About this file

This document is Section 01 31 23.13 20 of the specifications for FY 24 MCON Project P-222, MQ-25 Aircraft Laydown Facilities at Naval Station, Norfolk, Virginia, effective August 2023 with Change 1 dated February 2024. The section establishes requirements for the Electronic Construction and Facility Support Contract Management System (eCMS), a web-based platform for transferring, sharing, and managing electronic technical submittals and project documentation between the contractor and government.

The contractor must utilize eCMS as the mandatory system for all document submissions, with no paper media or email submissions permitted unless specifically identified in the contract. The contractor is responsible for all associated costs and time to utilize the system with no time extensions or additional government costs. Key personnel requiring eCMS access include the Project Manager, Superintendent, Quality Control Manager, Principal, and Site Safety and Health Officer. The contractor must provide a personnel list within 20 calendar days of contract award, with immediate notification of any personnel changes. User accounts are managed by the Contracting Officer's Representative (COR), who controls access privileges and roles. Users found conducting inappropriate actions including fraudulent representations, account sharing, or unauthorized record changes may have their access revoked temporarily or permanently, with appeal rights within 14 calendar days.

All project documentation must comply with security classification requirements, with unclassified data marked "U" and proprietary information marked "CUI" (Controlled Unclassified Information). The contractor must establish and maintain eCMS records throughout contract duration using specific modules for different document types: Submittals, RFIs, Daily Reports, Meeting Minutes, Communications, Issues, Punch Lists, Checklists, Non-Compliance Notices, and Flysheets. File naming conventions must use only uppercase letters, lowercase letters, numbers, hyphens, underscores, and periods. Government approval is required for submittals with "G" or "S" classifications, while those without such designations require only Contractor Quality Control approval. In cases where eCMS is unavailable for 8 hours or more, paper or email may be used temporarily, with all final records subsequently recreated in eCMS marked "Processed Outside of eCMS."

View the file

Other files

File Type Posted
Attachment G Individual Small Business Subcontracting Plan.docx DOCX document
Attachment F Small Business Participation Commitment.docx DOCX document
JA ML2650 25R2639 P222 ILDFA Redacted.pdf PDF
Solicitation Amendment N4008525R26390008 SF 30.pdf PDF
K3237099 LP-48 HazMat Report 3.5.26 - signed.pdf PDF
Amendment 0007 Continuation Sheet.pdf PDF
Solicitation Amendment N4008525R26390007 SF 30.pdf PDF
REGISTER.pdf PDF
TABLE OF CONTENTS.pdf PDF
13 49 20.00 10.pdf PDF
Solicitation Amendment N4008525R26390006 SF 30.pdf PDF
P222_1737012_01 91 00.15 22.pdf PDF
Crane - LP48 1-DATA SHEET.pdf PDF
P222_1737012_Geotech Report.pdf PDF
P222_1737012_28 31 76.pdf PDF
Attachment H - Price Proposal Form_rev1.pdf PDF
P222_1737012_Drawings_volume II_Rev 001_SIGNED.pdf PDF
Solicitation Amendment N4008525R26390005 SF 30.pdf PDF
P222_1737012_04 20 00.pdf PDF
Amendment 0005 Continuation Sheet.pdf PDF
P222_1737012_32 13 13.06.pdf PDF
P222_1737012_09 29 00.pdf PDF
P222_1737012_07 60 00.pdf PDF
FY26 Naval Station Norfolk Utility Costs.pdf PDF
P222_1737012_07 21 13.pdf PDF
P222_1737012_REGISTER.pdf PDF
P222_1737012_Drawings_volume I_Rev 001_SIGNED.pdf PDF
P222_1737012_13 34 20.pdf PDF
Crane - LP48 2-DATA SHEET.pdf PDF
Solicitation Amendment N4008525R26390004 SF 30.pdf PDF
JA ML2623 25R2639 P222 ASSA Abloy Redacted.pdf PDF
JA ML2624 25R2639 P222 SRG RF Shielding Redacted.pdf PDF
26R2639 P222 Site Visit Log.pdf PDF
Solicitation Amendment N4008525R26390003 SF 30.pdf PDF
Solicitation Amendment N4008525R26390002 SF 30.pdf PDF
Solicitation Amendment N4008525R26390001 SF 30.pdf PDF
Attachment B - PIEE Vendor Access Instructions.pdf PDF
1737012_dwg 02of02_P222.pdf PDF
Attachment M - P222 Site Visit Map.pdf PDF
1737012_spec 01of04_P222.pdf PDF
1737012_dwg 01of02_P222.pdf PDF
Attachment C- Construction Experience Project Data.docx DOCX document
Attachment D- Past Performance Questionnaire.docx DOCX document
Attachment H - Price Proposal Form.pdf PDF
Attachment E- Historical Small Business Utilization.docx DOCX document
Attachment G- Individual Small Business Subcontracting Plan.docx DOCX document
1737012_spec 04of04_P222.pdf PDF
Attachment F- Small Business Participation Commitment.docx DOCX document
Attachment L - JA ML-26-01 P222 MQ25 Hangar Brand Name or Equal Finishes_Reda.pdf PDF
1737012_spec 03of04_P222.pdf PDF
Show 40 more

