This is a Task Assignment (TA) issued by the State of Florida Department of Environmental Protection (FDEP) to GHD Services, Inc. for groundwater sampling and monitoring at the Terrace Cleaners site in Temple Terrace, Hillsborough County, Florida. The Task Assignment DC017A is issued under Contract Number HW684, with Kevin Kane serving as the Department Project Manager and Brian Moore as the Contractor's Project Manager. The work is identified under project number ERIC_4728 and is associated with environmental remediation and monitoring activities at the former drycleaner facility.
The contract specifies two subtasks: Subtask 1 (Project Management) and Subtask 2 (Groundwater Monitoring). Groundwater sampling will be conducted at six monitoring wells (MW007, MW010, MW013, MW016, MW017, and MW018), with depth-to-water measurements taken from all ten available wells. Samples will be analyzed for volatile organic halocarbons (VOHs) using EPA Method 8260 by a certified laboratory. The deliverable is a Groundwater Monitoring Report with a due date of July 14, 2022, and a task completion date of October 14, 2022. The fixed unit rate total cost for the Task Assignment is $4,560.31, with labor costs of $3,021.28, travel costs of $120.00, subcontractor costs totaling $110.00 (including $100.00 for investigation-derived waste disposal), laboratory analytical costs of $496.50, field expenses of $510.40, and a completion fee of $302.13. Payment is due upon submittal and FDEP approval of the Groundwater Monitoring Report and Project Management deliverables.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Funding Information:
Org. Code E.O. Object Code Budget Entity Appropriation
Category Grant # Project # Year Amount
☐ Additional Funding Information attached on separate page.
Rev. 8/26/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .
1. TA Number: TA Completion Date:
TA Description:
2. Parties State of Florida Department of Environmental Protection
(Department)
Department Project Manager: Department Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number)
Project Location(s):
Project Name:
4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:
☐ Fixed Price:
☐ Fixed Unit Rate: (Extended Price)
☐ Cost Reimbursement:
Total TA Value:
5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:
Attachment 1:
☐ Additional Attachments (if necessary):
IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.
State of Florida Department of Environmental Protection CONTRACTOR Department Name:
Title:
Secretary or Designee
(Authorized Signature) (Authorized Signature) Date:
☐ Additional signatures attached on separate page.
HW684
DC017A Completion October 14, 2022
GHD Services, Inc. will conduct groundwater sampling at the Terrace Cleaners site located in Temple Terrace, Florida. All work will be conducted in accordance with the scope of work and cost proposal submitted on April 20, 2022.
Kevin Kane (850) 245-8971 Contractor Contractor
Contractor Contractor
Contractor Contractor
Contractor
GHD Services, Inc.
GHD Services, Inc.
Brian Moore (813) 257-0658
ERIC_4728
8866 N 56th St, Temple Terrace, Hillsborough County
Terrace Cleaners
✔ $ 4,560.31
$ 4,560.31
Scope of Work
Brian Moore
Contract Manager
Brian Moore Digitally signed by Brian Moore Date: 2022.05.12 17:27:47 -04'00'
William E. Burns, Jr.
William E. Burns, Jr. Digitally signed by William E. Burns, Jr.
Date: 2022.05.12 14:47:11 -04'00'
N/A
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WCP TAFORM 04-2017
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
Groundwater Monitoring Report + Project Management 07/14/2022
Subtasks 1 and 2: Upon submittal and FDEP approval of the Groundwater Monitoring Report + Project Management $ 4,560.31
$ 4,560.31
HW684
DC017A
FLORIDA DEPARTMENT OF
Environmental Protection
Bob Martinez Center
2600 Blair Stone Road Tallahassee, FL 32399-2400
Ron DeSantis Governor
Jeanette Nuñez
Lt. Governor
Shawn Hamilton Secretary
TO: HW684 Contract File
FROM: Kevin Kane, Contract Manager
DATE: May 12, 2022
SUBJECT: Task Assignment DC017A
Terrace Cleaners
ERIC_4728
Monitoring
GHD Services, Inc. (GHD) will conduct annual groundwater sampling. Specific subtasks are detailed below:
Subtask 1: Project Management Project Management is calculated at 13% of the direct labor.
Subtask 2: Groundwater Monitoring Groundwater sampling will be conducted at six (6) monitoring wells, including monitoring wells MW007, MW010, MW013, MW016, MW017, and MW018. During mobilization for sampling, depth to water measurements will be gathered from all wells (10 total). Groundwater sampling will be conducted in general accordance with FDEP SOPs. Samples will be submitted to a fixed laboratory for analysis for the presence of VOHs by EPA Method 8260.
Following receipt of analytical data, a Groundwater Monitoring Report will be prepared.
The report will include a detail of field activities along with a summary of laboratory analytical data. The monitoring report will also include recommendations regarding additional monitoring.
Investigation derived waste (IDW) disposal is anticipated and has been accounted for under this subtask. Subcontractors for IDW disposal were chosen on a lowest-cost basis. The Florida Department of Environmental Protection (FDEP) has a current and valid Site Access Agreement for this site, signed February 8, 2016.
This work will be conducted in line with the scope of work included with GHD’s proposal, received April 20, 2022. Documentation of the costs is included in the attached CEF, Level-of-Effort sheets, and proposal letter. The final deliverable due date is July 14, 2022, and the completion date for the task assignment is October 14, 2022.
The final cost total for Task Assignment DC017A is $4,560.31.
FDEP COST ESTIMATEContractor: GHD Services Inc.
Date: 05/12/22
Task #: DC017A SubTask 1 Project Management SubTask 6
Site: Terrace Cleaners SubTask 2 Groundwater Monitoring SubTask 7
Activity/Phase: Monitoring SubTask 3 SubTask 8
Project Manager: Brian Moore, PE SubTask 4 SubTask 9
SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category
$40.12 Project Manager JM 3.20 3.2 $0.00 Principal Engineer/Scientist 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Technical Director 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
$46.33 Sr Professional Engineer JH 1.00 1.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 Senior Project Manager 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
$43.28 Professional Engineer/Sc GE 12.00 12.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $39.82 Project Engineer/Scientis TC 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $40.12 Project Manager/ Engine JM 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $33.17 Staff Engineer/Scientist DB 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $32.40 Data Analyst JL 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $43.35 Field Manager OT 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $19.76 Senior Technician SA 11.75 11.75 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $19.65 Senior Technician SC 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $23.69 Senior Technician WM 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $18.58 Junior Technician WO 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $18.75 Junior Technician JM 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $29.69 Drafting Technician PM 3.00 3.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $22.44 Administrative Assistant DA 5.00 5.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
$0.00 Driller 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 HSEQ&R Manager 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 $0.00 0 0 0 0 0 0 0 0 0 0
Total Hours 35.95 3.20 32.75 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Direct Labor $1,129.03 $129.89 $999.14 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Overhead 129.80% $1,465.48 $168.60 $1,296.88 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 37.80% $426.77 $49.10 $377.67 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $3,021.28 $347.59 $2,673.69 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Travel Vehicle Rental $120.00 $120.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
REV: 02/03 CEF ARCADIS Page 1
FDEP COST ESTIMATEContractor: GHD Services Inc.
Date: 05/12/22
Task #: DC017A SubTask 1 Project Management SubTask 6
Site: Terrace Cleaners SubTask 2 Groundwater Monitoring SubTask 7
Activity/Phase: Monitoring SubTask 3 SubTask 8
Project Manager: Brian Moore, PE SubTask 4 SubTask 9
SubTask 5 SubTask 10
Totals 1 2 3 4 5 6 7 8 9 10 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $120.00 $120.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
IDW $100.00 $100.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subcontractor Subtotal $100.00 $100.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $10.00 $10.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $110.00 $110.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Laboratory Analytical Costs $438.00 $438.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $58.50 $58.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $496.50 $496.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $40.00 $40.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Drilling related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $470.40 $470.40 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $510.40 $510.40 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Subtotal $4,258.18 $347.59 $3,910.59 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $302.13 $34.76 $267.37 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
Total Estimated Cost $4,560.31 $382.35 $4,177.96 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00
REV: 02/03 CEF ARCADIS Page 2
LEVEL OF EFFORT/EXPENSE WORKSHEET
SITE : Terrace Cleaners SUBTASK 2: Groundwater Monitoring
DATE: 05/12/22
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Sr Professional Engineer JH Conclusions/Recommendations 1
Professional Geologists GE Contact Property Owner/Prepare field SOW 1 Professional Geologists GE Review field notes, verify COC 0.5 Professional Geologists GE Historical Summary 2 Professional Geologists GE Groundwater sampling methodology 0.5 Professional Geologists GE Profile IDW and coordinate disposal 1 Professional Geologists GE Field parameter summaries 1 Professional Geologists GE Groundwater Flow summary (shallow) 1 Professional Geologists GE Groundwater Well analytical summary (shallow/deep) 2 Professional Geologists GE QA/QC 1 Professional Geologists GE Conclusions/Recommendations 2
Senior Technician SA Mob/demob (1 day) 1 Senior Technician SA Water Levels (10 wells total)) 1.75 Senior Technician SA Groundwater Sampling (6 wells) 9
11.75
Drafting Technician PM Water Level map (shallow zone only) 1 Drafting Technician PM Groundwater Analytical Results (shallow and deep) 2
Staff Assistants DA Field Data Entry (6 GW samples/10 WLs) 1 Staff Assistants DA Update summary tables (DP, WLs, parameter, analytical) 2 Staff Assistants DA Publish Report (generate pdf) 2
TOTAL LABOR 32.75
VEHICLE TYPE RATE UNIT USEAGE
Company Truck $120.00 day 1 $120.00
TOTAL VEHICLE $120.00
PER DIEM STAFF RATE UNIT USEAGE
$0.00 $0.00 $0.00 $0.00
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
Erwin IDW Drum 1 drum $100 $100.00
TOTAL $100.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
VOHs $73.00 6 $438.00 sample shipping (Two Day) small cooler $52.00 1 $52.00
Ice $6.50 1 $6.50
TOTAL LAB $496.50
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Expendables
Expendable $40.00 day 1 $40.00
Equipment (Analytical Related)
Groundwater Sampling Kit $290.00 Day 1 $290.00 Poly Tubing $0.30 ft 208 $62.40 silicon Tubing $3.00 ft 6 $18.00 Drum $100.00 drum 1 $100.00
Equipment (Other) $0.00
TOTAL EQUIPMENT $510.40
FINAL --7/24/96
COST PROPOSAL FOR TASK DC017A
Terrace Cleaners, ERIC_4728
Groundwater Monitoring
1. INTRODUCTION:
Although site redevelopment activities began several years ago, during the past seven years, site redevelopment has been stalled. The developer completed demolished the former strip center, and the southern portion of the property was renovated. In addition, Interim Source Removal (ISR) activities were undertaken that included the excavation and off-site disposal of PCE-impacted soils. Currently, the location of the former drycleaner is grass and asphalt covered; however, construction activities are occurring immediately north of the site. The site is currently being utilized for the storage of construction materials. In 2016, GHD oversaw the installation of replacement monitor wells on-site. The previous monitoring report (July 2021) recommended continued annual groundwater monitoring. Task DC017A includes annual monitoring.
Subtask 1: Project Management Subtask 1 includes all activities associated with project management of sampling of site monitoring wells, and report preparation.
Subtask 2: Groundwater Sampling Groundwater sampling will be conducted at ten site monitor wells. Prior to sampling, depth-to-water measurements will be made at all available wells (10 total). Groundwater sampling will be conducted at wells MW007, MW010, MW013, MW016, MW017, and MW018.
Sampling will be conducted in general accordance with FDEP Standard Operating Procedures. The groundwater samples will be for analyzed by a Florida-certified laboratory for the presence of volatile organic halocarbons (VOHs) by EPA Method 8260.
Following receipt of analytical data, a summary report will be prepared. The summary report will include a summary of field sampling procedures and analytical results. The report will also include recommendations for additional monitoring and/or remediation.
Deliverables:
Deliverable Deliverable Due Date
Groundwater Monitoring Report 7/14/22
408 Ditmar Street
Pensacola, FL 32503
ErwinRemediation@Gmail.com - P.O. Box 884 Gulf Breeze, FL 32562
(850) 292-6511
To: Mr. Brian Moore
GHD
5904 Hampton Oaks Parkway – Suite F
Tampa, FL 33610
March 16, 2020
Re: IP Cleaners - Miami, FL
Mr. Moore:
The price for disposal of two (2) drums of non-hazardous groundwater located in Miami, FL will be $100.00 per drum, or $200.00 total, for both transportation and disposal.
Respectfully, Jonathan Erwin
Erwin Remediation, Inc.
Email: ErwinRemediation@Gmail.com
Office: (850) 292-6511 mailto:Remediation@Gmail.com
From: Jamie Infinger To: Brian Moore Subject: RE: IP Cleaners - Miami Date: Monday, March 16, 2020 8:39:32 AM Attachments: image001.png image002.png image003.png image004.png
$95.00 per drum plus $150.00 stop charge Have a great day
Thanks, Jamie Infinger A Nationwide Waste Disposal Company Clean Management Environmental Group, Inc.
P: (800)-538-8131 F: (843)-538-7845 C: (912)-674-6783 jinfinger@cleanmanagement.com www.cleanmanagement.com
From: Brian.Moore@ghd.com [mailto:Brian.Moore@ghd.com] Sent: Sunday, March 15, 2020 11:45 AM To: Jamie Infinger <jinfinger@cleanmanagement.com> Subject: IP Cleaners - Miami
Jamie, Can you provide quote for disposal of 2 drums of water from the above site. Low level solvents, assume non-haz thanks
Brian Moore, PE
GHD
Proudly employee owned T: 813 257 0658 | M: 813 335 2147 | E: Brian.Moore@ghd.com 5904 Hampton Oaks Parkway Suite F Tampa Florida 33610 USA | www.ghd.com Connect
WATER | ENERGY & RESOURCES | ENVIRONMENT | PROPERTY & BUILDINGS | TRANSPORTATION
mailto:jinfinger@cleanmanagement.com mailto:Brian.Moore@ghd.com mailto:jinfinger@cleanmanagement.com http://www.cleanmanagement.com/ mailto:Brian.Moore@ghd.com http://www.ghd.com/ https://www.linkedin.com/company/ghd https://www.facebook.com/GHDGroup https://twitter.com/GHD_Namerica https://www.youtube.com/channel/UCwUGfe6zgaddIXqA7entIwQ https://www.ghd.com/en/sectors/water.aspx https://www.ghd.com/en/sectors/energy---resources.aspx https://www.ghd.com/en/sectors/environment.aspx https://www.ghd.com/en/sectors/property---buildings.aspx https://www.ghd.com/en/sectors/transportation.aspx
Please consider our environment before printing this email
CONFIDENTIALITY NOTICE: This email, including any attachments, is confidential and may be privileged. If you are not the intended recipient please notify the sender immediately, and please delete it; you should not copy it or use it for any purpose or disclose its contents to any other person. GHD and its affiliates reserve the right to monitor and modify all email communications through their networks.
This e-mail has been scanned for viruses
ID Task Mode
Task Name Duration Start Finish
1 LOE Submittal/Approval 2 wks Wed 4/20/22Tue 5/3/22
2 Subtask 1: Project Management
52 days Wed 5/4/22 Thu 7/14/22
3 Subtask 2: Groundwater Monitoring
47 days Wed 5/11/22
Thu 7/14/22
4 Field Work Preparation 2 wks Wed 5/11/22Tue 5/24/22
5 Groundwater Sampling 1 day Wed 5/25/22Wed 5/25/22
6 Groundwater Monitoring Report
6 wks Fri 6/3/22 Thu 7/14/22
4/10 4/17 4/24 5/1 May
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Schedule for the Implementation of Task DC017A at the Terrace Cleaners site located in Temple Terrace, Hillsborough
Project: TA_017A Date: Wed 4/20/22
Task Name Duration Start Finish
1 LOE Submittal/Approval 2 wks Wed 4/20/22Tue 5/3/22
2 Subtask 1: Project Management
52 days Wed 5/4/22 Thu 7/14/22
3 Subtask 2: Groundwater Monitoring
47 days Wed 5/11/22
Thu 7/14/22
4 Field Work Preparation 2 wks Wed 5/11/22Tue 5/24/22
5 Groundwater Sampling 1 day Wed 5/25/22Wed 5/25/22
6 Groundwater Monitoring Report
6 wks Fri 6/3/22 Thu 7/14/22
Gabrielle Enos
Skylar Albritton
5/8 5/15 5/22 5/29 June
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Schedule for the Implementation of Task DC017A at the Terrace Cleaners site located in Temple Terrace, Hillsborough
Task Name Duration Start Finish
1 LOE Submittal/Approval 2 wks Wed 4/20/22Tue 5/3/22
2 Subtask 1: Project Management
52 days Wed 5/4/22 Thu 7/14/22
3 Subtask 2: Groundwater Monitoring
47 days Wed 5/11/22
Thu 7/14/22
4 Field Work Preparation 2 wks Wed 5/11/22Tue 5/24/22
5 Groundwater Sampling 1 day Wed 5/25/22Wed 5/25/22
6 Groundwater Monitoring Report
6 wks Fri 6/3/22 Thu 7/14/22
6/5 6/12 6/19 6/26 July
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Schedule for the Implementation of Task DC017A at the Terrace Cleaners site located in Temple Terrace, Hillsborough
Task Name Duration Start Finish
1 LOE Submittal/Approval 2 wks Wed 4/20/22Tue 5/3/22
2 Subtask 1: Project Management
52 days Wed 5/4/22 Thu 7/14/22
3 Subtask 2: Groundwater Monitoring
47 days Wed 5/11/22
Thu 7/14/22
4 Field Work Preparation 2 wks Wed 5/11/22Tue 5/24/22
5 Groundwater Sampling 1 day Wed 5/25/22Wed 5/25/22
6 Groundwater Monitoring Report
6 wks Fri 6/3/22 Thu 7/14/22 Jeremy Hess,Gabrielle Enos,Peter Mc
7/3 7/10 7/17 7/24
Task
Split
Milestone
Summary
Project Summary
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
External Tasks
External Milestone
Deadline
Progress
Manual Progress
Schedule for the Implementation of Task DC017A at the Terrace Cleaners site located in Temple Terrace, Hillsborough