Q_A_Amend 0009.pdf

PDF 53 KB Posted

Attached to
YON-285 Outfit
Solicitation number
N6264926R0013
Issued by

About this file

This is a Questions and Answers document for federal contract solicitation N6264926R00130009, titled "YON 285 Outfit_Additional Solicitation Q&A," issued by the U.S. Navy. The document addresses five key concerns raised by potential offerors regarding the outfit and maintenance of vessel YON 285 at the Sasebo Repair Facility (SRF).

The Government's responses clarify critical contract parameters: the desired work start date is 28 September 2026, with permissible early actions including material ordering, pre-fabrications, dock preparation, and document reviews beginning immediately upon award. Regarding the compressed execution timeline, the Government acknowledges resource limitations and permits offerors to propose their own Period of Performance based on contractor location availability and estimated completion duration. For welding certification requirements, the Government maintains that offerors must hold appropriate certifications per solicitation requirements but will subject all proposed welding processes to strict Government Quality Assurance vetting. Offerors must submit alternate welding standards with objective documentation proving technical equivalence to U.S. Navy standards as part of their technical proposals before award, with formal procedure qualification and approval handled by SRF QA after award. Regarding docking facility availability, the Government is coordinating with the Planning Yard to clarify lifting procedures for the craft and will issue a response following technical review. The Government confirmed that Item No. 518 regarding Government Furnished Material with thicknesses under 0.1875 inches cannot be excluded from contract specifications as it is inherent to the component drawing and installation requirements.

View the file

Other files

File Type Posted
Solicitation Amendment N6264926R00130015 SF 30.pdf PDF
Solicitation Amendment N6264926R00130014 SF 30.pdf PDF
LETTER-130-0011-26.pdf PDF
2.01 Soli Amendment 0013 LAR explaination for KTR.pdf PDF
Solicitation Amendment N6264926R00130012 SF 30.pdf PDF
2.01 Amend 0011 Attachment.pdf PDF
2.01 Solicitation Amendment N6264926R00130011 SF 30.pdf PDF
2.01 Amend 0011 Q&A.pdf PDF
Solicitation Amendment N6264926R00130011 SF 30.pdf PDF
2.01 Solicitation Amendment N6264926R00130011 SF 30.pdf PDF
Solicitation Amendment N6264926R00130010 SF 30.pdf PDF
Solicitation Amendment N6264926R00130009 SF 30.pdf PDF
89MVA15006_00_A01 v2.pdf PDF
89MVA15005_00_A01 v2.pdf PDF
89MVA15002_00_A01 v2.pdf PDF
89MVA86303_00_A01 v2.pdf PDF
89MVA15007_00_A01 v2.pdf PDF
Solicitation Amendment N6264926R00130008 SF 30.pdf PDF
89MVA12301_00_A01 v2.pdf PDF
89MVA15003_00_A01 v2.pdf PDF
89MVA86401_00_A01 v2.pdf PDF
2.01 RFP N6264926R00130006 Q&A YON 285 Outfit.pdf PDF
2.01 Solicitation Amendment N6264926R00130006 SF 30.pdf PDF
Solicitation Amendment N6264926R00130004 SF 30.pdf PDF
Geographical Akasaki YONs.docx DOCX document
YON Location Akasaki.pdf PDF
2.01 Solicitation Amendment N6264926R00130002 SF 30.pdf PDF
89MVA15007_00_A01.pdf PDF
89MVA86301_00_A01.pdf PDF
89MVA86303_00_A01.pdf PDF
Attachment II Price Proposal Form N6264926R0013_Final.xlsx XLSX spreadsheet
89MVA15003_00_A01.pdf PDF
89MVA15006_00_A01.pdf PDF
89MVA86401_00_A01.pdf PDF
89MVA15005_00_A01.pdf PDF
DD1423 YON-285 6B1 DSRA CDRL A006 CONFERENCE REPORT.pdf PDF
DD1423 YON-285 6B1 DSRA CDRL A008 TEMPORARY SERVICES.pdf PDF
YON 285 6B1 Specs 1-4.pdf PDF
YON 285 6B1 Specs 9-11.pdf PDF
Attachment 5 YON 285 6B1 MILESTONE DSRA.xlsx XLSX spreadsheet
DD1423 YON-285 6B1 DSRA CDRL A010 KTR DEFICIENCY REPORTING.pdf PDF
DD1423 YON-285 6B1 DSRA CDRL A002 QUALITY ASSURANCE PROGRAM PLAN.pdf PDF
YON 285 6B1 Specs 5-8.pdf PDF
Attachment 3 YON 285 6B1 CONTRACTOR QUESTIONS.pdf PDF
Attachment 4 YON 285 6B1 DSRA PERL.xlsx XLSX spreadsheet
Attachment 6 YON 285 6B1 CONTRACT DATA SHEET.docx DOCX document
DD1423 YON-285 6B1 DSRA CDRL A005 WEEKLY PROGRESS REPORT.pdf PDF
DD1423 YON-285 6B1 DSRA CDRL A004 DAILY REPORT.pdf PDF
Attachment 2 YON 285 6B1 PROPOSAL BREAKDOWN.xlsx XLSX spreadsheet
DD1423 YON-285 6B1 DSRA CDRL A007 KEY EVENT REPORT.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Solicitation: N6264926R00130009

