance period is mandatory negotiable.
calendar days and complete it within calendar days after receiving
a. NAME b. TELEPHONE NUMBER (Include area code) (NO COLLECT CALLS)
12b. CALENDAR DAYS
2. TYPE OF SOLICITATION
SEALED BID (IFB)
INVITATION FOR BID
NEGOTIATED (RFP)
REQUEST FOR PROPOSAL
3. DATE ISSUED PAGE OF PAGES
Created On:
26 Jan 2026, 19:25 PM Greenwich Mean Time
AWARD (To be completed by Government)
17. The offeror agrees to perform the work required at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement by the Government in writing within stated in Item 13d. Failure to insert any number means the offeror accepts the minimum in Item 13d.)
OFFER (Must be fully completed by offeror)
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
(The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each)
AMENDMENT
NUMBER
DATE
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)
CODE FACILITY CODE
15. TELEPHONE NUMBER (Include area code)
16. REMITTANCE ADDRESS (Include only if different than Item 14.)
20a. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)
21. ITEMS ACCEPTED:
22. AMOUNT
26. ADMINISTERED BY
30a. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print)
31c. DATE
STANDARD FORM 1442 (REV. 12/2022) BACK
31b. UNITED STATES OF AMERICA
BY
31a. NAME OF CONTRACTING OFFICER (Type or print)
29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30b. SIGNATURE 30c. DATE
28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return and deliver all items or perform all work requirements identified on this form and any continuation sheets for the consideration stated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications incorporated by reference in or attached to this contract.
copies to issuing office.) Contractor agrees to furnish
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
23. ACCOUNTING AND APPROPRIATION DATA
ITEM
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO THE UNITED STATES
CODE AT
27. PAYMENT WILL BE MADE BY
10 U.S.C. 3204(a) ( ) 41 U.S.C. 3304(a) ( )
20b. SIGNATURE 20c. OFFER DATE
Section 00 00 00 - Procurement and Contracting Requirements
DESIGN-BID-BUILD P-222: MQ-25 AIRCRAFT LAYDOWN FACILITIES, NORFOLK STATION
NORFOLK, NORFOLK, VA
Defense Priorities Allocation System (DPAS) Priority Rating: DO-C2 Date: 26 Jan 2026
N4008525R2639
Section 00 10 00 - Solicitation, Contract Line Item Number (CLIN) Schedule
Additional Information/Notes
Item Supplies/Service Quantity Unit Unit Price Amount
Base Bid - Total Price for the entire work for Project P222 line item 0001 (subtotal of line item 0001A-0001G) in accordance with the drawings and specifications, complete, but excluding work provided in another Priced line Item.
Centralized Unique Program Identification (CUPID): 000 Program Code: C20 Pricing Arrangement: Firm Fixed Price
1 Project
Option Line Item
Option Item No. 1: Price for providing Electronic Security System (ESS) equipment, testing, and associated training, but excluding work provided in another Priced line item. The ESS includes, but is not limited to, Intrusion Detection System (IDS), Access Control System (ACS), and Video Systems complete in accordance with the drawings and specifications. Equipment includes items such as Premise Control Units (PCU), central processing units, field panels, sensors, card readers, keypads, cameras, switches, video recorders, workstations, and the communication cabling connecting these devices together.Include the price for supporting permanent infrastructure under the Base Price.
Interior supporting infrastructure includes items such as conduit, junction boxes, electronic door strikes, door-hardware, mounting hardware, and power connections.
Exterior supporting infrastructure includes items such as exterior duct banks, manholes, utility poles, utility connections, and power connections.
Centralized Unique Program Identification (CUPID): 000 Program Code: C20 Pricing Arrangement: Firm Fixed Price
1 Project
Option Line Item
Option Item No. 2: AV Design Services Option- Price for providing the professional Services of a Certified Technology Specialist - Design (CTS- D) detailed in Spec Section 01 30 02.00 22
Centralized Unique Program Identification (CUPID): 000 Program Code: C20 Pricing Arrangement: Firm Fixed Price
1 Project
Option Item No. 3: Price for
Option Line Item providing Audio Visual System (A/V) Equipment, testing, and associated training in accordance with the drawings and specifications, but excluding work provided in another Priced line item for Building LP48A.
Equipment includes, but is not limited to, items such as flat panel monitors, projectors, wall input boxes, touch screens, push button control panels, video teleconferencing codecs, microphones, speakers and the communication cabling connecting these devices together. Include the price for supporting permanent infrastructure under the Base Price.
AV supporting infrastructure includes items such as conduit, junction boxes, mounting hardware, and power connections.
Centralized Unique Program Identification (CUPID): 000 Program Code: C20 Pricing Arrangement: Firm Fixed Price
1 Project
Option Line Item
Option Item No. 4: Price for providing Audio Visual System (A/V) Equipment, testing, and associated training in accordance with the drawings and specifications but excluding work provided in another Priced line item for Building LP48.
Equipment includes, but is not limited to, items such as flat panel monitors, projectors, wall input boxes, touch screens, push button control panels, video teleconferencing codecs, microphones, speakers and the communication cabling connecting these devices together. Include the price for supporting permanent infrastructure under the Base Price.