Latest 50 of 56 listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

FY 24 MCON Project P-222 eProject Work Order No: 1737012 MQ-25 Aircraft Laydown Facilities Naval Station, Norfolk, Virginia

SECTION 01 31 23.13 20

ELECTRONIC CONSTRUCTION AND FACILITY SUPPORT CONTRACT MANAGEMENT SYSTEM

(eCMS)

08/23, CHG 1: 02/24

PART 1 GENERAL

1.1 CONTRACT ADMINISTRATION

Utilize the Naval Facilities Engineering Systems Command's (NAVFAC's) Electronic Construction and Facility Support Contract Management System (eCMS) for the transfer, sharing, and management of electronic technical submittals and documents. The web-based eCMS is the designated means of transferring technical documents between the Contractor and the Government. Paper media or email submission, including originals or copies, of the documents are not permitted unless identified within the contract.

All government contracting specialist/officer, legal, and command communications will remain the same.

1.2 USER PRIVILEGES

The Contractor's key staff may be provided access to eCMS. Contact the COR for eCMS account access. Project roles and system roles will be established to control each user's menu, application, and software privileges, including the ability to create, edit, or delete objects.

Additional project roles may be assigned for workflow. The COR makes the final decision on roles for the project. User's ability to view, edit documents may be lowered at the discretion of the COR.

Only one eCMS user account is required regardless of the number of user's projects. Notify the COR within seven calendar days if a contractor user is no longer associated with company or project so they can remove them from any open record and inactivate them from the project.

1.2.1 eCMS Subcontractor Users

If the contractor's user is a subcontractor, the subcontractor must be registered under the name of their company and email. For example it is common for contractors to contract Quality Control Managers. The QC Manager's account should be under their company's name and email reducing the number of eCMS accounts required.

1.2.2 Users with Multiple Roles

Users may have multiple roles associated with their account within eCMS.

Roles are used in workflow. When a user is added to the project, they will be assigned the default role when the user was created. Contact the COR to change or add roles to the user for the project.

1.2.3 Loss of Privilege

Users may lose privilege to access eCMS at the discretion of the Contracting Officer. The eCMS is a collaborative system that allows flexibility of use and does not restrict all inappropriate user actions.

User activities are logged into eCMS in visible and background data

SECTION 01 31 23.13 20 Page 1 collection. Users found to use eCMS in an inappropriate action may have their eCMS access revoked. Examples include, but not limited to, fraudulent representations, sharing user accounts with others, and changing approved records without the consent of the COR. Depending on the severity of the infraction, the users can lose eCMS access for a period of time, permanently for the project, or lose eCMS access for any project. The contractor may appeal the suspension in writing to the contracting officer within 14 calendar days of notice. The appeal must identify the infraction, supporting information, and steps to ensure the infraction will not happen in the future.

1.3 SUBMITTALS

Government approval is required for submittals with a "G" or "S" classification. Submittals not having a "G" or "S" classification are for Contractor Quality Control approval. Submit the following in accordance with Section 01 33 00 SUBMITTAL PROCEDURES:

SD-01 Preconstruction Submittals

List of Contractor's Personnel ; G

For Division 1 government approved Pre-Construction submittals, combine into a single Pre-Construction Submittal Package.

