EXHIBIT H- TRANSITION IN PLAN.pdf
PDF 109 KB Posted
- Solicitation number
- 0000039767
- Issued by
- California
About this file
This is a Transition In Plan document for the State of California (Cal ICH) detailing the operational handoff of the Healthcare Data Integration System (HDIS) and supporting platforms from an outgoing contractor to an incoming contractor. The transition encompasses management of multiple enterprise platforms including Informatica IDMC (Intelligent Data Management Cloud), Informatica MDM (on-premises), Snowflake, Tableau Cloud, and associated managed IT infrastructure. The transition period spans July 2027 through December 2027, with the incoming contractor shadowing the first quarterly data load in July and assuming full operational ownership beginning with the second quarterly load in August through October 2027. The scope includes nine major workstreams: project management and governance, HDIS platform management, IDMC configuration, MDM operations, Snowflake data platform, Tableau Cloud, software licensing transitions, quarterly data management processes, and contract initiation with compliance readiness. Key milestones include access provisioning and documentation validation by July 30, 2027; platform configuration and data load execution through October 2027; full operational readiness validation by November 2027; and complete cutover with outgoing contractor contract closeout by December 2027.
The transition plan establishes clear governance with Cal ICH serving as the state sponsor and approval authority, the incoming contractor assuming responsibility for operational implementation and independent execution of all processes, and the outgoing contractor providing comprehensive knowledge transfer and continued support during the shadow phase. Entry criteria require Cal ICH approval of the transition plan, baseline system access for the incoming contractor, and delivery of complete documentation packages including runbooks and standard operating procedures. Exit criteria mandate demonstration of independent process execution, validated SLAs with tested escalation paths, and Cal ICH sign-off on all deliverables. The incoming contractor is responsible for establishing weekly transition stand-ups, bi-weekly workstream deep dives, and monthly steering committee meetings with formal tracking through status reports, risk logs, and decision logs. A post-transition stabilization period throughout December 2027 provides elevated support coverage and hypercare protocols, with continuous improvement documentation and final state acceptance by Cal ICH.
View the file
Other files
Show all 40
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
EXHIBIT H: TRANSITION IN PLAN
1. TRANSITION IN PLAN
Transition Period: July 2027 to Dec 2027 (To be Determined) Primary Parties: Incoming Contractor, Outgoing Contractor, Cal ICH (State)
1. Purpose & Objectives
The purpose of this Transition In Plan is to ensure a seamless onboarding of the Incoming Contractor and transfer of operational ownership for all HDIS platforms, services, data management, and support functions from the Outgoing Contractor to the Incoming Contractor and Cal ICH staff.
Objectives
• Establish full operational readiness for HDIS and supporting platforms (Informatica IDMC & MDM, Snowflake, Tableau, Monitoring & Operations).
• Execute knowledge transfer with shadow → lead → own progression.
• Validate governance, security, compliance, and DR readiness.
• Maintain service continuity, meeting SLA commitments throughout the transition.
• Complete licensing transitions and vendor relationship handoffs with no interruption.
2. Scope
This plan covers Transition In for the following domains (aligned to Transition Out areas):
1. Project Management & Governance
2. HDIS Platform Management / Managed IT
3. Informatica IDMC (Intelligent Data Management Cloud)
4. Informatica MDM (on-prem)
5. Snowflake Data Platform
6. Tableau Cloud
7. Software Licensing
8. HDIS Data Management (quarterly refresh process)
9. Contract Initiation & Compliance Readiness
10. Cutover & Post-Transition Stabilization
3. Transition Period
• Transition period is July 2027 – December 2027, with Incoming Contractor shadowing Q1 load (July) and owning Q2 load (Aug–Oct 2027) per Transition Out plan.
• Outgoing Contractor continues support during transition per contractual terms and provides all documentation, runbooks, SOPs, and system configurations.
• Cal ICH approves entry/exit criteria and transition acceptance deliverables.
• Access provisioning (AD/Okta, RBAC in Snowflake/IDMC/MDM/Tableau) will be pre-authorized by
Cal ICH.
• Licensing constraints (OEM-bound licenses such as Datto) may require replacement strategy coordinated with Cal ICH.