AV supporting infrastructure includes items such as conduit, junction boxes, mounting hardware, and power connections.
Centralized Unique Program Identification (CUPID): 000 Program Code: C20 Pricing Arrangement: Firm Fixed Price
1 Project
Option Line Item
Option Item No. 5: Building LP48A FF&E Price for providing work in connection with labor, material, equipment, transportation and supervision required for the Furniture, Fixtures, and Equipment (FF&E), complete in accordance with the drawings and specifications, but excluding work provided in another Priced line item.
Centralized Unique Program Identification (CUPID): 000 Program Code: C20 Pricing Arrangement: Firm Fixed Price
1 Project
Option Item No. 6: Building LP48
Option Line Item
FF&E Price for providing work in connection with labor, material, equipment, transportation and supervision required for the Furniture, Fixtures, and Equipment (FF&E), complete in accordance with the drawings and specifications, but excluding work provided in another Priced line item.
Centralized Unique Program Identification (CUPID): 000 Program Code: C20 Pricing Arrangement: Firm Fixed Price
1 Project
Option Line Item
Option Item No. 7: Unit Price for undercut of geotechnically unsuitable subgrade soils and replacement with imported structural fill material within the building and pavement limits, complete in accordance with the drawings and specifications, but excluding work provided in another line item.
Disposal of undercut excavation spoils will be paid for under CLIN 0001D.
Centralized Unique Program Identification (CUPID): 000 Program Code: C20 Pricing Arrangement: Firm Fixed Price
5,476 Project
Option Line Item
Option Item No. 8: Unit Price for demolition, excavation and disposal of buried concrete structures, utility lines and debris greater than 1/2 cubic yard in size, encountered within planned excavation limits and not identified in the Contract Documents, complete in accordance with the drawings and specifications, but excluding work provided in another line item. Note:
Pieces of buried concrete and debris encountered within the planned excavation limits smaller than 1/2 cubic yard in size are considered incidental to the work.
Centralized Unique Program Identification (CUPID): 000 Program Code: C20 Pricing Arrangement: Firm Fixed Price
1,500 Project
Option Line Item
Option Item No. 9: Unit price for removal and disposal of buried (below grade) asbestos containing pipe insulation (insulation on pipe up to 24 inches in diameter) complete in accordance with drawings and specifications, but excluding work provided in another line item.
Centralized Unique Program Identification (CUPID): 000 Program Code: C20 Pricing Arrangement: Firm Fixed Price
534 Project
Section 00 21 00 - Instructions
TABLE OF CONTENTS
1. GENERAL
1.1 GENERAL OVERVIEW OF PROCUREMENT PROCESS
1.2 GENERAL OVERVIEW OF CONTRACT
2. BASIS FOR AWARD
3. EVALUATION FACTORS FOR AWARD
4. PROPOSAL REQUIREMENTS
4.1 SITE VISIT
4.2 PROPOSAL SUBMISSION INSTRUCTIONS
4.3 PRE-PROPOSAL INQUIRIES (PPIs)
4.4 CONTRACT OPPORTUNITIES (SAM.GOV)
5. INCORPORATION OF TECHNICAL PROPOSAL
6. ATTACHMENTS: MAY BE LOCATED ON CONTRACT OPPORTUNITIES AND PIEE UNDER
ATTACHMENTS
Attachment A - Pre-Proposal Inquiry Log Template Attachment B - PIEE Vendor Access Instructions Attachment C - Construction and Design Experience Project Data Sheet Attachment D - Past Performance Questionnaire Attachment E - Historical Small Business Utilization Attachment F - Small Business Participation Commitment Attachment G - Individual Small Business Subcontracting Plan Attachment H - Price Proposal Form Attachment I - SECNAV 5212 Attachment J - ODP ML Attachment K - Class JA ML 25-30 FRCS Standardization NSN_Redacted Attachment L - JA ML-26-01 P222 MQ25 Hangar Brand Name or Equal Finishes_Redacted Attachment M - P222 Site Visit Map
Drawings and Specification Attachments provided with Solicitation:
1737012_dwg 01of02_P222 1737012_dwg 02of02_P222 1737012_spec 01of04_P222 1737012_spec 02of04_P222 1737012_spec 03of04_P222 1737012_spec 04of04_P222
*** Please note: Construction Security Plan (CSP) documents below are included within this solicitation and are CUI. These documents will need to be requested from Catharine Keeling - catharine.a.keeling.civ@us.navy.mil and will be sent via DOD Safe.
P222_LP-48A CSP V5_Redacted- 22OCT25 P222_LP-48 CSP V5 _Redacted 22OCT25 CSP Facility layout
1. GENERAL
1.1 GENERAL OVERVIEW OF PROCUREMENT PROCESS
1.1.1 This acquisition is being solicited on an unrestricted basis, with Full and Open Competition.
1.1.2 The NAICS code for this procurement is 236220 and the size standard is $45,000,000.
1.1.3 In accordance with DFARS 236.204(iii), the magnitude of construction for this project is between $100,000,000 to $250,000,000.
