1737012_spec 04of04_P222.pdf
PDF 2 MB Posted
- Attached to
- N4008525R2639 DESIGN-BID-BUILD P-222: MQ-25 AIRCRAFT LAYDOWN FACILITIES, NAVAL STATION NORFOLK, NORFOLK, VA
- Solicitation number
- N4008525R2639
About this file
This file is a comprehensive Unified Facilities Guide Specification (UFGS) document for the design-bid-build P-222 MQ-25 Aircraft Laydown Facilities project at Naval Station Norfolk, Virginia. The specifications encompass extensive technical requirements across multiple construction divisions including site preparation, earthwork, concrete work, structural elements, mechanical and electrical systems, and telecommunications infrastructure necessary for the aircraft maintenance facility.
The specifications detail requirements for numerous construction elements including geotextile materials, excavation and fill operations, chemical termite control, precast and concrete-filled steel piles, cold milling asphalt paving, rigid pavement sealing, landscape establishment, concrete curbs and gutters, pavement markings, high-security fencing, sodding, leak detection systems, water utility distribution, sanitary sewerage, stormwater utilities, fuel systems piping, fuel storage tanks, underground electrical distribution, and telecommunications outside plant infrastructure. Key materials and performance standards are referenced from industry standards including ASTM, AWS, AWWA, NFPA, and IEEE specifications. The document establishes submittal requirements including shop drawings, product data, test reports, and certificates of compliance; quality control procedures with specific testing protocols and acceptance criteria; and field execution requirements including installation procedures, inspection protocols, and performance testing. All work must comply with federal environmental regulations, safety standards, and military specifications relevant to naval facilities construction. The contractor must obtain necessary permits, provide qualified personnel certifications, and maintain comprehensive record documentation throughout the construction process.
View the file
Other files
Show 40 more
Latest 50 of 56 listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
WORK ORDER NO.
At the
PREPARED BY:
Architectural: Mechanical:
Civil: Electrical:
Structural:
APPROVED BY:
Specifications:
For Commander, NAVFAC:
Date:
Submitted By: Date:
Telecomm: Donald Andrew Elliott, RCDD, PMP
7/16/2025
7/16/2025
THIS PAGE INTENTIONALLY LEFT BLANK
FY 24 MCON Project P-222 eProject Work Order No: 1737012 MQ-25 Aircraft Laydown Facilities Naval Station, Norfolk, Virginia
PROJECT TABLE OF CONTENTS
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
00 01 15 02/24 LIST OF DRAWINGS
DIVISION 01 - GENERAL REQUIREMENTS
01 11 00 02/24 SUMMARY OF WORK
01 14 00 11/22, CHG 2: 05/24 WORK RESTRICTIONS
01 20 00 11/20, CHG 3: 02/23 PRICE AND PAYMENT PROCEDURES
01 30 00 11/20, CHG 3: 08/23 ADMINISTRATIVE REQUIREMENTS
01 30 02.00 22 05/23 DESIGN, PROCUREMENT, AND INSTALLATION
OF AUDIOVISUAL EQUIPMENT
01 32 17.00 20 11/23, CHG 1: 08/24 COST-LOADED NETWORK ANALYSIS SCHEDULES
(NAS)
01 33 00 08/18, CHG 4: 02/21 SUBMITTAL PROCEDURES
01 33 29 02/21 SUSTAINABILITY REQUIREMENTS AND
REPORTING
01 35 26 05/24 GOVERNMENTAL SAFETY REQUIREMENTS
01 42 00 05/24 SOURCES FOR REFERENCE PUBLICATIONS
01 45 00 08/23, CHG 1: 05/24 QUALITY CONTROL
01 45 35 05/24 SPECIAL INSPECTIONS
01 50 00 11/20, CHG 2: 08/22 TEMPORARY CONSTRUCTION FACILITIES AND
CONTROLS
01 57 19 08/22 TEMPORARY ENVIRONMENTAL CONTROLS
01 58 00 08/19, CHG 5: 08/22 PROJECT IDENTIFICATION
01 74 19 02/19, CHG 3: 11/21 CONSTRUCTION WASTE MANAGEMENT AND
DISPOSAL
01 78 00 05/19, CHG 1: 08/21 CLOSEOUT SUBMITTALS
01 78 23 05/23 OPERATION AND MAINTENANCE DATA
01 78 24.00 20 05/23, CHG 1: 11/23 FACILITY DATA WORKBOOK (FDW)
01 78 30.00 22 01/23 GIS DATA DELIVERABLES
01 91 00.15 05/23, CHG 2: 11/23 BUILDING COMMISSIONING
01 91 19 05/2023 BUILDING ENCLOSURE COMMISSIONING
DIVISION 02 - EXISTING CONDITIONS
02 41 00 08/22 DEMOLITION
02 83 00 11/18 LEAD REMEDIATION
02 84 16 11/22 HANDLING OF LIGHTING BALLASTS AND
LAMPS CONTAINING PCBs AND MERCURY
DIVISION 03 - CONCRETE
03 30 00 02/19, CHG 8: 05/24 CAST-IN-PLACE CONCRETE
03 42 13.00 10 05/16 PLANT-PRECAST CONCRETE PRODUCTS FOR
BELOW GRADE CONSTRUCTION
DIVISION 04 - MASONRY
04 20 00 11/15, CHG 2: 05/19 UNIT MASONRY
DIVISION 05 - METALS
05 05 20 05/22 POST-INSTALLED CONCRETE AND MASONRY
ANCHORS
05 12 00 08/18, CHG 2: 05/21 STRUCTURAL STEEL
05 21 00 05/15, CHG 1: 08/18 STEEL JOIST FRAMING
PROJECT TABLE OF CONTENTS Page 1
05 30 00 05/15, CHG 2: 08/18 STEEL DECKS
05 40 00 05/15, CHG 1: 08/18 COLD-FORMED METAL FRAMING
05 50 13 08/24 MISCELLANEOUS METAL FABRICATIONS
05 51 00 08/23 METAL STAIRS
05 51 33 02/16, CHG 2: 02/18 METAL LADDERS
05 52 00 08/23 METAL RAILINGS
05 73 13 08/23 GLAZED DECORATIVE METAL RAILINGS
DIVISION 06 - WOOD, PLASTICS, AND COMPOSITES
06 10 00 08/16, CHG 2: 11/18 ROUGH CARPENTRY
06 41 16.00 10 08/10, CHG 1: 11/18 PLASTIC-LAMINATE-CLAD ARCHITECTURAL