Annotated with SD Type of SD-01. Pre-Construction submittal package approval date will be used as a KPI.

1.4 SYSTEM REQUIREMENTS AND CONNECTIVITY

1.4.1 General

NAVFAC eCMS requires a web-browser (platform-neutral) and Internet connection. For best results, recommend using browser in InPrivate/Incognito mode; Internet speeds greater than 40mbps when uploading files, computers with high RAM and Solid State Drives, "White List" eCMS website, Zip or Split files for better uploading. Non-NAVFAC Users are not to use VPN when using eCMS per NAVFAC IT.

The use of eCMS is required by the Contractor and all associated costs and time necessary to utilize eCMS will be borne by the Contractor with no allowance for time extensions and at no additional cost to the government.

1.4.2 Contractor Personnel List

Within 20 calendar days of contract award, provide to the Contracting Officer a list of Contractor's personnel who will have the responsibility for the transfer, sharing and management of electronic submittals, RFIs, daily reports, and other files and will require access to the eCMS.

Project personnel roles which must be filled as applicable in the eCMS, include, at a minimum, the Contractor's Project Manager (KTR-PM), Superintendent (KTSUPT), Quality Control (QC) Manager (KTR-QC), Principal (KTR-PRIN), and Site Safety and Health Officer (KTR-SSHO). Notify the COR immediately of any personnel changes to the project. The Contracting Officer reserves the right to perform a security check on all potential users.

Provide the following information:

Company Name

SECTION 01 31 23.13 20 Page 2

Name (First, Last)

Email Address

Project Role (CQM, SSHO, Superintendent, CM, PM, Principal)

Existing or New eCMS User

1.5 SECURITY CLASSIFICATION

In accordance with Department of Navy guidance, all military construction contract data are unclassified, unless specified otherwise by a properly designated Original Classification Authority (OCA) and in accordance with an established Security Classification Guide (SCG). Refer to the project's OCA when questions arise about the proper classification of information.

In conformance with the Freedom of Information Act (FOIA), DoD INSTRUCTION 5200.48 CONTROLLED UNCLASSIFIED INFORMATION (CUI), and DoD requirements, any unclassified project documentation uploaded into the eCMS must be designated either "U - UNCLASSIFIED" (U) or "CUI - CONTROLLED UNCLASSIFIED INFORMATION" (CUI).NAVFAC eCMS must only be used for the transaction of unclassified information associated with construction projects. Controlled Unclassified Identification (CUI) documents may be loaded into eCMS with the appropriate markings.

1.5.1 Markings on CUI Documents

Contractor's proprietary information, or documents determined by the originator in accordance with CUI guidance, should be marked CUI.

Proprietary information not marked CUI can be released under the Freedom of Information Act (FOIA). Apply the appropriate markings before any document is uploaded into eCMS. Markings are not required on Unclassified U documents.

1.6 eCMS UTILIZATION

Establish, maintain, and update data and documentation in the eCMS throughout the duration of the contract. Utilize eCMS to transfer all submittals, RFIs, daily reports, and other files required by contract to be forwarded to the government.

Full eCMS use is required. All Submittals/Information to use eCMS Modules including, but not limited to, RFIs, Daily Reports, Meeting Minutes, Communications, Issues, Punch Lists, Checklists, and Flysheets, unless otherwise directed by the COR or Contracting Officer.

1.6.1 Restricted Information

Personally Identifiable Information (PII) transmittal such as credit card, driver's license, passport, social security, and payroll number are not permitted in eCMS. Name, address, and email are permitted.

Pre-negotiation information such as cost estimates that require formal negotiations are not allowed. For example, proposed changes over the SAP level of $250k require formal negotiations. Cost estimates for LEAN, ULTRA LEAN, and Design Changes under the SAP level are at the discretion of the COR's or Contract Specialist/Officer's direction. The eCMS must only be used for the transaction of unclassified information associated

SECTION 01 31 23.13 20 Page 3 with construction projects. Controlled Unclassified Identification (CUI) documents may be loaded into eCMS with the appropriate markings.