1.1.4 This solicitation is formatted as a Request for Proposal according to FAR Part 15. This method permits evaluation of proposals based on price competition, technical merit and other factors; permits impartial and comprehensive evaluation of offerors' proposals; permits discussions if necessary; and ensures selection of the source whose performance provides the best value to the Government.
1.2 GENERAL OVERVIEW OF CONTRACT
Description of Work:
1. This acquisition will result in the award of a firm-fixed-price (FFP) contract for construction.
2. The procurement is a design-bid-build construction project for P222 MQ-25 Aircraft Laydown Facilities Naval Station Norfolk, Norfolk, Virginia.
a. Constructs a two-story annex to support existing high bay hangar facility, Building LP48. Annex will consist of 01 and 02 spaces constructed of reinforced concrete masonry unit (CMU) walls and a combination of masonry and metal panel veneer. Annex spaces will include maintenance shops, secured storage spaces, Unmanned Carrier Aviation Mission Control System (UMCS) spaces, Weapons Training Unit (WTU) operational trainer and applied instruction space, Aerial Refueling Storage (ARS) Workcenter with overhead bridge crane, mission equipment support areas and other equipment rooms and personnel support areas. Facility includes controlled areas.
b. Constructs a Ground Based Detection and Avoidance (GBDAA) System radar tower with electrical and fiber optic tie-ins to existing installation infrastructure and/or outside plant upgrades as required with connection to Air Traffic Control (ATC) tower.
c. Renovates Existing LP48 hangar and provides multiple additions. The additions include: a one-story addition on the ground floor for the tool room, a one-story addition to the ground floor for the battery charging and storage spaces, and two one-story additions to the second floor for expansion to include the RCS Shelter and Command functions. A stair and catwalk are constructed over the existing hangar for placement of antennas supporting the MQ-25 mission, shop spaces, crew spaces, command suite, administrative areas and repair the existing high bay Vertical Lift Fabric Door (VLFD). Renovation includes plumbing, electrical, fire protection and HVAC repairs.
2. BASIS FOR AWARD
2.1 The Government reserves the right to eliminate from consideration for award any or all offers at any time prior to award of the contract; to negotiate with offerors in the competitive range; and to award the contract to the offeror submitting the proposal determined to represent the best value--the proposal most advantageous to the Government, cost/price and other factors considered.
2.2 The Government intends to evaluate proposals and award a contract without discussions with offerors (except clarifications as described in FAR 15.306(a)). The Government reserves the right to conduct discussions if the Contracting Officer later determines them to be necessary. In addition, if the Contracting Officer determines that the number of proposals that would otherwise be in the competitive range exceeds the number at which an efficient competition can be conducted, the Contracting Officer may limit the number of proposals in the competitive range to the greatest number that will permit an efficient competition among the most highly rated proposals.
2.3 The tradeoff process is selected as appropriate for this acquisition. The Government considers it to be in its best interest to allow consideration of award to other than the lowest priced offeror or other than the highest technically rated offeror.
2.4 The relative order of importance of the non-price evaluation factors is the technical factors (Factors 1, 2, 3, and 5) are of equal importance to each other and, when combined, are equal in importance to the past performance evaluation/performance confidence assessment factor (Factor 4). When the proposal is evaluated as a whole, the technical factors and past performance/ performance confidence assessment factor combined (i.e., the non-cost/price evaluation factors) are approximately equal price.
2.5 Any proposal found to have a deficiency in meeting the stated solicitation requirements or performance objectives will be considered ineligible for award, unless the deficiency is corrected through discussions. An Unacceptable rating in any of the non-cost/price factors will result in an overall rating of "Unacceptable" for the non-cost/price factors, unless corrected through discussions. Proposals may be found to have either a significant weakness or multiple weaknesses that impact either the individual factor rating or the overall rating for the proposal. The evaluation report must document the evaluation board's assessment of the identified weakness(s) and the associated risk to successful contract performance resulting from the weakness(s). This assessment must provide the rationale for proceeding to award without discussions.
3. EVALUATION FACTORS FOR AWARD
1. The solicitation requires the evaluation of price and the following non-cost/price factors:
Factor 1 - Corporate Experience Factor 2 - Management Approach and Schedule Factor 3 - Safety Factor 4 - Past Performance Factor 5 - Small Business Utilization and Participation
The distinction between corporate experience and past performance is corporate experience pertains to the types of work and volume of work completed by a contractor that are comparable to the types of work covered by this requirement, in terms of size, scope, and complexity. Past performance pertains to both the relevance of recent efforts and how well a contractor has performed on the contracts.
2. The relative order of importance of the non-price evaluation factors is the technical factors (Factors 1, 2, 3, and 5) are of equal importance to each other and, when combined, are equal in importance to the past performance evaluation/performance confidence assessment factor (Factor 4). When the proposal is evaluated as a whole, the technical factors and past performance/performance confidence assessment factor combined (i.e., the non-cost /price evaluation factors) are approximately equal price.
