0109_A_JP-5_PUMPROOM_BILGE_PRESERVATION_ARCTICROH20_REV_1.docx

DOCX document 33 KB Posted

Attached to
REGULAR OVERHAUL USNS ARCTIC
Solicitation number
N32205-19-R-6012
Issued by

About this file

This document outlines the statement of work for Item Number 109 under Solicitation Number N32205-19-R-6012 for the regular overhaul and dry docking of the USNS ARCTIC (T-AOE 8). The statement of work requires cleaning, surface preparation, and coating of approximately 12,000 square feet of bilge areas in the JP-5 Pump Room aboard the vessel. The contractor will perform solvent cleaning, abrasive blasting to remove existing coatings, environmental monitoring, and application of a multi-coat paint system consisting of Amerlock Sealer, Amercoat 240 in buff and red oxide colors, and stripe coats. The project will be overseen by a Government Protective Coatings Representative.

Revised Work Item 0109

View the file

Other files

File Type Posted
0021_A_CLEAN AND GAS FREE TANKS VOIDS AND COFFERDAMS REV OCT 2012_ARCTICROH20_REV2.docx DOCX document
0013_A_PROJECT PLANNING AND PRODUCTION STATUS MONITORING REPORTS REV 1-1May18.docx DOCX document
N3220519R6012 Amendment 4.docx DOCX document
0305_A_REPLACE SSDG FORWARD CRANKSHAFT SEAL REV ARCTICROH20.docx DOCX document
Q_and_A__5.docx DOCX document
0118_B_7-105-0-JJ_TANK_TOP_REPAIR_ARCTICROH2020_Revised.docx DOCX document
6362478_H.zip ZIP file
N3220519R6012_Amendment_2.docx DOCX document
J_-_3_Category_B_Items_ARCTIC_Revised_21_OCT_19.xls XLS spreadsheet
J_-_2_Category_A_Items_ARCTIC_Revised_21_OCT_19.xls XLS spreadsheet
0118_B_7-105-0-JJ_TANK_TOP_REPAIR_ARCTICROH2020.docx DOCX document
N3220519R6012_Amendment_3.docx DOCX document
0117_A_7-105-0-JJ_HYDROSTATIC_TESTING_ARCTICROH20.docx DOCX document
Q_and_A__4.docx DOCX document
0912_A_UNDERWATER_HULL_CLEANING_and_PAINTING_REV_1_.docx DOCX document
0107_A_REPLACE_REPAIR_SURVEY_WATERTIGHT_DOORS_ARCTICROH20_REV1.docx DOCX document
0913_A_HULL_FREEBOARD_CLEANING_AND_PAINTING_REV_1_ARCTICROH20.docx DOCX document
0201_A__INSTRUMENT_CALIBRATION_AND_REPAIR_ARCTICROH20.docx DOCX document
0113_A_FANTAIL_OVERHEAD_CLEANING_AND_PRESERVATION_ARCTICROH20_REV_1.docx DOCX document
J_-_2_Category_A_Items_ARCTIC_Revised_20_SEP_19.xls XLS spreadsheet
N3220519R6012_Amendment_1.docx DOCX document
Q_and_A__3.docx DOCX document
0116_B_BILGE_WELL_STAGING_SUPPORT_REV_1_ARCTICROH20.docx DOCX document
0517_A_INSTALL_OILY_WATER_SEPERATOR_TALT_301_ARCTICROH20_REV1.docx DOCX document
0112_A_REPLACE_WEATHER_DECK__DRAIN_PIPING_REV2_ARCTICROH20.docx DOCX document
0104_A_RENEW_01_LEVEL_NON_SKID_REV_1_ARCTICROH20.docx DOCX document
0202_A_SEAL_CHANGE_OUT_FOR_REDUCTION_GEAR_MAIN_THRUST_BEARINGS_ARCTICROH20_REV2.docx DOCX document
Q_AND_A__2.docx DOCX document
0112_A_REPLACE_WEATHER_DECK__DRAIN_PIPING_REV1_ARCTICROH20_(002).docx DOCX document
J_-_3_Category_B_Items_ARCTIC_Correction.xls XLS spreadsheet
Q_and_A__1.doc DOC document
J_-_3_Category_B_Items_ARCTIC.xls XLS spreadsheet
J_-_2_Category_A_Items_ARCTIC.xls XLS spreadsheet
J_and_A_Redacted.docx DOCX document
N3220519R6012.docx DOCX document
USNS_ARCTIC_ROHDD_2020_J_Attachments.zip ZIP file
J_-_14_Technical_Data_Non-Disclosure.docx DOCX document
SYNOPSIS_N3220519R6012_USNS_ARCTIC.docx DOCX document
SOURCES_SOUGHT_FOR_USNS_ARCTIC_ROH_2020.docx DOCX document
Show all 39

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USNS ARCTIC

T-AOE 8)

HULL STRUCTUREN32205-19-R-6012
14 JANUARY 2014
ITEM NO. 109CATEGORY "A"N756/MJP

JP5 PUMPROOM BILGE PRESERVATION

1.0 ABSTRACT:

1.1 This item describes the renewal preservation of the JP-5 Pump Room Bilges.

2.0 REFERENCES:

2.1 Steel Structures Painting Council, Good Painting Practice, Volume 1, Fourth Edition. (Contractor held)

2.2 NAVSEA Drawing 085-6362912, Booklet of General Drawings

2.3 NAVSEA Drawing 111-6362062, ASSY BOT SHL W/FRMG FR200-251 (P)

2.4 NAVSEA Drawing 111-6362063, ASSY BOT SHL W/FRMG FR200-251 (S)

2.5 NAVSEA Drawing 111-6361168, COMP ARR A2-029 IB, FR200-251 (P)

2.6 NAVSEA Drawing 111-6361190, COMP ARR A2-039 IB, FR200-251 (S)

2.7 NAVSEA Drawing 801-6360544, Scantling Drawing 01 LVL and BLW Fr205-455

3.0 ITEM LOCATION/DESCRIPTION:

3.1 Location:

3.1.1 Location: JP-5 Pump Room (7-205-01-E) Bilge; From four inches above deck plates, down to bilge bottom plating, Refer to References 2.2 through 2.7

3.2 Quantity:

3.2.1 Twelve Thousand (12,000) square feet of surface area to include: bilge bottom plating, shell stringers, keel, bilge boxes, frames, troughs, deck grating supports, piping supports, structural appendages, bilge wells, drainage holes, stanchions, and foundations, fixtures/supports. All 12,000 SqFt gets a Top Coat, 4800 SqFt will need to be scaled to bare metal.

4.0 GOVERNMENT FURNISHED EQUIPMENT/MATERIAL/SERVICES:

4.1 Government Furnished Equipment: None

4.2 Government Furnished Material:

4.2.1 PPG Marine Paint Amount

Coating Type
QTY

(Gal)

Amerlock Sealer
10
Amercoat 240 Buff
50
Amercoat 240 Haze Gray
50
Amercoat 240 Red Oxide
100
Amercoat Thinner (T-10)
25
T-10
25

4.3 Government Furnished Service:

4.3.1 Government Protective Coatings Representative

5.0 NOTES:

5.1 The contractor and all subcontractors regardless of tier shall consult the General Technical Requirements (GTR) to determine applicability to this work item. In performance of this work item, the contractor and all subcontractors regardless of tier must comply with the requirements of all applicable GTRs including but not limited to GTRs 1 through 7, 22, 23, and 29.

5.2 The contractor and all subcontractors regardless of tier are advised to review other work items under this contract to determine their effect on the work required under this work item. Many of the definitions relating to performance of this work item are found in Work Item 001.

6.0 QUALITY ASSURANCE REQUIREMENTS: None Additional

7.0 STATEMENT OF WORK REQUIRED:

7.1 Maintain JP-5 Pump Room interior ambient temperature and steel deck temperature five degrees above dew point at all times During coating the temperature shall be within Manufacturer’s published limits required for each of the different coating applications. Remove and reinstall following the completion of work all interferences, including lagging, in way of temporary services

7.2 (CHECKPOINT) Conduct an as found operational test of ALL electronic and electrical gear, lighting; in the vicinity of the bilge work to be completed; Prove drains clear and free flowing to the MSCREP. These tests shall be completed prior to the start of work to demonstrate existing conditions.

7.2.1 Plug or suitably stopper any leaky lines draining into the bilge.

7.3 Install shrink wrap, drop cloths, masking, temporary division shields, seals, blanks and filtering materials to prevent foreign substances from entering electrical machinery and controls, lights, machinery, piping, hatches, deck drains, ventilation systems and temporary openings during blasting and painting operations.

7.4 (CHECKPOINT) Prior to the start of productive work, protective covering shall be inspected and approved by the MSCREP. Deficiencies noted during this inspection shall be corrected and the MSCREP shall be afforded the opportunity to inspect and approve the corrective measures before work commences.

7.5 Prepare a numbering system and submit a sketch showing the location of all Pump Room deck plates. The “As Found Report” shall include a Count of Missing Deck Plate Screws.

