This document outlines the requirements for staging areas in fuel tanks to support bilge well repair and renewal aboard the USNS ARCTIC as part of its regular overhaul. Key details include the requirement to provide staging in 16 specific locations within various bunker and cargo tanks, ranging from 20 to 60 feet in length. Daily safety checks must be performed for any erected staging. All industrial debris generated during staging setup must be cleaned from the tanks. The related federal contract opportunity is a pre-solicitation for the regular overhaul and dry docking of the USNS ARCTIC (T-AOE 8) to be conducted by the Department of the Navy Military Sealift Command.

Revised Work Item 0116

View the file

Other files

File Type Posted
0021_A_CLEAN AND GAS FREE TANKS VOIDS AND COFFERDAMS REV OCT 2012_ARCTICROH20_REV2.docx DOCX document
0013_A_PROJECT PLANNING AND PRODUCTION STATUS MONITORING REPORTS REV 1-1May18.docx DOCX document
N3220519R6012 Amendment 4.docx DOCX document
0305_A_REPLACE SSDG FORWARD CRANKSHAFT SEAL REV ARCTICROH20.docx DOCX document
Q_and_A__5.docx DOCX document
0118_B_7-105-0-JJ_TANK_TOP_REPAIR_ARCTICROH2020_Revised.docx DOCX document
6362478_H.zip ZIP file
N3220519R6012_Amendment_2.docx DOCX document
J_-_3_Category_B_Items_ARCTIC_Revised_21_OCT_19.xls XLS spreadsheet
J_-_2_Category_A_Items_ARCTIC_Revised_21_OCT_19.xls XLS spreadsheet
0118_B_7-105-0-JJ_TANK_TOP_REPAIR_ARCTICROH2020.docx DOCX document
N3220519R6012_Amendment_3.docx DOCX document
0117_A_7-105-0-JJ_HYDROSTATIC_TESTING_ARCTICROH20.docx DOCX document
Q_and_A__4.docx DOCX document
0912_A_UNDERWATER_HULL_CLEANING_and_PAINTING_REV_1_.docx DOCX document
0107_A_REPLACE_REPAIR_SURVEY_WATERTIGHT_DOORS_ARCTICROH20_REV1.docx DOCX document
0913_A_HULL_FREEBOARD_CLEANING_AND_PAINTING_REV_1_ARCTICROH20.docx DOCX document
0201_A__INSTRUMENT_CALIBRATION_AND_REPAIR_ARCTICROH20.docx DOCX document
0113_A_FANTAIL_OVERHEAD_CLEANING_AND_PRESERVATION_ARCTICROH20_REV_1.docx DOCX document
J_-_2_Category_A_Items_ARCTIC_Revised_20_SEP_19.xls XLS spreadsheet
N3220519R6012_Amendment_1.docx DOCX document
Q_and_A__3.docx DOCX document
0517_A_INSTALL_OILY_WATER_SEPERATOR_TALT_301_ARCTICROH20_REV1.docx DOCX document
0112_A_REPLACE_WEATHER_DECK__DRAIN_PIPING_REV2_ARCTICROH20.docx DOCX document
0109_A_JP-5_PUMPROOM_BILGE_PRESERVATION_ARCTICROH20_REV_1.docx DOCX document
0104_A_RENEW_01_LEVEL_NON_SKID_REV_1_ARCTICROH20.docx DOCX document
0202_A_SEAL_CHANGE_OUT_FOR_REDUCTION_GEAR_MAIN_THRUST_BEARINGS_ARCTICROH20_REV2.docx DOCX document
Q_AND_A__2.docx DOCX document
0112_A_REPLACE_WEATHER_DECK__DRAIN_PIPING_REV1_ARCTICROH20_(002).docx DOCX document
J_-_3_Category_B_Items_ARCTIC_Correction.xls XLS spreadsheet
Q_and_A__1.doc DOC document
J_-_3_Category_B_Items_ARCTIC.xls XLS spreadsheet
J_-_2_Category_A_Items_ARCTIC.xls XLS spreadsheet
J_and_A_Redacted.docx DOCX document
N3220519R6012.docx DOCX document
USNS_ARCTIC_ROHDD_2020_J_Attachments.zip ZIP file
J_-_14_Technical_Data_Non-Disclosure.docx DOCX document
SYNOPSIS_N3220519R6012_USNS_ARCTIC.docx DOCX document
SOURCES_SOUGHT_FOR_USNS_ARCTIC_ROH_2020.docx DOCX document
Show all 39

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USNS ARCTIC

T-AOE 8)

HULL STRUCTUREN32205-19-R-6012
14 JANUARY 2014
ITEM NO. 116CATEGORY "B"N756/JEB

BILGE WELL STAGING SUPPORT.