Uploading of files directly into the Documents folder is not allowed. All documents must be uploaded using an eCMS module.

1.6.2 Naming Convention for Files

Titles of files uploaded are to be descriptive of the purpose and content of the file. For example RFI_ROOF_Leak.doc or for submittals, SUB_LIGHT_FIXTURE.pdf. Titles of file to be uploaded must only contain uppercase letters, lowercase letters, numbers, hyphens (-), underscores (_) and periods (.). Use of any other characters is not allowed and may create an error. When practicable, adding the record number to the title is desired. For example RFI_XYZ12345_ROOF_Leak.doc. Uploading files with the same title will create a new revision in eCMS. Original revision is Rev 0, the first revision is Rev 1. Uploaded files are to use the default file location regardless of the module used unless directed by the COR.

Table 1 also identifies which eCMS application is to be used in the transmittal of data (these are subject to change based on the latest software configuration).

Table 1 - Project Documentation Types

SUBJECT/NAME REMARKS eCMS APPLICATION

As-Built Drawings Locations of sensitive areas must be labeled as either "Controlled Area" or "Restricted Area" and may be shown on unclassified documents with the approval from Site Security Manager

Submittals

Building Information Modeling (BIM)

Locations of sensitive areas must be labeled as either "Controlled Area" or "Restricted Area" and may be shown on unclassified documents with the approval from Site Security Manager

Submittals

Construction Permits Refer to rules of the issuing activity, state or jurisdiction

Submittals

Construction Schedules (Activities and Milestones)

Submittals

Construction Schedules Submittals

Construction Schedules (3-Week Look ahead)

Import the schedule file into the scheduling application, and select "Approve" to establish a new schedule baseline

Meeting Minutes

SECTION 01 31 23.13 20 Page 4

SUBJECT/NAME REMARKS eCMS APPLICATION

DD 1354 Transfer of Real Property

When applicable, required for final billing.

Submittals

Daily Production Reports

Provide weather conditions, crew size, man-hours, equipment, and materials information

Daily Report

Daily Quality Control (QC) Reports

Provide QC Phase, Definable Features of Work Identify visitors

Daily Report

Designs and Specifications

Locations of sensitive areas must be labeled as either "Controlled Area" or "Restricted Area" and may be shown on unclassified documents with the approval from Site Security Manager

Submittals

Environmental Notice of Violation (NOV), Corrective Action Plan

Refer to rules of the issuing activity, state or jurisdiction

Submittals

Environmental Protection Plan (EPP)

Submittals

Invoice (Supporting Documentation)

Applies to supporting documentation only. Invoices are submitted in Wide-Area Workflow (WAWF)

Submittals

Jobsite Documentation, Bulletin Board, Labor Laws, SDS

Redact any PII information when loaded into eCMS

Submittals

Meeting Minutes Meeting Minutes

Modification Documents Provide final modification documents for the project. Upload into Modifications RFPs folder

Communications

Operations & Maintenance Support Information (OMSI/eOMSI), Facility Data Worksheet

1. Locations of sensitive areas must be labeled as either "Controlled Area" or "Restricted Area" and may be shown on unclassified documents with the approval from Site Security Manager

2. Design reviews will be performed in existing "Dr Checks"

Submittals

SECTION 01 31 23.13 20 Page 5

SUBJECT/NAME REMARKS eCMS APPLICATION

Photographs Subject to base/installation restrictions Submittals

QCM Initial Phase Checklists

Meeting Minutes or Checklists

QCM Preparatory Phase Checklists

Meeting Minutes or Checklists

Quality Control Plans Submittals

QC Certifications Submittals

QC Punch List Punch Lists

Red-Zone Checklist Punch List or Checklists

Rework Items List Punch Lists

Request for Information (RFI) Post-Award

RFIs

Safety Plan Submittals

Safety - Activity Hazard Analyses (AHA)

Submittals

Safety - Mishap Reports Daily Report

Shop Drawings Locations of sensitive areas must be labeled as either "Controlled Area" or "Restricted Area" and may be shown on unclassified documents with the approval from Site Security Manager

Submittals

Storm Water Pollution Prevention (Notice of Intent - Notice of Termination)

Refer to rules of the issuing activity, state or jurisdiction

Submittals

Submittals and Submittal Register

Submittals

SECTION 01 31 23.13 20 Page 6

SUBJECT/NAME REMARKS eCMS APPLICATION

Testing Plans, Logs, and Reports

Submittals

Training/Reference Materials

Submittals

Training Records (Personnel)

Redact any PII information if storing in eCMS

Submittals

Utility Outage/Tie-In Request/Approval

Submittals

Warranties/BOD Letter Submittals

Quality Assurance Reports

Checklists (Government initiated)

Non-Compliance Notices Non-Compliance Notices (Government initiated)

Other Government-prepared documents

GOV ONLY

Letters to government contracting, claims, REAs, and other contracting officer communications eCMS is not the primary tool to use in contracting officer communications. eCMS can only store documents or letters after the submission to the contracting officer is made.

Communications

All Othere Documents Refer to FOIA guidelines and contact the FOIA official to determine whether exemptions exist

As applicable

1.6.3 RFIs Module

Create contractor RFIs using eCMS RFIs module. The contractor must confirm the numbering convention with the COR if different than eCMS default.

If the government (GOV) Response has "No" Cost or Schedule Impact, this reply is given with the expressed understanding that it does not constitute a basis for any change in the amount or time of subject contract. Information provided in this response does not authorize work not currently included in the contract. If GOV Response is "Yes" or "Potentially" then this response may require a change to the contract. If the contractor disagrees with either the government's No Cost determination or No Schedule impact determination, or both, the contractor has 14 calendar days to notify the COR and Contracting Officer in writing.

SECTION 01 31 23.13 20 Page 7

1.6.4 Submittals Module

Create contractor submittals using eCMS Submittals module. The contractor must confirm the numbering convention with the COR if different than eCMS default.

1.6.5 Submittal Packages Module

Create submittal packages using the eCMS Submittal Packages module in lieu of or in addition to Related Objects. Submittal Packages track completion of the packaged submittals and is used in NAVFAC HQ's KPIs.

1.6.6 Communications Module

Create communications using the eCMS Communications module. The Communications module is used to create or document communications that are not a part of other eCMS modules. Use of Communications module will memorialize information into an eCMS record file. The following are Types of Communications:

Email

Memo to File

Face to Face

Telephone

Web Collaboration

Photos

Other Documents

Other

Unless directed by the COR, upload documents or files that do not have a corresponding eCMS module. Choose "Photos" Type for Photos and "Other Documents" for all other documents.

1.6.7 Issues Module

Create or respond to issues using the eCMS Issues module. Respond to CPARS issues using the Issues module.

1.6.8 Meeting Minutes Module

Create or respond to Meeting Minutes using the eCMS Meetings module.

Document required contractual meetings. Dates of meetings are used in NAVFAC KPIs. Minimum meetings in eCMS include the following:

Post Award Kickoff (PAK)

Pre-construction (Pre Con)

Initial and Preparatory Three Phases of Control

SECTION 01 31 23.13 20 Page 8

Quality Control (QC)

1.6.9 Potential Change Items Module

Not used.

1.6.10 Daily Report Module

Create Daily Reports using the eCMS Daily Report Module. The contractor must confirm the numbering convention with the COR if different than eCMS default.

1.6.11 Punchlists Testing Logs (Legacy)

Punchlist Testing Logs is a legacy program that is being replaced by the Punch Lists Module. This module is to be used for reference of past projects. Use the Punch Lists Module for all future work.

1.6.12 Punch Lists Module

The eCMS Punch Lists module is useful more than just for Punchlists. The module includes the capability of batch editing, create items from Optical Character Recognition (OCR) plans, assign tasks and track completion of individual items.

Create the following using the Punch Lists module:

Rework Items List

DFOW List

Punch-Out Inspection

Pre-Final Punchlist Inspection

Final Punchlist Inspection

Testing Logs

1.6.13 FWD UltraLean COAR RFP Module

Not used.

1.6.14 Non-Compliance Notices (NCN) Module

Respond to Non-Compliance Notices listed in the Non-Compliance Notices module.

1.6.15 Checklists

Use Checklist listed in the contractor's eCMS menu and as directed by the COR. Checklists capture data and is used in dashboards and KPIs.

