Att. O) 01 30 00 App A Red Zone 102623.pdf
PDF 155 KB Posted
- Solicitation number
- N6247026R0012
About this file
This document is a NAVFAC Red Zone Facility Turnover Planning Meeting Checklist and Plan of Action and Milestones (POAM), dated 18 March 2008, designed to guide the systematic completion and turnover of a facility construction project. The comprehensive checklist covers three primary phases: Required for Facility Delivery (BOD), Required for Contract Close-out, and final administrative actions, involving multiple stakeholders including the Contractor (KTR), NAVFAC, and the Client.
The document provides a detailed, collaborative roadmap for project completion, outlining critical activities across various technical domains such as electrical systems testing, HVAC commissioning, systems training, O&M manual preparation, cybersecurity checks, and documentation requirements. Key responsibilities are assigned to specific parties with designated points of contact, due dates, and spaces to track actual completion dates. The checklist ensures comprehensive project management by addressing technical testing, administrative documentation, warranty provisions, site restoration, and final project close-out activities, with the Construction Manager (CM) responsible for monitoring milestones and overall process execution.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Resource for Red Zone BMS Process B-1.6.11 18 March 2008
01 30 00 APPENDIX A
Date
NAVFAC Red Zone Facility Turnover Planning Meeting
AGENDA
I. Introduction and Overview – Purpose CM
The purpose of the Facility Turnover Planning Meeting is to address elements within the project team’s purview – schedule management, assure completed facility complies with contract requirements, and other contractual issues. Each member of the project delivery team (Client, NAVFAC, and the contractor) has critical responsibilities to ensure timely completion and turnover of the new facility and each member should execute the NRZ process to achieve this end. The NRZ process provides a final re-focusing of attention to details of those key elements critical for a successful construction contract completion. In implementing NRZ processes, the NAVFAC/Contractor/Client team take a collective “snapshot” of contract status, identifying remaining actions to be accomplished, and confirm required resources needed for successful contract completion and turnover to the Client.
The Facility Turnover Planning Meeting is a collaborative effort between the Client, NAVFAC, and the contractor and results in a completed “NRZ Checklist/POAM Items” list that identifies the major items (and their due dates) that must be completed by the Contractor, the Client and the NAVFAC team to ensure timely completion of the contract.
II. Attendees
NAVFAC Echelon IV (PM); NAVFAC FEAD/ROICC Team (AROICC, CM, ET/QA, Contracting Officer); Client Team (Project Manager, Program Coordinator, User/Tenant); Contractor Team (Project Manager, Project Superintendent, CQC Manager)
III. Schedule to Completion (POAM) Contractor
IV. Schedule of Final Outfitting and Occupancy (POAM) Client
V. Critical feature(s) of project (POAM) CM
VI. Transfer of Maintenance Responsibility CM
VII. Systems training & O&M Manuals (POAM) CQC Manager
VIII. Other Items to include on NRZ checklists All
IX. Summary of Required Actions and Responsibility CM
Resource for Red Zone BMS Process B-1.6.11
Guidelines for conducting Facility Turnover Planning Meeting are as follows:
a. Meeting is held at approximately 75% construction contract completion or three to six months prior to BOD. NAVFAC representatives will include the Project Manager, Construction Manager/AROICC (CM) and Design Manager (DM), as appropriate. The contractor representatives include applicable prime contractor staff and decision-makers from major subcontractors. Design- Build contractors will have A-E representatives attending. The Client should include representatives from Public Works Officer (PWO) staff, a Client scope and financial decision maker, a user tenant representative, a facility start-up person, and others such as SPAWAR, NMCI, telephone, and furniture contractor, etc.
b. The purpose of the meeting is to plan the remaining work, identify critical project features that still need to be completed (such as “soft” construction contract requirements as shown on the NRZ Checklist/POAM Items), and to complete the filling out of the “NRZ Checklist/POAM Items”.
c. The contractor, client and NAVFAC provide a POC and due date for each item on their checklist. The team fills in the checklists by selecting items applicable to the project, selects due dates on each item, and appoints a person who has responsibility to ensure the item gets completed by the due date. The CM will be responsible to monitor the milestones.
Resource Document for B-1.6.11
NRZ Checklist/POAM Items
The table below provides typical NRZ checklist items for contractor, Client, and NAVFAC actions. Items listed on the checklists are required to remain on the checklists if they are part of the project/contract or required by construction convention. Items not listed on the checklists, but required in the contract or by construction convention, must be added to the checklists by the contractor, Client and NAVFAC. Checklists are applicable to all contracts no matter what Category of Work.
The Point of Contact and due date shall initially be determined during the Facility Turnover Planning Meeting by the NAVFAC, client and contractor leads. During execution of the NRZ process, for each item on the entire list, the Construction Manager (CM) shall indicate date completed and initial to indicate completion of the item. If a party fails to complete an item by the due date, this should be noted on the checklist and new due date established and indicated. The completed NRZ Checklist/POAM shall be placed in the contract file.
NAVFAC Red Zone Facility Turnover Planning Meeting Checklist and POAM
A B C D E F G H I
Resp. Critical Activities Point of Contact Due Date
Actual Complete
Date
CM
Initials Notes
KTR Electrical Systems Testing
NAVFAC Transformer Performance Verification
KTR Generator Testing
NAVFAC Generator Performance Verification
KTR Final Electrical Connections
NAVFAC Coordinate Final Electrical Connections Coordinate w/PW Shops
NAVFAC
Acceptance Testing of Critical Electrical Systems
Exceptions must be raised to FEAD Leadership with technical evaluation, for acceptance.
KTR Final Gas Connections
NAVFAC Coordinate Final Gas Connections Coordinate w/PW Shops
KTR Final Water Connections
KTR
Super chlorination of Potable Water Systems
KTR Plumbing/Backflow Testing
NAVFAC Coordinate Final Water Connections Coordinate w/PW Shops
KTR
Critical System Start-up: (Edit & add detail accordingly)
KTR Duct Air Leakage Testing (DALT)
NAVFAC DALT Field Acceptance
KTR Air Barrier Testing
NAVFAC
All HVAC Commissioning/Testing Complete
Exceptions must be raised to FEAD Leadership with technical evaluation, for acceptance.
KTR Elevator Testing
NAVFAC Elevator Certification Notify ML elev inspector 30 days prior to required site visit.
KTR Boiler/UPV Testing
NAVFAC Boiler/UPV Certification Notify ML boiler inspector 30 days prior to required site visit.
KTR Crane Testing
C700 Crane Certification Notify C700 30 days prior to required testing.
KTR Fire Alarm/Sprinkler Testing
NAVFAC FA & FP test results to ML & DOR days prior to acceptance testing by FPE
Edit the document to remove Facility Delivery items that are not in the contract.
To delete the rows highlight the row(s) and use Control - (minus sign).
To insert additional rows use Control + (plus sign).
* INFO / DIRECTIONS
- This NRZ Checklist/POAM is a tool to track the status of critical activities required for BOD, to help ensure their timely completion and prevent delays with facility acceptance and turnover.
- The critical activities are organized by section according to requirements (e.g. NMCI & BCO acceptance and connections)
- Critical items missing from this list should be added as necessary to ensure the list is comprehensive. Likewise, unnecessary items should be deleted.
- Any critical items left off the NRZ Checklist that are later identified after initial NRZ meeting is conducted should be added immediately so their progress can be tracked.
- A copy of the latest project customized NRZ Checklist/POAM shall be maintained in the Project contract file.
Required for Facility Delivery (BOD)
R ev is io n
- 4
/2 4/
A B C D E F G H I
Resp. Critical Activities Point of Contact Due Date
Actual Complete
Date
CM
Initials Notes
NAVFAC
Fire Alarm/Sprinkler Acceptance Test (exceptions must be raised to Chief Engineer).
Notify ML FPE 30 days prior to required testing.
Exceptions must be raised to FEAD Leadership with technical evaluation, for acceptance.
NAVFAC
All Life Safety Inspections/Testing complete
Exceptions must be raise up through the DCBL chain so that the Command can take action under our Technical Authority.
KTR Keying Plan Meeting
Client Keying Plan Meeting
NAVFAC Keying plan to NAVFAC Locksmith
KTR Deliver Lockset Cores to CM/ET
NAVFAC Lockset cores & keys and installed Locksmith
KTR NMCI Connections/IT Systems Testing
Client NMCI Install or other networks (C109)
Client Secure Network Installations
KTR IDS & SCIF Testing
Client IDS & SCIF Security Insp & Acceptance
NAVFAC IDS & SCIF Insp & Test
KTR Telecommunications Connections & Test
Client Telecommunication install (BCO phones)
Client Mod service contracts for Phone/Utilities/ Custodial/Grounds
KTR
Commissioning Functional Performance Testing (FPT)
KTR TAB (Air and Water Balancing)
KTR TAB Proportional Balancing Report
NAVFAC Proportional Balanc'g TAB Field Accept
KTR TAB Field Acceptance Testing
KTR TAB Season 1 Report*
KTR TAB Field Acceptance Testing
NAVFAC 1st Season TAB Field Acceptance
KTR DDC Trend Logs / Endurance Testing
KTR ACATS (controls) Testing
NAVFAC ACATS Performance Verification
KTR
Performance Verification Testing (PVT) Controls
NAVFAC Roofing final acceptance
Exceptions must be raised to FEAD Leadership with technical evaluation, for acceptance.
NAVFAC Underwater Structure Acceptance
Exceptions must be raised to FEAD Leadership with technical evaluation, for acceptance.2 of 5
A B C D E F G H I
Resp. Critical Activities Point of Contact Due Date
Actual Complete
Date
CM
Initials Notes
NAVFAC
Performance Verification Testing (PVT) Controls NAVFAC Acceptance
KTR
Facility-Related Control System Cybersecurity Commissioning
NAVFAC
Completed Cyber Hygiene Checklist
NAVFAC
Completed RMF Step 4 Validation
Client GFE status/delivery schedule (GFCI, GFGI)
Client Client provided equipment KTR installed
Client Client provided equipment SELF installed
NAVFAC Training Coordinated/Scheduled with FMS
KTR System Training of Navy Personnel
Client Attend Training
KTR Provide As-Built Dwgs & floor plans in CAD
NAVFAC
CM to Submit floor plan As-Builts to CAD Dept.
RQ'd for Fire Bill - RQ'd before
BOD(A)
KTR
Submit sample as-built drawings for CAD review
Submit 3 drawings from ea.
discipline for review
NAVFAC
CM to submit to DM who must review and submit Sample As-Built documents to CAD Dept.
KTR
Pre-Warranty Conference
KTR
Contractor’s Pre Final Punch List Complete
NAVFAC
Obtain a copy and ensure QA Inspections are completed. Include a completed copy for
BOD Mangament sign off.
NAVFAC
Obtain a copy and ensure Special Inspections are completed. Include a completed copy for
BOD Mangament sign off.
KTR
Pre Final Inspection
NAVFAC
Client walk-thru Inspection
KTR
Pre-Final Inspection
NAVFAC
Pre-Final Inspection
KTR
Punch List
KTR
Final Inspection
NAVFAC
Final Inspection
NAVFAC
BOD/Use and Possession
Client Ribbon-cutting ceremony
Client Planned User Move-in
KTR Delivery of O&M Manuals Must be provided before BOD
NAVFAC
CM to submit the O&M's to DM who must review and submit to NAVFAC PWD ME Requirements FMS
KTR Delivery of Product Warranties Must be provided before BOD
A B C D E F G H I
Resp. Critical Activities Point of Contact Due Date
Actual Complete
Date
CM
Initials Notes
NAVFAC
CM to submit Warranties to NAVFAC PWD ME Requirements FMS
KTR
As-Built Drawings Must be provided 30 cal days before BOD
NAVFAC
CM to submit the As-Builts to DM who must review and submit documents to CAD Dept.
KTR
Submit eOMSI Facility Data Workbook
Must be provided before BOD
NAVFAC
CM to submit the eOMSI Workbook to the DM who must review and submit to the
NAVFAC PWD ME FOS.
KTR
Submit the Internal Service Requirement List (ISRL).
Must be provided before BOD
NAVFAC
CM to submit the ISRL to the DM who must review and submit to the NAVFAC PWD ME FSC. Confirm ISRL submitted to FSC.
NAVFAC Warranty documentation to FMS Must be provided before CCD
KTR
Site Restoration
KTR
Final Landscaping
KTR
Spare Parts, Extra Stock, Special Tools, etc
KTR
Final Demobilization and Clean-up
KTR
Temp Construction Fence Removed
KTR
Project Close-out Meeting
NAVFAC
As-Builts to PWD ME PDC CADD Branch (Preston Gowen)
KTR
Complete DD1354
NAVFAC
DD 1354 Signed & turned over to RPAO
KTR
Closeout & submit permits and inspection reports Notice of Termination (NOT);
Storm water insp rpts;
Stormwater BMP Install rpts;
Archaeological Monitor'g rpts and artifacts, salvaged mat. etc.
NAVFAC
Closeout & submit permits and inspection reports NPDES, Notice of Termination
(NOT);
Storm water insp rpts;
Stormwater BMP Install rpts;
Archaeological Monitor'g rpts and artifacts, salvaged mat. etc.
KTR
Seasonal/Deferred Commissioning FPT
KTR
2nd Season TAB Report
NAVFAC
2nd Season TAB Field Accept Testing
KTR
Annual Elevator Maintenance Complete
NAVFAC
Annual Elevator Maintenance Complete
NAVFAC
Authority to Operate delivered to client
KTR
Commissioning 10-Month/Warranty Visit
NAVFAC
Inform PM of BOD
Required for Contract Close-out:
A B C D E F G H I
Resp. Critical Activities Point of Contact Due Date
Actual Complete
Date
CM
Initials Notes
NAVFAC BOD (A) entered into eContracts
NAVFAC BOD Letter to Contractor Sample ltr can be found here
NAVFAC Acceptance Letter to Client Sample ltr can be found here
NAVFAC
Process recycled/recovered materials report
NAVFAC Contractor Evaluations (CPARS) Complete assist PM
NAVFAC Finalize Outstanding Contract Mods
| Red Zone Checklist-POAM_10922.pdf |