RPR Parking Lot B1440
Edwards AFB, California
SCOPE OF WORK:
In accordance with the Statement of Work attached to the Request for Proposal, the basic IDIQ specifications, and the following, the contractor shall provide all labor, equipment and material to RPR parking lot at B1440
1. The specific required work includes but may not be limited to the following:
A. Option 1 : Demolish and replace front parking lot, Crack Seal & Slurry rear parking lot with ACC as shown on the attached sketch. PCC Dumpster Pads (1) and wall around the dumpster pad and PCC Valley Gutters, location TBD .
B. Option 2 : Demolish and replace with ACC front and back parking lot as shown on the attached sketch. PCC Dumpster Pads (1) and wall around the dumpster pad and PCC
Valley Gutters, location TBD .
C. Adjust/Replace all manholes and utility covers within the area as required.
Per UFC 4-010-01 – DOD Minimum Antiterrorism Standards for Buildings, site design shall incorporate security provisions, if required, such as walls, fences, gates, berms or other barriers as determined during project design review. Refer to attachment for typical site wall details, Split-face CMU Color to be TAN or to match adjacent structures. The knee walls to be backed with earth. Relocate the (10) plants in front of the building only.
Removal Retractable and lockable security bollard with decorative cover as needed.
Install two (2) gates
D. Stripe and provide ADA, van-compliant stalls. ADA-compliant stalls are to be blue, with standard ADA stall signage. All are to be van-compliant.
a. Ensure unbroken wheelchair access from parking locations to ADA-accessible building entrances.
2. All contractor personnel shall comply with all measures in the attached "Environmental
Requirements Checklist”
3. Positive actions are required at the end of each work day to collect and properly dispose of all foreign objects from the AFB.
A. DELIVERABLES
a) Plans as required by the basic contract specifications.
b) Material Submittals for paint and retro-reflective beads.
B. ADDITIONAL INFORMATION
a. The Statement of Work provides information specific to work at Edwards Air
Force Base. CE is administrating this task order and is the Contractor’s primary point of contract. Please notify the Contracting Officer’s
Representative in the case of any perceived conflict between this Scope of
Work and the basic contract requirements.
Typical Removable Steel Bollard – Detail 1
February 2, 2012 Cannon Air Force Base Page 33
Appendix D: Typical Removable ATFP Bollard Details
Appendix D: Typical Removable ATFP Bollard Details
Appendix D: Typical Removable ATFP Bollard Details (Continued)
Typical Removable Steel Bollard – Detail 2
Page 34 Cannon Air Force Base February 2, REQUIREMENTS CHECKLIST
Current 16 June 2015
This project (Control No.15-0285, Repair and Replace Parking Lots, Add Curbs and Sidewalks, Building 1440) is covered by the Update to the Environmental Assessment to Modernize Storage
Facilities in the Munitions Complex and Throughout Edwards Air Force Base, California
(AFFTC 2006), prepared in support of Control No. 01-0796a, and is being categorically excluded (A2.3.11) off this document. The project is approved contingent upon compliance of the following minimization measures.
1. The proponent/contractor shall inform Environmental Management’s EIAP Planners of all changes to the project scope. The proponent/contractor shall also provide the Statement of
Work to ensure that the National Environmental Policy Act (NEPA) analysis stays current and that all environmental issues are addressed. Contact Environmental Management at
(661) 277-1442, 277-9225 or e-mail 412TW.CEV.EIAP@us.af.mil for more information.
2. Reduce or suspend all grading, disking, and other earth working projects when wind speeds exceed 25 miles per hour, i.e. high wind conditions.
3. Apply water or chemical stabilizers to suppress dust on unpaved roads and disturbed areas where work is performed. Wind barriers must be erected when winds generate dust that reduces visibility.
4. Any portable internal combustion engine (ICE) operated on Edwards AFB requires a permit from the local air agency. All portable engines and equipment with a rating of 50 brake horsepower and greater must either have an air permit, be registered under the California Air
Resources Board (CARB) Statewide Portable Equipment Registration Program (PERP).
Contact 412 CEG/CEVC at (661) 277-1457 for permit/registration requirements.
5. The proposed project shall comply with Air Force Test Center Instruction (EAFBI) 32-601, Edwards AFB Wastewater Instruction. Contact Environmental Management at
(661) 277-1411.
6. The procedures and controls outlined in the Edwards Air Force Base Storm Water Pollution
Prevention Plan (SWPPP) shall be followed to meet the requirements of the Clean Water
Act. Contact Environmental Management at (661) 277-1411.
7. The proponent/contractor shall ensure all hazardous materials are authorized and managed in compliance with applicable sections of Edwards Air Force Base Instruction (EAFBI) 32-119, Edwards Air Force Base Installation Hazardous Material Management Program (HMMP)
The contractor/proponent should contact 412 CEG/CEVC at (661) 277-9252 for guidance regarding tracking of hazardous material usage.
8. The proponent/contractor shall ensure that all solid and hazardous waste management on this project complies with all applicable sections of AFI 32-7042, Waste Management and the
Edwards Air Force Base Hazardous Waste Management Plan (HWMP). Contact mailto:412TW.CEV.EIAP@us.af.mil
412 CEG/CEVC’s J-TECH Hazardous Waste Support contractor at (661) 277-3681 or
412 CEG/CEVC at 277-9252 for questions and guidance.
9. The proponent/contractor shall be responsible for collection and disposal of inert debris to include waste concrete, asphalt and concrete rinsate generated from project activities and shall be collected in a designated area within the project work site. At project completion, inert debris must be removed from project site, concrete rinsate must be dry, and disposal of waste will be in an approved base inert debris location or off base landfill. Contact
412 CEG/CEO at (661) 277-1167 for information on base inert debris locations. Contact
412 CEG/CEVC at 277-1411 for inert debris disposal requirements.
10. To the extent possible, the proponent/contractor should recycle and/or reuse the old asphalt on site.
11. This project is located near Environmental Restoration Monitoring (ERP) wells (see attached map for ERP well location). Damage to ERP monitoring wells must be avoided. If the proponent/contractor notices soil discoloration or odors during activities, they shall report this observation immediately to Bioenvironmental Engineering (412 AMDS/SGPB) at
(661) 277-3272. Contact Paul Schiff AFCEC/CZOW) at (661) 277-1469 for additional information about this ERP site.
12. All trash shall be contained within raven-proof (covered) containers and removed from the project site.
13. The proposed project, Repair and Replace Parking Lots, Add Curbs and Sidewalks, Building
1440, is an undertaking in accordance with 36 CFR §800.16(y). As such, and in accordance with Section 106 of the National Historic Preservation Act, as amended (NHPA), Edwards
AFB Cultural Resources (Base Historic Preservation Officer [BHPO] or qualified personnel under the direction or supervision of the BHPO) has reviewed the proposed undertaking and determined that the actions constituted therein will not adversely affect historic properties.
14. If the undertaking is modified subsequent to this review, the proponent shall coordinate with
Cultural Resources to ensure compliance with Section 106 of the NHPA. Coordination can be accomplished by contacting 412 CEG/CEVA at (661) 277-1413.
15. If inadvertent above- or below-ground discoveries (e.g., artifacts or bones) are made during the project’s execution:
The Contractor shall:
Immediately cease activity in the area of the discovery.
Notify the supervising Project Manager.
Secure the discovery location and establish a 50-foot buffer zone around the discovery.
The Project Manager shall:
Immediately notify the BHPO of the discovery at (661) 277-1413.
Confirm that the activity has ceased within 50 feet of the discovery.
Examine the location of the discovery to ensure that it has been properly secured. Take appropriate measures to further secure the location, if needed.
Await review by 412 CEG/CEVA before returning to work in the area of discovery.
16. Based upon the information provided, there is no requirement to consult with the California
State Historic Preservation Officer.
17. This project will require an AFTC IMT 5926, Edwards AFB Civil Engineering Work
Clearance Request (digging permit). The proponent/contractor shall coordinate the digging permit with the Base Civil Engineer Execution Support by contacting 412 CEG/CENME at
(661) 277-1530 for specific requirements.