4. Governance & Roles
4.1 Key Roles
• Cal ICH (State): Sponsor, approvals, compliance oversight, environment owner.
• Incoming Contractor: Operational lead; implements configurations, processes, and support ownership.
• Outgoing Contractor: Knowledge transfer provider; continues service delivery during shadow phase; delivers all artifacts.
4.2 RACI (Summary)
Workstream Responsible (R)
Accountable (A)
Consulted (C)
Informed (I)
Project Mgmt. & Governance Incoming Contractor
Cal ICH Outgoing Contractor
Stakeholders
Managed IT / HDIS Platform Incoming Contractor
Cal ICH Outgoing Contractor
Stakeholders
IDMC
Incoming Contractor
Cal ICH Outgoing Contractor
Stakeholders
MDM (on-prem) Incoming Contractor
Cal ICH Outgoing Contractor
Stakeholders
Snowflake Incoming Contractor
Cal ICH Outgoing Contractor
Stakeholders
Tableau Incoming Contractor
Cal ICH Outgoing Contractor
Stakeholders
Licensing Incoming Contractor
Cal ICH Outgoing Contractor
Stakeholders
Data Management Incoming Contractor
Cal ICH Outgoing Contractor
Stakeholders
Compliance & Contract Initiation Incoming Contractor
Cal ICH Outgoing Contractor
Stakeholders
Cutover & Stabilization Incoming Contractor
Cal ICH Outgoing Contractor
Stakeholders
5. Timeline & Milestones (July–Dec 2027)
• July 2027: Kickoff, access provisioning, documentation validation; Incoming Contractor shadows Q1 data load; governance cadence established.
• Aug–Oct 2027: IC leads Q2 data load; platform configuration, RBAC, monitoring, DR validation;
licensing updates; dashboards QA/release.
• Nov 2027: Full run-through of all operational cycles, audit readiness, SLA validation, sign-offs on workstreams; cutover rehearsals.
• Dec 2027: Full cutover; Outgoing Contractor contract closeout complete; Incoming Contractor assumes 100% ownership with stabilization period and post-cutover support.
6. Entry & Exit Criteria
Entry Criteria
• Cal ICH-approved Transition In Plan and RACI.
• Incoming Contractor has baseline access to all systems (IDMC, MDM, Snowflake, Tableau, AD/
Okta, Jira/GitHub/AWS).
• Outgoing Contractor delivers comprehensive documentation packages and runbooks.
Exit Criteria (per workstream)
• Incoming Contractor demonstrates independent execution of processes (loads, patching, monitoring, DR).
• All SOPs, configurations, and knowledge bases validated and stored in State repository.
• SLA reporting and alerting operational, with tested escalation paths.
• Cal ICH sign-off for each artifact set and final Transition In Report.
7. Communication Plan
• Cadence: Weekly Transition Stand-up; Bi-weekly Workstream Deep Dives; Monthly Steering Committee.
• Artifacts: Status report, risk log, decision log, action tracker, issues register, change log.
• Channels: Teams (meetings, chat), Jira (work items), SharePoint (documents), Email (formal notices).
• Escalation: Workstream lead → Incoming Contractor PM → Cal ICH Sponsor
8. Risk & Issue Management
• Key Risks: Access delays, license transfer constraints, data quality issues in Q2, DR gaps, RBAC misconfiguration.
• Mitigation: Early access checklist; vendor engagement plan; dual-run validation; DR tabletop and failover test; RBAC peer review.
• Tracking: Risk log with impact/probability, owner, mitigation, ETA; weekly review.
9. Quality & SLA Management
• SLA Metrics: Data load timeliness, ingestion success rate, incident response & resolution time, dashboard availability/refresh SLAs, patch compliance.
• Quality Gates: Pre-load checks, post-load validations (record counts, referential integrity, null thresholds), QA → Prod promotion checklists, DR test evidence.
• Reporting: Monthly SLA dashboard; incident metrics; platform performance and cost optimization reports.
10. Detailed Workstreams & Activities
Note:
• Task numbers are aligned to the Transition Out Plan, with Transition In counterparts and acceptance criteria.
• Shadow/lead notes included where applicable.
10.1 Project Management & Governance
Task No.
Transition In Activity Deliverable / Acceptance Owner Target Date
Conduct onboarding briefing;
validate documentation, Transition In/Out timelines
Signed Documentation Validation Checklist
Incoming Contractor / Outgoing Contractor / Cal ICH
7/16/27
Configure Jira (projects, boards, workflows), import sprint/backlog;
set roles
Jira Configuration Runbook + access matrix
Incoming Contractor 7/30/27
Establish meeting cadences & governance (Steering Committee, workstreams)
Published Calendar & Charter
Incoming Contractor / Cal ICH
7/30/27
Build an integrated project schedule with milestones/risks/ dependencies
Baseline MSP/Smartsheet schedule approved
Incoming Contractor 7/30/27
Adopt M&O deliverables, assign future owners
M&O Ownership Map Incoming Contractor 7/30/27
Catalog external support/ compliance efforts
Compliance Support Register
Incoming Contractor 7/30/27
Transition tracking & closeout (by workstream)
Signed Workstream Acceptance (IC/Cal ICH)
Incoming Contractor 7/1–11/30/
10.2 HDIS Platform Management (Managed IT)
Task No.
Transition In Activity Deliverable / Acceptance Owner Target Date
Import HDIS topology; verify environments & connectivity
Platform Topology Diagram verified
Incoming Contractor
7/30/
2 Implement security tools & SOPs (Datto/ Security SOPs active; alerts Incoming 7/30/
Task No.
Transition In Activity Deliverable / Acceptance Owner Target Date
SentinelOne/BlackPoint or replacements) tested Contractor 27
3 Configure AD/Okta structure; access review Access Governance Report Incoming Contractor
7/30/
Activate onboarding/offboarding workflow;
verify access logs
Workflow documentation; handoff checklist; user access lists
Incoming Contractor
7/30/
Validate DR runbook; schedule DR test;
rollback verified
DR Test Evidence & Rollback Plan
Incoming Contractor
7/30/
Implement patching cadence & compliance reporting
Patching Compliance Dashboard Incoming Contractor
7/30/
7 Stand-up monitoring & alert thresholds;
Monitoring Architecture & On-call Roster
Incoming Contractor
7/30/
Assume Helpdesk; SLAs; CoC outreach process
Helpdesk SOP & SLA Matrix Incoming Contractor
7/30/
Adopt full M&O routines/runbooks;
acceptance tests
M&O Sign-off Incoming Contractor
7/30/
10 Workstream closeout Cal ICH Approval Incoming Contractor
7/30/
10.3 Informatica IDMC
Task No.
Transition In Activity Deliverable / Acceptance Owner Target Date
Configure IDMC environments per handoff
IDMC Config Guide (Validated) Incoming Contractor
7/30/27
Implement RBAC; access review & approvals
RBAC Matrix & Audit Trail Incoming Contractor
7/30/27
Deploy file management scripts; unit tests
Script Inventory + Test Evidence Incoming Contractor
8/13/27
Document/validate quarterly load task flows
Task Flow Docs + Timing Map Incoming Contractor
8/13/27
Implement SPM task flows & control points
SPM Flow Diagrams Incoming Contractor
8/13/27
Stand-up exception handling & alerting
Exception scenarios; remediation steps; alerting logic
Incoming Contractor
8/13/27
Configure service accounts; rotation policy
Service Account Register Incoming Contractor
8/13/27
Adopt M&O dashboards; ticketing (Informatica Support)
M&O SOPs & Escalation Matrix Incoming Contractor
8/13/27
Transition In Activity Deliverable / Acceptance Owner Target Date
Validate GitHub integration;
branching; permissions
Source Control Standards Incoming Contractor
8/13/27
Execute code migration process & approvals
Migration Checklist & Approvals Incoming Contractor
8/13/27
11 Workstream closeout Cal ICH Approval Incoming Contractor
8/15/27
10.4 Informatica MDM (On-Prem)
Task No.
