This request for proposal outlines requirements for replacing and repairing watertight doors aboard the USNS ARCTIC. The contractor will survey exterior watertight doors to identify any needing repair, replace specific interior doors listed by number and type, and test repaired doors for watertight integrity. Replacement doors must be supplied with the latest equipment alterations and painted prior to installation following surface preparation standards. The contractor will install protective measures, conduct chalk and pressure tests on exterior doors and air tests on interior doors witnessed by government inspectors, and insulate, paint and clean areas impacted by the work. The soliciting agency is the Department of the Navy Military Sealift Command for their regular overhaul of the USNS ARCTIC.

Revised Work item 0107

View the file

Other files

File Type Posted
0021_A_CLEAN AND GAS FREE TANKS VOIDS AND COFFERDAMS REV OCT 2012_ARCTICROH20_REV2.docx DOCX document
0013_A_PROJECT PLANNING AND PRODUCTION STATUS MONITORING REPORTS REV 1-1May18.docx DOCX document
N3220519R6012 Amendment 4.docx DOCX document
0305_A_REPLACE SSDG FORWARD CRANKSHAFT SEAL REV ARCTICROH20.docx DOCX document
Q_and_A__5.docx DOCX document
0118_B_7-105-0-JJ_TANK_TOP_REPAIR_ARCTICROH2020_Revised.docx DOCX document
6362478_H.zip ZIP file
N3220519R6012_Amendment_2.docx DOCX document
J_-_3_Category_B_Items_ARCTIC_Revised_21_OCT_19.xls XLS spreadsheet
J_-_2_Category_A_Items_ARCTIC_Revised_21_OCT_19.xls XLS spreadsheet
0118_B_7-105-0-JJ_TANK_TOP_REPAIR_ARCTICROH2020.docx DOCX document
N3220519R6012_Amendment_3.docx DOCX document
0117_A_7-105-0-JJ_HYDROSTATIC_TESTING_ARCTICROH20.docx DOCX document
Q_and_A__4.docx DOCX document
0912_A_UNDERWATER_HULL_CLEANING_and_PAINTING_REV_1_.docx DOCX document
0913_A_HULL_FREEBOARD_CLEANING_AND_PAINTING_REV_1_ARCTICROH20.docx DOCX document
0201_A__INSTRUMENT_CALIBRATION_AND_REPAIR_ARCTICROH20.docx DOCX document
0113_A_FANTAIL_OVERHEAD_CLEANING_AND_PRESERVATION_ARCTICROH20_REV_1.docx DOCX document
J_-_2_Category_A_Items_ARCTIC_Revised_20_SEP_19.xls XLS spreadsheet
N3220519R6012_Amendment_1.docx DOCX document
Q_and_A__3.docx DOCX document
0116_B_BILGE_WELL_STAGING_SUPPORT_REV_1_ARCTICROH20.docx DOCX document
0517_A_INSTALL_OILY_WATER_SEPERATOR_TALT_301_ARCTICROH20_REV1.docx DOCX document
0112_A_REPLACE_WEATHER_DECK__DRAIN_PIPING_REV2_ARCTICROH20.docx DOCX document
0109_A_JP-5_PUMPROOM_BILGE_PRESERVATION_ARCTICROH20_REV_1.docx DOCX document
0104_A_RENEW_01_LEVEL_NON_SKID_REV_1_ARCTICROH20.docx DOCX document
0202_A_SEAL_CHANGE_OUT_FOR_REDUCTION_GEAR_MAIN_THRUST_BEARINGS_ARCTICROH20_REV2.docx DOCX document
Q_AND_A__2.docx DOCX document
0112_A_REPLACE_WEATHER_DECK__DRAIN_PIPING_REV1_ARCTICROH20_(002).docx DOCX document
J_-_3_Category_B_Items_ARCTIC_Correction.xls XLS spreadsheet
Q_and_A__1.doc DOC document
J_-_3_Category_B_Items_ARCTIC.xls XLS spreadsheet
J_-_2_Category_A_Items_ARCTIC.xls XLS spreadsheet
J_and_A_Redacted.docx DOCX document
N3220519R6012.docx DOCX document
USNS_ARCTIC_ROHDD_2020_J_Attachments.zip ZIP file
J_-_14_Technical_Data_Non-Disclosure.docx DOCX document
SYNOPSIS_N3220519R6012_USNS_ARCTIC.docx DOCX document
SOURCES_SOUGHT_FOR_USNS_ARCTIC_ROH_2020.docx DOCX document
Show all 39

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USNS ARCTIC

(T-AOE 8)

HULL STRUCTURERFP NO. N32205-19-R-6012
14 JANUARY 2014
ITEM NO. 107CATEGORY "A"N756/MJP/JB

REPLACE/REPAIR/SURVEY WATERTIGHT DOORS REV 1

1. ABSTRACT:

0. This item describes the requirements to perform water tight door maintenance which includes replace/repair and survey of various watertight doors throughout the vessel.

1. REFERENCES:

1. NAVSEA Drawing 085-6363081, Rev B, USS Arctic SRD Booklet of General Drawings.

1. NAVSEA Drawing 167-6361161; List of Steel Doors

1. NAVSEA Drawing 167-6361160, Rev L; List of Hatches and Scuttles.

1. NAVSEA Drawing 601-6363091; Selected Record Drawing Compt, Access & Deck Support Second Deck.

1. NAVSEA Drawing 601-6363092; Selected Record Drawing Compt, Access & Deck Support Main Deck.

1. NAVSEA Drawing 601-6363093; Selected Record Drawing Compt Access & Deck Support 01 Level.

1. NAVSEA Drawing 601-6363094; Selected Record Drawing Compt Access & Deck Support 02 Level

1. NAVSEA Drawing 601-6363095; Selected Record Drawing Compt Access & Deck Support 03 Level

1. NAVSEA Drawing 601-6363096; Selected Record Drawing Compt Access & Deck Support 04 Level & Abv.

1. Surface Preparation Standard, SSPC-SP-10, NEAR WHITE METAL BLAST CLEANING (CONTRACTOR OBTAIN)

1. Surface Preparation Standard, SSPC-SP-3, POWER TOOL CLEANING (CONTRACTOR OBTAIN)

1. MSC Standard Item 96, “Watertight Closures, Shop Repair”

1. NAVSEA TM S9169-AW-DCB-010; Watertight Closure Installation and Maintenance

1. ITEM LOCATION/DESCRIPTION:

2. Watertight doors (WTDs), and Watertight Hatches

Door #
Access To
Type
Size(inches)
Swing
Dogs
01-560-1
ESC TRK
QAWT
26x66
R
10
01-514-1
DRESS AREA
QAWT
26X66
R
10
01-505-1
ESC TRK
QAWT
26X66
R
10
01-366-1
OOD STA
QAWT
26X66
R
10
01-515-2
ESC TRK
QAWT
26X66
L
10
01-344-2
OOD STA
QAWT
26X66
L
10
01-186-4
DRESS AREA
QAWT
26X66
L
10
01-501-1
DK GR LKR
WT
26X66
R
10
01-205-2
AIRLOCK
QAWT
30X66
R
6
01-270-1
DK GR LKR
WT
26X66
R
10
01-186-1
DK GR LKR
WT
26X66
R
10
01-166-1
AIR LOCK
QAWT
26X66
R
8
01-469-1
CPS FAN ROOM
WT
26X66
R
10
01-409-1
EQP LKR
WT
26X66
R
10
01-334-1
DK GR LKR
WT
26X66
R
10
01-134-1
CPS FN RM 1
WT
26X66
R
10
01-115-1
CPS FN RM 1
WT
26X66
R
10
02-367-1
ELV MCHY ROOM 6
WT
26X66
R
10
02-392-1
UNRP MTR RM 7
WT
26X66
R
10
02-392-2
UNRP MTR RM 8
WT
26X66
L
10
04-509-2
MMR 1 CONT RM
WT
26X66
L
8
04-513-2
MMR2 INTAKE
WT
18X39
R
4

1. GOVERNMENT FURNISHED EQUIPMENT/MATERIAL/SERVICES: None

1. NOTES:

4. The contractor and all subcontractors, regardless of tier, must consult the General Technical Requirements to determine applicability to this Work Item. In performance of this Work Item, the contractor and all subcontractors, regardless of tier, must comply with the requirements of all applicable GTR's, including but not limited to, GTR's 1 through 7 and 24.

4. The contractor and all subcontractors, regardless of tier, are advised to review the other Work Items under this contract to determine their effect on the work required under this Work Item. Many of the definitions relating to the performance of this Work Item are found in Work Item 001.

1. QUALITY ASSURANCE REQUIREMENTS: None Additional

1. STATEMENT OF WORK REQUIRED:

6. Perform a survey of ship-wide exterior water tight doors only. The doors listed in Paragraph 3.0 should not be included in the survey. The doors shall be inspected for:

0. Missing or damaged wedges.

0. Holes.

0. Warpage, creases or irregular shaping.

0. Damaged or inoperable individual dogs.

0. Damaged or inoperable quick acting mechanisms.

0. Holes in steel above or below door.

7.1.1 Submit a condition report for any/all findings from inspection. The condition report shall contain the following information:

a. Door Number

b. QAWTD or Individual Dogged.

c. Repair recommendation.

0. Repair of doors included in the condition report shall be subject to a contract change order.

6. Accomplish Water Tight Door (WTD) replacements using References in 2.0 for guidance.

6. Replace WTD Doors listed in 3.0, all replacement doors shall be supplied with latest MachAlts; at a minimum all doors shall have MachAlt 538 and MachAlt 526 for exterior doors.

2. Contractor will procure closures with a factory finish suitable for application of the paint system described below

2. For weather deck doors provide temporary closure to protect the vessel’s interior and to maintain climate controlled conditions during the period that the closure is removed. Closures for deck openings shall be able to support 30 pounds per square foot. Closures for doors shall be hinged so as not to impede personnel flow and shall be securable.

2. At each location the contractor shall take all precautions to protect surrounding areas from damage and degradation.

2. Door panels, door components requiring preservation, and door frames shall be painted (except for edges) prior to installation inside a paint booth at the contractors shop.

2. Contractor shall disassemble new closure in preparation for applying paint system.

6. (CHECKPOINT) The MSC Paint Rep shall inspect and approve the surface preparation from the vendor prior to application of any coating.

3. Mask off portions of the door not requiring preservation.

3. Perform an SSPC-SP-1 on all areas to be painted.

3. Watertight closures shall be coated with one coat of inorganic zinc primer followed by one coat of epoxy A.C., and one topcoat of to all required surfaces. The topcoat color and paint type shall match the removed WTD colors.

2. (CHECKPOINT) The MSC Paint Rep shall inspect and approve each coat of paint prior to the application of the successive coat.

3. Match all parts and prepare door frame for installation onboard ship.

6. Install protective measures in way of all work to protect decks and equipment.

6. Accomplish the following test to the repaired doors:

5. (CHECKPOINT) Perform a chalk test on all closures prior to final tightness test. The impression of the knife-edge shall be continuous around the closure and shall be centered on the gasket.

5. (CHECKPOINT) Watertight closures located on weather decks or exterior bulkheads shall be hose tested. A 1-1/2 inch hose with not less than 70 PSI water pressure shall be directed all around the closure from a distance of not more than 10 feet. The water shall be applied from the weather deck side of the closure. The stream of water shall be moved slowly to ensure that the entire sealing surface, particularly the butt joint, is subjected to the full force of the water. No leakage shall be allowed.

5. (CHECKPOINT) Watertight closures located within the vessel's interior shall be soap and air tested in lieu of being hose tested. Compressed air of not less than 90 PSI shall be directed all around the closure from a distance of not more than 1 Foot. From the opposite side of the closure, a soapy water solution or a commercially available leak indicating solution shall be liberally applied to the gasket to indicate leaks. The stream of air shall be moved slowly to ensure that the entire sealing surface, particularly the butt joint, is subjected to the full force of the air. No leakage shall be allowed.

5. All tests shall be witnessed and approved by the MSCREP and the ABS Surveyor.

NOTE:

Neither hammers, mauls, or materials of like intent nor cheater pipes more than one foot in length shall be used to operate the dogs for securing the closure for testing. Use of force greater than that normally expected from one man, utilizing a one-foot cheater pipe would be grounds for rejecting the tests.

6. Renew all disturbed, soiled, missing, and removed insulation resulting from work accomplished in this item.

6. Feather disturbed areas into sound paint then prime and paint all new, soiled and disturbed areas to match surroundings

6. Remove all debris generated in the performance of this item and leave the area in a clean and ready to use condition.

6. Preparation of Drawings: None Additional

6. Manufacturer's Representative: None Additional

1. GENERAL REQUIREMENTS: None Additional

0107 - 1