CABINETS
06 61 16 08/20 SOLID SURFACING FABRICATIONS
06 73 01 08/23 FIBERGLASS REINFORCED PLASTIC (FRP)
GRATING
DIVISION 07 - THERMAL AND MOISTURE PROTECTION
07 11 13 08/23 BITUMINOUS DAMPPROOFING
07 13 53 02/16, CHG 1: 08/17 ELASTOMERIC SHEET WATERPROOFING
07 21 13 08/23 BOARD AND BLOCK INSULATION
07 21 16 08/23 MINERAL FIBER BLANKET INSULATION
07 22 00 02/16, CHG 3: 11/18 ROOF AND DECK INSULATION
07 22 70 12/24 STANDING SEAM METAL ROOF ANCHOR
07 26 23.19 22 11/16 BROWNFIELD MEMBRANE SYSTEMS
07 27 10 08/23 BUILDING AIR BARRIER SYSTEM
07 27 19.01 08/23 SELF-ADHERING AIR BARRIERS
07 27 26 08/23 FLUID-APPLIED MEMBRANE AIR BARRIERS
07 42 13 05/11, CHG 2: 02/18 METAL WALL PANELS
07 42 63 05/11, CHG 4: 08/20 FABRICATED WALL PANEL ASSEMBLIES
07 52 00 05/12, CHG 5: 11/19 MODIFIED BITUMINOUS MEMBRANE ROOFING
07 60 00 08/23 FLASHING AND SHEET METAL
07 61 14.00 20 08/16, CHG 1: 08/18 STEEL STANDING SEAM ROOFING
07 81 00 02/11 SPRAY-APPLIED FIREPROOFING
07 84 00.00 22 07/24 FIRESTOPPING
07 92 00 08/23 JOINT SEALANTS
DIVISION 08 - OPENINGS
08 11 13 08/20 STEEL DOORS AND FRAMES
08 14 00 08/16, CHG 1: 08/18 WOOD DOORS
08 31 00 05/17, CHG 1: 08/18 ACCESS DOORS AND PANELS
08 33 13 05/09, CHG 2: 11/12 COILING COUNTER DOORS
08 33 23 08/20, CHG 1: 02/22 OVERHEAD COILING DOORS
08 34 16.20 08/21, CHG 2: 08/24 VERTICAL LIFT FABRIC DOORS
08 34 73 11/19, CHG 1: 02/21 SOUND CONTROL DOOR ASSEMBLIES
08 41 13 08/18, CHG 1: 08/18 ALUMINUM-FRAMED ENTRANCES AND
STOREFRONTS
08 44 00 05/19 CURTAIN WALL AND GLAZED ASSEMBLIES
08 60 45 08/20 TRANSLUCENT PANELS
08 71 00 02/16, CHG 4: 02/22 DOOR HARDWARE
08 81 00 05/19 GLAZING
08 91 00 08/20 METAL WALL LOUVERS
DIVISION 09 - FINISHES
09 22 00 02/10, CHG 2: 08/18 SUPPORTS FOR PLASTER AND GYPSUM BOARD
09 29 00 08/16, CHG 4: 02/20 GYPSUM BOARD
PROJECT TABLE OF CONTENTS Page 2
09 30 10 08/20 CERAMIC, QUARRY, AND GLASS TILING
09 51 00 08/20 ACOUSTICAL CEILINGS
09 62 38 08/17, CHG 1: 08/18 STATIC-CONTROL FLOORING
09 65 00 08/10, CHG 3: 08/18 RESILIENT FLOORING
09 67 23.13 11/19 STANDARD RESINOUS FLOORING
09 67 23.16 02/21 FUEL RESISTIVE RESINOUS FLOORING,
5-COAT SYSTEM
09 68 00 11/17, CHG 2: 08/20 CARPETING
09 69 13 11/15, CHG 1: 08/18 RIGID GRID ACCESS FLOORING
09 84 33 11/24 SOUND-ABSORBING WALL UNITS
09 84 36 11/24 SOUND-ABSORBING CEILING UNITS
09 90 00 02/21 PAINTS AND COATINGS
09 96 00 11/14 HIGH-PERFORMANCE COATINGS
DIVISION 10 - SPECIALTIES
10 11 00 08/20 VISUAL DISPLAY UNITS
10 14 00.10 08/17, CHG 1: 11/18 EXTERIOR SIGNAGE
10 14 00.20 08/20 INTERIOR SIGNAGE
10 21 13 08/20 TOILET COMPARTMENTS
10 21 23.16 08/24 CUBICLE TRACK AND HARDWARE
10 26 00 08/20 WALL AND DOOR PROTECTION
10 28 13 08/20 TOILET ACCESSORIES
10 44 16 11/19 FIRE EXTINGUISHERS
10 51 13 05/11 LOCKERS
DIVISION 11 - EQUIPMENT
11 66 00 01/23 HIGH BAY DIVIDER CURTAIN EQUIPMENT
DIVISION 12 - FURNISHINGS
12 00 01.00 20 02/23 FURNITURE, FIXTURES AND EQUIPMENT
(FF&E) PACKAGE
12 22 00 08/16, CHG 1: 08/18 CURTAINS AND DRAPES
12 24 13 08/20 ROLLER WINDOW SHADES
12 48 13 08/23 ENTRANCE FLOOR MATS AND FRAMES
DIVISION 13 - SPECIAL CONSTRUCTION
13 34 20 12/24 PREFABRICATED STEEL BUILDINGS
13 49 20.00 10 10/07 RFI SHIELDING
13 50 00 09/22 IGNITABLE LIQUID DRAINAGE FLOOR
ASSEMBLY, FIRE PROTECTION
DIVISION 14 - CONVEYING EQUIPMENT
14 24 13 05/16 HYDRAULIC FREIGHT ELEVATORS
DIVISION 21 - FIRE SUPPRESSION
21 13 13 08/20 WET PIPE SPRINKLER SYSTEMS, FIRE
PROTECTION
21 22 00 04/20 CLEAN AGENT FIRE EXTINGUISHING SYSTEMS
DIVISION 22 - PLUMBING
22 00 00 11/15, CHG 4: 05/21 PLUMBING, GENERAL PURPOSE
22 05 48.00 20 04/06, CHG 1: 05/15 MECHANICAL SOUND, AND VIBRATION CONTROL
PROJECT TABLE OF CONTENTS Page 3
DIVISION 23 - HEATING, VENTILATING, AND AIR CONDITIONING (HVAC)
23 01 30.41 05/22 HVAC SYSTEM CLEANING
23 03 00.00 20 08/10, CHG 3: 08/18 BASIC MECHANICAL MATERIALS AND METHODS
23 05 93 11/15 TESTING, ADJUSTING, AND BALANCING FOR
HVAC
23 07 00 02/13, CHG 7: 05/20 THERMAL INSULATION FOR MECHANICAL
SYSTEMS
23 09 00.00 22 08/20, CHG 1: 03/22 INSTRUMENTATION AND CONTROL FOR HVAC
23 09 13.00 22 08/20, CHG 1: 03/22 INSTRUMENTATION AND CONTROL DEVICES
FOR HVAC
23 09 23.02 22 08/20, CHG 1: 03/22 BACNET DIRECT DIGITAL CONTROL FOR HVAC
AND OTHER BUILDING CONTROL SYSTEMS
23 11 20 05/20 FACILITY GAS PIPING
23 21 23 08/17 HYDRONIC PUMPS
23 23 00 08/21 REFRIGERANT PIPING
23 25 00 05/21 CHEMICAL TREATMENT OF WATER FOR
MECHANICAL SYSTEMS
23 30 00 05/20, CHG 1: 02/22 HVAC AIR DISTRIBUTION
23 52 43.00 20 05/15, CHG 2: 08/18 LOW PRESSURE WATER HEATING BOILERS
(UNDER 800,000 BTU/HR OUTPUT)
23 64 26 08/09, CHG 7: 02/24 HOT, AND CONDENSER WATER PIPING SYSTEMS
23 81 00 05/18, CHG 1: 02/21 DECENTRALIZED UNITARY HVAC EQUIPMENT
23 81 23 11/20 COMPUTER ROOM AIR CONDITIONING UNITS
23 81 47 08/08, CHG 4: 08/18 WATER-LOOP HEAT PUMP SYSTEMS
23 82 00.00 20 02/16, CHG 1: 08/18 TERMINAL HEATING UNITS
DIVISION 25 - INTEGRATED AUTOMATION
25 05 11.05 05/21, CHG 1: 08/23 CYBERSECURITY FOR FACILITY-RELATED
CONTROL SYSTEMS - UTILITY CONTROL
SYSTEM - ADVANCED METERING
INFRASTRUCTURE
25 05 11.14 05/21, CHG 1: 08/23 CYBERSECURITY FOR FACILITY-RELATED
CONTROL SYSTEMS - BUILDING CONTROL
SYSTEM - CONVEYANCE SYSTEM - VERTICAL
TRANSPORT
25 05 11.26 01 05/21, CHG 1: 08/23 CYBERSECURITY FOR FACILITY-RELATED
CONTROL SYSTEMS - BUILDING CONTROL
SYSTEM - LIGHTING CONTROL SYSTEM
25 05 11.26 02 05/21, CHG 1: 08/23 CYBERSECURITY FOR FACILITY-RELATED
CONTROL SYSTEMS - UTILITY CONTROL
SYSTEM - CATHODIC PROTECTION
25 05 11.28 05/21, CHG 1: 08/23 CYBERSECURITY FOR FACILITY-RELATED
CONTROL SYSTEMS - UNIFIED
COMMUNICATION SYSTEM
DIVISION 26 - ELECTRICAL
26 08 00 11/22 APPARATUS INSPECTION AND TESTING
26 11 13.13 10/22 PACKAGED (GBDAA) BUILDING
26 12 19 05/24 PAD-MOUNTED, LIQUID-FILLED,
MEDIUM-VOLTAGE TRANSFORMERS
26 20 00 08/23 INTERIOR DISTRIBUTION SYSTEM
26 24 13 08/21 SWITCHBOARDS
26 27 14.00 20 02/21, CHG 1: 05/21 ELECTRICITY METERING
26 29 23 02/20, CHG 1: 05/21 ADJUSTABLE SPEED DRIVE (ASD) SYSTEMS
UNDER 600 VOLTS
PROJECT TABLE OF CONTENTS Page 4
26 32 15 05/24 ENGINE-GENERATOR SET STATIONARY
15-2500 KW, WITH AUXILIARIES
26 35 43 08/21, CHG 1: 05/24 400-HERTZ (HZ) SOLID STATE FREQUENCY
CONVERTER
26 36 23 05/20, CHG 1: 08/21 AUTOMATIC TRANSFER SWITCHES AND
BY-PASS/ISOLATION SWITCH
26 41 00 08/23 LIGHTNING PROTECTION SYSTEM
26 51 00 05/20, CHG 2: 11/21 INTERIOR LIGHTING
DIVISION 27 - COMMUNICATIONS
27 05 29.00 10 08/11 PROTECTIVE DISTRIBUTION SYSTEM (PDS)
FOR SIPRNET COMMUNICATION SYSTEMS
27 10 00 08/11 BUILDING TELECOMMUNICATIONS CABLING
SYSTEM
27 32 50.00 22 7/21 ELEVATOR LANDING TWO-WAY COMMUNICATION
SYSTEM
27 51 26 11/21 UNIFIED COMMUNICATION SYSTEM
27 53 19.13 05/20 FIRST RESPONDER DISTRIBUTED ANTENNAE
SYSTEMS (DAS)
DIVISION 28 - ELECTRONIC SAFETY AND SECURITY
28 08 10 08/23 ELECTRONIC SECURITY SYSTEM ACCEPTANCE
TESTING
28 10 05 05/24 ELECTRONIC SECURITY SYSTEMS (ESS)
28 31 76 08/20 INTERIOR FIRE ALARM AND MASS
NOTIFICATION SYSTEM, ADDRESSABLE
DIVISION 31 - EARTHWORK
31 05 19.13 02/21 GEOTEXTILES FOR EARTHWORK
31 11 00 11/18 CLEARING AND GRUBBING
31 23 00.00 20 02/11, CHG 2: 08/15 EXCAVATION AND FILL
31 31 16.13 08/22, CHG 1: 11/23 CHEMICAL TERMITE CONTROL
31 62 13.20 11/20, CHG 2: 02/24 PRECAST/PRESTRESSED CONCRETE PILES
31 62 23.13 02/21 CONCRETE-FILLED STEEL PILES
DIVISION 32 - EXTERIOR IMPROVEMENTS
32 01 16.71 11/22 COLD MILLING ASPHALT PAVING
32 01 19.61 11/19 SEALING OF JOINTS IN RIGID PAVEMENT
32 05 33 08/17 LANDSCAPE ESTABLISHMENT
32 12 13 05/24 BITUMINOUS TACK COATS
32 12 16.16 11/20 ROAD-MIX ASPHALT PAVING
32 13 13.06 05/20 PORTLAND CEMENT CONCRETE PAVEMENT FOR
ROADS AND SITE FACILITIES
32 16 19 05/18 CONCRETE CURBS, GUTTERS AND SIDEWALKS
32 17 23.16 11/24 ROAD AND PARKING LOT PAVEMENT MARKINGS
32 31 13.53 11/21 HIGH-SECURITY FENCES (CHAIN LINK AND
ORNAMENTAL) AND GATES
32 92 23 04/06, CHG 1: 08/21 SODDING
DIVISION 33 - UTILITIES
33 01 50.31 02/20 LEAK DETECTION FOR SPILL CONTAINMENT
SYSTEM ABOVEGROUND TANK
33 11 00 02/18, CHG 2: 11/23 WATER UTILITY DISTRIBUTION PIPING
33 30 00 05/18 SANITARY SEWERAGE
PROJECT TABLE OF CONTENTS Page 5
33 40 00 11/21 STORMWATER UTILITIES
33 52 10 11/18, CHG 1: 11/20 FUEL SYSTEMS PIPING (SERVICE STATION)
33 52 23.15 11/18 POL SERVICE PIPING WELDING
33 56 10 05/19, CHG 1: 11/20 FACTORY-FABRICATED FUEL STORAGE TANKS
33 71 02 08/21 UNDERGROUND ELECTRICAL DISTRIBUTION
33 82 00 04/06 TELECOMMUNICATIONS OUTSIDE PLANT (OSP)
33 83 02 11/24 STEEL ANTENNA TOWER
DIVISION 41 - MATERIAL PROCESSING AND HANDLING EQUIPMENT
41 22 13.15 11/22, CHG 1: 02/23 BRIDGE CRANES, OVERHEAD ELECTRIC,
UNDER RUNNING TROLLEY
-- End of Project Table of Contents --
PROJECT TABLE OF CONTENTS Page 6
SECTION 31 05 19.13
GEOTEXTILES FOR EARTHWORK
02/21
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
AMERICAN ASSOCIATION OF STATE HIGHWAY AND TRANSPORTATION OFFICIALS
(AASHTO)
AASHTO M 288 (2021) Standard Specification for Geosynthetic Specification for Highway Applications
ASTM INTERNATIONAL (ASTM)
ASTM D123 (2015b; R 2017) Standard Terminology Relating to Textiles
ASTM D4354 (2012; R 2020) Sampling of Geosynthetics for Testing
ASTM D4873/D4873M (2017) Standard Guide for Identification, Storage, and Handling of Geosynthetic Rolls and Samples
ASTM D4884/D4884M (2014a) Strength of Sewn or Thermally Bonded Seams of Geotextiles
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 1110-2-1601 (1991; 1994 Change 1) Engineering and Design -- Hydraulic Design of Flood Control Channels
1.2 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-04 Samples
Geotextiles
Minimum of 60 days prior to the beginning of installation of the same textile
SD-06 Test Reports
Geotextiles
SECTION 31 05 19.13 Page 1
Site Verification
SD-07 Certificates
Geotextiles Needle Punched Geotextile
1.3 DELIVERY, STORAGE, AND HANDLING
Deliver only approved geotextile rolls to the project site. Label, ship, store, and handle all geotextile in accordance with ASTM D4873/D4873M . Do not use hooks, tongs, or other sharp instruments for handling geotextile.
