N4019222R2012_Amendment_0004.pdf

PDF 359 KB Posted

Attached to
FY22 MILCON P-052 National Guard Readiness Center, Barrigada, Guam
Solicitation number
N4019222R2012
Issued by

About this file

This document is an amendment to a solicitation for a construction contract. The solicitation is for the design and construction of a 36,139 square foot National Guard Readiness Center in Barrigada, Guam to support training, administrative, and logistical requirements of the Guam Army National Guard. The supporting development includes utilities, a backup emergency generator, paved parking, and other necessary site improvements. Function areas include ESC Administrative, Arms Vaults and Cages, Classrooms, and Unit Locks. The amendment incorporates revisions to the project program and room requirements attachments, provides responses to requests for information, and extends the proposal due date to July 22, 2022 at 4:30pm local time. Offerors must acknowledge the amendment in their proposals. The estimated price range for the construction project is between $25 million and $100 million.

View the file

Other files

File Type Posted
N4019222R2012_Amend0007_Encl(1)_RFI_Notice_7.pdf PDF
N4019222R2012_Amend0007_Attach(1)_Civil_C2toC4_Rev_ 20220727.pdf PDF
N4019222R2012_Amendment_0007.pdf PDF
N4019222R2012_Amend0006_Attach(1)_6_ESR_C10._Rev4.pdf PDF
N4019222R2012_Amend0006_Encl(1)_RFI_Notice_6.pdf PDF
N4019222R2012_Amendment_0006.pdf PDF
N4019222R2012_Amend0006_Attach(2)_6_ESR_G20_Rev2.pdf PDF
N4019222R2012_Amendment_0005.pdf PDF
N4019222R2012_Amend0005_Attach(1)_6_ESR_C10._Rev3.pdf PDF
N4019222R2012_Amend0005_Encl(1)_RFI_Notice_5.pdf PDF
N4019222R2012_Amend0004_Attach(1)_6_ESR_C10._Rev3.pdf PDF
N4019222R2012_Amend0004_Encl_(1)_RFI_Notice_4.pdf PDF
N4019222R2012_Amend0004_Attach(2)_5_Room_Requirements_Rev3.pdf PDF
N4019222R2012_Amendment_0003.pdf PDF
N4019222R2012_Amend0003_Attach(8)_6_ESR_D30_Rev1.pdf PDF
N4019222R2012_Amend0003_Attach(6)_5_Room_Requirements_Rev2.pdf PDF
N4019222R2012_Amend0003_Attach(7)_6_ESR_C10._Rev2.pdf PDF
N4019222R2012_Amend0003_Encl (1)_RFI_Notice_3.pdf PDF
N4019222R2012_Amend0003_Attach(3)_6_ESR_G20_Rev1.pdf PDF
N4019222R2012_Amend0003_Attach(10)_6_ESR_G20_Rev1.pdf PDF
N4019222R2012_Amend0003_Attach(1)_NGRC_C2 Site Layout Plan_Rev1.pdf PDF
N4019222R2012_Amend0003_Attach(5)_4_Figure 1_Space Tabulation_Rev1.pdf PDF
N4019222R2012_Amend0003_Attach(9)_6_ESR_E20_Rev2.pdf PDF
N4019222R2012_Amend0003_Attach(2)_6_ESR_C10_doneF._Rev1.pdf PDF
N4019222R2012_Amend0003_Attach(4)_01 50 00.05 20_Rev1.pdf PDF
N4019222R2012_Amend0002_Attach(7)_6_ESR_D40_20220614_Rev1.pdf PDF
N4019222R2012_Amend0002_Attach(5)_5_Room_Requirements_Rev1.pdf PDF
N4019222R2012_Amend0002_Attach(3)_E1_NGRC_Elect_Site_Plan_20220614_Rev1.pdf PDF
N4019222R2012_Amend0002_Encl(3)_RFI_Notice_2.pdf PDF
N4019222R2012_Amend0002_Attach(9)_6_ESR_E20_Rev1.pdf PDF
N4019222R2012_Amend0002_Attach(2)__AS1_Architectural_Site_Plan_20220614_Rev1.pdf PDF
N4019222R2012_Amend0002_Attach(4)_P1_NGRC_Enlarged_Plumbing_Plan_Rev1.pdf PDF
N4019222R2012_Amend0002_Encl(2)_NGRC_CID_20211228_Final.pdf PDF
N4019222R2012_Amend0002_Attach(6)_6_ESR_C30_20220614_Rev1.pdf PDF
N4019222R2012_Amend0002_Attach(10)_PTS_SECTION_G20_Rev1.pdf PDF
N4019222R2012_Amend0002_Attach(1)_A4_NGRC_Building_Elevations_20220614_Rev1.pdf PDF
N4019222R2012_Amend0002_Encl(1)_Price Proposal Schedule_REV1.pdf PDF
N4019222R2012_Amend0002_Attach(8)_6_ESR_D50_20220614_Rev1.pdf PDF
N4019222R2012_Amend0002_Encl(4)_1224th_laydown_sketch.pdf PDF
N4019222R2012_Amendment_0002.pdf PDF
Amendment_0001_N4019222R2012.pdf PDF
N4019222R2012_Amendment0001_Encl (1)_RFI_Notice_1.pdf PDF
N4019222R2012_Pre-proposal_Conference_Slides.pdf PDF
N4019222R2012_Site_Visit_Attendance_Sheet.pdf PDF
N4019222R2012_RFP_Part_A_Proposal_Forms_and_Documents.pdf PDF
N4019222R2012_RFP_Part_A_Attachment _1_Request_for_Information_(RFI)_Form.pdf PDF
N4019222R2012_RFP_Part_B_Part_3_Project_Program.pdf PDF
N4019222R2012_RFP_Part_C_Drawings.pdf PDF
N4019222R2012_RFP_Part_B_Part_2_Specification_01_57_19_03_20_SUPP_TEMP_ENVI_CON_JRM_ESS.pdf PDF
N4019222R2012_RFP_Part_B_Prelim-Draft Munitions_Response_ESS_Guam_Construction_AMD7.pdf PDF
Show all 50

