This is a Price Schedule (Attachment H) for Federal Contract N40085-25-R-2639, a construction project for DBB P222 MQ-25 Aircraft Laydown Facilities located in Norfolk, Virginia.

The base contract (CLIN 0001) requires pricing for the entire project work including: building construction to the 5-foot line (0001A), sitework outside the facility (0001B), foundation piling at 18,060 vertical linear feet (0001C), handling and disposal of contaminant-impacted soil including PFAS and petroleum at 17,268 tons (0001D), treatment of construction dewatering effluent at 1,500,000 gallons (0001E), dynamic pile analysis testing for 8 units (0001F), and First Responder Distributed Antennae Systems installation (0001G). Award will be evaluated on the total price for CLIN 0001 and the sum of extended prices for CLINs 0001C through 0001G. The contract includes nine optional line items: Electronic Security System (0002, $627,025 government estimate), AV Design Services (0003), AV Equipment for Building LP48A (0004, $77,149 estimate), AV Equipment for Building LP48 (0005, $62,701 estimate), FF&E for Building LP48A (0006, $3,341,739 estimate), FF&E for Building LP48 (0007, $2,809,372 estimate), geotechnical subgrade soil removal at 5,476 cubic yards (0008), buried concrete and debris demolition at 1,500 tons (0009), and asbestos pipe insulation removal at 534 linear feet (0010). Offerors may propose a Handling and Administration Rate (HAR) not exceeding 5 percent for ESS, FF&E, and AV items. The Government reserves the unilateral right to award optional items 0008-0010 within 360 days after contract award. All line items require firm fixed prices with no economic price adjustment provisions. The contract completion date is 1,017 calendar days after award.

View the file

Other files

File Type Posted
Attachment G Individual Small Business Subcontracting Plan.docx DOCX document
Attachment F Small Business Participation Commitment.docx DOCX document
JA ML2650 25R2639 P222 ILDFA Redacted.pdf PDF
Solicitation Amendment N4008525R26390008 SF 30.pdf PDF
K3237099 LP-48 HazMat Report 3.5.26 - signed.pdf PDF
01 31 23.13 20.pdf PDF
Amendment 0007 Continuation Sheet.pdf PDF
Solicitation Amendment N4008525R26390007 SF 30.pdf PDF
REGISTER.pdf PDF
TABLE OF CONTENTS.pdf PDF
13 49 20.00 10.pdf PDF
Solicitation Amendment N4008525R26390006 SF 30.pdf PDF
P222_1737012_01 91 00.15 22.pdf PDF
Crane - LP48 1-DATA SHEET.pdf PDF
P222_1737012_Geotech Report.pdf PDF
P222_1737012_28 31 76.pdf PDF
Attachment H - Price Proposal Form_rev1.pdf PDF
P222_1737012_Drawings_volume II_Rev 001_SIGNED.pdf PDF
Solicitation Amendment N4008525R26390005 SF 30.pdf PDF
P222_1737012_04 20 00.pdf PDF
Amendment 0005 Continuation Sheet.pdf PDF
P222_1737012_32 13 13.06.pdf PDF
P222_1737012_09 29 00.pdf PDF
P222_1737012_07 60 00.pdf PDF
FY26 Naval Station Norfolk Utility Costs.pdf PDF
P222_1737012_07 21 13.pdf PDF
P222_1737012_REGISTER.pdf PDF
P222_1737012_Drawings_volume I_Rev 001_SIGNED.pdf PDF
P222_1737012_13 34 20.pdf PDF
Crane - LP48 2-DATA SHEET.pdf PDF
Solicitation Amendment N4008525R26390004 SF 30.pdf PDF
JA ML2623 25R2639 P222 ASSA Abloy Redacted.pdf PDF
JA ML2624 25R2639 P222 SRG RF Shielding Redacted.pdf PDF
26R2639 P222 Site Visit Log.pdf PDF
Solicitation Amendment N4008525R26390003 SF 30.pdf PDF
Solicitation Amendment N4008525R26390002 SF 30.pdf PDF
Solicitation Amendment N4008525R26390001 SF 30.pdf PDF
Attachment B - PIEE Vendor Access Instructions.pdf PDF
1737012_dwg 02of02_P222.pdf PDF
Attachment M - P222 Site Visit Map.pdf PDF
1737012_spec 01of04_P222.pdf PDF
1737012_dwg 01of02_P222.pdf PDF
Attachment C- Construction Experience Project Data.docx DOCX document
Attachment D- Past Performance Questionnaire.docx DOCX document
Attachment E- Historical Small Business Utilization.docx DOCX document
Attachment G- Individual Small Business Subcontracting Plan.docx DOCX document
1737012_spec 04of04_P222.pdf PDF
Attachment F- Small Business Participation Commitment.docx DOCX document
Attachment L - JA ML-26-01 P222 MQ25 Hangar Brand Name or Equal Finishes_Reda.pdf PDF
1737012_spec 03of04_P222.pdf PDF
Show 40 more

Latest 50 of 56 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

DBB P222 MQ-25 Aircraft Laydown Facilities N40085-25-R-2639 Norfolk, Virginia Attachment H

PRICE SCHEDULE

Provide line-item prices, where indicated by blank underlines, for the following items:

Line Item

Description Quantity Unit Unit Price

Sub-Total Total Price

0001 BASE PRICE: Total Price for the entire work for Project P222 in accordance with the drawings and specifications, complete, but excluding work provided in another Priced line Item.

1 EA $______

0001A Subtotal of Base Price for the entire work for P222 complete to the 5-foot line outside of the building in accordance with the drawings and specifications, but excluding work provided in another line item

1 EA $______ $______

0001B Subtotal of Base Price for the entire project sitework, outside the facility 5- foot line, for P222, complete in accordance with the drawings and specifications, but excluding work described in another line Item.

1 EA $______ $______

0001C Unit Price for providing Foundation Piling complete in accordance with the drawings and specifications but excluding work provided in another line item.

18,060 VLF $______ $______

0001D Unit Price for handling, temporary stockpiling, sampling, analysis, hauling and disposal of contaminant impacted soil media (including but not limited to, PFAS, petroleum, VOCs, PAHs and metals) excavation spoils at a permitted licensed facility, complete, in accordance with the drawings and specifications, but excluding work provided in another line item.

17,268 TONS $______ $______

Norfolk, Virginia Attachment H

0001E Unit price for handling, testing, management (including operation and oversight), and treatment of contaminant impacted construction dewatering effluent (including but not limited to, PFAS, petroleum, VOCs, PAHs and metals). Price for providing work in connection with labor, material, equipment, transportation, spent treatment media characterization, transport, disposal, and supervision, complete in accordance with the drawings and specifications, but excluding work provided in another line item. Discharge quantities in gallons must be certified and approved by the Contracting Officer.

1,500,000 GAL $______ $______

0001F Unit Price for providing additional Dynamic Pile Analysis testing as requested by the Contracting Officer, complete in accordance with the drawings and specifications, but excluding work provided in another line item.

8 EA $______ $______

0001G Price to provide First Responder Distributed Antennae Systems (DAS) within LP-48A in accordance with the drawings and specifications.

Include the price for supporting permanent infrastructure under the Base Price. Supporting infrastructure includes items such as conduit, junction boxes, power connections, fire rated chases, wall and roof penetrations.

1 LS $______ $______

0002 Option Item No. 1:

Price for providing Electronic Security System (ESS) equipment, testing, and associated training, but excluding work provided in another Priced line item. The ESS includes, but is not limited to, Intrusion Detection System (IDS), Access Control System (ACS), and Video Systems complete in accordance with the drawings and specifications.

Equipment includes items such as Premise Control Units (PCU), central processing units, field panels, sensors, card readers, keypads, cameras, switches, video recorders, workstations, and the communication cabling connecting these devices together.

Government Estimated Price:

$627,025

HAR

Perce nt

(NTE

5%)

Subtotal

Total

FF&E

Estimated Price

Include the price for supporting permanent infrastructure under the Base Price. Interior supporting infrastructure includes items such as conduit, junction boxes, electronic door strikes, door-hardware, mounting hardware, and power connections. Exterior supporting infrastructure includes items such as exterior duct banks, manholes, utility poles, utility connections, and power connections.

Norfolk, Virginia Attachment H

0003 Option Item No. 2:

AV Design Services Option Price for providing the professional Services of a Certified Technology Specialist - Design (CTS- D) detailed in Spec Section 01 30 02.00 22

1 EA $______ $______

0004 Option Item No. 3:

Price for providing Audio Visual System (A/V) Equipment, testing, and associated training in accordance with the drawings and specifications, but excluding work provided in another Priced line item for Building LP48A. Equipment includes, but is not limited to, items such as flat panel monitors, projectors, wall input boxes, touch screens, push button control panels, video teleconferencing codecs, microphones, speakers and the communication cabling connecting these devices together. Include the price for supporting permanent infrastructure under the Base Price. AV supporting infrastructure includes items such as conduit, junction boxes, mounting hardware, and power connections.

Government

$77,149

Perc ent

(NT

E

Total AV

Price

0005 Option Item No. 4:

Price for providing Audio Visual System (A/V) Equipment, testing, and associated training in accordance with the drawings and specifications but excluding work provided in another Priced line item for Building LP48. Equipment includes, but is not limited to, items such as flat panel monitors, projectors, wall input boxes, touch screens, push button control panels, video teleconferencing codecs, microphones, speakers and the communication cabling connecting these devices together. Include the price for supporting permanent infrastructure under the Base Price. AV supporting infrastructure includes items such as conduit, junction boxes, mounting hardware, and power connections.

Government

$62,701

Perc ent

(NT

Total AV

Price

0006 Option Item No. 5: Building LP48A FF&E Price for providing work in connection with labor, material, equipment, transportation and supervision required for the Furniture, Fixtures, and Equipment (FF&E), complete in accordance with the drawings and specifications, but excluding work provided in another Priced line item.

Government

$3,341,739

Perc ent

(NT

Norfolk, Virginia Attachment H

0007 Option Item No. 6: Building LP48 FF&E Price for providing work in connection with labor, material, equipment, transportation and supervision required for the Furniture, Fixtures, and Equipment (FF&E), complete in accordance with the drawings and specifications, but excluding work provided in another Priced line item.

Government

$2,809,372

Perc ent

(NT

0008 Option Item No. 7:

Unit Price for undercut of geotechnically unsuitable subgrade soils and replacement with imported structural fill material within the building and pavement limits, complete in accordance with the drawings and specifications, but excluding work provided in another line item.

Disposal of undercut excavation spoils will be paid for under CLIN 0001D.

5,476 CY $______ $______

0009 Option Item No. 8:

Unit Price for demolition, excavation and disposal of buried concrete structures, utility lines and debris greater than 1/2 cubic yard in size, encountered within planned excavation limits and not identified in the Contract Documents, complete in accordance with the drawings and specifications, but excluding work provided in another line item. Note: Pieces of buried concrete and debris encountered within the planned excavation limits smaller than 1/2 cubic yard in size are considered incidental to the work.

1,500 TONS $______ $______

0010 Option Item No. 9:

Unit price for removal and disposal of buried (below grade) asbestos containing pipe insulation (insulation on pipe up to 24 inches in diameter) complete in accordance with drawings and specifications, but excluding work provided in another line item.

534 LF $______ $______

GENERAL BID NOTES

a) Award will be evaluated on the price proposed for CLIN 0001, which consists of Contract Line

Items 0001A, and 0001B, as well as the sum of the extended prices for Contract Line Items 0001C, 0001D, 0001E, 0001F, and 0001G. For CLINs 0001C, 0001D, 0001E, 0001F, and 0001G, enter unit prices and extended totals in spaces provided. If there is a difference between a unit price and the extended total, the unit price will be held to be the intended bid and the total recomputed accordingly. If an Offeror provides a total but fails to enter a unit price, the total divided by the specified quantity will be held to be the intended unit price.

b) Evaluation of Options (JUL 1990). Except when it is determined in accordance with FAR

17.206(b) not to be in the Government's best interest, the Government will evaluate offers for award purposes by adding the price for the Option(s) to the total price for CLIN 0001. In

Norfolk, Virginia Attachment H accordance with FAR 52.217-5 Evaluation of Options, evaluation of options will not obligate the Government to exercise the Option(s).

c) The Government reserves the unilateral right to award Line Items 0008-0010 to the Contractor at the proposed price within 360 calendar days after the contract award and in accordance with all bid notes. A firm fixed proposed price is required for Line Items 0008, 0009 and 0010. No provision is made for economic price adjustment. If the Option(s) are exercised, the contract completion date remains 1,017 calendar days after award of the contract.

d) The Government may reject an offer as nonresponsive if it is materially unbalanced as to prices for the basic requirement and the option quantities. An offer is unbalanced when it is based on prices significantly less than cost for some work and prices which are significantly overstated for other work.

e) Failure to enter a price for any Line Item will result in a proposal being rejected.

f) For bid items where unit prices are indicated as required, bidders shall enter unit prices and extended totals in spaces provided. If there is a difference between a unit price and the extended total, the unit price will be held to be the intended bid and the total recomputed accordingly. If an Offeror provides a total but fails to enter a unit price, the total divided by the specified quantity will be held to be the intended unit price. If Line Items 0002-0010 are exercised, additional bonding and consent of surety is required. Consequently, the Performance Bond must reflect 100 percent of the aggregate amount of all items.

g) For CLIN 0001D: Unit price for providing all work in connection with excavation, handling, storage, sampling, analysis, transportation, any necessary treatment and disposal of contaminant impacted soil media (including but not limited to, PFAS, petroleum, VOCs, PAHs and metals) at a permitted licensed facility. Sampling shall be performed in accordance with Specification Section 01 57 19. Soil samples shall be analyzed for Total Petroleum Hydrocarbons (TPH) diesel range and gasoline range organics (DRO & GRO), and Benzene, Toluene, Methylbenzene, and Xylenes (BTEX), PFAS, plus other analyses required by the treatment/disposal facility. Unit price shall include all work in connection with removal, testing, treatment and disposal of contaminant impacted soils encountered within planned excavations and CLIN 0007, at a permitted licensed treatment/disposal facility and backfilling the excavation with compacted clean imported structural backfill. Unit price shall include all work in connection with evaluation and handling, any necessary storage, stockpiling and related storage maintenance and transportation, and all that entails. The volume of contaminated soil removed will be based on approved truck scale measurement and the quantity will be approved by the Contracting Officer. Any work under this CLIN will not proceed without prior written approval and field verification from the Contracting Officer.

h) For CLIN 0001G: Price to provide First Responder Distributed Antennae Systems within LP-48A:

Provide First Responder Distributed Antennae System within all or parts of LP-48A as indicated by results of RF Survey included as part of Base Bid in accordance with the drawings and specifications.

i) For CLIN 0008 OPTION Item No. 7: Geotechnically Unsuitable Subgrade Soil Removal, Disposal, and Replacement: Unit price for all work in connection with the removal, disposal, and replacement of geotechnically unsuitable subgrade soil (i.e. soft subgrade soils) with imported structural back fill or imported aggregate as specified. Unsuitable subgrade soil determinations must be made by the Government Geotechnical Engineer and approved by the Contracting Officer. The price shall include removal of geotechnically unsuitable soils identified during proof rolling of planned subgrades, disposal at the specified disposal facility, and backfilling the excavation with compacted imported structural backfill or imported aggregate. Soils disturbed by the contractor's construction activities, or that are excessively wet and soft due to lack of proper site maintenance

Norfolk, Virginia Attachment H and protection measures, and lack of specified drainage or excavation dewatering will not be considered unsuitable. Unit price shall include all handling and transportation. The volume of material removed and imported backfill required shall be neat quantities determined based on field measurements (length x width x depth) of the completed excavation to remove the unsuitable soil as approved by the Contracting Officer. Any work under these CLIN's will not proceed without prior written approval of the Contracting Officer and direction of the Government Geotechnical Engineer.

j) For CLIN 0009 OPTION Item No. 8: Unit price for providing demolition and excavation of buried concrete foundations/structures, utility lines and construction debris that is encountered within planned excavation limits and not identified in the Contract Documents for demolition, greater than ½ cubic yard in size. Buried concrete foundations/structures, utility lines and debris meeting the specified criteria will be field verified by the Contracting Officer prior to removal and will be segregated from the surrounding soil during demolition and excavation operations. Pieces of buried concrete and debris encountered within the planned excavation limits smaller than ½ cubic yard in size shall be considered to be incidental to the work. Unit price shall include all work in connection with buried concrete and debris removal and disposal and replacement with clean imported structural backfill or other material specified. Unit price shall include removal and disposal of buried concrete, utility lines and construction debris encountered within planned excavations at a permitted licensed disposal facility and backfilling the excavation with compacted clean imported structural backfill or other material specified. Unit price shall include handling and transportation.

