89MVA86303_00_A01 v2.pdf

PDF 32 KB Posted

Attached to
YON-285 Outfit
Solicitation number
N6264926R0013
Issued by

About this file

This is a Job Specification document for naval shipyard work related to the installation of a temporary head (toilet facility) on Barge YON-285. The work is being conducted at the Sasebo naval facility and is identified by ICN 89MVA86303 with SRF Control Number 1301348511.

The anticipated award date is September 1, 2026, with a production completion date of April 2, 2027. The Period of Performance (POP) runs from September 28, 2026 through May 30, 2027. The work was prepared by H. Muta on January 23, 2026, approved by S. Murakami (Code S225), and concurred by S. Morooka (Code S231). The document includes approval by T. Escritor-Yamada under PMS320 and S300/S900 with a date of February 12, 2024. Additional coordination information is provided for contact and work certification purposes, with fields for completion of work review signatures, badge numbers, shop codes, and phone contact information. The document serves as the formal specification initiating the job order and establishing the timeline and responsible parties for this shipyard maintenance task.

View the file

Other files

File Type Posted
Solicitation Amendment N6264926R00130016 SF 30.pdf PDF
LETTER-130-0011-26.pdf PDF
2.01 Soli Amendment 0013 LAR explaination for KTR.pdf PDF
Solicitation Amendment N6264926R00130013 SF 30.pdf PDF
Solicitation Amendment N6264926R00130012 SF 30.pdf PDF
2.01 Solicitation Amendment N6264926R00130011 SF 30.pdf PDF
Solicitation Amendment N6264926R00130011 SF 30.pdf PDF
2.01 Amend 0011 LETTER-130-0008-26.pdf PDF
Solicitation Amendment N6264926R00130010 SF 30.pdf PDF
Solicitation Amendment N6264926R00130010 SF 30.pdf PDF
Q_A_Amend 0009.pdf PDF
89MVA12301_00_A01 v2.pdf PDF
89MVA15003_00_A01 v2.pdf PDF
89MVA86401_00_A01 v2.pdf PDF
89MVA15004_00_A01 v2.pdf PDF
89MVA11001_00_A01 v2.pdf PDF
89MVA86301_00_A01 v2.pdf PDF
2.01 Solicitation Amendment N6264926R00130006 SF 30.pdf PDF
Solicitation Amendment N6264926R00130005 SF 30.pdf PDF
Q_A.pdf PDF
YON Location Akasaki.pdf PDF
Attachment II Price Proposal Form N6264926R0013_Final.xlsx XLSX spreadsheet
89MVA15003_00_A01.pdf PDF
89MVA15006_00_A01.pdf PDF
89MVA86401_00_A01.pdf PDF
89MVA15005_00_A01.pdf PDF
Solicitation Amendment N6264926R00130003 SF 30.pdf PDF
89MVA15004_00_A01.pdf PDF
89MVA11001_00_A01.pdf PDF
89MVA15002_00_A01.pdf PDF
89MVA12301_00_A01.pdf PDF
Attachment 2 YON 285 6B1 PROPOSAL BREAKDOWN.xlsx XLSX spreadsheet
2.01 Solicitation Amendment N6264926R00130001 SF 30.pdf PDF
Attachment 5 YON 285 6B1 MILESTONE DSRA.xlsx XLSX spreadsheet
DD1423 YON-285 6B1 DSRA CDRL A010 KTR DEFICIENCY REPORTING.pdf PDF
DD1423 YON-285 6B1 DSRA CDRL A002 QUALITY ASSURANCE PROGRAM PLAN.pdf PDF
YON 285 6B1 Specs 5-8.pdf PDF
Attachment 3 YON 285 6B1 CONTRACTOR QUESTIONS.pdf PDF
Attachment 4 YON 285 6B1 DSRA PERL.xlsx XLSX spreadsheet
Attachment 6 YON 285 6B1 CONTRACT DATA SHEET.docx DOCX document
DD1423 YON-285 6B1 DSRA CDRL A005 WEEKLY PROGRESS REPORT.pdf PDF
DD1423 YON-285 6B1 DSRA CDRL A004 DAILY REPORT.pdf PDF
Attachment 2 YON 285 6B1 PROPOSAL BREAKDOWN.xlsx XLSX spreadsheet
DD1423 YON-285 6B1 DSRA CDRL A007 KEY EVENT REPORT.pdf PDF
DD1423 YON-285 6B1 DSRA CDRL A003 IPS.pdf PDF
DD1423 YON-285 6B1 DSRA CDRL A001 GFMnot.pdf PDF
2.01 Solicitation - N6264926R0013.pdf PDF
DD1423 YON-285 6B1 DSRA CDRL A006 CONFERENCE REPORT.pdf PDF
DD1423 YON-285 6B1 DSRA CDRL A008 TEMPORARY SERVICES.pdf PDF
YON 285 6B1 Specs 1-4.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Shi /HULL NO. Shi /HULL NAME

YON-285 BARGE JON:

ICN:

89MVA86303

Rev:

TITLE:

Temporary Head; provide

JOB SPECIFICATION

Anticipated Award Date: Production Completion Date: PREPARING ACTIVITY:

,/.al/ ~o~, 02/02/2027 POP Start Date: POP End Date: SASEBO

19/28/2026 'I-/ dO/ -M~,-.

PREPARED BY: CODE DATE

H. MUTA H MU 1/23/2026

APPROVED BY: G).,/\ CODE

$.MURAKAMI S225

CONCURRED BY: /2.,#v CODE

S. MOROOKA S231

ASSIST PLANNER'S NAME:

CODE

ASSIST PLANNER'S NAME: CODE

ASSIST PLANNER'S NAME: CODE

DESCRIPTION:

JSN(Sl: NIA CA§REP#

S/F CONTACT: N/A CWP# CCNS#

T. ESCRITOR-YAMADA

PMS320

Date: eh~ (yO Ht

Approved by S300/S900

Avl: ~

LWC:

Work Completed

S/Force: Rate: Date:

Ship Supt: Date: SRF CONTROL NO.: 1301348511

WQRK CERTIFICATION SIGNATURES

Key Op:

A01

COMPLETION OF WORK REVIEW: BADGE NO.: SHOP/CODE: PHONE: DATE:

Tasuku.Nagano.ja Text Box 9/1/2026

Tasuku.Nagano.ja Text Box 4/2/2027

Tasuku.Nagano.ja Text Box 5/30/2027

File details come from the government source that posted it. Updated .