PART 2 PRODUCTS
2.1 MATERIALS
2.1.1 General
Provide geotextile that is a woven pervious sheet of plastic yarn as defined by ASTM D123 matching or exceeding the requirements of AASHTO M 288 Class 1..
2.1.2 Geotextile Fiber
Use fibers consisting of a long-chain synthetic polymer composed of at least 85 percent by weight of polyolefins, polyesters, or polyamides. Add stabilizers and/or inhibitors to the base polymer, if necessary to make the filaments resistant to deterioration caused by ultraviolet light and heat exposure. Do not add reclaimed or recycled fibers or polymer to the formulation. Form geotextile into a network such that the filaments or yarns retain dimensional stability relative to each other, including the edges. Finish the edges of the geotextile to prevent the outer fiber from pulling away from the geotextile.
2.1.3 Seams
Sew the seams of the geotextile with thread of a material meeting the chemical requirements given above for geotextile yarn or bond the seams by cementing or by heat. Attach the sheets of geotextile at the factory or another approved location, if necessary, to form sections not less than 6 feet wide. Test seams in accordance with method ASTM D4884/D4884M .
Seam strength less than 90 percent of the required grab tensile strength of the unaged geotextile in any principal direction is not permitted.
2.1.4 Securing Pins
Secure the geotextile to the embankment or foundation soil by pins to prevent movement prior to placement of revetment materials. Other appropriate means to prevent movement such as staples, sand bags, and stone could also be used. Insert securing pins through both strips of overlapped geotextile along the line passing through midpoints of the overlap. Remove securing pins as placement of revetment materials are placed to prevent tearing of geotextile or enlarging holes. Maximum spacing between securing pins depends on the steepness of the embankment slope. Provide maximum pins spacing equal to or less than the values listed in TABLE 2. When windy conditions prevail at the construction site, increase the number of pins upon the demand of the Contracting
SECTION 31 05 19.13 Page 2
Officer. Anchor terminal ends of the geotextile with key trench or apron at crest, toe of the slope and upstream and downstream limits of installation.
TABLE 2
MAXIMUM SPACING FOR SECURING PINS
EMBANKMENT SPACING, feet
STEEPER THAN 1V ON 3H 2
1V ON 3H TO 1V ON 4H 3
FLATTER THAN 1V ON 4H 5
2.2 INSPECTIONS, VERIFICATIONS, AND TESTING
2.2.1 Manufacturing and Sampling
Provide geotextiles and factory seams meeting the requirements of AASHTO M 288 Class 1.
2.2.1.1 Conformance Testing
Perform conformance testing in accordance with the manufacturers approved quality control manual. Submit manufacturer's quality control conformance test results.
2.2.1.2 Factory Sampling
Randomly sample geotextiles in accordance with ASTM D4354 (Procedure Method A). Sample factory seams at the frequency specified in ASTM D4884/D4884M . Provide all samples from the same production lot as will be supplied for the contract, of the full manufactured width of the geotextile by at least 10 feet long, except that samples for seam strength may be a full width sample folded over and the edges stitched for a length of at least 5 feet. Identify samples submitted for testing by manufacturers lot designation.
2.2.1.3 Needle Punched Geotextile
For needle punched geotextile, provide manufacturer certification that the geotextile has been inspected using permanent on-line metal detectors and does not contain any needles.
2.2.1.4 Manufacturer Certification
Upon delivery of the geotextile, submit duplicate copies of the written certificate of compliance signed by a legally authorized official of the manufacturer. State that the geotextile shipped to the site meets the chemical requirements and exceeds the minimum average roll value conforming to AASHTO M 288 Class 1.
2.2.2 Site Verification and Testing
Collect samples at approved locations upon delivery to the site in accordance with ASTM D4354 (Procedure Method B). Test samples to verify
SECTION 31 05 19.13 Page 3 that the geotextile meets the requirements specified in Paragraph 2.1.1.
Identify samples by manufacturers name, type of geotextile, lot number, roll number, and machine direction. Perform testing at an approved laboratory. Submit test results from the lot under review for approval prior to deployment of that lot of geotextile. Immediately rewrap rolls which are sampled in their protective covering.
PART 3 EXECUTION
3.1 SURFACE PREPARATION
Prepare surface, on which the geotextile will be placed, to a relatively smooth surface condition in accordance with the applicable portion of this specification and must be free from obstruction, debris, depressions, erosion feature, or vegetation. Remove any irregularities so as to ensure continuous, intimate contact of the geotextile with all the surface.
Remove loose material, soft or low density pockets of material; grade erosion features such as rills and gullies out of the surface before geotextile placement.
3.2 INSTALLATION OF THE GEOTEXTILE
3.2.1 General
Place the geotextile in the manner and at the locations shown. At the time of installation, reject the geotextile if it has defects, rips, holes, flaws, deterioration or damage incurred during manufacture, transportation or storage.
3.2.2 Placement
Place the geotextile with the long dimension perpendicular to the trench and laid smooth and free of tension, stress, folds, wrinkles, or creases.
Place the strips to provide a minimum width of 12 inches of overlap for each joint. Adjust the actual length of the geotextile used based on initial installation experience. Temporary pinning of the geotextile to help hold it in place until the bedding layer is placed will be allowed.
Remove the temporary pins as the bedding is placed to relieve high tensile stress which may occur during placement of material on the geotextile.
Design protection of riprap in compliance with EM 1110-2-1601 . Perform trimming in such a manner that the geotextile is not damaged in any way.
3.3 PROTECTION
Protect the geotextile at all times during construction from contamination by surface runoff; remove any geotextile so contaminated and replaced with uncontaminated geotextile. Replace any geotextile damaged during its installation or during placement of bedding materials at no cost to the Government. Schedule the work so that the covering of the geotextile with a layer of the specified material is accomplished within 7 calendar days after placement of the geotextile. Failure to comply will require replacement of geotextile. Protect the geotextile from damage prior to and during the placement of riprap or other materials. Before placement of riprap or other materials, demonstrate that the placement technique will not cause damage to the geotextile. Do not allow equipment on the unprotected geotextile.
SECTION 31 05 19.13 Page 4
3.4 PLACEMENT OF CUSHIONING MATERIAL
Perform placing of cushioning material in a manner to ensure intimate contact of the geotextile with the prepared surface and with the cushioning material. Do not damage the geotextile, including tear, puncture, or abrasion, during placement. On sloping surfaces place the cushioning material from the bottom of the slopes upward. During placement, the height of the drop of riprap material greater than 12 inches is not permitted. Uncover any geotextile damaged beneath the cushioning material, as necessary, and replaced at no cost to the Government.
3.5 OVERLAPPING AND SEAMING
3.5.1 Overlapping
The overlap of geotextile rolls must be 12 inches. Appropriate measures will be taken to ensure required overlap exists after cushion placement.
3.5.2 Sewn Seams
High strength thread should be used so that seam test conforms to ASTM D4884/D4884M . Provide thread meeting the chemical, ultraviolet, and physical requirements of the geotextile, and provide color different from that of the geotextile. Provide seam strength equal to the strength required for the geotextile in the direction across the seam. Overlapping J-type seams are preferable over prayer-type seams as the overlapping geotextile reduces the chance of openings to occur at the seam. Use double sewing, specially for field seams, to provide a safety factor against undetected missed stitches.
-- End of Section --
SECTION 31 05 19.13 Page 5
THIS PAGE INTENTIONALLY LEFT BLANK
SECTION 31 05 19.13 Page 6
SECTION 31 11 00
CLEARING AND GRUBBING
11/18
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to within the text by the basic designation only.
U.S. DEPARTMENT OF DEFENSE (DOD)
DODI 4150.07 (2019) DOD Pest Management Program
1.2 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Herbicide Application Plan
SD-03 Product Data
Tree Wound Paint
Herbicides; G
SD-07 Certificates
Qualifications; G
SD-11 Closeout Submittals
Pest Management Report
1.3 QUALITY CONTROL
1.3.1 Regulatory Requirements
Comply with DODI 4150.07 for requirements on Contractor's licensing, certification, and record keeping. Maintain daily records using the Pest Management Maintenance Record, DD Form 1532-1, or a computer generated equivalent. These forms may be obtained from the main web site:
https://www.acq.osd.mil/eie/afpmb/docs/standardlists/dd1532-1.xlsm .
1.3.2 Qualifications
For the application of herbicides, use the services of an applicator who is commercially certified in the state where the work is to be performed as required by DODI 4150.07 . Submit a copy of the pesticide applicator certificates.
SECTION 31 11 00 Page 1
1.4 DELIVERY, STORAGE, AND HANDLING
Deliver materials to the site, and handle in a manner which will maintain the materials in their original manufactured or fabricated condition until ready for use.
1.4.1 Storage
Storage of herbicides on the installation will not be permitted unless it is written into the contract.
1.4.2 Handling
Handle herbicides in accordance with the manufacturer's label and Safety Data Sheet (SDS), preventing contamination by dirt, water, and organic material. Protect herbicides from weather elements as recommended by the manufacturer's label and SDS. Spill kits must be maintained on herbicide control vehicles. Mixing of herbicides on the installation will not be permited unless it is written into the contract.
PART 2 PRODUCTS
2.1 MATERIALS
2.1.1 Tree Wound Paint
Use bituminous based paint from standard manufacture specially formulated for tree wounds.
2.1.2 Herbicide
Provide herbicides currently registered by the EPA or approved for such use by the appropriate agency of the host county and approved by the Contracting Officer. Select a herbicide that is suitable for the climatic conditions at the project site. Submit manufacturer's label and SDS for herbicides proposed for use.
PART 3 EXECUTION
3.1 PREPARATION
3.1.1 Herbicide Application Plan
Prior to commencing application of herbicide, submit a herbicide application plan with proposed sequence of treatment work including dates and times of application. Include the herbicide trade name, EPA registration number, chemical composition, formulation, application rate of active ingredients, method of application, area or volume treated, and amount applied. Include a copy of the pesticide applicator certificates.
3.1.2 Protection
3.1.2.1 Roads and Walks
Keep roads and walks free of dirt and debris at all times.
SECTION 31 11 00 Page 2
3.1.2.2 Trees, Shrubs, and Existing Facilities
Provide protection in accordance with Section 01 57 19 TEMPORARY
ENVIRONMENTAL CONTROLS.
3.1.2.3 Utility Lines
Protect existing utility lines that are indicated to remain from damage.
Notify the Contracting Officer immediately of damage to or an encounter with an unknown existing utility line. The Contractor is responsible for the repair of damage to existing utility lines that are indicated or made known to the Contractor prior to start of clearing and grubbing operations. When utility lines which are to be removed are encountered within the area of operations, notify the Contracting Officer in ample time to minimize interruption of the service. Refer to Section 01 30 00 ADMINISTRATIVE REQUIREMENTS and Section 01 57 19 TEMPORARY ENVIRONMENTAL CONTROLS for additional utility protection.
3.2 APPLICATION
3.2.1 Herbicide Application
Adhere to safety precautions as recommended by the manufacturer concerning handling and application of the herbicide.
3.2.1.1 Clean Up, Disposal, And Protection
Once application has been completed, proceed with clean up and protection of the site without delay. Clean the site of all material associated with the treatment measures, according to label instructions, and as indicated. Remove and dispose of excess and waste material off Government property.
3.2.1.1.1 Disposal of Herbicide
Dispose of residual herbicides and containers off Government property, and in accordance with the approved disposal plan, label instructions and EPA requirements.
3.3 CLEARING
Clearing consists of the satisfactory disposal of vegetation designated for removal within the areas to be cleared. Clearing also includes the removal and disposal of structures that obtrude, encroach upon, or otherwise obstruct the work. Apply herbicide in accordance with the manufacturer's label.
3.4 DISPOSAL OF MATERIALS
Dispose of excess materials in accordance with the approved solid waste management permit and include those materials in the solid waste management report.
3.5 CLOSEOUT ACTIVITIES
3.5.1 Herbicides
Upon completion of this work, submit the Pest Management Report DD Form 1532, or an equivalent computer product, to the Integrated Pest Management
SECTION 31 11 00 Page 3
Coordinator. This form identifies the type of operation, brand name and manufacturer of herbicide, formulation, concentration or rate of application used.
SECTION 31 11 00 Page 4
SECTION 31 23 00.00 20
EXCAVATION AND FILL
02/11, CHG 2: 08/15
PART 1 GENERAL
1.1 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by the basic designation only.
AMERICAN WATER WORKS ASSOCIATION (AWWA)
AWWA C600 (2017) Installation of Ductile-Iron Mains and Their Appurtenances
ASTM INTERNATIONAL (ASTM)
ASTM C33/C33M (2023) Standard Specification for Concrete Aggregates
ASTM C136/C136M (2019) Standard Test Method for Sieve Analysis of Fine and Coarse Aggregates
ASTM D698 (2012; E 2014; E 2015) Laboratory Compaction Characteristics of Soil Using Standard Effort (12,400 ft-lbf/cu. ft.
(600 kN-m/cu. m.))
ASTM D1140 (2017) Standard Test Methods for Determining the Amount of Material Finer than 75-µm (No. 200) Sieve in Soils by Washing
ASTM D1556/D1556M (2015; E 2016) Standard Test Method for Density and Unit Weight of Soil in Place by Sand-Cone Method
ASTM D1557 (2012; E 2015) Standard Test Methods for Laboratory Compaction Characteristics of Soil Using Modified Effort (56,000 ft-lbf/ft3) (2700 kN-m/m3)
ASTM D1883 (2016) Standard Test Method for California Bearing Ratio (CBR) of Laboratory-Compacted Soils
ASTM D2216 (2019) Standard Test Methods for Laboratory Determination of Water (Moisture) Content of Soil and Rock by Mass
ASTM D2487 (2017; E 2020) Standard Practice for Classification of Soils for Engineering Purposes (Unified Soil Classification System)
SECTION 31 23 00.00 20 Page 1
ASTM D4318 (2017; E 2018) Standard Test Methods for Liquid Limit, Plastic Limit, and Plasticity Index of Soils
ASTM D6938 (2017a) Standard Test Method for In-Place Density and Water Content of Soil and Soil-Aggregate by Nuclear Methods (Shallow Depth)
U.S. ARMY CORPS OF ENGINEERS (USACE)
EM 385-1-1 (2024) Safety -- Safety and Health Requirements Manual
VIRGINIA DEPARTMENT OF TRANSPORTATION
VDOT RBS (2020) Virginia Department of Transportation Road and Bridge Specifications
1.2 DEFINITIONS
1.2.1 Capillary Water Barrier
A layer of clean, poorly graded crushed rock, stone, or natural sand or gravel having a high porosity which is placed beneath a building slab with or without a vapor barrier to cut off the capillary flow of pore water to the area immediately below a slab.
1.2.2 Degree of Compaction
Degree of compaction is expressed as a percentage of the maximum density obtained by the test procedure presented in ASTM D1557, for general soil types, abbreviated as percent laboratory maximum density.
1.2.3 Hard Materials
Weathered rock, dense consolidated deposits, or conglomerate materials which are not included in the definition of "rock" but which usually require the use of heavy excavation equipment, ripper teeth, or jack hammers for removal.
1.2.4 Rock
Solid homogeneous interlocking crystalline material with firmly cemented, laminated, or foliated masses or conglomerate deposits, neither of which can be removed without systematic drilling and blasting, drilling and the use of expansion jacks or feather wedges, or the use of backhoe-mounted pneumatic hole punchers or rock breakers; also large boulders, buried masonry, or concrete other than pavement exceeding 1 cubic yard in volume. Removal of hard material will not be considered rock excavation because of intermittent drilling and blasting that is performed merely to increase production.
1.2.5 Geotechnically Unsuitable Subgrade
Existing subgrade materials that exhibit insufficient strength or excessive movement after proper execution of work specified in Paragraphs PROTECTION, SURFACE PREPARATION, EXCAVATION and SUBGRADE PREPARATION.
SECTION 31 23 00.00 20 Page 2
Unsuitable subgrade also contains soil mixed with appreciable degradable matter such as organic material, wood, trash and non-inert debris which may affect the performance of life expectancy of the supported facility.
Unsuitable subgrade will be determined by the Government Geotechnical Engineer and confirmed by the Contracting Officer. Existing subgrade soil materials (which do not comply with the requirements for satisfactory materials do not necessarily classify as Geotechnically Unsuitable Subgrade.
1.2.6 Pile Supported Structure
As used herein, a structure where both the foundation and floor slab are pile supported.
1.3 SUBMITTALS
Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:
SD-01 Preconstruction Submittals
Shoring and Sheeting Plan; G
Dewatering work plan; G
Soil Management Plan
Submit 15 days prior to starting work.
Preconstruction Meeting Agenda
Indicate the expected meeting date and time, meeting location, list of attendees, and agenda items/topics that will be covered.
SD-06 Test Reports
Fill and backfill test; G
Select material test; G
Porous fill test for capillary water barrier; G
Density tests
Copies of all laboratory and field test reports within 24 hours of the completion of the test.
1.4 DELIVERY, STORAGE, AND HANDLING
Perform in a manner to prevent contamination or segregation of materials.
1.5 CRITERIA FOR BIDDING
Base bids on the following criteria:
a. Surface elevations are as indicated.
SECTION 31 23 00.00 20 Page 3
b. Pipes or other artificial obstructions, except those indicated, will not be encountered.
c. Ground water elevations indicated by the boring log were those existing at the time subsurface investigations were made and do not necessarily represent ground water elevation at the time of construction.
d. Normal ground water elevation is 5 feet below existing surface elevation. Seasonal high ground water elevation is 4 feet below existing ground surface. Employ measures and equipment to permit construction to proceed during periods of seasonal high ground water.
e. Material character is indicated by the boring logs. Linear interpolation of stratification depths must be used to estimate quantities of material types between adjacent boring test locations.
f. Hard materials will be encountered. A layer of 12 inch thick cement treated aggregate is beneath the existing concrete pavement.
g. Suitable backfill, fill material, and bedding material in the quantities required is not available at the project site. Fill materials imported from off government property will be required.
Excavated onsite soils removed from planned excavations may not be reused.
h. Removal of unknown buried concrete, pipes and debris not identified on the project plans and greater than 1 cubic yard in volume from planned excavations will be paid for under the Unit Price Line Item on the Price Proposal Form.
i. Blasting will not be permitted. Remove material in an approved manner.
j. All construction dewatering effluent will be required to be treated prior to discharge. See Section 01 57 19.
1.6 REQUIREMENTS FOR OFF SITE SOIL
Refer to section 01 57 19 paragraph 1.5.1.1.2
1.7 QUALITY ASSURANCE
1.7.1 Preconstruction Meeting
A preconstruction meeting must be held at the jobsite at least 5 business days prior to the start of earthwork operations on the project. The preconstruction meeting must be arranged by the Contractor and will follow the written preconstruction meeting agenda submitted prior to the meeting.