The importance of price will increase if the Offerors' non-cost/price proposals are considered essentially equal in terms of overall quality, or if price is so high as to significantly diminish the value of a non-cost/price proposal's superiority to the Government. Award will be made to the responsible Offeror(s) whose offer conforms to the solicitation and represents the best value to the Government, price and non-price factors considered.
3. Basis of Evaluation and Submittal Requirements for Each Factor.
Price Proposal:
(i) Solicitation Submittal Requirements:
The offeror shall submit one (1) electronic copy via PIEE of the solicitation submittal requirements identified below. The Price and Non-price proposals shall be submitted in separate files and submitted in Portable Document Format (PDF). In addition, non- price/technical information included in the price proposal will not be considered, likewise, price information included in the non-price/technical proposal will not be considered.
All required proposal documents shall be submitted in accordance with FAR 15.208.
All submissions shall include the following:
1. Executed SF1442. Offeror shall insert its company name and address in Block #14, telephone number in Block #15, acknowledge all amendments in Block #19 (if applicable), name and title of person authorized to sign in Block #20A, signature in Block #20B, and offer date in Block #20C of the SF1442. In addition, Offeror shall provide a cover page with solicitation number, solicitation title, Offeror name, address, phone number, fax number, Unique Entity Identifier (UEI), CAGE code, Federal Tax ID number, Point of Contact (POC), POC phone number, and POC email address with its proposal.
2. Completed Price Proposal Form. The Offeror is required to submit a complete Price Proposal Form that includes completion of all contract line items numbers (CLINs). Pricing information is not required to be completed under Section 00 10 00 - Solicitation Contract Form in SF 1442.
3. Bid Bond (SF-24). Offeror shall submit a bid bond (SF-24) in the amount of 20% of total project bid price for the project or $3M, whichever amount is less. The bid bond shall be in the name of the offeror identified on the SF1442.
4. SAM registration. Offeror shall ensure current registration on the SAM Website, www.sam.gov, including Annual Representations and Certifications are complete and updated for this procurement. If a Representation or Certification required by Section 00 45 00 of the RFP is not provided in SAM, include the representation or certification in your price proposal. Please also submit the representation and certification for 52.209- 13 - Violation of Arms Control Treaties or Agreements- Certification separately. It is not included in the annual representations and certifications in the System for Award Management. The Contracting Officer and/or Contract Specialist will verify the Offeror's registration in SAM only at time of submission of an offer and at the time of contract award, unless an exemption applies under FAR 4.1102 (a).
5. FAPIIS. Offeror shall ensure Federal Awardee Performance and Integrity Information System (FAPIIS) is current, accurate, and complete, as required by FAR 52.209-7, Information Regarding Responsibility Matters.
6. VETS-4212 registration. Confirmation of filing of Veterans' Employment and Training (VETS-4212) for the 2024/2025 filing cycle, if the Offeror is required to submit. Offeror shall ensure a current VETS-4212 report has been submitted to the Department of Labor (DOL) website, http://www.dol.
gov/vets/vets4212.htm. An email confirmation of submission can be requested and received by the Offeror from the DOL website and submitted in the price proposal. If the Offeror is not required to submit a report to VETS-4212, include a brief statement and justification explaining why the Offeror is not required to submit a report. Visit the VETS-4212 website for details concerning if your company is required to submit a VETS-4212 report and to request an email confirmation of submission.
7. Small Business Subcontracting Plan (Reference FAR 52.219-9 ALT II and DFARS 252.219-7003).
In accordance with FAR 19.7, all other than small businesses shall submit a Small Business Subcontracting Plan (SBSP) utilizing the template provided as Attachment G. Acceptability of the SBSP will be considered a responsibility matter. The SBSP will not be evaluated or rated by the SSEB, but reviewed by a Small Business Professional/Authorized Representative and the Contracting Officer for acceptability. The SBSP shall be negotiated and/or accepted within the time specified by the Contracting Officer. Failure to negotiate an acceptable subcontracting plan within the time limit prescribed by the Contracting Officer will render the Offeror ineligible for award of the contract. The SBSP will be incorporated into the resulting contract.
NAVFAC's command-wide small business subcontracting targets are shown below. These may be higher or lower than percentages that would represent, challenging, small business subcontracting goals for this acquisition consistent with efficient and effective performance of the contract.
These targets are based on a percentage of total planned subcontract dollars.
Small Business (SB) 40% Small Disadvantaged Business (SDB) 5% HUBZone SB 3% Woman-Owned Small Business (WOSB) 9% Service-Disabled Veteran-Owned Small Business (SDVOSB) 5%
The SBSP shall be consistent with the commitments offered in the Small Business Utilization and Participation factor. In accordance with DFARS 215.304(c)(i), when an evaluation assesses the extent that small businesses are specifically identified in proposals, those small businesses considered in the evaluation shall be listed in the SBSP.
