N4019222R2012_Amend0002_Encl(1)_Price Proposal Schedule_REV1.pdf

PDF 110 KB Posted

Attached to
FY22 MILCON P-052 National Guard Readiness Center, Barrigada, Guam
Solicitation number
N4019222R2012
Issued by

About this file

This document contains a price proposal schedule and related federal contract opportunity notice for construction services. The price proposal schedule outlines various contract line item numbers (CLINs) and sub-CLINs for the base bid and optional items to design and construct a 36,139 square foot National Guard Readiness Center in Barrigada, Guam. The base bid CLIN includes all work for the readiness center and munitions response. Optional items include a photovoltaic system, training bay, unheated storage building, wash platform, furniture, fixtures and equipment, additional munitions response services, and audio-visual equipment. Offerors must submit pricing for the base bid and optional items. The federal contract opportunity notice provides additional details on the solicitation number, project name and location, opportunity type, description of work, NAICS code, estimated value of $25-100 million, submission instructions, pre-proposal conference, and site visit. Offerors must submit technical and past performance proposals along with pricing. The contracting agency is the Department of the Navy Naval Facilities Engineering Command.

View the file

Other files

File Type Posted
N4019222R2012_Amend0007_Encl(1)_RFI_Notice_7.pdf PDF
N4019222R2012_Amend0007_Attach(1)_Civil_C2toC4_Rev_ 20220727.pdf PDF
N4019222R2012_Amendment_0007.pdf PDF
N4019222R2012_Amend0006_Attach(1)_6_ESR_C10._Rev4.pdf PDF
N4019222R2012_Amend0006_Encl(1)_RFI_Notice_6.pdf PDF
N4019222R2012_Amendment_0006.pdf PDF
N4019222R2012_Amend0006_Attach(2)_6_ESR_G20_Rev2.pdf PDF
N4019222R2012_Amendment_0005.pdf PDF
N4019222R2012_Amend0005_Attach(1)_6_ESR_C10._Rev3.pdf PDF
N4019222R2012_Amend0005_Encl(1)_RFI_Notice_5.pdf PDF
N4019222R2012_Amend0004_Attach(1)_6_ESR_C10._Rev3.pdf PDF
N4019222R2012_Amend0004_Encl_(1)_RFI_Notice_4.pdf PDF
N4019222R2012_Amend0004_Attach(2)_5_Room_Requirements_Rev3.pdf PDF
N4019222R2012_Amendment_0004.pdf PDF
N4019222R2012_Amendment_0003.pdf PDF
N4019222R2012_Amend0003_Attach(8)_6_ESR_D30_Rev1.pdf PDF
N4019222R2012_Amend0003_Attach(6)_5_Room_Requirements_Rev2.pdf PDF
N4019222R2012_Amend0003_Attach(7)_6_ESR_C10._Rev2.pdf PDF
N4019222R2012_Amend0003_Encl (1)_RFI_Notice_3.pdf PDF
N4019222R2012_Amend0003_Attach(3)_6_ESR_G20_Rev1.pdf PDF
N4019222R2012_Amend0003_Attach(10)_6_ESR_G20_Rev1.pdf PDF
N4019222R2012_Amend0003_Attach(1)_NGRC_C2 Site Layout Plan_Rev1.pdf PDF
N4019222R2012_Amend0003_Attach(5)_4_Figure 1_Space Tabulation_Rev1.pdf PDF
N4019222R2012_Amend0003_Attach(9)_6_ESR_E20_Rev2.pdf PDF
N4019222R2012_Amend0003_Attach(2)_6_ESR_C10_doneF._Rev1.pdf PDF
N4019222R2012_Amend0003_Attach(4)_01 50 00.05 20_Rev1.pdf PDF
N4019222R2012_Amend0002_Attach(7)_6_ESR_D40_20220614_Rev1.pdf PDF
N4019222R2012_Amend0002_Attach(5)_5_Room_Requirements_Rev1.pdf PDF
N4019222R2012_Amend0002_Attach(3)_E1_NGRC_Elect_Site_Plan_20220614_Rev1.pdf PDF
N4019222R2012_Amend0002_Encl(3)_RFI_Notice_2.pdf PDF
N4019222R2012_Amend0002_Attach(9)_6_ESR_E20_Rev1.pdf PDF
N4019222R2012_Amend0002_Attach(2)__AS1_Architectural_Site_Plan_20220614_Rev1.pdf PDF
N4019222R2012_Amend0002_Attach(4)_P1_NGRC_Enlarged_Plumbing_Plan_Rev1.pdf PDF
N4019222R2012_Amend0002_Encl(2)_NGRC_CID_20211228_Final.pdf PDF
N4019222R2012_Amend0002_Attach(6)_6_ESR_C30_20220614_Rev1.pdf PDF
N4019222R2012_Amend0002_Attach(10)_PTS_SECTION_G20_Rev1.pdf PDF
N4019222R2012_Amend0002_Attach(1)_A4_NGRC_Building_Elevations_20220614_Rev1.pdf PDF
N4019222R2012_Amend0002_Attach(8)_6_ESR_D50_20220614_Rev1.pdf PDF
N4019222R2012_Amend0002_Encl(4)_1224th_laydown_sketch.pdf PDF
N4019222R2012_Amendment_0002.pdf PDF
Amendment_0001_N4019222R2012.pdf PDF
N4019222R2012_Amendment0001_Encl (1)_RFI_Notice_1.pdf PDF
N4019222R2012_Pre-proposal_Conference_Slides.pdf PDF
N4019222R2012_Site_Visit_Attendance_Sheet.pdf PDF
N4019222R2012_RFP_Part_A_Proposal_Forms_and_Documents.pdf PDF
N4019222R2012_RFP_Part_A_Attachment _1_Request_for_Information_(RFI)_Form.pdf PDF
N4019222R2012_RFP_Part_B_Part_3_Project_Program.pdf PDF
N4019222R2012_RFP_Part_C_Drawings.pdf PDF
N4019222R2012_RFP_Part_B_Part_2_Specification_01_57_19_03_20_SUPP_TEMP_ENVI_CON_JRM_ESS.pdf PDF
N4019222R2012_RFP_Part_B_Prelim-Draft Munitions_Response_ESS_Guam_Construction_AMD7.pdf PDF
Show all 50

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CLIN SubCLIN DESCRIPTION ESTIMATED

QUANTITY

UNIT UNIT

PRICE

AMOUNT GRAND TOTAL

0001 TOTAL BASE BID

Total price of Base Bid SubCLINs (SLINs) 000101 though 000102 for the entire work to provide all necessary labor, material, transportation, supervision, equipment, and other incidental work required for the construction of the National Guard Readiness Center and appurtenances with the project program and drawings for WON 1674991 FY22 MILCON PROJECT P-052 National Guard Readiness Center; except for work described in CLINs 0002 through 0007.

000101 BASE BID ITEM: National Guard Readiness Center The basis for CLIN 000101 is the price for all work complete in accordance with the project program and drawings, but not including work specified under SLIN 000102, CLIN 0002-0008.

1 LS $___________ $____________

000102 BASE ITEM: MEC/UXO/MMPEH 1 LS $___________ $____________

The basis for CLIN 000102 is the price for all work complete in accordance with the drawings and specifications to furnish and deliver MEC/UXO/MPPEH, but not inlcuding work specified under SLIN 000101 and CLINs 0007-0008.

0002 OPTION 1 - PHOTOVOLTAIC SYSTEM

Total price for the entire work to provide all necessary labor, material, transportation, supervision, equipment, and other incidental work required to furnish and deliver PHOTOVOLTAIC SYSTEM in accordance with the project program and drawings; except for work described in CLINs 0001 and 0003-0008. The Contracting Officer may exercise this option by written notice within 180 calendar days from the date of contract award.

1 LS $___________ $____________

0003 OPTION 2 -TRAINING BAY

Total price for the entire work to provide all necessary labor, material, transportation, supervision, equipment, and other incidental work required to furnish and deliver GENERAL PURPOSE TRAINING BAY in accordance with the project program and drawings; except for work described in CLINs 0001-0002 and 0004-0008. Exclude the price for all work associated with the common wall and other common building elements between the Training Bay and Unheated Storage Building. The Contracting Officer may exercise this option by written notice within 180 calendar days from the date of contract award.

1 LS $___________ $____________

0004 OPTION 3 - UNHEATED STORAGE BUILDING

Total price for the entire work to provide all necessary labor, material, transportation, supervision, equipment, and other incidental work required to furnish and deliver UNHEATED STORAGE BUILDING, in accordance with the project program and drawings;

except for work described in CLINs 0001-0003 and 0005-0008. Price must include all work associated with the common wall and other common building elements between the Training Bay and Unheated Storage Building. The Contracting Officer may exercise this option by written notice within 180 calendar days from the date of contract award.

1 LS $___________ $____________

0005 OPTION 4 - WASH PLATFORM

Total price for the entire work to provide all necessary labor, material, transportation, supervision, equipment, and other incidental work required to furnish and deliver WASH PLATFORM in accordance with the project program and drawings; except for work described in CLINs 0001- 0004 and 0006-0008. The Contracting Officer may exercise this option by written notice within 180 calendar days from the date of contract award.

1 LS $___________ $____________

0006 OPTION BID 5 - Furniture, Fixutres & Equipment Est. 501,809.00$ Total price for the entire work to provide all necessary labor, material, transportation, supervision, equipment, and other incidental work required to procure and install Furniture, Fixtures & Equipment (FF&E) (Handling and Administrative Rate (HAR) NTE 5%) in accordance with the project program and drawings; except for work described in CLINs 0001-0005 and 0007-0008.

The Contracting Officer may exercise this option by written notice within 180 calendar days from the date of contract award.

Handling and Administrative Rate (HAR) NTE 5% ___________% $____________

Total FF&E Amount for FY22 MILCON Project P-052 National Guard Readiness Center, Barrigada, Guam (Estimated)

Enter total amount for FF&E (FF&E Budget + HAR) $____________

Revision 1

PRICE PROPOSAL SCHEDULE

FOR WON 16744991 FY22 MILCON PROJECT P-052

NATIONAL GUARD READINESS CENTER

BARRIGADA, GUAM

CLIN SubCLIN DESCRIPTION ESTIMATED

QUANTITY

UNIT UNIT

PRICE

AMOUNT GRAND TOTAL

Revision 1

PRICE PROPOSAL SCHEDULE

FOR WON 16744991 FY22 MILCON PROJECT P-052

NATIONAL GUARD READINESS CENTER

BARRIGADA, GUAM

0007 OPTION 6 - MEC MUNITION RESPONSE 1 day $ $ The basis for CLIN 0007 is the Unit price per day for a MEC munitions respnose team of members (enter proposed number of members) to perform additional unforeseen MEC anomaly investigation, except for work described in CLINs 0001-0006 and 0008. The munitions response team shall have a minimum number of eight (8) members. The unit price in this CLIN shall include all material, labor, equipment, supervision, and indirect costs complete for price adjustment in accordance with FAR 52.243-4, Changes.

0008 OPTION 7 - AUDIO-VISUAL EQUIPMENT

Total price for the entire work to provide all necessary labor, material, transportation, supervision, equipment, and other incidental work required to procure and install Audio-Visual Equipment for Base Bid; except for work described in CLINs 0001-0007. The Contracting Officer may exercise this option by written notice within 180 calendar days from the date of contract award.

1 LS $___________ $____________