Title: YON 285 Outfit_Additional Solicitation Q&A

1. Insufficient Preparation Period Post-Award

Based on our operational experience, a minimum of two to three months is required from the contract award to the actual commencement of work. This lead time is essential for securing the necessary personnel and equipment, as well as for the import and procurement of Contractor- Furnished Materials (CFM), including specific coatings/paints. The proposed schedule--with a contract award expected on September 1 and work starting on September 28--provides less than a month, which presents severe logistical risks.

Response: The desired start date for this requirement is 28 September 2026. Upon this start date, any work encompassing action for this project is authorized to commence. Permissible early actions include, but are not limited to, material ordering, pre-fabrications, dock preparation, and document reviews.

2. Insufficient Performance Period (Execution Time)

We evaluate that the proposed execution timeframe is insufficient for a project of this scope. To ensure safe and high-quality completion of the scope of work, a minimum dry-docking period of six months is required.

Response: The Government acknowledges potential resource limitations. The docking schedule may be reworked and amended to alleviate resource constraints. Offerors are permitted to include a proposed Period of Performance (POP) in their submissions. This proposed POP should be based on the contractor's location availability and their estimated duration to complete the required work.

3. Availability of Qualified Welders and Certification Requirements

There is currently a critical shortage of welders in the Sasebo area who meet the specific U.S. Navy qualifications. Furthermore, given that the technical standards required for a barge (YON) differ fundamentally from those for standard surface combatants, compliance with the current rigid requirements is extremely difficult. Unless the welding and Non-Destructive Testing (NDT) requirements are amended to accept alternative commercial certifications (such as ABS, NK, or JIS), it is unfeasible for us to support this project.

Response: While offerors must hold the appropriate welding certifications as required by the solicitation, all proposed welding processes will be subject to strict vetting and approval through the Government's Quality Assurance (QA) program. The following 2-step approach for this requirement is as follows:

A. Before award (RFP requirement): Please submit alternate welding standards along with objective documentation as soon as possible proving technical equivalence to the USN standards as part of your technical proposal/PoP plan.

B. After award: The actual formal vetting, detailed procedure qualification, and final approval of the specific welding procedures will be handled by the SRF QA as soon as possible after award.

Offerors must account for this QA vetting process--including associated timelines and compliance measures--and explicitly address their approach to meeting these QA requirements within their technical proposal. Please submit proposals to use alternate welding qualifications and their associated procedures to the SRF QA Department for consideration as soon as possible.

4. Lack of Available Docking Space

We currently have no available facility or space to dock and dry-dock the vessel. To make execution feasible, we would require the U.S. Navy to provide and make available Dry Dock No. 2 for this project.

Response: We are working with the Planning yard to clarify the lifting of the craft. Response will be sent out once technical review by the designated Planning Yard is complete.

5. We are concerned that we may not be able to handle this project because we do not possess the Welding Procedure Specification (WPS) for thicknesses under 0.1875 inches regarding Item No. 518 under "5. Government Furnished Material (GFM), 5.1 SRF will provide following material. "Therefore, we would appreciate it if you could advise us whether this item can be excluded from the contract specifications, or if there are any alternative solutions we could implement.

Response: We cannot exclude this from the contract since it is inherently apart of the drawing and installation of the component.

File details come from the government source that posted it. Updated .