Please note that SBSP goals and the participation rates provided in the Small Business Participation Commitment Document (SBPCD) WILL NOT be the same. The participation rates within the SBPCD are provided as percentages of the total contract value; subcontract plan goals are provided as a percentage of planned subcontracting dollars. While the percentages will differ, the types of products/services identified in the SBSP, should be the same as those products/services identified in the SBPCD. Likewise, the planned small business subcontract dollars in the SBSP will be equal to (or in some cases greater than) the extent of small business participation identified in the SBPCD.
8. Bank Reference. One (1) Signed Bank Reference demonstrating adequate financial resources. If offeror's firm has a line of credit, provide information on how many figures the offeror can borrow against the line of credit (i.e. medium 6 figures - exact line of credit is not required).
9. Financial Statements. The Offeror shall provide the latest three complete fiscal year financial statements for the prime contractor, certified by an independent accounting firm, if practicable, or signed by an authorized officer of the organization. Submit evidence of availability of working /operating capital, which will be used for the performance of the resultant contract. For Joint Venture arrangements, submit the latest three complete fiscal year financial statements for each company in the Joint Venture and discuss the financial responsibilities among the companies.
10. Facilities and Equipment. Provide a description of offeror's facilities and equipment.
11. Other Work. Provide a list of offeror's other work presently under contract.
(ii) Basis of Evaluation:
The Government will evaluate price based on the total price. Total price consists of the basic requirements and all option items (See Attachment H- Price Proposal Form). The Government intends to evaluate all options and has included the provision FAR 52.217-5, Evaluation of Options (JUL 1990) in Section 00 21 16 of the solicitation. In accordance with FAR 52.217-5, evaluation of options will not obligate the Government to exercise the option(s). Analysis will be performed by one or more of the following techniques to ensure a fair and reasonable price:
(i) Comparison of proposed prices received in response to the RFP.
(ii) Comparison of proposed prices with the IGCE.
(iii) Comparison of proposed prices with available historical information.
(iv) Comparison of market survey results.
Although required to be submitted with offeror's price proposal, Items 3 through 11 above will not be evaluated as part of the price proposal. This information will be utilized by the Government in the responsibility determination and for considering responsiveness to the solicitation requirements.
Non-price Proposal:
All submissions shall include the following:
The Offeror shall submit one (1) electronic copy via PIEE of the solicitation submittal requirements identified below. The Price and Non-price proposals shall be submitted in separate files and submitted in Portable Document Format (PDF). In addition, non- price/technical information included in the price proposal will not be considered, likewise, price information included in the non-price/technical proposal will not be considered.
All required proposal documents shall be submitted in accordance with FAR 15.208.
Offeror shall provide a cover page with solicitation number, solicitation title, Offeror name, address, phone number, fax number, Unique Entity Identifier (UEI), CAGE code, Federal Tax ID number, Point of Contact (POC), POC phone number, and POC email address with its proposal.
Refer to individual factors for page limitations. Pages that exceed indicated page limitations shall not be evaluated.
Note: If proposing as a Joint-Venture (JV), please submit the POC, UEI, and CAGE Code for each JV partner.
Factor 1 - Corporate Experience:
(i) Solicitation Submittal Requirements:
Offerors shall submit a minimum of three (3) up to a maximum of five (5) relevant construction projects that best demonstrate their experience on relevant projects similar in size, scope, and complexity to this RFP.
Experience shall be that of the Offeror, performed as a prime contractor. Experience of proposed subcontractors will not be considered.
For purposes of this evaluation, a relevant project is further defined as:
Size: A final construction cost of $75,000,000 or greater.
Scope/Complexity: New Construction of a multi-story steel framed building with concrete masonry walls.
For all submitted projects, ensure that the project description clearly provides the final construction cost and addresses how the project meets the scope /complexity requirements.
Projects submitted for the Offeror shall have been completed within the past seven (7) years from the date of issuance of this RFP. Projects which are not complete as of the date of issuance of this RFP will be considered "Not Relevant". Additionally, projects completed prior to seven (7) years from the date of issuance of this RFP will be considered "Not Relevant."
A project is defined as a construction project performed under a single task order or contract. For multiple award and indefinite delivery/indefinite quantity type contracts, the contract as a whole shall not be submitted as a project; rather, offerors shall submit the work performed under a task order as a project. The submission of a multiple award and/or indefinite delivery/indefinite quantity type contract as a whole will be considered Not
Relevant.
The attached Construction Experience Project Data Sheet (Attachment C) is MANDATORY and SHALL be used to submit project Except as specifically requested, the Government will not consider information submitted in addition to this form nor will the information.
Government consider submissions via any other medium. Individual blocks on this form may be expanded; however, total length for each project data sheet shall not exceed two (2) pages. Information beyond this page limit will not be considered.
If the Offeror is a Joint Venture (JV), relevant project experience should be submitted for projects completed by the Joint Venture entity. If the Joint Venture does not have shared experience, projects may be submitted for the Joint Venture members. Offerors are still limited to a total of five (5) projects combined. Offerors may submit experience where a member of the JV performed as a JV with another entity, but must clearly demonstrate how its work on that project met size, scope, and complexity as defined above. Likewise, Offerors that are not submitting as a JV may submit a project where it performed as a JV with another entity, but must clearly demonstrate how its work on that project met size, scope, and complexity as defined above. Offerors are still limited to a total of five (5) projects combined.
