About this file

This document outlines a pre-solicitation synopsis for the AN/SPQ-15 Data Distribution System production contract. The Navy seeks to award a C-type contract to produce hardware including switchboards, decoders, converters, and upgrades for existing AN/SPQ-14 and AN/SPQ-15 systems. The contract is set aside as a small business opportunity with a period of performance of five years. Pricing includes firm-fixed-price, cost-plus-fixed-fee, and not-separately-priced contract line items. The solicitation number is N0017822R2501 and is expected to be available on March 7, 2022, with proposals due by April 5, 2022. Award is planned for November 2022 with a period of performance start date of November 2022. The requirement falls under NAICS code 334118 and PSC codes K012 and 1285.

View the file

Other files for this federal contract opportunity

Other files attached to AN/SPQ-15 Data Distribution System Production, newest first.
File Type Posted
CDRLs_24_August_Draft.pdf PDF
N00178-22-R-2501_24_August_Draft.pdf PDF
N0017822R2501_DRAFT_QA_Responses.xlsx XLSX spreadsheet
DMSMS report.xlsx XLSX spreadsheet
N0017822R2501_DRAFT_QA_Responses.xlsx XLSX spreadsheet
N0017822R2501_DRAFT_QA_Responses.xlsx XLSX spreadsheet
DRAFT_Exhibit A_CDRLs.pdf PDF
N00178-22-R-2501_DRAFT_6.1.22.docx DOCX document
455048J ATP for the SDC.doc DOC document
455047E ATP for the SSSM.doc DOC document
Attachment L.1 AN-SPQ 15 Staffing Matrix Format.xlsx XLSX spreadsheet
DRAFT J.5 - Labor Category Qualifications.pdf PDF
DRAFT J.3 - GFP List.xlsx XLSX spreadsheet
DRAFT J.1 - DD 254.pdf PDF
455105A ATP for the Extender Card.doc DOC document
455049P ATP for the RSDS.doc DOC document
455279 456357-2 DIM ATP.doc DOC document
455281A 456060-2 QSDM ATP.doc DOC document
455068B ATP for the RS422_RS232 Converter.doc DOC document
Attachment J.9 - Question Submittal Form.xlsx XLSX spreadsheet
DRAFT J.4 - QASP.pdf PDF
455054D ATP for Spare Power Conditioner.doc DOC document
455287A ATP for the CRC 456010-2.doc DOC document
455278A RIM ATP (PN 456354-2).doc DOC document
455056L ATP for the Spare Processor Assy.doc DOC document
409079C ATP for the Converter PS Module.doc DOC document
DRAFT J.2 - GFI List.pdf PDF
455088F ATP for the Media Converter.doc DOC document
455063H ATP for the SBC.doc DOC document
455280B IIM ATP (PN 456370-2).doc DOC document
455060J ATP for the RVC.doc DOC document
455055B - ATP for the HMI.doc DOC document
DRAFT J.8 - Cost_Summary_Format.xls XLS spreadsheet
DRAFT J.6 - eCRAFT_SCA Crosswalk.xlsx XLSX spreadsheet
N0017822R2501_Unclassified Terms of Use Agreement.pdf PDF
N0017822R2501_DRAFT_QA_Responses.xlsx XLSX spreadsheet
N0017822R2501_DRAFT_QA_Responses.xlsx XLSX spreadsheet
N0017822R2501_DRAFT_2.9.22.docx DOCX document
N00178-22-R-2501 CDRL DRAFT.pdf PDF
N0017822R2501_DRAFT SOL_QA_MATRIX.xlsx XLSX spreadsheet
Show all 40

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

409030D

SHAPE \* MERGEFORMAT

REVISIONS

REV
DESCRIPTION
DATE
APPROVED
A
Incorporated Changes per CO # 24-1291
5-13-04
AFW
B
Incorporated Changes per CO # 24-1610
11/1/05
PDC
C
Incorporated Changes per CO # 24-1801
4/11/07
PDC
D
Incorporated Changes per CO # 24-3481
7/16/2012
PDC
ORIGINAL DATE 25 AUGUST 2003
DATE APPROVED
FRONTIER ELECTRONIC SYS.

STILLWATER, OKLAHOMA 74076-1023

ORIGINATOR
JORY BLAGDEN
08/27/03
DOC. COORDINATOR
KELLY WHITFIELD
8-27-03
ACCEPTANCE TEST PROCEDURE

FOR THE SIGNAL SPLITTER MODULE

(P/N 500034-1)

PROJECT ENGINEER
CHRISTOPHER JOBE
27 AUG 2003
PROGRAM MGR.
A.F. WINEMILLER
8-28-03
QUALITY
S. ZELESNIKAR
27 AUG 03

CODE IDENT.