1.6.15.1 Partnering Team Health Survey Checklist

Contractor must use the eCMS checklist to document the partnering team health survey. Partnering Team Health Survey is in accordance with the Partnering Specification of this contract.

SECTION 01 31 23.13 20 Page 9

1.6.16 Flysheets

Use Flysheets listed in the contractor's eCMS menu, if available, and as directed by the COR. Flysheets allow the contractor to print out information from other systems and upload into eCMS. The eCMS will use OCR to capture the information as data. Flysheets capture data and used in dashboards and KPIs.

1.6.17 eCMS Outage

In the case where eCMS is unavailable for 8 hours or more, paper or email may be used in the interim to maintain project schedule.

Once the system is operational, all final records are required to be recreated using the appropriate module. Subject/title of the record to include the type of record i.e., RFI/Submittal/Daily Report/Communication/Other, the identification number(s), and the statement "Processed Outside of eCMS". Example, "RFI 001 Processed Outside of eCMS".

1.6.18 User Account Activity

NAVFAC eCMS captures user data and activities that are directly related to the user's account. The user agrees through the use of eCMS, their account activities will be captured and can be displayed on eCMS printed reports.

1.7 QUALITY ASSURANCE

Requested Government response dates on Submittals must be in accordance with the terms and conditions of the Contract unless previously agreed by the COR. Requesting response dates earlier than the required review and response time, without concurrence by the Government COR, may be cause for rejection.

Incomplete submittals will be rejected without further review and must be resubmitted. Required Government response dates for resubmittals must reflect the date of resubmittal, not the original submittal date.

All submittals and associated attachments must be transmitted to the Government via the COR. Transmittals are no longer required when using eCMS since approval status is tracked on the submittal. Transmittal forms can be attached to submittals if approved by the COR. Submittals requiring government approval are "Transmitted For" "Approval".

Submittals requiring contractor approved submittals, including those designated for Contractor Quality Control approval or Information Only, are "*Transmitted For" "Information Only" in the Submittal Module.

Provide and sign the QC certification or approving statement on the attachment per submittal specification section. When Submittal Packages are required, use eCMS Submittal Packages after creating individual submittals. Importing Submittals from the Submittal Register is optional. Contact the COR for the data conversion requirements.

SECTION 01 31 23.13 20 Page 10

PART 2 PRODUCTS

Not used.

PART 3 EXECUTION

Not used.

-- End of Section --

SECTION 01 31 23.13 20 Page 11

THIS PAGE INTENTIONALLY LEFT BLANK

SECTION 01 31 23.13 20 Page 12

01 31 23.13 20 - ELECTRONIC CONSTRUCTION AND FACILITY SUPPORT CONTRACT MANAGEMENT SYSTEM
PART 1 GENERAL
1.1 CONTRACT ADMINISTRATION
1.2 USER PRIVILEGES
1.2.1 eCMS Subcontractor Users
1.2.2 Users with Multiple Roles
1.2.3 Loss of Privilege
1.3 SUBMITTALS
1.4 SYSTEM REQUIREMENTS AND CONNECTIVITY
1.4.1 General
1.4.2 Contractor Personnel List
1.5 SECURITY CLASSIFICATION
1.5.1 Markings on CUI Documents
1.6 eCMS UTILIZATION
1.6.1 Restricted Information
1.6.2 Naming Convention for Files
1.6.3 RFIs Module
1.6.4 Submittals Module
1.6.5 Submittal Packages Module
1.6.6 Communications Module
1.6.7 Issues Module
1.6.8 Meeting Minutes Module
1.6.9 Potential Change Items Module
1.6.10 Daily Report Module
1.6.11 Punchlists Testing Logs Legacy
1.6.12 Punch Lists Module
1.6.13 FWD UltraLean COAR RFP Module
1.6.14 Non-Compliance Notices NCN Module
1.6.15 Checklists
1.6.15.1 Partnering Team Health Survey Checklist
1.6.16 Flysheets
1.6.17 eCMS Outage
1.6.18 User Account Activity

1.7 QUALITY ASSURANCE

PART 2 PRODUCTS
PART 3 EXECUTION

File details come from the government source that posted it. Updated .