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

P-052

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print)

30-105-04EXCEPTION TO SF 30

APPROVED BY OIRM 11-84

STANDARD FORM 30 (Rev. 10-83) Prescribed by GSA

FAR (48 CFR) 53.243

FY22 MILCON PROJECT P-052 National Guard Readiness Center, Barrigada, Guam

See continuation page.

1. CONTRACT ID CODE PAGE OF PAGES

1 2

16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

16C. DATE SIGNED

BY 08-Jul-2022

16B. UNITED STATES OF AMERICA15C. DATE SIGNED15B. CONTRACTOR/OFFEROR

(Signature of Contracting Officer)(Signature of person authorized to sign)

8. NAME AND ADDRESS OF CONTRACTOR (No., Street , County, State and Zip Code) X N4019222R2012

X 9B. DATED (SEE ITEM 11)

22-Apr-2022

10B. DATED (SEE ITEM 13)

9A. AMENDMENT OF SOLICITATION NO.

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

X The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offer X is extended, is not extended.

Offer must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended by one of the following methods:

(a) By completing Items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN

REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE

CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(B).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

10A. MOD. OF CONTRACT/ORDER NO.

2. AMENDMENT/MODIFICATION NO. 5. PROJECT NO.(If applicable)

6. ISSUED BY

3. EFFECTIVE DATE

08-Jul-2022

CODE

COMMANDING OFFICER - NAVFAC MARIANAS

MAR CORE DC

PSC 455, BOX 195

FPO AP 96540-2937

N40192 7. ADMINISTERED BY (If other than item 6)

4. REQUISITION/PURCHASE REQ. NO.

CODE

See Item 6

FACILITY CODECODE

EMAIL:TEL:

N4019222R2012

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

SECTION SF 30 - BLOCK 14 CONTINUATION PAGE (SF 30)

The following have been added by full text:

AMENDMENT 0004

In accordance with FAR 52.252-3 Alterations in Solicitation (APR 1984), portions of this solicitation are altered as follows:

1. Incorporate the following revisions:

a. PART 3 – PROJECT PROGRAM: The following have been revised.

i. C10 Interior Construction provided as Attachment (1).

ii. 5.0 Room Requirements provided as Attachment (2).

2. Provide Notice 4 in response to requests for information provided as enclosure (1).

3. Extend the date for receipt of proposals to Friday, July 22, 2022 at 4:30pm local time.

Offerors shall acknowledge this amendment in Block 19 of the Standard Form 1442 with their proposals.

(End of Summary of Changes)

File details come from the government source that posted it. Updated .