Multiple Award Construction Contract (MACC) Italy Federal contract opportunity
Solicitation number
FA568219RA001
Issued by
Department of the Air Force United States Air Forces in Europe - Air Forces Africa

About this file

This notice is a draft request for proposal for an indefinite delivery indefinite quantity multiple award construction contract for the Department of the Air Force United States Air Forces in Europe - Air Forces Africa. The scope of work will include design-build construction services such as grading, water and sewer lines, painting, roofing, building renovation, new construction, electrical substation construction, structural construction, HVAC systems, fire suppression systems, fuel pipelines and storage, power and utilities, generators, communication systems, and asbestos, lead, and petroleum abatement and disposal at various facilities primarily located at Aviano Air Base in Italy. The contract will have a one year base period and four option years, with a minimum of $2,500 guaranteed per contractor and a total maximum value of $96 million across all contracts. Individual task orders will range from $2,500 to $7 million. Interested parties must submit any comments on the draft attachments by April 19, 2019. The formal solicitation is expected to be issued in May 2019 via the Federal Business Opportunities website.

Solicitation Amendment FA568219RA001 0003

View the file

Other files for this federal contract opportunity

Other files attached to Multiple Award Construction Contract (MACC) Italy, newest first.
File Type Posted
38BOQ0~1.PDF PDF
Attachment_5_Past_Performance_Questionnaire_(PPQ)_REV_03.doc DOC document
H2UST0~1.PDF PDF
MACC_Questions_and_Answers_10162019.pdf PDF
Attachment_1_Section_L_REV_01.pdf PDF
Solicitation_Amendment_FA568219RA0010001_SF_30.pdf PDF
ATTACH~4.DOC DOC document
ANNEX_E_-_ELECTRICAL_Part16.pdf PDF
ANNEX_E_-_ELECTRICAL_Part11.pdf PDF
ANNEX_E_-_ELECTRICAL_Part15.pdf PDF
ANNEX_S_-_STRUCTURAL_Part3.pdf PDF
ANNEX_F_-_FIRE_PROTECTION.pdf PDF
ANNEX_S_-_STRUCTURAL_Part6.pdf PDF
Attachment_10_ASHE_18-1025_TS_(Seed_Project)__Part1.pdf PDF
Attachment_10_ASHE_18-1025_TS_(Seed_project)_Part6_Part2.pdf PDF
Attachment_11_ASHE_18-1025_Drawings_(Seed_project)_Part5.pdf PDF
Attachment_11_ASHE_18-1025_Drawings_(Seed_project)_Part15_Part1.pdf PDF
Attachment_11_ASHE_18-1025_Drawings_(Seed_project)_Part1_Part1.pdf PDF
Attachment_11_ASHE_18-1025_Drawings_(Seed_project)_Part2_Part2.pdf PDF
Attachment_11_ASHE_18-1025_Drawings_(Seed_project)_Part13_Part1.pdf PDF
Attachment_11_ASHE_18-1025_Drawings_(Seed_project)_Part15_Part2.pdf PDF
Attachment_11_ASHE_18-1025_Drawings_(Seed_project)_Part13_Part2.pdf PDF
Attachment_10_ASHE_18-1025_TS__(Seed_project)_Part5.pdf PDF
Attachment_11_ASHE_18-1025_Drawings_(Seed_project)_Part6.pdf PDF
Attachment_10_ASHE_18-1025_TS_(Seed_project)_Part2.pdf PDF
Attachment_11_ASHE_18-1025_Drawings_(Seed_project)_Part10_Part2.pdf PDF
Attachment_11_ASHE_18-1025_Drawings_(Seed_project)_Part9_Part3.pdf PDF
Attachment_10_ASHE_18-1025_TS_(Seed_project)_Part6_Part1.pdf PDF
Attachment_11_ASHE_18-1025_Drawings_(Seed_project)_Part13_Part3.pdf PDF
Attachment_11_ASHE_18-1025_Drawings_(Seed_project)_Part2_Part3.pdf PDF
Attachment_11_ASHE_18-1025_Drawings_(Seed_project)_Part15_Part3.pdf PDF
Attachment_11_ASHE_18-1025_Drawings_(Seed_project)_Part11.pdf PDF
Attachment_10_ASHE_18-1025_TS(Seed_project)_Part6_Part8.pdf PDF
Attachment_11_ASHE_18-1025_Drawings_(Seed_project)_Part3.pdf PDF
Attachment_10_ASHE_18-1025_TS_(Seed_project)_Part6_Part3.pdf PDF
Attachment_11_ASHE_18-1025_Drawings_(Seed_project)_Part16_Part3.pdf PDF
Attachment_11_ASHE_18-1025_Drawings_(Seed_project)_Part2_Part4.pdf PDF
Attachment_2_Section_M.pdf PDF
Attachment_8_Client_Authorization_Letter.pdf PDF
Attachment_9_Questions_and_Answers.pdf PDF
Attachment_4_Past_Performance_Information_(PPI).pdf PDF
Attachment_6_Experience_Overview_Sheet.pdf PDF
Attachment_5_Past_Performance_Questionnaire_(PPQ).pdf PDF
Attachment_1_Section_L.pdf PDF
Questions_and_Answers_draft_RFP_FA568219RA0001_May_02_2019.pdf PDF
(draft)_Attachment_10_Questions_and_Answers.pdf PDF
(draft)_Attachment_7_Experience_Information_Sheet.pdf PDF
(draft)_Attachment_2_Section_M_20_March.pdf PDF
(draft)_Attachment_11_Construction_Cost_Estimate_Breakdown.xls XLS spreadsheet
(draft)_Attachment_4_Past_Performance_Information_(PPI).pdf PDF
Show all 50

Multiple Award Construction Contract (MACC) Italy has more files on GovTribe.