1.0 ABSTRACT:

1.1 This item describes the requirement to stage areas of fuel tanks in support of bilge well repair/renewal.

2.0 REFERENCES:

2.1 ABS Rules for Building and Classing Steel Vessels, Part 7 (Contractor Provided)

2.2 NAVSEA Drawing No. 085-6362912; USNS SUPPLY SRD Booklet of General Drawings

2.3 NAVSEA Drawing No. 141-6362169, Assembly 1st Platform

2.4 NAVSEA Drawing No. 501-6359953, AMR Arrangement

2.5 NAVSEA Drawing No. 801-6360543, Scantling Drawing Fr 35 – Fr 205 01 Lvl and Below

2.6 NAVSEA Drawing No. 801-6360544, Scantling Drawing Fr 205 - Fr 455 01 Lvl and Below

2.7 NAVSEA Drawing No. 801-6360545, Scantling Drawing Fr 455 – Fr 565 01 Lvl and Below

2.8 NAVSEA Drawing No. 085-6360524, Shell Expansion

3.0 ITEM LOCATION/DESCRIPTION:

3.1 Location:

3.1.1 NOT INCLUDED IN THIS WORK ITEM

3.1.2 ADP Workshop (2-661-2-Q)

3.1.3 AFFF Station 1 (1-289-1-Q) Forward Bilge Well

3.1.4 AFFF Station 1 (1-289-1-Q) After Bilge Well

3.1.5 Forward MSD (3-160-1-Q) Bilge Well

3.1.6 Fan Room (2-205-5-Q) Bilge Well

3.1.7 Battery Shop - Fwd (1-231-2-Q) Bilge Well

3.1.8 Fan Room (1-265-6-Q) Bilge Well

3.1.9 Fan Room (1-265-4-Q) Bilge Well

3.1.10 ET Shop (1-330-7-Q) Bilge Well

3.1.11 Hold 1, 2nd Plat, Stbd, (4-205-0-MM) Bilge Well

3.1.12 Hold 1, 2nd Plat, Port, (4-205-0-MM) Bilge Well

3.1.13 Hold 2, 2nd Plat, Stbd, (4-265-0-MM) Bilge Well

3.1.14 Hold 3, 2nd Plat, Port, (4-265-0-MM) Bilge Well

3.1.15 Hold 3, 2nd Plat, Stbd, (4-330-0-MM) Bilge Well

3.1.16 Hold 1, 2nd Plat, Port, (4-330-0-MM) Bilge Well

4.0 GOVERNMENT FURNISHED EQUIPMENT/MATERIAL/SERVICES:

4.1 Government Paint Representative.

5.0 NOTES:

5.1 The contractor and all subcontractors regardless of tier shall consult the General Technical Requirements (GTR) to determine applicability to this work item. In performance of this work item, the contractor and all subcontractors regardless of tier must comply with the requirements of all applicable GTRs including but not limited to GTRs 1 through 7.

5.2 The contractor and all subcontractors regardless of tier are advised to review ALL other work items under this contract, in particular items 021 and 101 to determine their effect on the work required under this work item. Many of the definitions relating to performance of this work item are found in Work Item 001.

6.0 QUALITY ASSURANCE REQUIREMENTS: None Additional

7.0 STATEMENT OF WORK REQUIRED:

7.1 For each of the locations listed in 3.0 and shown in Figures 2 through 16 accomplish the following:

7.1.1 For location 3.1.2 provide 20 feet of staging in the 625-2 Bunker Tank.

7.1.2 For location 3.1.3 and 4, provide sixty (60) feet of staging in the 7-265-1-JJ cargo JP5 tank (2 locations in one tank).

7.1.3 For location 3.1.5, provide an additional sixty (60) feet of vertical staging in the 7-150-0-FF/JJ tank.

7.1.4 For location 3.1.6 & 7, provide sixty (60) feet of vertical staging IN 7-205-1-JJ so that both bilge wells may be accessed.

7.1.5 For location 3.1.8 & 9, provide sixty (60) feet of vertical staging in the 7-265-2-JJ cargo JP-5 tank.

7.1.6 For location 3.1.10, provide 60 feet of vertical staging in the 7-330-1-FF/JJ tank.

7.1.7 For location 3.1.11 & 12, provide 60 feet of staging in the JP5 Pumproom.

7.1.8 For location 3.1.13 & 14, provide 25 feet of vertical staging in two locations in the 7-265-0-JJ cargo tank.

7.1.9 For location 3.1.15 & 16, provide 25 feet of vertical staging in two locations in the 7-330-0-FF/JJ cargo tank.

7.1.10 Perform daily safety checks for any/all staging erected by this work item.

7.1.11 Once staging is removed from tank, verify all industrial debris generated by the erection of staging is cleaned and cleared to the satisfaction of the MSCREP.

8.0 GENERAL REQUIREMENTS: None Additional

116 - 1