7.5.1 Stamp each plate as with its location number taken from the sketch submitted in Paragraph 7.5. Match mark each plate as to its orientation to assure that the plate will be installed as removed. Numbers shall be permanently stamped on the underside of each plate only.

7.5.2 Deck plates shall be secured with at least two screws unless removed for access to bilge work area. Contractor shall maintain a sufficient number of plates in place to allow safe transit throughout space. At completion of work contractor shall replace missing and damaged deck plate screws. Replacement fasteners shall be the same as original. For bidding purposes estimate that (50%) of the deck plate securing holes will need to have threads chased and 30% will need screws replaced. Existing screws are Slotted Truss Head ½-13UNC x 1”lg CRES.

7.6 Using biodegradable detergents, accomplish the requirements of SSPC-SP-1, Solvent Cleaning, to remove all oil, grease, dirt and soluble salts from all surface below the deck plates. Final washdown shall be made with clean, fresh water at 2,500 to 3,000 psi. Upon completion of all water washing chloride testing shall be performed at random locations. If contamination is found, additional tests shall be made as necessary to determine the extent of contamination and to prove the success of remediation. The maximum allowable contamination concentrations shall be less than 10 ug/cm2 of chloride contaminants as determined by field or laboratory analysis using reliable, reproducible test equipment.

7.7 Clean/Prepare all surfaces where coating system appears compromised in including all stiffeners and permanently attached structures (e.g. deck supports, pipe hangers, and etcetera) in accordance with Surface Preparation Standard SSPC-SP-11 Power Tool Cleaning to White Metal. Surfaces so prepared shall have at least a 1 mil surface profile. Profile shall be determined using a Keane-Tator (or equal) Surface Profile Comparator. Testex (or equal) Replica Tape shall be used at a rate of one (1) reading per 500 SF for verification. Replica Tape shall be mounted, identified as to location and included as part of the final paint report. For bidding purposes it is estimated that 4800 SqFt will have to be prepared in this manner.

7.8 Well adhered paint areas are to be feathered into prepped areas. The government paint representative will have final determination if whether an area requires preparation to SSPC-SP-11. Paint surface on structure that is retained shall be scuffed with 60 grits sand paper.

7.9 Take and record environmental conditions such as wet bulb, dry bulb, relative humidity, ambient temperature, surface temperature and cure time. MSCREP to inspect surface preparation and review environmental data prior to application of coating.

7.10 Surfaces to be painted are to be free of dust, oil, grease, moisture, salt and all other foreign materials that will affect the proper application and adherence of the paint system being applied an SSPC-SP-1 surface prep shall be accomplished with an approved solvent and allowed to dry just prior to the application of paint.

NOTE:

No coating shall be applied without the Government Paint Rep in attendance.

NOTE:

Temporarily provide a means to keep all GFM paint and PRC products at a constant 70 degree temperature PRIOR TO opening, mixing, and applying the products. Contractor may “pre-stage” the GFM in a heated Conex box (or other equal means) located on the Flight Deck (or other adjacent area), where products can be quickly accessed and transported to the area being worked

7.11 Paint all areas prepped to and SSPC-SP-11 using the following paint system and in accordance with the Government’s Paint representative direction and the following instructions:

One (1) coat Amerlock Sealer1-2 mils DFT
One (1) coat Amercoat 240 Buff4-6 mils DFT
One (1) stripe coat Amercoat 240 LG2-4 mils DFT
One (1) coat Amercoat 240 Red Oxide4-6 mils DFT

7.12 Paint all areas listed in 3.2 using the following paint system and in accordance with the Government’s Paint representative direction and the following instructions:

One (1) coat Amercoat 240 Red Oxide 4-6 mils DFT

7.13 Renew insulation and lagging where removed or damaged during the performance of this work item.

7.14 Paint all disturbed surfaces to match surrounding surfaces.

7.15 Upon completion remove all installed protective measures and equipment and restore all interferences and deck plates. Clean space of all dust and debris generated as a result of work under this item. Space returned in the same cleanliness condition it was found.

7.16 (CHECKPOINT) Conduct final operational test of ALL electronic and electrical gear, lighting; in the vicinity of the bilge work; Prove drains clear and free flowing to the MSCREP. Corrections of deficient conditions not noted during initial checks shall be the responsibility of the contractor.

7.17 Preparation of Drawings: None Additional

7.18 Test/Inspection: None Additional

7.19 Manufacturer's Representative:

7.19.1 Government Paint Representative

8.0 GENERAL REQUIREMENTS: None Additional

109 - 1