Project Phase Court Unit Department Existing Space Building
Existing Space Suite Move from Existing to Swing
Swing Space Building
Swing Space Move to New Space
New Space Building
New Space Suite Swing Space Office Requirements
Swing Space Support Requirements
Swing Space IT Requirements
Phase 1 USBC Courtrooms & Chambers
Roybal 14th Floor Phase 1 n/a n/a n/a n/a n/a n/a n/a n/a
Phase 1 USBC Operations Support Roybal 12th Floor Open Office
Phase 1 Roybal 9th Floor Courtroom Services Suite n/a n/a n/a Absorbed into Unassigned Workstations in Courtroom Services n/a n/a
Phase 1 USBC Board of Judges' Conference Room
Roybal 12th Floor Phase 1 Roybal 2nd Floor Training Room
Completion of Project
Roybal (Option) 16th Floor (Former USBC Courtroom)
Relocate & reconfigure loop conference table n/a 1 voice, 1 data, 1 power at loop conference table
Phase 1 USBC General Assembly Room Roybal 12th Floor Phase 1 300 NLA 1st Floor (Storage)
Completion of Project
Roybal (Option) 15th Floor (Former USBC Courtroom)
Storage of Furniture until Project Completion n/a n/a
Phase 2 USBC Executive Suite ‐ Chief Deputy
Roybal 10th Floor Executive Suite
Phase 2 Roybal Chambers 1482 Phase 3 Roybal 10th Floor Executive Suite
(1) Office, (2) Workstations (2) Printer Area, (1) Copier Per Office/Workstation: 1 data, 1 voice High‐Duty Copy Area (dedicated outlet)
Phase 2 USBC Human Resources Roybal 10th Floor HR Suite Phase 2 Roybal Chambers 1434 Phase 3 Roybal 10th Floor Open Office
(1) Office, (6) Workstations, (1) Testing Room, (1) Conference Room
(2) Printer Area, (1) Copier Per Office/Workstation: 1 data, 1 voice Conference Room: 2 data, 1 voice Testing Room: 2 data
Phase 2 USBC A&I Roybal 10th Floor A&I/Fiscal Suite
Phase 2 300 NLA 1st Floor (Office Services)
Phase 3 Roybal 10th Floor Open Office
(1) Office, (3) Workstations (2) Printer Area, (1) Copier Per Office/Workstation: 1 data, 1 voice
Phase 2 USBC Fiscal Roybal 10th Floor A&I/Fiscal Suite
Phase 2 300 NLA 1st Floor (Fiscal) Phase 3 Roybal 10th Floor Open Office
(1) Office, (3) Workstations, (1) Secure Storage Room
Per Office/Workstation: 1 data, 1 voice
Phase 2 USBC Help Desk Roybal 10th Floor Help Desk Suite
Phase 2 300 NLA Basement Phase 3 Roybal 10th Floor Open Office
(4) Workstations, (1) Lab, Storage
(2) Printer Area, (1) Copier Per Office/Workstation: 2 data, 1 voice
Phase 2 USBC Network Roybal 10th Floor Network Suite
Phase 2 300 NLA Basement Phase 3 Roybal 10th Floor Network/ Developers Suite
(3) Offices, (3) Workstations (2) Printer Area, (1) Copier Per Office/Workstation: 2 data, 1 voice
Phase 2 USBC Developers Roybal 10th Floor Developers Suite
Phase 2 300 NLA Basement Phase 3 Roybal 10th Floor Network/ Developers Suite
(1) Office, (1) Office or Larger Workstation, (5) Workstations
(2) Printer Area, (1) Copier Per Office/Workstation: 2 data, 1 voice
Phase 2 USBC Communications Roybal 10th Floor Communications Suite
Phase 2 300 NLA Basement Phase 3 Roybal 10th Floor Open Office
(1) Office, (3) Workstations, (1) Work Area, Storage
(1) Copier, (1) High‐Speed Copier,
(1) Plotter, (1) Photo Printer
Per Office/Workstation: 2 data, 1 voice High‐Duty Copy: 1 data, (dedicated outlet) Per Copier: 1 Phone, 1 Data Per Plotter: 1 Data
Phase 3 USBC Office Services 300 NLA 1st Floor (Office Services) n/a n/a n/a Phase 3 Roybal 10th Floor Open Office n/a n/a n/a
Phase 3 USBC Fiscal 300 NLA 1st Floor (Fiscal) n/a n/a n/a Phase 3 Roybal 10th Floor Open Office n/a n/a n/a
Phase 3 USBC Executive Suite ‐ Clerk of Court & Chief Deputy
Roybal 12th Floor (2 Chambers) n/a n/a n/a Phase 3 Roybal 10th Floor Executive Suite n/a n/a n/a
Phase 4 USBC Intake Roybal 9th Floor (Intake) n/a n/a n/a Phase 4 Roybal Terrace Level Intake n/a n/a n/a
Phase 4 USBC Pro Se Clinic 300 NLA 1st Floor (Pro Se) n/a n/a n/a Phase 4 Roybal Terrace Level Intake n/a n/a n/a
Phase 4 USBC Staff Development Roybal 9th Floor Training Suite
Phase 4 300 NLA 1st Floor (Former Office Services)
Phase 5 Roybal 9th Floor Open Office
(4) Workstations Existing USBC Space Existing USBC Space
Phase 4 USBC Training Room Roybal 9th Floor Training Suite
Phase 4 300 NLA 1st Floor (Former Pro Se Area)
Phase 5 Roybal 9th Floor Training Room
(1) Training Area n/a n/a
Phase 4 USBC Courtroom Services & Operations Support
Roybal 9th Floor Courtroom Services Suite
Phase 4 300 NLA Basement Phase 5 Roybal 9th Floor Open Office
(6) Offices, (33) Workstations Established in Phase 2 Established in Phase 2
Phase 4 USBC Break Room Roybal 9th Floor Break Room
Phase 4 300 NLA Basement Phase 5 Roybal 9th Floor Break Room
(1) Open Area (2) Printer Area, (1) Copier (6) duplex outlets for Appliances
Project Phase Court Unit Department Existing Space Building
Existing Space Suite Move from Existing to Swing
Swing Space Building
Swing Space Move to New Space
New Space Building
New Space Suite Swing Space Office Requirements
Swing Space Support Requirements
Swing Space IT Requirements
Phase 5 USBC Records 300 NLA 1st Floor n/a n/a n/a Phase 5 Roybal 9th Floor Open Office n/a n/a n/a
Phase 5 USBC 2 Courtrooms Roybal 13th Floor n/a n/a n/a Phase 5 TBD
Undetermined Storage for Courtroom Furniture n/a n/a n/a
Phase 5 USBC Courtroom (Option ) Roybal 15th Floor n/a n/a n/a Phase 5 TBD
Undetermined Storage for Courtroom Furniture n/a n/a n/a
Phase 5 USBC Courtroom (Option ) Roybal 15th Floor n/a n/a n/a Phase 5 TBD
Undetermined Storage for Courtroom Furniture n/a n/a n/a
Phase 5 USBC Courtroom (Option ) Roybal 16th Floor n/a n/a n/a Phase 5 TBD
Undetermined Storage for Courtroom Furniture n/a n/a n/a
Phase 5 USBC Courtroom (Option ) Roybal 16th Floor n/a n/a n/a Phase 5 TBD
Undetermined Storage for Courtroom Furniture n/a n/a n/a
Project Completion
USBC Storage 300 NLA 1st Floor n/a n/a n/a Project Completion
Roybal 9th/10th Floor Storage Areas n/a n/a n/a