The volume of buried concrete and debris removed will be based on approved truck scale measurement and the quantity will be approved by the Contracting Officer. Any work under this CLIN will not proceed without prior written approval and field verification from the Contracting Officer.

k) For CLIN 0010 OPTION Item No. 9: Removal and disposal of buried asbestos containing pipe insulation: Unit price for providing all work in connection with identifications, sampling, removal, and disposal of buried asbestos containing pipe insulation. If suspect pipe insulation or pipe fitting insulation is encountered during excavation the Contractor must stop work in the immediate area until the material is properly identified (sampled) and addressed. The Contracting Officer, government Environmental Design Specialist, and Installation asbestos manager must be notified prior to sampling the pipe insulation/pipe fitting insulation. The quantity will be determined based on field measurements that are agreed upon by the Contracting Officer, government Environmental Design Specialist, Installation asbestos manager, and Contractor. Work from this line item must not proceed without prior field verification and written approve from the Contracting Officer.

BID NOTES FOR ESS, FF&E AND A/V (LINE ITEMS 0002 – 0007)

a) The estimated amount for FF&E, A/V, and ESS has been supplied by the Government, to provide offerors with the projected magnitude of effort. The estimated amount includes the actual cost of the FF&E, A/V, and ESS including freight and installation charges. The Government FF&E, A/V, and ESS Estimate is only an estimated amount.

b) If awarded, line items will be funded separately after completion of FF&E, A/V, and ESS design package review by the Government, and receipt of appropriate funding by the Government, and receipt of appropriate funding by the Government. Requirements and details for FF&E are provided in Section 12 00 01.00 20 FURNITURE, FIXTURES, AND EQUIPMENT (FF&E)

PACKAGE.

c) Bonding

1) Bonding is not required for the design, procurement and installation of FF&E at time of

Construction Contract Award.

Norfolk, Virginia Attachment H

FAR 28.102-1(a) requires that performance and payment bonds be included in all construction contracts exceeding the SAT, except under the conditions listed. Since the FF&E Option Item is not part of the original contract award, the Construction Contractor must not be required to secure bond for the FF&E at the time the basic contract is awarded.

2) Additional Bond at FF&E Option Item Award

FAR 28.102-2(d) requires the Government to secure additional bond from the Construction Contractor for any contract price increases. Therefore, an increase to the original contract bond is required at the time of the FF&E Option Items award, to protect the Government against the Construction Contractor not providing FF&E ordered and to ensure that the vendor(s) receive payment if the Construction Contractor goes out of business. The increased cost of the bond must come from the FF&E funding source and is not a part of the Construction Contractor’s HAR.

3) Bonds Required by the Construction Contractor

If the Construction Contractor requires bonding from the FF&E subcontractor(s), the cost must be covered in the Construction Contractor’s HAR.

d) Offerors may propose a Handling and Administration Rate (HAR) for the FF&E, A/V, and ESS not to exceed 5 percent. This fee will account for all administrative costs, overhead, bonding fees, administration of subcontracts, profit, and any other costs associated with and related to the coordination and processing of the procurement and installation of FF&E, A/V, and ESS. The proposed HAR percentage will be incorporated into the contract award and will not be adjusted regardless of fluctuations from the estimate amount for the FF&E, A/V, and ESS. The proposed HAR is a fixed rate.

e) The Government is not obligated to award Line Items 0002, 0003, 0004, 0005, 0006 and 0007.

Should the Government choose to award ESS, FFE and AV, the line item will be awarded as a negotiated modification to the contract/task order. The Contractor's proposed HAR will be applied to all vendor/supplier costs for the FF&E, A/V, and ESS.

f) If awarded, the FF&E, A/V, and ESS modification will be awarded at least six months prior to the contract completion date. A minimum of six months is required for the Contractor to purchase, deliver and install the FF&E, A/V, and ESS without impacting the overall completion date of the project. The Contractor's schedule must assume the award of the FF&E, A/V, and ESS as a option. No schedule extensions will be granted if the option is awarded at least eight months prior to the contract completion date. If the Government decides to negotiate and award the furniture option with less than six months prior to the contact completion date, the Contractor may be entitled to a contract extension and extended field overhead. A contract extension and extended field overhead will only be granted in those cases where the Contractor demonstrates that an accepted Final FF&E, A/V, and ESS package was submitted within the approved schedule deadlines and sufficient lead time for the FF&E, A/V, and ESS is not available and the Government's award of the option is in the last six months of the contract.