63812 409030D

ACCEPTANCE TEST PROCEDURE

FOR THE SIGNAL SPLITTER MODULE

(P/N 500034-1)

TABLE OF CONTENTS

Section Title Page

GENERAL INFORMATION

1.1

SCOPE

1.2

PURPOSE

1.3

TEST EQUIPMENT

1.4

GENERAL REQUIREMENTS

1.4.1 Production Routers 1.4.2 Test Conditions 1.4.3 Failure Reporting

1.4.4 Test Data

PRE-TEST EVALUATION

2.1

INSTALLATION AND SETUP PROCEDURE

2.2

AUTOMATED TEST PROGRAM (CONVERTER)

2.3

AUTOMATED TEST PROGRAM (SWITCHBOARD)

BURN-IN

FINAL TEST

4.1

AUTOMATED TEST PROGRAM (CONVERTER)

4.2

AUTOMATED TEST PROGRAM (SWITCHBOARD)

APPENDIX A

PRODUCTION ROUTERS

A-1

TABLE OF CONTENTS (Continued) Section Title Page

APPENDIX B

NON-CONFORMANCE REPORTS

B-1

APPENDIX C

BURN-IN LOG

C-1

LIST OF FIGURES

Figure Title Page 1.1-1 Testing Flow

2.1-1 Converter and Switchboard Test Rack Configurations

LIST OF TABLES

Table Title Page 1.3-1 Test Equipment

2.2-1 Pre-Test Verification Table (Converter) 2.3-1 Pre-Test Verification Table (Switchboard) 3-1 Burn-in Test Information 4.1-1 Final Test Verification Table (Converter) 4.2-1 Final Test Verification Table (Switchboard)

SECTION 1

GENERAL INFORMATION

1.1

SCOPE

This document contains the test requirements for the acceptance testing of the Signal Splitter Module (P/N 500034-1). This document contains the following sections:

Section 1: General Information

Section 2: Pre-Test Evaluation Procedures

Section 3: Burn-In Procedures

Section 4: Final Test Procedures

The figure below illustrates the order of testing.

Figure 1.1-1. Testing Flow

1.2

PURPOSE

The purpose of this document is to demonstrate that the Signal Splitter Module, as manufactured by Frontier Electronic Systems, meets or exceeds all recurring requirements identified within document 409023, PDT Module Validation Plan.

1.3

TEST EQUIPMENT

Table 1.3-1 lists the equipment required to perform the procedures contained in this document. Enter the serial number and calibration expiration date for each piece of test equipment.

Table 1.3-1. Test Equipment

DESCRIPTION
MODEL
SERIAL NUMBER
MANUFACTURER/

SPECIFICATIONS

CALIBRATION

EXP. DATE

Cruiser Converter Tester
500129-1
001
FES
N/A
Switchboard Tester
204306
001
FES
N/A

1.4

GENERAL REQUIREMENTS

1.4.1 Production Routers

Insert the Production Routers for the module into Appendix A.

1.4.2 Test Conditions

Unless otherwise specified herein, testing shall be performed at standard room ambient temperature, 60( to 80(F.

1.4.3 Failure Reporting

Non-Conformance Reports (NCRs) shall be used to document test failures in accordance with FES-QSP-8.3-3 when required. A copy of each NCR shall be inserted into Appendix B.

1.4.4 Test Data Successful completion of each test shall be annotated within these procedures. Test data recorded during automated testing shall be maintained on the FES network at data3\Shared Data\Naval Systems\Test Data\part number\serial number.

SECTION 2

PRE-TEST EVALUATION

This section contains the steps for conducting a preliminary test of the Signal Splitter Module before subjecting it to a burn-in cycle. Both the Cruiser Converter Tester and Switchboard Tester are required for these tests.

2.1

INSTALLATION AND SETUP PROCEDURE

The Installation and Setup Procedure verifies the test configuration.

1. On the Cruiser Converter Tester, set the Gold Board Converter Chassis’ Power Supply Module switch to the OFF position.

2.

Install the Signal Splitter Module into the Converter Chassis slot designated Signal Splitter in the Cruiser Converter Tester.

3.

Connect the Tester cables as shown in Figure 2.1-1.

Figure 2.1-1. Converter and Switchboard Tester Configurations 2.2

AUTOMATED TEST PROGRAM (CONVERTER)

These procedures are performed using the Cruiser Converter Tester.

1.

Set the Gold Board Converter Chassis’ Power Supply Module switch to the ON position.

2.

Select the Cruiser Converter Tester icon on the initial windows screen and follow the displayed instructions.

3.

The program will display dialog boxes to provide the operator with step-by-step instructions for completing testing. Upon completion of each test, annotate the appropriate entry in Table 2.2-1.

Table 2.2-1. Pre-Test Verification Table (Converter)

TEST
ESTIMATED RUN TIME
COMPLETE
Oscope-Pulse Characteristics Measurements (Splitter)
5 Minutes
LED and Test Point Test (Splitter)
5 Minutes

2.3

AUTOMATED TEST PROGRAM (SWITCHBOARD)

These procedures are performed using the Switchboard Tester.

1.

Apply power to the Switchboard Tester.

2.

Select the Switchboard Tester Icon on the initial windows screen and following displayed instructions.

3.

The program will display dialog boxes to provide the operator with step-by-step instructions for completing testing. Upon completion of the test, annotate the entry in Table 2.3-1.

Table 2.3-1. Pre-Test Verification Table (Switchboard)

TEST
ESTIMATED RUN TIME
COMPLETE
Splitter Video Test
15 minutes

SECTION 3

BURN-IN

This section contains the procedures to accomplish a burn-in cycle on the Signal Splitter Module.

1.

Place the Signal Splitter Module into a test bed capable of providing power to the module per VMEbus standards.

2.

Place the test bed into a thermal chamber.

3.

Complete a 48 hour (minimum) burn-in cycle at 45°C ± 5°C with power applied to the module.

4.

In Table 3-1 record the time and date of the beginning and end of the cycle and the total burn-in time.

Table 3-1. Burn-in Test Information

Date/Time

5.

Insert the temperature burn-in chart into Appendix C.

Completion Verified: ________________

SECTION 4

FINAL TEST

This section details the functional testing of the Signal Splitter Module.

4.1

AUTOMATED TEST PROGRAM (CONVERTER)

These procedures are performed using the Cruiser Converter Tester.

1. Ensure power is OFF on the Cruiser Converter Tester Gold Board Chassis.

2. Install the Signal Splitter Module into the Converter Chassis slot designated “Signal Splitter” in the Cruiser Converter Tester.

3. Connect the Tester Cables as shown in Figure 2.1-1.

4.

Apply power to the Gold Board Chassis.

5.

Select the Cruiser Converter Testers icon on the initial windows screen and follow the displayed instructions.

6.

The program will display dialog boxes to provide the operator with step-by-step instructions for completing testing. Upon completion of each test, annotate the appropriate entry in Table 4.1-1.

Table 4.1-1. Final Test Verification Table (Converter)

TEST
ESTIMATED RUN TIME
COMPLETE
Oscope-Pulse Characteristics Measurements (Splitter)
5 Minutes
LED and Test Point Test (Splitter)
5 Minutes

4.2

AUTOMATED TEST PROGRAM (SWITCHBOARD)

These procedures are performed using the Switchboard Tester.

1. Apply power to the Switchboard Tester

2. Select the Switchboard Tester icon on the initial windows screen and follow the displayed instructions.

3.

The program will display dialog boxes to provide the operator with step-by-step instructions for completing testing. Upon completion of the test, annotate the entry in Table 4.2-1.

Table 4.2-1. Final Test Verification Table (Switchboard)

TEST
ESTIMATED RUN TIME
COMPLETE
Splitter Video Test
15 minutes

4.

Copy test data files to the FES network drive at data3\Shared Data\Naval Systems\Test Data\part number\serial number.

Verified: _______________

Comments:

Validation

This sheet is supplied as a validation of the completion and accuracy of the data contained herein. The Test Technician will sign and date as an indication that all instructions have been followed and that each test step has been successfully completed. Signature by the Quality Engineer is an acknowledgement that the test data has been reviewed for completion and accuracy. Applicable Test/Inspection stamps will be affixed by the signature blocks

Test Technician: ________________________________Date:____________

Quality Engineer: _______________________________Date:____________

APPENDIX A

PRODUCTION ROUTERS

APPENDIX B

NON-CONFORMANCE REPORTS

APPENDIX C

BURN-IN LOG

MODULE TEST

REPAIR

BOARD PER

PARA 1.4.3

Pass�Test?

ACCEPTANCE TEST PROCEDURE

FOR THE SIGNAL SPLITTER MODULE

(P/N 500034-1)

S/N: _________________

13 JULY 2012

DISTRIBUTION STATEMENT D: Distribution authorized to the Department of Defense and U.S. DoD contractors only due to protecting technical, operational, or operational use information from automatic dissemination under the International Exchange Program or by other means as determined on or after date of task order award. Other requests for this document shall be referred to NAVSEA CDSA Code F31.

WARNING – This document contains technical data whose export is restricted by the Arms Export Control Act (Title 22, U.S.C., Sec 2751, et seq.) or the Export Administration Act of 1979, as amended, Title 50, U.S.C., App. 2401 et seq. Violations of these export laws are subject to severe criminal penalties. Disseminate in accordance with provisions of DoD Directive 5230.25.

Prepared By:

FRONTIER ELECTRONIC SYSTEMS CORP.

P.O. BOX 1023

STILLWATER, OKLAHOMA 74076-1023

AUTOMATED

TEST PROGRAM (CONVERTER)

SECTION 4.1

AUTOMATED TEST PROGRAM (SWITCHBOARD) SECTION 2.3

SECTION 2.2

INSTALLATION

AND SETUP

SECTION 2.1

BURN-IN

BOARD

SECTION 3

Pass�Test?

AUTOMATED TEST PROGRAM (CONVERTER) SECTION 2.2

INSTALLATION AND SETUP

SECTION 2.1

START�MODULE �TEST

FINAL TEST

Pre-test �Evaluation

YES

NO

NO

YES

AUTOMATED TEST PROGRAM (SWITCHBOARD) SECTION 4.2

MODULE �TEST COMPLETE