The purpose of this meeting is to review the requirements of this specification and the associated plans. The following individuals will be in attendance at this meeting: Contractor's Project Manager and Project Superintendent, earthwork subcontractor's Project Manager and Site Foreman, Contractor's Geotechnical Engineer and Testing Agency, Government Geotechnical Engineer and Civil Engineer, and Government Construction Manager and Engineering Technician. The minutes of this meeting must be recorded by the Contractor and published via email within 48 hours to all attendees. The minutes must be re-published within 48 hours via email pending any subsequent comments from the attendees.
SECTION 31 23 00.00 20 Page 4
1.7.2 Shoring and Sheeting Plan
Submit drawings and calculations, certified by a registered professional engineer, describing the methods for shoring and sheeting of excavations.
Drawings must include material sizes and types, arrangement of members, and the sequence and method of installation and removal. Calculations must include data and references used.
The Contractor is required to hire a Professional Geotechnical Engineer to provide inspection of excavations and soil/groundwater conditions throughout construction. The Geotechnical Engineer must be responsible for performing pre-construction and periodic site visits throughout construction to assess site conditions. The Geotechnical Engineer must update the excavation, sheeting and dewatering plans as construction progresses to reflect changing conditions and must submit an updated plan if necessary. A written report must be submitted, at least monthly, informing the Contractor and Contracting Officer of the status of the plan and an accounting of the Contractor's adherence to the plan addressing any present or potential problems. The Geotechnical Engineer must be available to meet with the Contracting Officer at any time throughout the contract duration.
1.7.3 Dewatering Work Plan
Submit procedures for accomplishing dewatering work. The plan must address and describe how the Contractor will accomplish required site preparation and excavation work when surface and subsurface water is present. The plan must be in accordance with Section 01 57 19.
1.7.4 Special Inspections
Perform special inspections and testing in accordance with Section 01 45 35
SPECIAL INSPECTIONS.
1.7.5 Utilities
Movement of construction machinery and equipment over pipes and utilities during construction must be at the Contractor's risk. Perform work adjacent to non-Government utilities as indicated in accordance with procedures outlined by utility company. Excavation made with power-driven equipment is not permitted within two feet of known Government-owned utility or subsurface construction. For work immediately adjacent to or for excavations exposing a utility or other buried obstruction, excavate by hand. Start hand excavation on each side of the indicated obstruction and continue until the obstruction is uncovered or until clearance for the new grade is assured. Support uncovered lines or other existing work affected by the contract excavation until approval for backfill is granted by the Contracting Officer. Report damage to utility lines or subsurface construction immediately to the Contracting Officer.
1.7.6 Soil Management Plan
Submit procedures for accomplishing soil related activities. The plan must address and describe how the Contractor will accomplish required site soils related work in accordance with Section 01 57 19.
1.8 ENVIRONMENTAL CONSIDERATIONS
The project site is classified as an AFFF release site with PFAS
SECTION 31 23 00.00 20 Page 5 contamination. Earthwork must be coordinated with the NAVFAC MIDLANT Environmental Services (EVS) through the Contracting Officer and conform to the requirements in the paragraph titled Soil Management Plan, in this specification. Dewatering effluent must be containerized and tested as specified in the paragraph titled Dewatering, in this specification.
PART 2 PRODUCTS
2.1 SOIL MATERIALS
2.1.1 Satisfactory Materials
Any materials classified by ASTM D2487 as GW, GP, GM, GP-GM, GW-GM, GC, GP-GC, GM-GC, SW, SP, SM, SW-SM, SC, SW-SC, SP-SM, and SP-SC, free of debris, roots, wood, scrap material, vegetation, refuse, soft unsound particles, and frozen, deleterious, or objectionable materials. Unless specified otherwise, the maximum particle diameter must be 3 inches. All material will be moisture conditioned to within +/- 2 percent of the optimum moisture content as defined by ASTM D1557 prior to placement and compaction.
2.1.2 On-Site Materials for Reuse
On-Site Materials are not permitted for reuse.
2.1.3 Unsatisfactory Materials
Materials which do not comply with the requirements for satisfactory materials. Unsatisfactory materials also include man-made fills, containing trash or refuse and undocumented backfills from previous construction. Unsatisfactory material also includes fill material classified as satisfactory which contains root and other organic matter, frozen material, and stones larger than 3 inches. The unsatisfactory material classification is applicable to proposed fill materials only and not to existing subgrade materials. The Contracting Officer must be notified of any contaminated materials. Unsatisfactory material determination will be made by the contractor's Geotechnical Engineer and confirmed by the Contacting Officer.
2.1.4 Common Fill
Approved, unclassified soil material with the characteristics required to compact to the soil density specified for the intended location.
2.1.5 Backfill and Fill Material
ASTM D2487, classification GW, GP, SW, SP, SM, and SP-SM with a maximum ASTM D4318 liquid limit of 30, maximum ASTM D4318 plasticity index of 6, and a maximum of 20 percent by weight passing ASTM D1140, No. 200 sieve.
2.1.6 Select Material
Provide materials classified as GW, GP, SW, SP, or SP-SM by ASTM D2487 where indicated. The plasticity index must not be greater than zero percent when tested in accordance with ASTM D4318 0.1 inch penetration must be 20 percent at 95 percent ASTM D1557 maximum density as determined in accordance with ASTM D1883 for a laboratory soaking period of not less than 4 days.
SECTION 31 23 00.00 20 Page 6
Bearing Ratio: At 0.1 inch penetration, the bearing ratio must be 20 percent at 95 percent ASTM D1557 maximum density as determined in accordance with ASTM D1883 for a laboratory soaking period of not less than 4 days.
2.1.7 Topsoil
Provide as specified in Section 32 92 23 SODDING.
2.1.8 Compost
Compost derived from plant material and meet the criteria set forth by the U.S. Composting Seal of Testing Assurance (STA) program. 100 percent of the material must pass through a half inch screen. The pH of the material must be between 5.5 and 8.5 and the manufactured inert material (plastic, concrete, ceramics, metal) is less than 1.0 percent by weight. The organic matter content must be greater than 35 percent and the soluble salt content less than 6.0 mmhos/cm. The compost must be mature and stable per the appropriate test(s) as specified by STA. The carbon to nitrogen ratio must be less than 25:1 and meet the USEPA part 503 levels for heavy metals. The compost should have an optimum dry bulk density ranging from 40 to 50 lbfs/ft3, certain fully mature coarse textured composts may be lower.
2.2 POROUS FILL FOR CAPILLARY WATER BARRIER
ASTM C33/C33M fine aggregate grading with a maximum of 3 percent by weight passing ASTM D1140, No. 200 sieve, or coarse aggregate Size 57, 67, 78, or 8 and conforming to the general soil material requirements specified in paragraph entitled "Satisfactory Materials."
2.3 UTILITY BEDDING MATERIAL
Except as specified otherwise in the individual piping section, provide bedding for buried piping in accordance with AWWA C600, Type 4, except as specified herein. Backfill to top of pipe must be compacted to 95 percent of ASTM D698 maximum density. Plastic piping must have bedding to spring line of pipe. Provide bedding conforming to VDOT No. 57 Stone. Provide geotextile fabric below bedding layer where indicated in the plans and where excessively wet or yielding foundation conditions are present.
