0112_A_REPLACE_WEATHER_DECK__DRAIN_PIPING_REV2_ARCTICROH20.docx

DOCX document 34 KB Posted

Attached to
REGULAR OVERHAUL USNS ARCTIC Federal contract opportunity
Solicitation number
N32205-19-R-6012
Issued by
Department of the Navy Military Sealift Command

About this file

This document outlines requirements for repairing weather deck drain piping aboard the USNS ARCTIC as part of a regular overhaul and dry docking solicited by the Department of the Navy Military Sealift Command. The contractor will replace deteriorated sections of 2-inch schedule 40 stainless steel drain piping totaling 80 linear feet, with options to replace additional footage through a contract modification if more work is identified. Associated requirements include surface preparation, welding certification, providing pipe hangers and staging, hydrostatic testing, and painting disturbed areas. The solicitation number for the overall ship overhaul is N32205-19-R-6012.

Revised Work Item 0112

View the file

Other files for this federal contract opportunity

Other files attached to REGULAR OVERHAUL USNS ARCTIC, newest first.
File Type Posted
0305_A_REPLACE SSDG FORWARD CRANKSHAFT SEAL REV ARCTICROH20.docx DOCX document
0013_A_PROJECT PLANNING AND PRODUCTION STATUS MONITORING REPORTS REV 1-1May18.docx DOCX document
0021_A_CLEAN AND GAS FREE TANKS VOIDS AND COFFERDAMS REV OCT 2012_ARCTICROH20_REV2.docx DOCX document
N3220519R6012 Amendment 4.docx DOCX document
6362478_H.zip ZIP file
Q_and_A__5.docx DOCX document
0118_B_7-105-0-JJ_TANK_TOP_REPAIR_ARCTICROH2020_Revised.docx DOCX document
N3220519R6012_Amendment_2.docx DOCX document
0117_A_7-105-0-JJ_HYDROSTATIC_TESTING_ARCTICROH20.docx DOCX document
J_-_3_Category_B_Items_ARCTIC_Revised_21_OCT_19.xls XLS spreadsheet
0118_B_7-105-0-JJ_TANK_TOP_REPAIR_ARCTICROH2020.docx DOCX document
N3220519R6012_Amendment_3.docx DOCX document
J_-_2_Category_A_Items_ARCTIC_Revised_21_OCT_19.xls XLS spreadsheet
0912_A_UNDERWATER_HULL_CLEANING_and_PAINTING_REV_1_.docx DOCX document
Q_and_A__4.docx DOCX document
0517_A_INSTALL_OILY_WATER_SEPERATOR_TALT_301_ARCTICROH20_REV1.docx DOCX document
Q_and_A__3.docx DOCX document
0913_A_HULL_FREEBOARD_CLEANING_AND_PAINTING_REV_1_ARCTICROH20.docx DOCX document
0109_A_JP-5_PUMPROOM_BILGE_PRESERVATION_ARCTICROH20_REV_1.docx DOCX document
0104_A_RENEW_01_LEVEL_NON_SKID_REV_1_ARCTICROH20.docx DOCX document
0202_A_SEAL_CHANGE_OUT_FOR_REDUCTION_GEAR_MAIN_THRUST_BEARINGS_ARCTICROH20_REV2.docx DOCX document
0107_A_REPLACE_REPAIR_SURVEY_WATERTIGHT_DOORS_ARCTICROH20_REV1.docx DOCX document
J_-_2_Category_A_Items_ARCTIC_Revised_20_SEP_19.xls XLS spreadsheet
N3220519R6012_Amendment_1.docx DOCX document
0201_A__INSTRUMENT_CALIBRATION_AND_REPAIR_ARCTICROH20.docx DOCX document
0113_A_FANTAIL_OVERHEAD_CLEANING_AND_PRESERVATION_ARCTICROH20_REV_1.docx DOCX document
0116_B_BILGE_WELL_STAGING_SUPPORT_REV_1_ARCTICROH20.docx DOCX document
0112_A_REPLACE_WEATHER_DECK__DRAIN_PIPING_REV1_ARCTICROH20_(002).docx DOCX document
J_-_3_Category_B_Items_ARCTIC_Correction.xls XLS spreadsheet
Q_AND_A__2.docx DOCX document
J_-_2_Category_A_Items_ARCTIC.xls XLS spreadsheet
Q_and_A__1.doc DOC document
J_-_3_Category_B_Items_ARCTIC.xls XLS spreadsheet
N3220519R6012.docx DOCX document
J_and_A_Redacted.docx DOCX document
USNS_ARCTIC_ROHDD_2020_J_Attachments.zip ZIP file
J_-_14_Technical_Data_Non-Disclosure.docx DOCX document
SYNOPSIS_N3220519R6012_USNS_ARCTIC.docx DOCX document
SOURCES_SOUGHT_FOR_USNS_ARCTIC_ROH_2020.docx DOCX document
Show all 39