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

R

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers is extended. is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing items 8 and 15, and returning copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or electronic communication which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by letter or electronic communication, provided each letter or electronic communication makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS.

IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.

CHECK ONE A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN THE CONTRACT ORDER

NUMBER IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation data, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not is required to sign this document and return copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.)

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

15B. CONTRACTOR/OFFEROR

(Signature of person authorized to sign)

15C. DATE SIGNED 16B. UNITED STATES OF AMERICA

(Signature of Contracting Officer)

16C. DATE SIGNED

Previous edition unusable STANDARD FORM 30 (REV. 11/2016) Prescribed by GSA FAR (48 CFR) 53.243

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT 1. CONTRACT ID CODE PAGE OF PAGES

2. AMENDMENT/MODIFICATION NUMBER 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQUISITION NUMBER 5. PROJECT NUMBER (If applicable)

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE

8. NAME AND ADDRESS OF CONTRACTOR (Number, street, county, State and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NUMBER

9B. DATED (SEE ITEM 11)

10A. MODIFICATION OF CONTRACT/ORDER NUMBE

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

SECTION SF 30 BLOCK 14 CONTINUATION PAGE

SUMMARY OF CHANGES

The Purpose of This Amendment Is: to change the solicitation closing date from October 30 2019 at 04.00 pm (Local Time/Central European Time) to November 13 2019 at 04.00 pm (Local Time/ Central European Time).

to change the wording "Prior to starting any work, the Contractor shall submit a Work Plan for approval by the Contracting Officer." with the wording "Project will be executed in two phases.

Addition will be constructed first and once completed and fully functional, existing facility will be vacated and renovation will start. Prior to starting any work, the Contractor shall submit a Work Plan for approval by the Contracting Officer." in Attachment 10 ASHE 18-1025 Technical Specifications (Seed project) paragraph AC1.20 - Procedures and work phases (page 16).

to change the title of Attachment 10 ASHE 18-1025 Technical Specifications (Seed project) with Attachment 10 ASHE 18-1025 Technical Specifications (Seed project) Rev.1.

to change the email address "melissa.mauhart.it@us.af.mil" to " melissa.maurhart.it@us.af.mil" in Attachment 5 Past Performance Questionnaire (PPQ) REV 02.

to add the Euro symbol in paragraph h. and i. of Attachment 5 Past Performance Questionnaire

(PPQ) REV 02.

to change the title of Attachment 5 Past Performance Questionnaire (PPQ) REV 02 with Attachment 5 Past Performance Questionnaire (PPQ) REV 03.

***Be aware that Past Performance Questionnaires that have already been received by 31 CONS do not need to be re-submitted in order to insert the corresponding contract Euro value.***

Section C - Specification/SOW/SOO/ORD

The Requirements text has been modified to:

SEE SECTION J:

ATTACHMENT 3, CEN-MACC SOW REV01

ATTACHMENT 10, ASHE 18-1025 Technical Specifications (Seed project) Rev.1

Section J - List of Attachments

The following attachments were added:

Attachment 5 Past Performance Questionnaire (PPQ) REV 03

Attachment 10 ASHE 18-1025 Technical Specifications (Seed Project) Rev.1

The following attachments were deleted:

Attachment 5 Past Performance Questionnaire (PPQ) REV 02

Attachment 10 ASHE 18-1025 Technical Specifications (Seed project)

Miscellaneous text in this section has been deleted.

FA568219RA0010003

IDCode:
Page: 1
Pages: 2
AmendNo: 0003
EffDate: 10/23/2019
ReqNo: A001351
ProjNo: MACC
IssCode: FA5682
AdmCode:
IssuedBy: FA5682 31 CONS DA LGC

UNIT 6102 BOX 140

APO AE 09604-6102

APO, AE 09604-6102

United States Melissa Maurhart, Email: melissa.maurhart.it@us.af.mil Telephone: 00390434304318

AdminBy:
ContractorNameAdd:
Code:
FacCode:
SolChg: 1
SolNo: FA568219RA001
SolDate: 8/28/2019
AwardChg:
AwardNo:
AwardDate:
Amended: 1
OffrExt: 1
OffrNoEx: Off
NoCopies: 1
ApprData: See Section G
ChgeOrd:
ChgeOrder:
Modify:
SuppAgre:
SuppAuth:
ModOthr:
OthrSpec:
NoReq: Off
Require:
Copies:
Descript:

SEE CONTINUATION PAGE

ContNameTitle:
CoNameTitle: Christian M Ruefer

Email: christian.ruefer.1@us.af.mil Telephone: 632-7080

ContDate:
CODate: