89MVA15007_00_A01 v2.pdf

PDF 29 KB Posted

Attached to
YON-285 Outfit
Solicitation number
N6264926R0013
Issued by

About this file

This is a Job Specification document for a knuckle crane installation on Barge YON-285. The work is identified by ICN 89MVA15007, Revision A01, and is being prepared by the Sasebo facility. The anticipated award date is 9/1/2026, with a production completion date of 4/2/2027. The Period of Performance (POP) runs from 9/8/2026 through 5/30/2027.

The specification is organized into three parts: Part I covers hull work (pages 2-5) under S. Noda; Part II addresses machinery work (pages 6-26) under T. Ookubo and electrical work under J. Sakurai; and Part III covers pipe work (pages 27-31) under T. Yoahinaga. The document was prepared by S. Noda (H_NO) on 1/30/2026, approved by S. Murakami (S225), and concurred by S. Morooka (S231). The work is managed under PM S320 with T. Escritor-Yamada listed as the S/F contact. Approval by S300/S900 was granted on 2/12/2027. The SRF Control Number is 130/130 S/1. The document includes space for work completion certification signatures, including badge number, shop/code, phone, and date fields, though these sections remain incomplete on the provided copy.

View the file

Other files

File Type Posted
Solicitation Amendment N6264926R00130016 SF 30.pdf PDF
LETTER-130-0011-26.pdf PDF
2.01 Soli Amendment 0013 LAR explaination for KTR.pdf PDF
Solicitation Amendment N6264926R00130013 SF 30.pdf PDF
Solicitation Amendment N6264926R00130012 SF 30.pdf PDF
2.01 Solicitation Amendment N6264926R00130011 SF 30.pdf PDF
Solicitation Amendment N6264926R00130011 SF 30.pdf PDF
2.01 Amend 0011 LETTER-130-0008-26.pdf PDF
Solicitation Amendment N6264926R00130010 SF 30.pdf PDF
Solicitation Amendment N6264926R00130010 SF 30.pdf PDF
Q_A_Amend 0009.pdf PDF
89MVA12301_00_A01 v2.pdf PDF
89MVA15003_00_A01 v2.pdf PDF
89MVA86401_00_A01 v2.pdf PDF
89MVA15004_00_A01 v2.pdf PDF
89MVA11001_00_A01 v2.pdf PDF
89MVA86301_00_A01 v2.pdf PDF
2.01 Solicitation Amendment N6264926R00130006 SF 30.pdf PDF
Solicitation Amendment N6264926R00130005 SF 30.pdf PDF
Q_A.pdf PDF
YON Location Akasaki.pdf PDF
Attachment II Price Proposal Form N6264926R0013_Final.xlsx XLSX spreadsheet
89MVA15003_00_A01.pdf PDF
89MVA15006_00_A01.pdf PDF
89MVA86401_00_A01.pdf PDF
89MVA15005_00_A01.pdf PDF
Solicitation Amendment N6264926R00130003 SF 30.pdf PDF
89MVA15004_00_A01.pdf PDF
89MVA11001_00_A01.pdf PDF
89MVA15002_00_A01.pdf PDF
89MVA12301_00_A01.pdf PDF
Attachment 2 YON 285 6B1 PROPOSAL BREAKDOWN.xlsx XLSX spreadsheet
2.01 Solicitation Amendment N6264926R00130001 SF 30.pdf PDF
Attachment 5 YON 285 6B1 MILESTONE DSRA.xlsx XLSX spreadsheet
DD1423 YON-285 6B1 DSRA CDRL A010 KTR DEFICIENCY REPORTING.pdf PDF
DD1423 YON-285 6B1 DSRA CDRL A002 QUALITY ASSURANCE PROGRAM PLAN.pdf PDF
YON 285 6B1 Specs 5-8.pdf PDF
Attachment 3 YON 285 6B1 CONTRACTOR QUESTIONS.pdf PDF
Attachment 4 YON 285 6B1 DSRA PERL.xlsx XLSX spreadsheet
Attachment 6 YON 285 6B1 CONTRACT DATA SHEET.docx DOCX document
DD1423 YON-285 6B1 DSRA CDRL A005 WEEKLY PROGRESS REPORT.pdf PDF
DD1423 YON-285 6B1 DSRA CDRL A004 DAILY REPORT.pdf PDF
Attachment 2 YON 285 6B1 PROPOSAL BREAKDOWN.xlsx XLSX spreadsheet
DD1423 YON-285 6B1 DSRA CDRL A007 KEY EVENT REPORT.pdf PDF
DD1423 YON-285 6B1 DSRA CDRL A003 IPS.pdf PDF
DD1423 YON-285 6B1 DSRA CDRL A001 GFMnot.pdf PDF
2.01 Solicitation - N6264926R0013.pdf PDF
DD1423 YON-285 6B1 DSRA CDRL A006 CONFERENCE REPORT.pdf PDF
DD1423 YON-285 6B1 DSRA CDRL A008 TEMPORARY SERVICES.pdf PDF
YON 285 6B1 Specs 1-4.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Ship/HULL NO. Ship/HULL NAME ICN: Rev: Key Op:

YON-285 BARGE

JON: 89MVA15007 A01

TITLE:

Knuckle Crane; Install

JOB SPECIFICATION

Anticipated Award Date: Production Completion Date: PREPARING ACTIVITY:

9/1/ ~~l y./ 1/ ~~, POP Start Date: POP End Date: SASEBO

9 / ~ / -U).)._t ~ I d0/ ..:\..o ..)_/

PREPARED BY: CODE DATE

S.NODA H NO 1/30/2026

APPROVED BY: ~Ml\ CODE

S.MURAKAMI S225

CONCURRED BY: 1',?/b CODE

S.MOROOKA S231 .

PART-I HULL-WORK: S.NODA (H_NO) ----------- Page 2 through 5 PART-II MACH-WORK: T.OOKUBO (M_OO) --------- Page 6 through 26

ELEC-WORK: J.SAKURAI (E_SJ)

PART-III PIPE-WORK: T.YOAHINAGA (P_YO) ------ Page 27 through 31

DESCRIPTION:

JSN(S): CASREP#

S/F CONTACT: CWP# CCNS#

T. ESCRITOR-YAMADA

PM S320 2-lpi-n::t Approved by S300/S900

Date: AVL: 7B1

LWC:

Work Completed

S/Force: Rate: Date:

Ship Supt: Date: SRF CONTROL NO.: ldDIJ'i_~S/l

WORK CERTIFICATION SIGNATURES

COMPLETION OF WORK REVIEW: BADGE NO.: SHOP/CODE: PHONE: DATE:

File details come from the government source that posted it. Updated .