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1.0 ABSTRACT

1.1 This item describes the requirements to repair various weather deck drain piping sections throughout the vessel.

2.0 REFERENCES and ENCLOSURES:

2.1 REFERENCES:

2.1.1 NAVSEA Drawing 526-6360591J, Weather Deck Drains Diagram

2.1.2 Surface Preparation Standard, SSPC-SP-10, NEAR WHITE METAL BLAST CLEANING(Contractor provide)

2.1.3 Surface Preparation Standard, SSPC-SP-3, POWER TOOL CLEANING (Contractor provide)

3.0 LOCATION /DESCRIPTION/OUTFITTINGS:

3.1 Location: Various

3.2 Description: None Additional

3.3 Outfitting:

3.3.1 2 IPS, Schedule 40, SSL Pipe; 80 linear feet.

3.3.2 Stainless Steel Pipe Hangers; 30 ea.

4.0 GOVERNMENT FURNISHED EQUIPMENT/ MATERIAL: None.

5.0 NOTES

5.1 The contractor and all subcontractors, regardless of tier, must consult the General Technical Requirements to determine applicability to this Work Item. In performance of this Work Item, the contractor and all subcontractors, regardless of tier, must comply with the requirements of all applicable GTR's, including but not limited to, GTR's 1 through 7 and 24.

5.2 The contractor and all subcontractors, regardless of tier, are advised to review the other Work Items under this contract to determine their effect on the work required under this Work Item. Many of the definitions relating to the performance of this Work Item are found in Work Item 001.

6.0 QUALITY ASSURANCE REQUIREMENTS:

6.1 All welding Certification, Materials and Procedures shall be in accordance with American Bureau of Shipping (ABS) requirements.

7.0 STATEMENT OF WORK REQUIRED

7.1 Arrangement and outfitting:

7.1.1 Provide initial outfitting listed in Para 3.3.

7.2 Structural:

7.3 Mechanical and Fluids

7.3.1 The contractor and MSCREP shall perform a ship tour no later than day three to identify areas for repair. If more than eighty linear feet is identified or a different size pipe is required, a contract change order shall be issued to cover the excess linear footage.

7.3.2 Provide labor and material to replace deteriorated sections of weather deck drain piping. The following requirements apply to all of the piping repairs and surrounding area affected by this work item.

a Obtain required hot work certifications.

b Protect ships equipment and structure and deck coverings from damage in area of work.

c New pipe sections shall be targeted and templated from existing (as found required); and shaped, hung, fitted, and/or flanged as per existing arrangement. Estimate one hundred sixty hours (160) of pipefitting hours to replace initial 80 linear feet of drainage piping.

d Estimate that 40 hours of pipe bending and shaping will be required.

e Estimate one hundred sixty hours of fire watch will be required.

f Replace gaskets in all new and disturbed mechanical joints.

g Contractor to replace all disturbed pipe hangers with new CRES hangers using new rubber lining material and new CRES hardware. Hanger replacement shall include hanger legs and support(s).

h Provide safe staging and platforms to work from while accomplishing work. For bidding purposes estimate that thirty feet of staging (total) will be required. If an excess of thirty feet is required, submit condition report and a contract change order shall be negotiated for the additional staging.

i Crop out and install new 2 IPS, Schedule 40, stainless steel drain pipe, pipe hangars, brackets, in way of deteriorated areas.

j Grind flush all scabs, scarfs and stubs smooth and flush to decks, bulkheads and structure.

7.4 Electrical: None Additional

7.5 Electronics: None Additional

7.6 Preparation of Drawings and Documents:

7.7 Inspection and Test:

7.7.1 Accomplish the following test to the repaired deck drains:

7.7.2 CHECKPOINT: Perform a Static head hydro test by completely filling repaired deck drain pipe runs. Prove drains are free and clear in the presence of the MSCREP.

7.8 Painting

7.8.1 Grit blast all new pipe, standoffs, pipe hangars, and brackets to provide a 2-4 mil profile prior to installation and paint with contractor furnished inorganic zinc primer, one strip coat of epoxy primer, one full coat of epoxy primer and one full coat of urethane to match surrounding all coats to be 5-6 mils DFT unless specified otherwise in product application guide.

7.8.2 Perform SSPC-SP-3 on disturbed area to be painted. Feather to solid paint and paint all effected, soiled and disturbed area to match surroundings

7.9 Marking: None

7.10 Manufacturer’s Representative: None

8.0 GENERAL REQUIREMENTS:

8.1 None Additional

USNS ARCTIC

(T-AOE 8)

HULL STRUCTUREN32205-19-R-6012
14 JANUARY 2014
ITEM NO. 112CATEGORY "A"N756/JEB

RENEW WEATHER DECK DRAIN PIPING REV2