2.4 BORROW
Obtain borrow materials required in excess of those furnished from excavations from sources outside of Government property.
2.5 FILTER FABRIC
Provide a pervious sheet of polyester, nylon, glass or polypropylene, ultraviolet resistant filaments woven, spun bonded, fused, or otherwise manufactured into a nonraveling fabric with uniform thickness and strength. Fabric must have manufacturer certified minimum average roll properties that conform with VDOT RBS Section 245 "Geosynthetics and Low Permeable Liners."
2.6 MATERIAL FOR RIP-RAP
Bedding material, Filter fabric, and rock conforming to VDOT RBS Section 204, "Stone for Masonry, Riprap, Porous Backfill, and Gabions" for
SECTION 31 23 00.00 20 Page 7 construction indicated.
2.7 BURIED WARNING AND IDENTIFICATION TAPE
Polyethylene plastic and metallic core or metallic-faced, acid- and alkali-resistant, polyethylene plastic warning tape manufactured specifically for warning and identification of buried utility lines.
Provide tape on rolls, 3 inch minimum width, color coded as specified below for the intended utility with warning and identification imprinted in bold black letters continuously over the entire tape length. Warning and identification to read, "CAUTION, BURIED (intended service) LINE BELOW" or similar wording. Color and printing must be permanent, unaffected by moisture or soil.
Warning Tape Color Codes
Red: Electric
Yellow: Gas, Oil; Dangerous Materials
Orange: Telephone and Other Communications
Blue: Potable Water Systems
Green: Sewer Systems
White: Steam Systems
2.7.1 Warning Tape for Metallic Piping
Acid and alkali-resistant polyethylene plastic tape conforming to the width, color, and printing requirements specified above. Minimum thickness of tape must be 0.003 inch. Tape must have a minimum strength of 1500 psi lengthwise, and 1250 psi crosswise, with a maximum 350 percent elongation.
2.7.2 Detectable Warning Tape for Non-Metallic Piping
Polyethylene plastic tape conforming to the width, color, and printing requirements specified above. Minimum thickness of the tape must be 0.004 inch. Tape must have a minimum strength of 1500 psi lengthwise and 1250 psi crosswise. Tape must be manufactured with integral wires, foil backing, or other means of enabling detection by a metal detector when tape is buried up to 3 feet deep. Encase metallic element of the tape in a protective jacket or provide with other means of corrosion protection.
2.8 DETECTION WIRE FOR NON-METALLIC PIPING
Detection wire must be insulated single strand, solid copper with a minimum of 12 AWG.
2.9 FLOWABLE FILL
VDOT RBS Section 249. Design compressive strength must be a minimum 50 psi mix design and a maximum 300 psi mix design at 28 days.
SECTION 31 23 00.00 20 Page 8
PART 3 EXECUTION
3.1 PROTECTION
3.1.1 Shoring and Sheeting
Provide shoring bracing, trench boxes and sheeting where indicated. In addition to Section 25 A and B of EM 385-1-1 , include provisions in the shoring and sheeting plan that will accomplish the following:
a. Prevent undermining of pavements, foundations and slabs.
b. Prevent slippage or movement in banks or slopes adjacent to the excavation.
3.1.2 Drainage and Dewatering
Provide for the collection and disposal of surface and subsurface water encountered during construction.
3.1.2.1 Drainage
So that construction operations progress successfully, completely drain construction site during periods of construction to keep soil materials sufficiently dry. The Contractor must establish/construct storm drainage features (ponds/basins) at the earliest stages of site development, and throughout construction grade the construction area to provide positive surface water runoff away from the construction activity and/or provide temporary ditches, swales, and other drainage features and equipment as required to maintain dry soils, prevent erosion and undermining of foundations. When unsuitable working platforms for equipment operation and unsuitable soil support for subsequent construction features develop, remove unsuitable material and provide new soil material as specified herein. It is the responsibility of the Contractor to assess the soil and ground water conditions presented by the plans and specifications and to employ necessary measures to permit construction to proceed. Excavated slopes and backfill surfaces must be protected to prevent erosion and sloughing. Excavation must be performed so that the site, the area immediately surrounding the site, and the area affecting operations at the site must be continually and effectively drained.
3.1.2.2 Dewatering
Groundwater flowing toward or into excavations must be controlled to prevent sloughing of excavation slopes and walls, boils, uplift and heave in the excavation and to eliminate interference with orderly progress of construction. French drains, sumps, ditches or trenches will not be permitted within 3 feet of the foundation of any structure, except with specific written approval, and after specific contractual provisions for restoration of the foundation area have been made. Control measures must be taken by the time the excavation reaches the water level in order to maintain the integrity of the in situ material. While the excavation is open, the water level must be maintained continuously, at least 2 feet below the working level. Dewatering must be in accordance with Section 01 57 19.
3.1.3 Underground Utilities
Location of the existing utilities indicated is approximate. The
SECTION 31 23 00.00 20 Page 9
Contractor must physically verify the location and elevation of the existing utilities indicated prior to starting construction. The Contractor must scan the construction site with electromagnetic and sonic equipment and mark the surface of the ground where existing underground utilities are discovered.
3.1.4 Machinery and Equipment
Movement of construction machinery and equipment over pipes during construction must be at the Contractor's risk. Repair, or remove and provide new pipe for existing or newly installed pipe that has been displaced or damaged.
3.2 SURFACE PREPARATION
3.2.1 Subgrade Maintenance
Maintenance of exposed subgrades is the responsibility of the Contractor.
The Contractor is required to prevent damage by heavy loads and equipment to the subgrade by implementing precautionary measures such as construction of temporary haul roads and the use of timber matting. Any defects or damage must be repaired or replaced at the Contractor's expense before placement of any succeeding courses.
3.2.2 Stripping at GBDAA Tower Site
Strip site of material where indicated on the plans. Existing surface materials will be stripped to a depth of 12 inches below the existing ground surface in areas designated as Clear and Grub on the plans.
Existing surficial soils will be stripped to a depth of 12 inches in all other areas. Stripping will be performed in all areas within the planned limits of disturbance. All stripped materials are not suitable for reuse as topsoil and will be wasted in the specified disposal area. All stripped soils will be screened to remove roots and organic materials prior disposal. All required topsoil will be imported and will meet the composition requirements of Section 32 92 23, Part 2.2.3. Strip suitable soil from the site where excavation or grading is indicated and stockpile separately from other excavated material. Protect topsoil and keep in segregated piles until needed.
3.2.3 Unsuitable Material
Remove vegetation, debris, decayed vegetable matter, sod, mulch, and rubbish underneath paved areas or concrete slabs.
3.3 EXCAVATION
Excavate to contours, elevation, and dimensions indicated. Reuse excavated materials that meet the specified requirements for the material type required at the intended location. Keep excavations free from water.
Excava…
This is the start of the file's text. The full file is on GovTribe.
File details come from the government source that posted it. Updated .