14. (L-8) Past Performance Questionnaire (PPQ)
View the file
Other files for this federal contract opportunity
Show all 48
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DEPARTMENT OF THE AIR FORCE
HEADQUARTERS AIR FORCE TEST CENTER (AFMC)
EDWARDS AIR FORCE BASE CALIFORNIA
FA9301-16-R-0011 PAVING ID/IQ
SOLICITATION ATTACHMENT 14 (L-8)
PAST PERFORMANCE QUESTIONAIRE Page 1 of 6
MEMORANDUM FOR DISTRIBUTION
FROM: AFTC/PZIOC
5 South Wolfe Avenue Building 2800 Edwards AFB, CA 93524
SUBJECT: FA9301-16-D-0011 Paving ID/IQ Solicitation Past and Present Performance Questionnaire (PPQ)
1. You have been identified as a point of contact for a past performance evaluation of the firm listed on the attached questionnaire. This firm would like to be considered for the Paving Services Indefinite Delivery/Indefinite Quantity (ID/IQ) construction contract at Edwards AFB, CA.
2. One of the considerations in proposal evaluation is the verification of the offerors’ past performance on contracts or other work efforts, which reflect the offeror’s ability to perform on the proposed effort. We depend on information received from organizations such as yours, which have had first-hand experience with the offeror, for the evaluation of the offeror’s performance on those contracts or work efforts.
3. Areas of interest regarding the offeror are summarized in the enclosed questionnaire. In order to meet the acquisition milestones, we request your written response no later than five calendar days after your receipt of this letter. This schedule will allow us sufficient time to analyze the data prior to the start of evaluations.
4. Your completed questionnaire will become part of the official Source Selection record. Your assistance is greatly appreciated and your prompt response will be one of the keys to the successful and timely completion of this Source Selection.
5. To assist you in preparing your response and expediting your reply, the questionnaire may be filled out electronically and e-mailed to the Contract Specialist, rosann.knarreborg.1@us.af.mil, and the Contracting Officer, vanessa.russell-reed@us.af.mil.
//signed//
VANESSA RUSSELL-REED
Procuring Contracting Officer
Attachment:
Past and Present Performance Questionnaire
(When Completed)
FOR OFFICIAL USE ONLY
Source Selection Sensitive Information See FAR 2.101 and 3.104
PAST PERFORMANCE QUESTIONAIRE Page 2 of 6
PAST AND PRESENT PERFORMANCE QUESTIONNAIRE (PPQ)
GENERAL INFORMATION: (Please correct any inaccurate information) Contractor’s Name:
Address:
Point of Contact:
Phone Number:
Email:
Project Title:
Description of Work:
Type of Work Completed (Majority): �Runway/Airfield �Roadway/Parking Lots
�Concrete Driveways/Sidewalks/Curbs
CONTRACT INFORMATION PROVIDED BY OFFEROR:
Contract Number:
Dollar Amount:
Contract Period or Dates of Performance:
Highest number of Task Orders performed concurrently:
Contractor performed as: �Prime Contractor �Sub-Contractor �Mentor/Protégé
RESPONDENT INFORMATION:
Name:
Title:
Address:
Phone Number:
Email:
Other suggested points of contact:
EMAIL COMPLETED QUESTIONAIRE TO:
Rosann Knarreborg Vanessa Russell-Reed Contract Specialist Contracting Officer rosann.knarreborg.1@us.af.mil vanessa.russell-reed@us.af.mil Phone: (661) 277-9522 Phone: (661) 277-2532
*Note: If offeror holds or has held other contracts with your agency/organization in the last five years, please complete separate questionnaires for those contracts as well.
PAST PERFORMANCE QUESTIONAIRE Page 3 of 6
PERFORMANCE INFORMATION:
In the tables below, indicate your rating for the contractor’s performance by placing an “X” in the appropriate block to the right of each question. PLEASE PROVIDE A NARRATIVE EXPLANATION FOR ANY RATINGS OF M or U. Attach additional pages if more space is needed.
The performance rating scale is defined as follows:
E EXCEPTIONAL Performance meets contractual requirements and exceeds many requirements to the Government’s benefit. The contractual performance being assessed was accomplished with few minor problems for which corrective actions taken by the contractor were highly effective.