Transition In Activity Deliverable / Acceptance Owner Target Date
Review & adopt MDM upgrade runbook;
rollback tested
Upgrade SOP + Test Evidence
Incoming Contractor
7/30/27
Validate system configuration (env, params, data model)
Config Reference Guide Incoming Contractor
7/30/27
3 Apply RBAC; provisioning & audit process Role Matrix & Audit Logs Incoming Contractor
8/13/27
Validate match/merge rules; trust scores;
schedule
Match/Merge Documentation
Incoming Contractor
8/13/27
Build support playbook; triage & resolution matrix
Support Playbook Incoming Contractor
8/13/27
6 Inventory service accounts & rotation Account Inventory Incoming Contractor
8/13/27
Establish quarterly refresh calendar & validation
Refresh Calendar & Validation SOP
Incoming Contractor
8/13/27
Adopt M&O routines, dashboards & escalation
M&O Sign-off Incoming Contractor
8/13/27
9 Workstream closeout Cal ICH Approval Incoming Contractor
8/15/27
10.5 Snowflake Platform
Task No.
Transition In Activity Deliverable / Acceptance Owner Target Date
Configure identity access (RBAC), MFA, groups
Access Strategy & MFA Evidence
Incoming Contractor
8/6/27
2 Enable monitoring & SLAs; alerts Monitoring Dashboard + SLAs
Incoming Contractor
8/6/27
3 Validate environment architecture & Architecture & Metadata Map Incoming 8/6/27
Transition In Activity Deliverable / Acceptance Owner Target Date metadata Contractor
Service accounts inventory & credential mgmt.
Service Account Register Incoming Contractor
8/6/27
Assume pipeline orchestration; SLA monitoring
Pipeline Docs & Orchestration SOP
Incoming Contractor
8/6/27
Implement data security (masking, encryption)
Security Policy Pack Incoming Contractor
8/6/27
Prepare for 3rd-party audit; response playbook
Audit Readiness Checklist Incoming Contractor
8/6/27
Cost & performance optimization policies
Cost Model & Tuning Reports
Incoming Contractor
8/6/27
Quarterly refresh calendar & reconciliation
Refresh & Reconciliation Checklist
Incoming Contractor
8/6/27
10 Adopt M&O runbooks & escalation M&O Sign-off Incoming Contractor
8/6/27
11 Workstream closeout Cal ICH Approval Incoming Contractor
8/10/27
10.6 Tableau Cloud
Task No.
Transition In Activity Deliverable / Acceptance Owner Target Date
Provisioning & deactivation process; access governance
Provisioning SOP & Governance
Incoming Contractor
8/13/27
2 Catalog & validate HDIS Work Products Dashboard Catalog Incoming Contractor
8/13/27
Validate dashboard logic, calcs, filters, business rules
Logic Mapping Docs Incoming Contractor
8/27/27
Permissions matrix & landing page experience
Permissions & UX Matrix Incoming Contractor
8/13/27
Data source connections & refresh schedules
Connection Map + Schedules
Incoming Contractor
8/13/27
Maintenance calendar; DR/failover readiness
Maintenance & DR Checklist
Incoming Contractor
8/13/27
7 QA/validation playbook; sign-off checklist QA Playbook & Checklist Incoming Contractor
8/13/27
8 Support guide; resolution flows & escalation Support Guide Incoming
8/13/27
Transition In Activity Deliverable / Acceptance Owner Target Date
10 Adopt M&O routines & runbooks M&O Sign-off Incoming Contractor
8/6/27
11 Workstream closeout Cal ICH Approval Incoming Contractor
8/30/27
10.7 Software Licensing Transition
Task No.
Transition In Activity Deliverable / Acceptance
Owner Target Date
1 Validate license inventory & terms Master License Tracker
(IC)
Incoming Contractor / Outgoing Contractor
9/3/27
Transition month-to-month licenses (AWS, Jira, GitHub)
Admin & Billing Transfer Evidence
Incoming Contractor 9/3/27
OEM-bound licenses replacement plan (Datto, etc.)
Replacement Strategy & 30-day Plan
Incoming Contractor / Cal
ICH
9/3/27
Import security monitoring configurations
Security Config Summary
Incoming Contractor 9/3/27
5 Cal ICH approval of replacement path Approved Decision Record
Cal ICH 9/3/27
Review annual expirations (Tableau, IDMC, Snowflake, Okta)
Renewal Timeline & Guidance
Incoming Contractor 9/3/27
Finalize transfer/renewal (WOA/ continuation)
Legal & Financial Docs Incoming Contractor / Cal
ICH
9/3/27
8 Confirm discount impacts & budgeting Cost Forecast Incoming Contractor 9/3/27
9 Complete WOA/payment updates Financial Transition Docs
Incoming Contractor 9/3/27
Document vendor contacts, renewals, support
Vendor Contact Handoffs
Incoming Contractor 9/3/27
10.8 HDIS Data Management (Quarterly Refresh)
Shadow Q1 (July). IC runs Q2 (Aug–Oct 2027).
Task No.
Transition In Activity Deliverable / Acceptance
Owner Target Window
CoC data upload SOP;
communications; run Q2 intake
CoC Submission SOP + Comm Plan
Incoming Contractor (Outgoing Contractor shadows Q1)
Jul–Oct
Snowflake data load (encryption, movement, storage)
Load Sequence Docs & Path Map
Incoming Contractor Jul–Oct
Transition In Activity Deliverable / Acceptance
Owner Target Window
File validation (structure, naming, pre-load checks)
File Validation Checklist
Incoming Contractor Jul–Oct
Post-load QA (counts, nulls, referential, QA→Prod)
QA Validation Evidence
Incoming Contractor Jul–Oct
Data refinement (business rules & transforms)
Transformation Logic Docs
Incoming Contractor Jul–Oct
Data mastering workflow (dedupe, entity resolution)
MDM Match/Trust Reports
Incoming Contractor Jul–Oct
Data warehouse load (order, dependencies, exceptions)
DW Load & Exception SOP
Incoming Contractor Jul–Oct
8 SPM load sequence & mappings SPM Load Docs Incoming Contractor Jul–Oct
Data lake refresh (ZCC schedule, versioning, retention)
DL Refresh & Retention SOP
Incoming Contractor Jul–Oct
Dashboard release cycle (QA/ Prod, publication)
Release Checklist & Sign-offs
Incoming Contractor Jul–Oct
Work product updates post-quarterly release
Work Products Release Pack
Incoming Contractor Jul–Oct
Troubleshooting guide for ingestion/transform/reporting
Troubleshooting Playbook
Incoming Contractor Jul–Oct
10b Adopt M&O tasks & documentation
M&O Sign-off Incoming Contractor 10/30/27
11b Workstream closeout Cal ICH Approval Incoming Contractor 11/15/27
10.9 Contract Initiation & Compliance Readiness
Task No.
Transition In Activity Deliverable / Acceptance
Owner Target Date
Confirm roles & responsibilities (State vs Contractor)
Transition In RACI Incoming Contractor / Cal ICH 7/9/27
Joint support coverage during transition
Support Calendar & Coverage Plan
Incoming Contractor / Outgoing Contractor
7/1–11/ 30/27
Execute training & OJT; populate knowledge repositories
Training Schedules & Repo Links
Incoming Contractor / Outgoing Contractor
7/1–11/ 30/27
Finalize design/config deliverables; sign-offs
Final Design Package Incoming Contractor 7/1–11/ 30/27
Entry & exit criteria for Transition In
Criteria Checklist (Approved)
Incoming Contractor / Cal ICH 7/1–11/ 30/27
Transition In Activity Deliverable / Acceptance
Owner Target Date
Supporting documentation for all transition tasks
SOPs, Guides, Diagrams centralized
Incoming Contractor 7/1–11/ 30/27
Data retention/destruction for superseded assets
Sanitization Certificates
Outgoing Contractor (w/ Incoming Contractor oversight)
7/1–11/ 30/27
Full cutover schedule & Transition In Report
Cutover Timeline + Final Report
Incoming Contractor 11/30/
10 Tracking tools for status & issues Live Status Board & Notifications
Incoming Contractor 7/1–11/ 30/27
11 Transition risk assessment Risk Log & Mitigation Plan
Incoming Contractor 7/1–11/ 30/27
12 Post-transition support Stabilization Plan (Dec 2027)
Incoming Contractor 12/ 1–12/ 31/27
11. Cutover Plan (High-Level)
1. Go/No-Go Readiness Review: Verify all workstream exit criteria met; confirm staffing and blackout windows.
2. Pre-Cutover Tasks: Freeze non-critical changes, backup configs, confirm DR availability.
3. Cutover Window: Transition ownership of runbooks, support queues, admin roles, vendor contacts, billing.
4. Validation: Run smoke tests (access, monitoring alerts, pipeline triggers, dashboard availability).
5. Contingency: Rollback steps per DR and change calendar; Outgoing Contractor standby support.
6. Sign-off: Cal ICH formal acceptance; publish Transition In Report.
12. Post-Transition Stabilization (Dec 2027)
• Hypercare: Incoming Contractor provides elevated support coverage and faster SLAs.
