Attachment E- Historical Small Business Utilization.docx

DOCX document 45 KB Posted

Attached to
N4008525R2639 DESIGN-BID-BUILD P-222: MQ-25 AIRCRAFT LAYDOWN FACILITIES, NAVAL STATION NORFOLK, NORFOLK, VA
Solicitation number
N4008525R2639
Issued by

About this file

This is a Historical Small Business Utilization form (Attachment E) that must be completed by all offerors—both large and small businesses—to support evaluation of Factor 5 (Small Business Utilization and Participation) for solicitation N4008525R2639, a Design-Bid-Build project for MQ-25 Aircraft Laydown Facilities at Naval Station Norfolk, Virginia. The form requires offerors to document historical small business utilization and achievements for up to five projects submitted under Factor 1 (Corporate Experience), with all percentages rounded to the nearest tenth of a percent and presented only in the prescribed format.

For each project, offerors must complete the Project Details section identifying the contract or task order number, project title, business size (large or small), performance role (prime contractor, subcontractor, or JV member), and whether a subcontracting plan was required. The form then requires completion of an Actual column (mandatory for all projects) and a Goal column (where applicable), documenting total project dollar value, self-performed value, subcontracted value, and breakdown of subcontracting by category including Small Business Concerns, Large Business Concerns, Small Disadvantaged Businesses, Women-Owned Small Businesses, HUBZone Small Businesses, Veteran-Owned Small Businesses, and Service-Disabled Veteran-Owned Small Businesses. Offerors must provide explanations for any unmet goals and for projects with zero small business subcontracting achievement; simply acknowledging missed goals is insufficient. The form provides five identical project templates and explicitly prohibits attachments, addendums, or alternative formats.

View the file

Other files

File Type Posted
Attachment G Individual Small Business Subcontracting Plan.docx DOCX document
Attachment F Small Business Participation Commitment.docx DOCX document
JA ML2650 25R2639 P222 ILDFA Redacted.pdf PDF
Solicitation Amendment N4008525R26390008 SF 30.pdf PDF
K3237099 LP-48 HazMat Report 3.5.26 - signed.pdf PDF
01 31 23.13 20.pdf PDF
Amendment 0007 Continuation Sheet.pdf PDF
Solicitation Amendment N4008525R26390007 SF 30.pdf PDF
REGISTER.pdf PDF
TABLE OF CONTENTS.pdf PDF
13 49 20.00 10.pdf PDF
Solicitation Amendment N4008525R26390006 SF 30.pdf PDF
P222_1737012_01 91 00.15 22.pdf PDF
Crane - LP48 1-DATA SHEET.pdf PDF
P222_1737012_Geotech Report.pdf PDF
P222_1737012_28 31 76.pdf PDF
Attachment H - Price Proposal Form_rev1.pdf PDF
P222_1737012_Drawings_volume II_Rev 001_SIGNED.pdf PDF
Solicitation Amendment N4008525R26390005 SF 30.pdf PDF
P222_1737012_04 20 00.pdf PDF
Amendment 0005 Continuation Sheet.pdf PDF
P222_1737012_32 13 13.06.pdf PDF
P222_1737012_09 29 00.pdf PDF
P222_1737012_07 60 00.pdf PDF
FY26 Naval Station Norfolk Utility Costs.pdf PDF
P222_1737012_07 21 13.pdf PDF
P222_1737012_REGISTER.pdf PDF
P222_1737012_Drawings_volume I_Rev 001_SIGNED.pdf PDF
P222_1737012_13 34 20.pdf PDF
Crane - LP48 2-DATA SHEET.pdf PDF
Solicitation Amendment N4008525R26390004 SF 30.pdf PDF
JA ML2623 25R2639 P222 ASSA Abloy Redacted.pdf PDF
JA ML2624 25R2639 P222 SRG RF Shielding Redacted.pdf PDF
26R2639 P222 Site Visit Log.pdf PDF
Solicitation Amendment N4008525R26390003 SF 30.pdf PDF
Solicitation Amendment N4008525R26390002 SF 30.pdf PDF
Solicitation Amendment N4008525R26390001 SF 30.pdf PDF
Attachment B - PIEE Vendor Access Instructions.pdf PDF
1737012_dwg 02of02_P222.pdf PDF
Attachment M - P222 Site Visit Map.pdf PDF
1737012_spec 01of04_P222.pdf PDF
1737012_dwg 01of02_P222.pdf PDF
Attachment C- Construction Experience Project Data.docx DOCX document
Attachment D- Past Performance Questionnaire.docx DOCX document
Attachment H - Price Proposal Form.pdf PDF
Attachment G- Individual Small Business Subcontracting Plan.docx DOCX document
1737012_spec 04of04_P222.pdf PDF
Attachment F- Small Business Participation Commitment.docx DOCX document
Attachment L - JA ML-26-01 P222 MQ25 Hangar Brand Name or Equal Finishes_Reda.pdf PDF
1737012_spec 03of04_P222.pdf PDF
Show 40 more

Latest 50 of 56 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DBB P222 MQ-25 Aircraft Laydown FacilitiesN40085-25-R-2639
Norfolk, VirginiaAttachment E

ATTACHMENT E

HISTORICAL SMALL BUSINESS UTILIZATION

N4008525R2639

This form is to be completed by ALL offerors (both large AND small businesses) in order to provide supporting information for the evaluation of Factor 5, Small Business Utilization and Participation. Attachment E documents the offeror’s historical small business utilization and achievements for each project submitted under Factor 1, Corporate Experience. Round all percentages to the nearest tenth of a percent (i.e., include only 1 number after the decimal point).

Information provided in a different format and/or on a form created by the offeror will not be evaluated. Attachments or addendums to Attachment E will not be evaluated. Only complete Attachment E. Offerors are permitted to expand portions of the form, as needed, to provide sufficient response.

INSTRUCTIONS FOR COMPLETING ATTACHMENT E:

· Complete the “PROJECT DETAILS” section for each Project submitted under Factor 1, Corporate Experience.

· Include contract or task order number; project title; the offeror’s business size; whether the contract was performed as a prime, subcontractor, or JV member; and whether a subcontracting plan was required.

· Complete the “ACTUAL” column (required for all projects regardless of whether goals were established)

· Enter dollar values actually subcontracted for each of the categories listed.

· Provide actual percentages calculated as a percentage of total subcontract value, unless goals were calculated as a percentage of total contract value.

· Complete the “GOAL” column - Enter goals, if applicable.

· If the project was a task order and no goals were established at the task order level, only complete the “ACTUAL” column. Goals for the overarching IDIQ contract should not be included in the “GOAL” column for task orders.

· Goals shall be included for standalone contracts when established.

· Goals can be entered as a percentage of total subcontract value or total contract value based on how the goals were established in the contract award.

· If goals were not established for the project submitted, or if goals were not established for a specific socioeconomic category, check N/A where applicable. The N/A block does not apply to the “ACTUAL” column, as actual subcontracted values are required for ALL projects, regardless of whether goals were established.

· If a goal was unmet for a Project, complete the section below titled “TO BE COMPLETED AS REQUIRED” under item #1.

· Explanation is required for each unmet goal.

· Item #1 is to be completed for each Project with unmet goal(s).

· If a Project has no small business subcontracting achievement (i.e.: $0 subcontracting in (d)), complete the “TO BE COMPLETED AS REQUIRED” under item #2.

· Item #2 is to be addressed for each Project with no small business subcontracting achievement.

· Enter zeroes (0) where applicable.

DEFINITION OF TERMS IN ATTACHMENT E:

· Total Project Dollar Value: the total contract or task order value; this is the actual value of the contract or task order, rather than a “Not To Exceed” dollar value on an IDIQ type contract.

· Total Self-Performed Value: the contract or task order dollar amount performed by the prime contractor, subcontractor or JV.

· Total Subcontract Value: the dollar amount of the contract or task order performed by subcontractors.

PROJECT DETAILS: Project #1

Contract/Project Number/Task Order Number:

Project Title:

Offeror Size: Large Business |_| Small Business |_|

Performed as: Prime Contractor |_| Subcontractor |_| JV Member |_|

Subcontracting Plan Required: |_| Yes |_| No

ACTUAL
GOAL

(if applicable)

1. Total Project Dollar Value: $
Whole Dollars
Percent of line (a) or (c)
Whole Dollars
Percent of line (a) or (c)
N/A

1. Total Self-Performed Value: $

1. Total Subcontracted Value: $

SUBCONTRACTING BREAKDOWN:

(d) Small Business Concerns (Includes overall SB subcontracting and subcontracting values from f-j below)
$
%
$
%
|_|
(e) Large Business Concerns
$
%
$
%
|_|
(f) Small Disadvantaged Business Concerns (SDB)
$
%
$
%
|_|
(g) Women-Owned Small Business Concerns (WOSB)
$
%
$
%
|_|
(h) HUBZone Small Business Concerns
$
%
$
%
|_|
(i) Veteran-Owned Small Business Concerns (VOSB)
$
%
$
%
|_|
(j) Service-Disabled Veteran-Owned Small Business Concerns (SDVOSB)
$
%
$
%
|_|

TO BE COMPLETED AS REQUIRED:

1. Provide an explanation for each unmet goal. Simply acknowledging that a goal was missed is not considered an adequate explanation:

1. Provide an explanation for no small business subcontracting achievement (i.e.: $0 subcontracting in (d)) (if applicable):

PROJECT DETAILS: Project #2

Project Title:

Offeror Size: Large Business |_| Small Business |_|

Performed as: Prime Contractor |_| Subcontractor |_| JV Member |_|

Subcontracting Plan Required: |_| Yes |_| No

ACTUAL
GOAL

(if applicable)

1. Total Project Dollar Value: $
Whole Dollars
Percent of line (a) or (c)
Whole Dollars
Percent of line (a) or (c)
N/A

1. Total Self-Performed Value: $

1. Total Subcontracted Value: $

SUBCONTRACTING BREAKDOWN:

(d) Small Business Concerns (Includes overall SB subcontracting and subcontracting values from f-j below)
$
%
$
%
|_|
(e) Large Business Concerns
$
%
$
%
|_|
(f) Small Disadvantaged Business Concerns (SDB)
$
%
$
%
|_|
(g) Women-Owned Small Business Concerns (WOSB)
$
%
$
%
|_|
(h) HUBZone Small Business Concerns
$
%
$
%
|_|
(i) Veteran-Owned Small Business Concerns (VOSB)
$
%
$
%
|_|
(j) Service-Disabled Veteran-Owned Small Business Concerns (SDVOSB)
$
%
$
%
|_|

1. Provide an explanation for each unmet goal. Simply acknowledging that a goal was missed is not considered an adequate explanation:

1. Provide an explanation for no small business subcontracting achievement (i.e.: $0 subcontracting in (d)) (if applicable):

PROJECT DETAILS: Project #3

Project Title:

Offeror Size: Large Business |_| Small Business |_|

Performed as: Prime Contractor |_| Subcontractor |_| JV Member |_|

Subcontracting Plan Required: |_| Yes |_| No

ACTUAL
GOAL

(if applicable)

1. Total Project Dollar Value: $
Whole Dollars
Percent of line (a) or (c)
Whole Dollars
Percent of line (a) or (c)
N/A

1. Total Self-Performed Value: $

1. Total Subcontracted Value: $

SUBCONTRACTING BREAKDOWN:

(d) Small Business Concerns (Includes overall SB subcontracting and subcontracting values from f-j below)
$
%
$
%
|_|
(e) Large Business Concerns
$
%
$
%
|_|
(f) Small Disadvantaged Business Concerns (SDB)
$
%
$
%
|_|
(g) Women-Owned Small Business Concerns (WOSB)
$
%
$
%
|_|
(h) HUBZone Small Business Concerns
$
%
$
%
|_|
(i) Veteran-Owned Small Business Concerns (VOSB)
$
%
$
%
|_|
(j) Service-Disabled Veteran-Owned Small Business Concerns (SDVOSB)
$
%
$
%
|_|

1. Provide an explanation for each unmet goal. Simply acknowledging that a goal was missed is not considered an adequate explanation:

1. Provide an explanation for no small business subcontracting achievement (i.e.: $0 subcontracting in (d)) (if applicable):

PROJECT DETAILS: Project #4

Project Title:

Offeror Size: Large Business |_| Small Business |_|

Performed as: Prime Contractor |_| Subcontractor |_| JV Member |_|

Subcontracting Plan Required: |_| Yes |_| No

ACTUAL
GOAL

(if applicable)

1. Total Project Dollar Value: $
Whole Dollars
Percent of line (a) or (c)
Whole Dollars
Percent of line (a) or (c)
N/A

1. Total Self-Performed Value: $

1. Total Subcontracted Value: $

SUBCONTRACTING BREAKDOWN:

(d) Small Business Concerns (Includes overall SB subcontracting and subcontracting values from f-j below)
$
%
$
%
|_|
(e) Large Business Concerns
$
%
$
%
|_|
(f) Small Disadvantaged Business Concerns (SDB)
$
%
$
%
|_|
(g) Women-Owned Small Business Concerns (WOSB)
$
%
$
%
|_|
(h) HUBZone Small Business Concerns
$
%
$
%
|_|
(i) Veteran-Owned Small Business Concerns (VOSB)
$
%
$
%
|_|
(j) Service-Disabled Veteran-Owned Small Business Concerns (SDVOSB)
$
%
$
%
|_|

1. Provide an explanation for each unmet goal. Simply acknowledging that a goal was missed is not considered an adequate explanation:

1. Provide an explanation for no small business subcontracting achievement (i.e.: $0 subcontracting in (d)) (if applicable):

PROJECT DETAILS: Project #5

Project Title:

Offeror Size: Large Business |_| Small Business |_|

Performed as: Prime Contractor |_| Subcontractor |_| JV Member |_|

Subcontracting Plan Required: |_| Yes |_| No

ACTUAL
GOAL

(if applicable)

1. Total Project Dollar Value: $
Whole Dollars
Percent of line (a) or (c)
Whole Dollars
Percent of line (a) or (c)
N/A

1. Total Self-Performed Value: $

1. Total Subcontracted Value: $

SUBCONTRACTING BREAKDOWN:

(d) Small Business Concerns (Includes overall SB subcontracting and subcontracting values from f-j below)
$
%
$
%
|_|
(e) Large Business Concerns
$
%
$
%
|_|
(f) Small Disadvantaged Business Concerns (SDB)
$
%
$
%
|_|
(g) Women-Owned Small Business Concerns (WOSB)
$
%
$
%
|_|
(h) HUBZone Small Business Concerns
$
%
$
%
|_|
(i) Veteran-Owned Small Business Concerns (VOSB)
$
%
$
%
|_|
(j) Service-Disabled Veteran-Owned Small Business Concerns (SDVOSB)
$
%
$
%
|_|

1. Provide an explanation for each unmet goal. Simply acknowledging that a goal was missed is not considered an adequate explanation:

1. Provide an explanation for no small business subcontracting achievement (i.e.: $0 subcontracting in (d)) (if applicable):

File details come from the government source that posted it. Updated .