About this file

This document is a Pre-Proposal Inquiry (PPI) Questions and Answers matrix for a federal solicitation. The table contains nine specific inquiries from potential bidders regarding discrepancies in the solicitation document, with corresponding government responses. Key points include clarification requests about project duration (ranging from 414 to 1080 calendar days), small business participation percentages (40% vs. 20%), proposal submission dates, and Controlled Unclassified Information (CUI) status. Most responses direct bidders to Amendment 0002 or the revised Attachment T for additional details. The contract appears to be a NAVFAC (Naval Facilities) project with specific small business subcontracting targets, and proposals are currently scheduled to be due on March 07, which falls on a Saturday. The government confirmed that the contract is not considered CUI and provided context for seemingly conflicting small business participation percentages.

View the file

Other files

File Type Posted
Att. Y) PPI responses AMD 0010.pdf PDF
Att. FF) Amendment 0010 Attachment Table of Contents.pdf PDF
01 11 00.00 22_AMENDMENT 010.pdf PDF
14 24 23_AMENDMENT 010.pdf PDF
119_AE440_R1_AMENDMENT 010.pdf PDF
123_AE444_R1_AMENDMENT 010.pdf PDF
138_AE640_R1_AMENDMENT 010.pdf PDF
164_PD102_R1_AMENDMENT 010.pdf PDF
172_P-104_R1_AMENDMENT 010.pdf PDF
174_P-106_R1_AMENDMENT 010.pdf PDF
176_P-108_R1_AMENDMENT 010.pdf PDF
180_P-403_R1_AMENDMENT 010.pdf PDF
183_P-701_R1_AMENDMENT 010.pdf PDF
222_M-703_R1_AMENDMENT 010.pdf PDF
Att. T) Price Schedule AMD 0009.pdf PDF
Att. EE) Amendment 0009 Attachment Table of Contents.pdf PDF
01 91 00.15 22_R1_AMENDMENT 009.pdf PDF
129_AE530_R1_AMENDMENT 009.pdf PDF
246_ES101_R1_AMENDMENT 009.pdf PDF
249_EP102_R1_AMENDMENT 009.pdf PDF
252_EP105_R1_AMENDMENT 009.pdf PDF
255_EP501_R1_AMENDMENT 009.pdf PDF
257_EP503_R1_AMENDMENT 009.pdf PDF
261_EP602_R1_AMENDMENT 009.pdf PDF
266_EL102_R1_AMENDMENT 009.pdf PDF
273_EL702_R1_AMENDMENT 009.pdf PDF
Att.pdf PDF
02 83 00.00 22_R1_AMENDMENT 008.pdf PDF
02 84 16.00 22_R1_AMENDMENT 008.pdf PDF
148_AE804_R1_AMENDMENT 008.pdf PDF
193_MD109_R1_AMENDMENT 008.pdf PDF
210_MP107_R1_AMENDMENT 008.pdf PDF
Att. Y) PPI responses AMD 0007.pdf PDF
Solicitation Amendment N6247026R00120005 SF 30.pdf PDF
Att. F) Individual Small Business Subcontracting Plan AMD 0004.docx DOCX document
Att. Z) B60 Continuation Sheet AMD 004.pdf PDF
Att. D) Historical Small Business Utilization AMD 0004.docx DOCX document
Att. T) Price Schedule AMD 0004.pdf PDF
Att. BB) B60 AMD 004 Specifications 012726.pdf PDF
Att. W) DBIDS 5512 FORM.pdf PDF
Att. V) SITE VISIT INFORMATION.pdf PDF
Att. I) Specifications Volume 2.pdf PDF
Att. L) Drawings Volume 1b.pdf PDF
Att. P) 01 45 35a Statement_of_Special_Inspections.xlsx XLSX spreadsheet
Solicitation - N6247026R0012.pdf PDF
Att. B) - Pre-Proposal Inquiry Log Template.xlsx XLSX spreadsheet
Att. C) - Past Performance Questionnaire.docx DOCX document
Att. N) Drawings Volume 2b.pdf PDF
Att. O) 01 30 00 App A Red Zone 102623.pdf PDF
Att. T) Price_schedule.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

PPI

PPI Government Answer

01 Ref. Solicitation Document: Page 1 gives 548 days to complete where schedule section on Page 15 only gives 414 days. Page 9 of Attachment T shows 1080 calendar days. Please clarify the duration for the seed project at B60.

Refer to Amendment 0002 and revised Attachment T

02 Ref. Solicitation Document: Page 9 stipulates 40% Small Business participation where Page 16 only requires 20%. Please clarify the Small Business participation percentage for the seed project at B60.

There is no discrepancy. 40% is a component of the NAVFAC command-wide target for small business subcontracting. These targets are based on a percentage of total planned subcontract dollars. The

20% in Factor 3 applies to the total contract value.

06 Ref. Solicitation Document Page 7 #3. Proposal Submission and Pre-proposal Inquiries. Section ends with 'Contractors should ensure that…' Please finish this sentence.

Refer to Amendment 0002

07 Ref. Solicitation Document Page 7 #3. Proposal Submission and Pre-proposal Inquiries. PPI are due by January 30, 2026 however proposals are due almost 5 weeks later. Please extend the due date for PPI to February to give bidders reasonable time to submit questions.

Refer to Amendment 0002

08 Ref. Solicitation Document Page 1. Proposals are due March 07, this is a Saturday. Please confirm this is correct.

Refer to Amendment 0002

09 Ref. Solicitation Document Page 32. Includes DFARS 252.7012, .7019, .7020 however none of the documents are labeled CUI or indicated to be controlled. Please confirm none of the contract is considered CUI.

Confirmed. The contract is not CUI.

File details come from the government source that posted it. Updated .