For a JV, the offeror shall submit the signed JV agreement. For an 8(a) Mentor-Protege Joint Venture, the offeror shall submit the signed U.S. Small Business Administration (SBA) Mentor-Protege approval letter and signed JV agreement.
If an Offeror is utilizing experience information of affiliates/subsidiaries/parent/LLC/LTD member companies (name is not exactly as stated on the SF1442), the proposal shall clearly demonstrate that the affiliate/subsidiary/parent firm will have meaningful involvement and clearly describe the role that firm will have in the performance of the contract. If meaningful involvement is not demonstrated, experience of the affiliate/subsidiary /parent firm will not be considered.
(ii) Basis of Evaluation:
The basis of evaluation will include the offeror's demonstrated experience and depth of experience in performing relevant construction projects as defined in the solicitation submittal requirements. The assessment of the offeror's relevant experience will be used as a means of evaluating the capability of the offeror to successfully meet the requirements of the RFP. The Government will only review five (5) projects for construction experience. Any projects submitted in excess of five (5) will not be considered. An offeror that does not submit a minimum of three (3) relevant projects as defined above will receive a rating of "Unacceptable" and will not be eligible for award.
Factor 2 - Management Approach and Schedule
(i) Solicitation Submittal Requirements:
The offeror shall submit a narrative schedule for this factor. The narrative shall not exceed ten (10) pages, 8-1/2" x 11" size. Provide the and schedule, documenting any multiple critical paths, in 11" x 17" pages and in an Adobe PDF file. There is no page limit on the schedule.
The narrative shall include, but not limited to:
1. Provide a narrative describing the proposed approach to management, for both subcontractors and your workforce, to ensure schedule adherence, early detection and correction of problems and the execution of the base bid items and all options, as referenced in the RFP.
2. Identify activities that may affect the project timeline, including other/off site work activities.
3. Describe how your firm will handle technical complexities relating to: simultaneous building construction, site utility work to include grading, installation of site utilities, concrete and asphalt paving.
4. Describe how your firm will handle unique features of work relating to each of the following work items. Specifically describe how your firm will manage and execute these unique features of work to include, if possible, named potential subcontractors or manufacturers with an established history of performing these types of work.
- RF Shielding in accordance with ICD705/CTTA requirements.
- Ignitable Liquid Drainage Floor Assembly (ILDFA) to collect spills and ILDFA discharge.
- Construction of radar tower with electrical and fiber infrastructure connected to Air Traffic Control (ATC) tower.
- Repair or installation of high bay Vertical Lift Fabric Door (VLFC).
5. Describe your plan to ensure full compliance with the requirements in the Construction Security Plan (CSP).
6. Describe how your firm will handle unforeseen problems with: material deliveries, subcontractor progress, weather, re-work, differing site conditions, and inspections relating to the subject project.
The schedule shall include, but not limited to:
1. Provide a Critical Path Method (CPM) construction schedule that illustrates your ability to achieve the schedule and meet all the requirements of the RFP (1,017 calendar days inclusive of all options, including 15 days for bond approval). The schedule shall be based on a contract award date of 21 May 2026. This date is for proposal purposes only and is not intended to indicate an anticipated/planned award date. Any proposed duration shorter than the RFP requirements will be incorporated into the contract award.
(ii) Basis of Evaluation:
Offerors will be evaluated on the extent to which they demonstrate a thorough understanding of the requirements of the RFP.
A narrative work plan that identifies areas of risk in logistics and resource management, and provides a comprehensive contingency plan that addresses mitigation of any identified risks with potential solutions, may be considered more favorably.
A schedule that proposes a realistic shorter contract duration that the required duration indicated in the RFP may be considered more favorably.
Factor 3 - Safety
The Offeror shall submit the following information: The Days Away from Work, Restricted Duty, or Job Transfer (DART) Rate; and Total Case Rate (TCR) for the specified five (5) Calendar Years (CY), as well as a safety narrative, as described further below. For a partnership or joint venture, the Offeror shall submit separate DART rates and TCR for the specified five (5) CY for each contractor who is part of the partnership/joint venture;
however, only one safety narrative is required. Any fatalities experienced within this 5-year timeframe must be explained in detail, to include root cause and corrective actions.
NOTE: DART and TCR shall not be submitted for subcontractors
1. DART Rate: Submit five (5) previous complete calendar years' [CY2021, CY2022, CY2023, CY2024, CY2025] worth of data (not an overall average). If the Offeror has no DART rate, for any year, affirmatively state so and explain why. Should a negative trend occur above moderate risk levels, an acceptable/detailed explanation is required that includes any corrective actions taken for improvement.
a. DART cases include injuries or illnesses resulting in death, days away from work, and/or restricted work or transfer to another job days beyond the day of injury/illness.
b. Calculation of DART rate: Multiply the total number of DART cases by 200,000, and then divide by the number of employee labor hours worked.