V VERY GOOD Performance meets contractual requirements and exceeds some requirements to the Government’s benefit. The contractual performance being assessed was accomplished with some minor problems for which corrective actions taken by the contractor were effective.
S SATISFACTORY Performance meets contractual requirements. The contractual performance being assessed contains some minor problems for which corrective actions taken by the contractor appear or were satisfactory.
M MARGINAL Performance does not meet some contractual requirements. The contractual performance being assessed reflects a serious problem for which the contractor has not yet identified corrective actions or the contractor’s proposed actions appear only marginally effective or were not fully implemented.
U UNSATISFACTORY Performance does not meet most contractual requirements and recovery is not likely in a timely manner. The contractual performance being assessed contains serious problem(s) for which the contractor’s corrective actions appear or were ineffective.
N/A NOT APPLICABLE Unable to provide a rating. Contract did not include performance for this aspect, performance was not observed, or information was not available.
Do not know.
PAST PERFORMANCE QUESTIONAIRE Page 4 of 6
Place an “X” in the appropriate column using the definitions matrix above.
Quality Control E V S M U N/A
1. Quality of Workmanship
2. Provided effective quality control and/or inspection procedures to meet contract requirements
3. Provided effective measures in implementing their established Quality Control Plan
4. Corrected deficiencies in a timely manner and pursuant to established quality control procedures
5. Provided adequate storage and facilities in order to properly store their materials
6. Adequacy of Submittals
7. Adequacy of Material Testing
Comments on Quality Control:
Timely Performance E V S M U N/A
1. Developed Realistic Progress Schedules
2. Adherence to Approved Schedule
3. Resolution of Delays
4. Submission of Required Documentation
5. Completion of Punchlist Items
6. Submission of Updated and Revised Progress Schedules
7. Provided timely resolution of warranty calls
8. Provided adequate Bonding as required
9. Contractor’s ability to handle a high volume of Task Orders concurrently
Comments on Timely Performance:
Effectiveness of Management E V S M U N/A
1. Cooperation with personnel after award
2. Coordination and Control of Subcontractors
3. Adequacy of Site Clean-Up
PAST PERFORMANCE QUESTIONAIRE Page 5 of 6
4. Effectiveness of Job-Site Supervision
5. Compliance with Laws and Regulations
6. Professional Conduct
7. Review and Resolution of Subcontractor Issues
8. Displayed effective Subcontractor Management
9. Paid Subcontractors and Suppliers in a timely manner
10. Provided accurate and complete proposals for task orders including all aspects of work required for each task
11. Provided adequate project supervision
12. Displayed initiative to solve problems
13. Responsiveness to Government inquiries after award
14. Compliance with environmental regulations such as SWPPP
15. Flexibility and coordination with all project stakeholders
16. Provided experienced managers and supervisors
17. Responsiveness to contract changes
18. Performed accurate quantity takeoffs for estimates
19. Performed concurrently on geographically separated projects at within a 20 mile radius
Comments on Effectiveness of Management:
Compliance with Labor Standards
E V S M U N/A
1. Corrected deficiencies in a timely manner and pursuant to their Quality Control Plan
2. Payrolls Properly Completed and Submitted
3. Compliance with Labor Laws and Regulations with Specific Attention to the Construction Wage Rate Requirements Statute formerly known as the Davis- Bacon Act
Comments on Compliance with Labor Standards:
PAST PERFORMANCE QUESTIONAIRE Page 6 of 6
Compliance with Safety Standards E V S M U N/A
1. Adequacy of Safety Plan
2. Implementation of Safety Plan
3. Adequacy and efficiency in correcting noted Deficiencies
Comments on Compliance with Safety Standards:
Overall Quality of Performance E V S M U N/A
1. Overall Quality of Performance
Please provide any additional information you feel is important and not covered elsewhere in this evaluation:
How would you rate the contractor’s overall quality of performance on this contract?
Would you award another contract to this contractor? (Yes/No) If No, please explain.
Thank you for your prompt response and assistance! Be sure to return to the Contracting Agency and not to the Contractor you are providing a reference for.
Name: Contact Phone #:
Respondent Signature: Date Completed: