Appendix_C_Roybal_Swing_Space_Requirements_and_Move_Matrix_04_06_2015.pdf

PDF 115 KB Posted

Attached to
Edward R. Roybal Repair and Alteration Tenant Improvement Prospectus Project
Solicitation number
GS-09P-15-KT-C-0014
Issued by

About this file

Volume 2B Roybal PDS Appendix C Swing Space Requirements and Move Matrix (purple sheet)

View the file

Other files

File Type Posted
Roybal_DB_RFP_Amendment_06.pdf PDF
Roybal_DB_RFP_Amendment_05.pdf PDF
Roybal_DB_RFP_Amendment_04.pdf PDF
Roybal_DB_RFP_Amendment_04_14th_Fl_Room_Reqs.pdf PDF
Roybal_DB_RFP_Amendment_04_6th_FL_room_reqs.pdf PDF
Roybal_DB_RFP_Amendment_04_revised_bid_sheet.pdf PDF
Roybal_DB_RFP_Amendment_04_9th_Fl_Room_Reqs.pdf PDF
Roybal_DB_RFP_Amendment_04_scope_reductions.pdf PDF
Roybal_DB_RFP_Amendment_04_16th_Fl_Room_Reqs.pdf PDF
Roybal_DB_RFP_Amendment_04_8th_Fl_Room_Reqs.pdf PDF
Roybal_DB_RFP_Amendment_04_15th_Fl_Room_Reqs.pdf PDF
Roybal_DB_RFP_Amendment_04_10th_Fl_Room_Reqs.pdf PDF
Roybal_DB_RFP_Amendment_04_7th_Fl_Room_Reqs.pdf PDF
Roybal_DB_RFP_Certificate_of_Current_Cost_or_Pricing_Data_(1).pdf PDF
Roybal_DB_RFP_Amendment_03_SF30.pdf PDF
Roybal_DB_bid_sheet_Amendment_03.pdf PDF
Roybal_DB_RFP_PPQ_Amendment_02.docx DOCX document
Roybal_DB_bid_sheet_Amendment_02.pdf PDF
Roybal_DB_RFP_Offeror_Representations_and_Certifications.doc DOC document
Roybal_DB_RFP_Amendment_02_SF30.pdf PDF
Roybal_DB_RFP_Amendment_01.pdf PDF
08_Roybal_room_requirements_Pg_117-138.pdf PDF
Roybal_Pre_proposal_Conference_Final_05_28_2015_(1).pdf PDF
Roybal_Fed_Bldg_BER_Final_Submittal.pdf PDF
Roybal_Fed_Bldg_BER_Final_Submittal_Appendices.pdf PDF
AmendmenttoAppendixCSwingSpaceandMovesSOWFinal.doc.pdf PDF
Roybal_DB_RFP_preproposal_attendees.pdf PDF
Volume_3_-_References.pdf PDF
Past_Performance_Questionnaire.docx DOCX document
Volume_2B_Roybal_PDS_and_Appendix.pdf PDF
VOLUME_2A_SCOPE_OF_WORK.pdf PDF
Roybal_DB_1442.pdf PDF
Roybal_DB_RFP_Agreement.pdf PDF
Roybal_DB_Division_1.pdf PDF
Roybal_DB_Solicitation.pdf PDF
Show all 35

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Project Phase Court Unit Department Existing Space Building

Existing Space Suite Move from Existing to Swing

Swing Space Building

Swing Space Move to New Space

New Space Building

New Space Suite Swing Space Office Requirements

Swing Space Support Requirements

Swing Space IT Requirements

Phase 1 USBC Courtrooms & Chambers

Roybal 14th Floor Phase 1 n/a n/a n/a n/a n/a n/a n/a n/a

Phase 1 USBC Operations Support Roybal 12th Floor Open Office

Phase 1 Roybal 9th Floor Courtroom Services Suite n/a n/a n/a Absorbed into Unassigned Workstations in Courtroom Services n/a n/a

Phase 1 USBC Board of Judges' Conference Room

Roybal 12th Floor Phase 1 Roybal 2nd Floor Training Room

Completion of Project

Roybal (Option) 16th Floor (Former USBC Courtroom)

Relocate & reconfigure loop conference table n/a 1 voice, 1 data, 1 power at loop conference table

Phase 1 USBC General Assembly Room Roybal 12th Floor Phase 1 300 NLA 1st Floor (Storage)

Completion of Project

Roybal (Option) 15th Floor (Former USBC Courtroom)

Storage of Furniture until Project Completion n/a n/a

Phase 2 USBC Executive Suite ‐ Chief Deputy

Roybal 10th Floor Executive Suite

Phase 2 Roybal Chambers 1482 Phase 3 Roybal 10th Floor Executive Suite

(1) Office, (2) Workstations (2) Printer Area, (1) Copier Per Office/Workstation: 1 data, 1 voice High‐Duty Copy Area (dedicated outlet)

Phase 2 USBC Human Resources Roybal 10th Floor HR Suite Phase 2 Roybal Chambers 1434 Phase 3 Roybal 10th Floor Open Office

(1) Office, (6) Workstations, (1) Testing Room, (1) Conference Room

(2) Printer Area, (1) Copier Per Office/Workstation: 1 data, 1 voice Conference Room: 2 data, 1 voice Testing Room: 2 data

Phase 2 USBC A&I Roybal 10th Floor A&I/Fiscal Suite

Phase 2 300 NLA 1st Floor (Office Services)

Phase 3 Roybal 10th Floor Open Office

(1) Office, (3) Workstations (2) Printer Area, (1) Copier Per Office/Workstation: 1 data, 1 voice

Phase 2 USBC Fiscal Roybal 10th Floor A&I/Fiscal Suite

Phase 2 300 NLA 1st Floor (Fiscal) Phase 3 Roybal 10th Floor Open Office

(1) Office, (3) Workstations, (1) Secure Storage Room

Per Office/Workstation: 1 data, 1 voice

Phase 2 USBC Help Desk Roybal 10th Floor Help Desk Suite

Phase 2 300 NLA Basement Phase 3 Roybal 10th Floor Open Office

(4) Workstations, (1) Lab, Storage

(2) Printer Area, (1) Copier Per Office/Workstation: 2 data, 1 voice

Phase 2 USBC Network Roybal 10th Floor Network Suite

Phase 2 300 NLA Basement Phase 3 Roybal 10th Floor Network/ Developers Suite

(3) Offices, (3) Workstations (2) Printer Area, (1) Copier Per Office/Workstation: 2 data, 1 voice

Phase 2 USBC Developers Roybal 10th Floor Developers Suite

Phase 2 300 NLA Basement Phase 3 Roybal 10th Floor Network/ Developers Suite

(1) Office, (1) Office or Larger Workstation, (5) Workstations

(2) Printer Area, (1) Copier Per Office/Workstation: 2 data, 1 voice

Phase 2 USBC Communications Roybal 10th Floor Communications Suite

Phase 2 300 NLA Basement Phase 3 Roybal 10th Floor Open Office

(1) Office, (3) Workstations, (1) Work Area, Storage

(1) Copier, (1) High‐Speed Copier,

(1) Plotter, (1) Photo Printer

Per Office/Workstation: 2 data, 1 voice High‐Duty Copy: 1 data, (dedicated outlet) Per Copier: 1 Phone, 1 Data Per Plotter: 1 Data

Phase 3 USBC Office Services 300 NLA 1st Floor (Office Services) n/a n/a n/a Phase 3 Roybal 10th Floor Open Office n/a n/a n/a

Phase 3 USBC Fiscal 300 NLA 1st Floor (Fiscal) n/a n/a n/a Phase 3 Roybal 10th Floor Open Office n/a n/a n/a

Phase 3 USBC Executive Suite ‐ Clerk of Court & Chief Deputy

Roybal 12th Floor (2 Chambers) n/a n/a n/a Phase 3 Roybal 10th Floor Executive Suite n/a n/a n/a

Phase 4 USBC Intake Roybal 9th Floor (Intake) n/a n/a n/a Phase 4 Roybal Terrace Level Intake n/a n/a n/a

Phase 4 USBC Pro Se Clinic 300 NLA 1st Floor (Pro Se) n/a n/a n/a Phase 4 Roybal Terrace Level Intake n/a n/a n/a

Phase 4 USBC Staff Development Roybal 9th Floor Training Suite

Phase 4 300 NLA 1st Floor (Former Office Services)

Phase 5 Roybal 9th Floor Open Office

(4) Workstations Existing USBC Space Existing USBC Space

Phase 4 USBC Training Room Roybal 9th Floor Training Suite

Phase 4 300 NLA 1st Floor (Former Pro Se Area)

Phase 5 Roybal 9th Floor Training Room

(1) Training Area n/a n/a

Phase 4 USBC Courtroom Services & Operations Support

Roybal 9th Floor Courtroom Services Suite

Phase 4 300 NLA Basement Phase 5 Roybal 9th Floor Open Office

(6) Offices, (33) Workstations Established in Phase 2 Established in Phase 2

Phase 4 USBC Break Room Roybal 9th Floor Break Room

Phase 4 300 NLA Basement Phase 5 Roybal 9th Floor Break Room

(1) Open Area (2) Printer Area, (1) Copier (6) duplex outlets for Appliances

Project Phase Court Unit Department Existing Space Building

Existing Space Suite Move from Existing to Swing

Swing Space Building

Swing Space Move to New Space

New Space Building

New Space Suite Swing Space Office Requirements

Swing Space Support Requirements

Swing Space IT Requirements

Phase 5 USBC Records 300 NLA 1st Floor n/a n/a n/a Phase 5 Roybal 9th Floor Open Office n/a n/a n/a

Phase 5 USBC 2 Courtrooms Roybal 13th Floor n/a n/a n/a Phase 5 TBD

Undetermined Storage for Courtroom Furniture n/a n/a n/a

Phase 5 USBC Courtroom (Option ) Roybal 15th Floor n/a n/a n/a Phase 5 TBD

Undetermined Storage for Courtroom Furniture n/a n/a n/a

Phase 5 USBC Courtroom (Option ) Roybal 15th Floor n/a n/a n/a Phase 5 TBD

Undetermined Storage for Courtroom Furniture n/a n/a n/a

Phase 5 USBC Courtroom (Option ) Roybal 16th Floor n/a n/a n/a Phase 5 TBD

Undetermined Storage for Courtroom Furniture n/a n/a n/a

Phase 5 USBC Courtroom (Option ) Roybal 16th Floor n/a n/a n/a Phase 5 TBD

Undetermined Storage for Courtroom Furniture n/a n/a n/a

Project Completion

USBC Storage 300 NLA 1st Floor n/a n/a n/a Project Completion

Roybal 9th/10th Floor Storage Areas n/a n/a n/a