DART RATE= (Number of DART Incidents x 200,000)/(Total Number of Employee Labor Hours Worked)
2. TCR Rate: Submit five (5) previous complete calendar years' [CY2021, CY2022, CY2023, CY2024, CY2025] worth of data (not an overall average). If the Offeror has no TCR rate, for any year, affirmatively state so and explain why. Should a negative trend occur above moderate risk levels, an acceptable/detailed explanation is required that includes any corrective actions taken for improvement.
a. TCR cases include injuries or illnesses resulting in death, days away from work, restricted work or transfer to another job days beyond the day of injury/illness, medical treatment beyond first aid, or loss of consciousness.
b. Calculation of TCR rate: Multiply the total number of TCR incidents by 200,000, and then divide by the number of employee labor hours worked.
TCR RATE= (Number of TCR Incidents x 200,000)/(Total Number of Employee Labor Hours Worked)
3. Technical Approach to Safety: Submit a narrative that addresses the following:
a. Describe the Offeror' s approach to implementing and executing a Safety Management System (SMS) including Management/Leadership involvement, Employee involvement, Hazard prevention, Hazard control, Worksite analysis, and Safety and health training, to include the standard(s) used to benchmark the SMS.
b. Describe the evaluation process used to select potential subcontractors.
c. Describe the processes of how the Offeror will oversee safety compliance of subcontractors at all levels throughout performance of the contract (to include the Offeror's own in-house workforce).
d. The Technical Approach to Safety narrative shall be limited to two (2) pages.
4. The Government reserves the right to review other available sources (public/Government internal) of information. These may include but are not limited to OSHA data, NAVFAC's Contractor Incident Reporting System (CIRS), Contractor Performance Assessment Reporting System (CPARS), Electronic Contract Management System (eCMS), etc.
(ii) Basis of Evaluation:
The Government is seeking to determine that the Offeror has consistently demonstrated a commitment to safety and that the Offeror plans to properly manage and implement safety procedures for itself and its subcontractors. The evaluation will collectively consider the DART rate, TCR rate, Technical Approach to Safety, and other sources of information available to the Government as part of such collective evaluation. The board will evaluate the DART rates and TCR rates to determine if the Offeror has demonstrated a history of safe work practices taking into account any negative trends and extenuating circumstances that impact the rating.
1. DART Rate: The board will evaluate trends over the last five years considering changes that take it from one risk level (or more) to the next up or down. Negative trends occurring above moderate risk levels require the Offeror to provide a detailed explanation that includes any corrective actions taken for improvement.
a. Missing data without an explanation is considered a deficiency.
b. Declining trends that push the risk levels from Moderate Risk (MR) or higher to Low Risk (LR) or Very Low Risk (VLR) would indicate a strength.
c. An increasing DART rate trend could be considered a weakness (i.e. MR or better to High Risk (HR) or Extremely High Risk EHR)) if an acceptable explanation is not provided for any trends that rise above Moderate.
d. This chart correlates the DART rate to the level of risk:
Risk DART Rate Very Low Risk: Less Than 1.0 Low Risk: From 1.0 to 1.99 Moderate Risk: From 2.0 to 2.99 High Risk: From 3.0 to 4.0 Extremely High Risk: Greater than 4.0
2. TCR Rate: The board will evaluate trends over the last five years considering changes that take it from one risk level (or more) to the next up or down. Negative trends occurring above moderate risk levels require the Offeror to provide a detailed explanation that includes any corrective actions taken for improvement.
a. Missing data without an explanation is considered a deficiency.
b. Declining trends that push the risk levels from Moderate Risk (MR) or higher to Low Risk (LR) or Very Low Risk (VLR) would indicate a strength.
c. An increasing TCR rate trend could be considered a weakness (i.e. MR or better to High Risk (HR) or Extremely High Risk EHR)) if an acceptable explanation is not provided for any trends that rise above Moderate.
d. This chart correlates the TCR rate to the level of risk:
Risk TCR Rate Very Low Risk: Less Than 2.49 Low Risk: From 2.5 to 3.49 Moderate Risk: From 3.5 to 4.49 High Risk: From 4.5 to 5.99 Extremely High Risk: Greater than 6.0
3. The Technical Approach to Safety Narrative. To determine the degree to which the Offeror:
a. Describes a viable SMS that addresses elements; such as Management/Leadership involvement, Employee involvement, Hazard prevention, Hazard control, Worksite analysis, and Safety and health training, to include the standard(s) used to benchmark the SMS.
b. Describes a methodical process of evaluating subcontractor's safety performance in their selection process.
c. Describes a logical management plan to hold themselves and their subcontractors accountable for adhering to the safety requirements of the contract.
d. The Technical Approach to Safety narrative shall be limited to two (2) pages. Information on pages beyond this will not be considered.
4. The Government reserves the right to review other available sources (public/Government internal) of information. These may include but are not limited to OSHA data, NAVFAC's Contractor Incident Reporting System (CIRS), Contractor Performance Assessment Reporting System (CPARS), Electronic Contract Management System (eCMS), etc.
Factor 4 - Past Performance
(i) Solicitation Submittal Requirements:
Recent, relevant projects are determined within the requirements for Factor 1, Corporate Experience.
If a completed Contractor Performance Assessment Reporting System (CPARS) evaluation is available, it shall be submitted with the proposal for each project included in Factor 1. The offeror shall include all completed CPARS evaluations (interim and final) for a project. If there is not a completed CPARS evaluation, the Past Performance Questionnaire (PPQ) included in the solicitation is provided for the offeror or its team members to submit to the client for each project the offeror includes in its proposal for Factor 1 Corporate Experience. AN OFFEROR SHALL NOT SUBMIT
A PPQ WHEN A COMPLETED CPARS IS AVAILABLE.
If a CPARS evaluation is not available, completed PPQs should be submitted with your proposal. If the Offeror is unable to obtain a completed PPQ from a client for a project(s) before proposal closing date, the Offeror should complete and submit with the proposal the first page of the PPQ (Attachment D), which will provide contract and client information for the respective project(s). Offerors should ensure correct phone numbers and email addresses are provided for the client point of contact. Offerors should follow-up with clients/references to ensure timely submittal of questionnaires. If the client requests, questionnaires may be submitted directly to the Government's point of contact, Catharine Keeling , via email at catharine.a.keeling.civ@us.navy.mil prior to proposal closing date. Offerors shall not incorporate by reference into their proposal PPQs or CPARS previously submitted for other RFPs. However, this does not preclude the Government from utilizing previously submitted PPQ information in the past performance evaluation.
Offerors may provide any information on problems encountered and the corrective actions taken on projects submitted under Factor 1 - Corporate Experience. Offerors may also address any adverse past performance issues. Such explanations shall not exceed four (4) pages in total. Information beyond this page limitation will not be considered.
Sources of Past Performance Information for evaluation that may be used are as follows:
- Past performance information provided by the offeror, as solicited;
- Past performance information obtained from questionnaires tailored to the circumstances of the acquisition; and
- Past performance information obtained from any other sources available to the Government, to include, but not limited to, Contractor Performance Assessment Reporting System (CPARS), Federal Awardee Performance and Integrity Information System (FAPIIS), Electronic Subcontract Reporting System (eSRS), or other databases; the Defense Contract Management Agency; and interviews with Program Managers, Contracting Officers, and Fee Determining Officials.
While the Government may elect to consider data from other sources, the burden of providing detailed, current, accurate and complete past performance information rests with the Offeror.
A copy of the blank Past Performance Questionnaire to be used for requesting client references is included as Attachment D.
The Government reserves the right to contact references for verification or additional information. The Government's inability to contact any of the Offeror's references or the references' unwillingness to provide the information requested may affect the Government's evaluation of this factor.
(ii) Basis of Evaluation:
This evaluation focuses on how well the Offeror performed on the projects submitted under Factor 1 - Corporate Experience and past performance on other projects currently documented in known sources. The Government will consider the currency and relevance of the information, the source of the information, context of the data, and general trends in Contractor's performance. In the case of Offerors for which there is no information on past performance, or where past performance information is not available or so sparse that no meaningful assessment can be performed, the Offeror may not be evaluated favorably or unfavorably, and will instead receive a "Neutral" rating (See FAR 15.305(a)(2)(iv)). The Government may determine that a "Substantial Confidence" or "Satisfactory Confidence" past performance rating is worth more than a "Neutral Confidence" past performance rating in a best value tradeoff as long as the determination is consistent with stated selection criteria.
The Government will consider the degree to which past performance evaluations and all other past performance information reviewed by the Government (e.g., CPARS, Federal Awardee Performance and Integrity Information System (FAPIIS), Electronic Subcontract Reporting System (eSRS), performance recognition documents, and information obtained from any other source) reflect a trend of satisfactory performance considering:
- A pattern of successful completion of tasks;
- A pattern of deliverables that are timely and of good quality;
- pattern of cooperativeness and teamwork with the Government at all levels (task managers, contracting officers, auditors, etc.); and
- Recency of tasks performed that are identical to, similar to, or related to the task at hand.
Factor 5 - Small Business Utilization and Participation:
It is the policy of the Government to provide maximum practicable opportunities in its acquisitions to Small Business (SB) concerns, including Small Disadvantaged Business (SDB), Woman-Owned Small Business (WOSB), Historically Underutilized Business Zone Small Business (HUBZone SB), Veteran-Owned Small Business (VOSB), Service-Disabled Veteran-Owned Small Business (SDVOSB), and other small business concerns. Further, it is the policy of the Government that such concerns will have the maximum practicable opportunity to participate in contract performance consistent with its efficient performance.
This Factor assesses both the historical achievements in utilizing small business concerns and the proposed small business participation commitment for this requirement. The offeror is required to demonstrate its previous commitment to SBs through its record of past utilization of SBs and the level of commitment to small business if awarded a contract under this solicitation.
(i) Solicitation Submittal Requirements:
1. Offerors (large, non-profits, small businesses) shall use Attachment E (Historical Small Business Utilization) to demonstrate their All AND historical utilization of SBs. Each project submitted under Factor 1, Corporate Experience, shall be included on Attachment E.