• Operational Reviews: Weekly health checks on ingestion success rate, incident trends, platform performance/costs.
• Continuous Improvement Backlog: Document improvement opportunities (automation, governance, cost optimization).
• Final Acceptance: Cal ICH signs off on stabilization completion.
13. Appendices
Appendix A – Detailed RACI (Task-Level)
Appendix B – Document Index
• System Architecture & Topology
• SOPs (M&O, DR, Patching, Helpdesk, Onboarding/Offboarding)
• Platform Configurations (IDMC, MDM, Snowflake, Tableau)
• Security Policies (RBAC, MFA, Masking, Encryption, ZCC)
• Runbooks (Loads, Exception Handling, Code Migration)
• QA & Validation Checklists (Pre-/Post-load, QA→Prod)
• Licensing Tracker & Vendor Contact Sheet
• Risk Log, Issue Register, Decision Log, Change Log
• Training Materials & Knowledge Base Links
14. Signatures
• Cal ICH Representative: Date: __
• Incoming Contractor (IC) Representative: Date: __
• Outgoing Contractor (OC) Representative: Date: __
Appendix A – Detailed RACI (Task-Level)
Workstream / Task Responsible (R) Accountable (A)
Consulted (C) Informed (I)
Project Mgmt – Transition briefing & docs
Outgoing Contractor
Cal ICH Incoming Contractor
Stakeholders
Project Mgmt – Jira handoff Outgoing Contractor
Cal ICH Incoming Contractor
Stakeholders
HDIS Platform – Security software review
Outgoing Contractor
Cal ICH Incoming Contractor
Stakeholders
HDIS Platform – DR process review Outgoing Contractor
Cal ICH Incoming Contractor
Stakeholders
IDMC – Config handoff Outgoing Contractor
Cal ICH Incoming Contractor
Stakeholders
IDMC – RBAC review Outgoing Contractor
Cal ICH Incoming Contractor
Stakeholders
MDM – Upgrade runbook handoff Outgoing Contractor
Cal ICH Incoming Contractor
Stakeholders
Snowflake – Identity & security handoff
Outgoing Contractor
Cal ICH Incoming Contractor
Stakeholders
Tableau – Dashboard logic handoff Outgoing Contractor
Cal ICH Incoming Contractor
Stakeholders
Licensing – Inventory & transfer Outgoing Contractor
Cal ICH Incoming Contractor
Stakeholders
Data Mgmt – Quarterly refresh handoff
Outgoing Contractor
Cal ICH Incoming
Stakeholders
Workstream / Task Responsible (R) Accountable (A)
Consulted (C) Informed (I)
Contract Closeout – Risk assessment Outgoing Contractor
Cal ICH Incoming Contractor
Stakeholders
Appendix B – Document Index
• System Architecture & Topology
◦ HDIS platform diagrams
◦ Snowflake environment architecture
◦ Tableau dashboard architecture
• Configuration Guides
◦ IDMC environment setup
◦ MDM configuration reference
◦ RBAC matrices for all platforms
• Runbooks & SOPs
◦ Data load sequences (Snowflake, IDMC, MDM)
◦ Exception handling playbooks
◦ DR procedures and rollback plans
◦ Monitoring & alerting SOPs
• Security Policies
◦ MFA and RBAC enforcement
◦ Data masking and encryption standards
• Operational Documentation
◦ M&O schedules and escalation paths
◦ Helpdesk workflows and SLA matrices
• Source Control
◦ GitHub repositories and branching strategy
• Licensing
◦ Master license tracker
◦ Vendor contact sheet
• Compliance
◦ Audit readiness checklists
◦ Risk logs and mitigation plans
• Training Materials
◦ Knowledge transfer session decks
◦ Recorded sessions
| EXHIBIT H: TRANSITION IN PLAN |
| 1. TRANSITION IN PLAN |