CN-370000-HW684-BIL2DCO2.pdf

PDF 2 MB Posted

Attached to
Master Agreement FL|HW684|68b160b8827755ddf560142dd2a41e53
Contract number
HW684
Issued by
Florida

About this file

This document package consists of a Task Assignment Change Order (TACO) Number 2 and supporting materials for Contract HW684 between the State of Florida Department of Environmental Protection (FDEP) and GHD Services, Inc. The contract pertains to environmental assessment activities at the Former Polk County Fertilizer site (Site ID: ERIC_13343). The TACO was executed on November 12, 2024, and amends the original Task Assignment BIL02D to settle a Work Change Directive (WCD) authorizing additional testing and to extend the project completion date.

The task assignment involves targeted brownfield site assessment activities including soil and groundwater assessment, site assessment reporting, and specialized SPLP (Synthetic Precipitation Leaching Procedure) testing. The amended total task value increased from $41,735.09 to $41,992.54, representing a net increase of $257.45. This increase resulted from a $4,020.00 cost addition for SPLP testing of 20 samples due to dieldrin leachability-based SCTL exceedances, offset by cost reductions in project management, soil assessment labor and equipment, totaling $3,762.55. The completion date was extended from November 15, 2024, to January 10, 2025 (56 additional days). Invoice payments are structured in three tranches: $27,238.73 for analytical data and field notes, $10,733.81 for project management and site assessment report addendum, and $4,020.00 for additional analytical work from supplemental fieldwork, totaling $41,992.54.

View the file

Other files

File Type Posted
CN-370000-GC922-TA3CO2.pdf PDF
CN-370000-HW684-BIL01A.pdf.crdownload CRDOWNLOAD file
CN-370000-HW684-BIL02A.pdf PDF
CN-370000-HW684-BIL2CCO1.pdf PDF
CN-370000-HW684-BIL2DCO1.pdf PDF
CN-370000-HW684-BIL2ECO2.pdf PDF
CN-370000-HW684-CSS2ACO1.pdf PDF
CN-370000-HW684-DC001B.pdf PDF
CN-370000-HW684-DC004C.pdf PDF
CN-370000-HW684-DC006D.pdf PDF
CN-370000-HW684-DC008B.pdf PDF
CN-370000-HW684-DC008C.pdf PDF
CN-370000-HW684-DC008E.pdf PDF
CN-370000-HW684-DC011B.pdf PDF
CN-370000-HW684-DC012C.pdf PDF
CN-370000-HW684-DC014E.pdf PDF
CN-370000-HW684-DC016A.pdf PDF
CN-370000-HW684-DC017A.pdf PDF
CN-370000-HW684-DC017D.pdf PDF
CN-370000-HW684-DC018A.pdf PDF
CN-370000-HW684-DC018B.pdf PDF
CN-370000-HW684-DC01ACO3.pdf PDF
CN-370000-HW684-DC01ACO4.pdf PDF
CN-370000-HW684-DC020A.pdf PDF
CN-370000-HW684-DC021A.pdf PDF
CN-370000-HW684-DC021C.pdf PDF
CN-370000-HW684-DC022A.pdf PDF
CN-370000-HW684-DC022C.pdf PDF
CN-370000-HW684-DC023B.pdf PDF
CN-370000-HW684-DC028D.pdf PDF
CN-370000-HW684-DC029B.pdf PDF
CN-370000-HW684-DC035A.pdf PDF
CN-370000-HW684-DC037B.pdf PDF
CN-370000-HW684-DC038B.pdf PDF
CN-370000-HW684-DC038C.pdf PDF
CN-370000-HW684-DC039C.pdf PDF
CN-370000-HW684-DC03DCO1.pdf PDF
CN-370000-HW684-DC041B.pdf PDF
CN-370000-HW684-DC042B.pdf PDF
CN-370000-HW684-DC043B.pdf PDF
CN-370000-HW684-DC043D.pdf PDF
CN-370000-HW684-DC046C.pdf PDF
CN-370000-HW684-DC047B.pdf PDF
CN-370000-HW684-DC04DCO1.pdf PDF
CN-370000-HW684-DC055A.pdf PDF
CN-370000-HW684-DC056B.pdf PDF
CN-370000-HW684-DC057ACO.pdf PDF
CN-370000-HW684-DC05BCO1.pdf PDF
CN-370000-HW684-DC05ECO1.pdf PDF
CN-370000-HW684-DC060B.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Funding Information:

Org. Code E.O.

Object Code

Budget Entity Appropriation

Category Grant # Project # Year Amount

Additional Funding Information attached on separate page.

Rev. 8/17/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment Change Order This Change Order is entered into between the Parties named below and amends the Task Assignment (TA) and any previous TA Change Orders (TACO) as follows:

1. TA Number: TACO Number: Contract Number:

TACO Description:

2. Parties State of Florida Department of Environmental Protection (Department)

Department’s Project Manager: Department’s Project Manager Phone:

Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:

3. Project Number:

(If different from TA Number)

Project Name:

4. There are no changes to the TA compensation.

The compensation of the TA is changed to the amounts indicated below:

Amended Price Price Prior to TACO

Fixed Price:

Fixed Unit Rate: (Extended Price)

Cost Reimbursement:

Total TA Value:

5. There are no changes to the TA Expiration Date.

The TA Completion Date is changed from ______________ to ______________ (a total of ______ days).

6. There are no changes to the Attachments.

Attachment ___ is replaced with Attachment -____.

7. No Additional Changes.

Additional Changes:

8. All other terms and conditions of the TA remain in effect. If and to the extent that any inconsistencies may appear between the TA and this TACO, the provisions of this TACO shall control.

IN WITNESS WHEREOF, this TACO shall be effective on the last date signed below.

State of Florida Department of Environmental Protection

CONTRACTOR Department

Name:

Title: Secretary or Designee

(Authorized Signature) (Authorized Signature)

Date:

Additional signatures attached on separate page.

BIL02D 2 HW684

This Task Assignment Change Order (TACO) settles the Work Change Directive for SPLP testing and extends the Task Assignment completion date, per the TACO request from GHD received on October 22, 2024..

Megan Johnson 850.245.8994 GHD Services, Inc.

Brian Moore 813.971.3882

ERIC_13343

Former Polk County Fertilizer

$ 41,992.54 $ 41,735.09

$ 41,992.54 $ 41,735.09

11/15/2024 01/10/2025 56

1 1 1

GHD Services, Inc.

Brian Moore, P.E.

Vice President

Brian Moore Digitally signed by Brian Moore Date: 2024.11.12 16:20:46 -05'00'

Jennifer Farrell

Digitally signed by Jennifer Farrell Date: 2024.11.12 13:51:18 -05'00'

N/A

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

Contract Number:

Task Assignment #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

FLORIDA DEPARTMENT OF

Environmental Protection

Bob Martinez Center 2600 Blair Stone Road

Tallahassee, FL 32399-2400

Ron DeSantis Governor

Jeanette Nuñez Lt. Governor

Shawn Hamilton Secretary

Memorandum

TO: GHD Services Inc. HW684 Contract File

FROM: Megan Johnson, Contract Manager

DATE: November 12, 2024

SUBJECT: Negotiation Summary – BIL22, Change Order #2 - TA BIL02D C2 Former Polk County Fertilizer - Site ID # ERIC_13343 Targeted Brownfield Site Assessment Activities

This Task Assignment Change Order (TACO) settles the WCD authorizing SPLP testing and extends the Task Assignment completion date. Specific changes are detailed below:

Subtask 1: Project Management The decrease in overall task hours produced a change associated with Project Management. This change resulted in a cost actual decrease of ($186.89).

Subtask 2: Soil Assessment There was a decrease in labor hours needed to perform this subtask, which also resulted in a decrease in vehicle usage. There was also a reduction in laboratory and equipment costs. This change resulted in a cost actual decrease of ($3,575.66).

Subtask 3: Site Assessment Report Addendum There are no changes in scope or cost associated with this Subtask.

Subtask 4: SPLP Sampling Due to dieldrin leachability-based SCTL exceedances, a Work Change Directive was authorized for SPLP testing of 20 samples. This change resulted in a cost actual increase of $4,020.00.

Summary The Department’s BIL Contract Manager and GHD’s Contract Manager have both agreed to the above changes. All changes noted above represent a total overall cost increase of $257.45, as shown in the Cost Actual LOE. The changes were noted in the TACO Request received from GHD on October 22, 2024. The final cost associated with this TA increased from $41,735.09 to $41,992.54. Documentation of the changes is included in the attached TACO Request, the Delta LOE spreadsheet and the Cost Actual LOE spreadsheet, and the TACO form for BIL02D C2, prepared by the Department.

LEVEL OF EFFORT/EXPENSE WORKSHEET

SITE : Former Polk County Fertilizer SUBTASK 2: Soil & Groundwater Assessment

DATE: 11/12/2024

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Project Manager JM Contact Property Owner 4 Project Manager JM Field Work Preparation 4 Project Manager JM Evaluate Data and Determine need for additional SPLP analysis 6 Project Manager JM Data Summary 8

Sr Technician WM Mob/demob (7 days) 10 Sr Technician WM Locate/measure soil borings 4 Sr Technician WM Soil Borings (72 total - 1 hr per boring) 64

Sr Technician SA Mob/demob (7 days) 10 Sr Technician SA Locate/measure soil borings 4 Sr Technician SA Soil Borings (72 total - 1 hr per boring) 64

TOTAL LABOR 178

VEHICLE TYPE RATE UNIT USEAGE

WM Company Truck $480.00 week 1 $480.00 WM Company Truck $120.00 day 0 $0.00 SA Company Truck $480.00 week 1 $480.00 SA Company Truck $120.00 day 0 $0.00

TOTAL VEHICLE $960.00

PER DIEM STAFF RATE UNIT USEAGE

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

TOTAL $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

OCPs Soil EPA 8081 $105.00 71 $7,455.00 PAHs Soil EPA 8270 SIM $110.00 18 $1,980.00 Nitrate SM4500 $23.00 0 $0.00 Sample Shipping - soil overnight - large cooler $150.00 5 $750.00 Ice $6.50 5 $32.50

TOTAL LAB $10,217.50

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Expendables $40.00 day 6 $240.00

Soil Assessment Kit $700.00 week 1 $700.00 Soil Assessment Kit $175.00 day 0 $0.00

GPS (Trimble) $700.00 week 1 $700.00 GPS (Trimble) $175.00 day 0 $0.00

TOTAL EQUIPMENT $1,640.00

FINAL --7/24/96

SUBTASK 3: Site Assessment Report Addendum

DATE: 11/12/2024

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Sr. Professional Engineer JH Conclusion and Recommendations 4

Project Manager JM Background Summary for Pok Fertilizer (SARA) 6 Project Manager JM Soil Sampling Methods (SARA) 6 Project Manager JM Soil Sampling Results (SARA) 6 Project Manager JM Dieldrin Delineation 4 Project Manager JM PAH Delineation 4 Project Manager JM Groundwater Sampling Methods (SARA) 4 Project Manager JM Laboratory Data Validation (soil) 4 Project Manager JM Conclusions and Recommendations 4

Drafting Technician PM Soil Analytical Results Figures 6 Drafting Technician PM Groundwater Flow Figure 2 Drafting Technician PM Groundwater Analytical Results Figure 2

Administrative Assistant JJ Data Entry (49 borings and 8 wells) 6 Administrative Assistant JJ Summary Tables (soil, groundwater) 3 Administrative Assistant JJ Finalize SARA (pdf) 3

TOTAL LABOR 64

VEHICLE TYPE RATE UNIT USEAGE

TOTAL VEHICLE $0.00

PER DIEM STAFF RATE UNIT USEAGE

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

TOTAL $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

TOTAL LAB $0.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

TOTAL EQUIPMENT $0.00

SUBTASK 4: WCD#1

DATE: 11/12/2024

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

TOTAL LABOR 0

VEHICLE TYPE RATE UNIT USEAGE

TOTAL VEHICLE $0.00

PER DIEM STAFF RATE UNIT USEAGE

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

TOTAL $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

OCPs SPLP extraction $48.00 20 $960.00 OCPs - leachate EPA 8081 $105.00 20 $2,100.00

Rush Extraction $48.00 20 $960.00

TOTAL LAB $4,020.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

TOTAL EQUIPMENT $0.00

SUBTASK 2: Soil & Groundwater Assessment

DATE: 11/12/2024

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Project Manager JM Contact Property Owner 0 Project Manager JM Field Work Preparation 0 Project Manager JM Evaluate Data and Determine need for additional SPLP analysis 0 Project Manager JM Data Summary 0

Sr Technician WM Mob/demob (7 days) -2 Sr Technician WM Locate/measure soil borings 0 Sr Technician WM Soil Borings (72 total - 1 hr per boring) -8

-10

Sr Technician SA Mob/demob (7 days) -2 Sr Technician SA Locate/measure soil borings 0 Sr Technician SA Soil Borings (72 total - 1 hr per boring) -8

-10

TOTAL LABOR -20

VEHICLE TYPE RATE UNIT USEAGE

WM Company Truck $480.00 week 0 $0.00 WM Company Truck $120.00 day -1 ($120.00) SA Company Truck $480.00 week 0 $0.00 SA Company Truck $120.00 day -1 ($120.00)

TOTAL VEHICLE ($240.00)

PER DIEM STAFF RATE UNIT USEAGE

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

TOTAL $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

OCPs Soil EPA 8081 $105.00 0 $0.00 PAHs Soil EPA 8270 SIM $110.00 -2 ($220.00) Nitrate SM4500 $23.00 -56 ($1,288.00) Sample Shipping - soil overnight - large cooler $150.00 0 $0.00 Ice $6.50 0 $0.00

TOTAL LAB ($1,508.00)

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Expendables $40.00 day -1 ($40.00)

Soil Assessment Kit $700.00 week 0 $0.00 Soil Assessment Kit $175.00 day -1 ($175.00)

GPS (Trimble) $700.00 week 0 $0.00 GPS (Trimble) $175.00 day -1 ($175.00)

TOTAL EQUIPMENT ($390.00)

SUBTASK 4: WCD#1

DATE: 11/12/2024

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

TOTAL LABOR 0

VEHICLE TYPE RATE UNIT USEAGE

TOTAL VEHICLE $0.00

PER DIEM STAFF RATE UNIT USEAGE

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

TOTAL $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

OCPs SPLP extraction $48.00 20 $960.00 OCPs - leachate EPA 8081 $105.00 20 $2,100.00

Rush Extraction $48.00 20 $960.00

TOTAL LAB $4,020.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

TOTAL EQUIPMENT $0.00

SUBTASK 2: Soil & Groundwater Assessment

DATE: 11/12/2024

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Project Manager JM Contact Property Owner 4 Project Manager JM Field Work Preparation 4 Project Manager JM Evaluate Data and Determine need for additional SPLP analysis 6 Project Manager JM Data Summary 8

Sr Technician WM Mob/demob (7 days) 12 Sr Technician WM Locate/measure soil borings 4 Sr Technician WM Soil Borings (72 total - 1 hr per boring) 72

Sr Technician SA Mob/demob (7 days) 12 Sr Technician SA Locate/measure soil borings 4 Sr Technician SA Soil Borings (72 total - 1 hr per boring) 72

TOTAL LABOR 198

VEHICLE TYPE RATE UNIT USEAGE

WM Company Truck $480.00 week 1 $480.00 WM Company Truck $120.00 day 1 $120.00 SA Company Truck $480.00 week 1 $480.00 SA Company Truck $120.00 day 1 $120.00

TOTAL VEHICLE $1,200.00

PER DIEM STAFF RATE UNIT USEAGE

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

TOTAL $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

OCPs Soil EPA 8081 $105.00 71 $7,455.00 PAHs Soil EPA 8270 SIM $110.00 20 $2,200.00 Nitrate SM4500 $23.00 56 $1,288.00 Sample Shipping - soil overnight - large cooler $150.00 5 $750.00 Ice $6.50 5 $32.50

TOTAL LAB $11,725.50

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

Expendables $40.00 day 7 $280.00

Soil Assessment Kit $700.00 week 1 $700.00 Soil Assessment Kit $175.00 day 1 $175.00

GPS (Trimble) $700.00 week 1 $700.00 GPS (Trimble) $175.00 day 1 $175.00

TOTAL EQUIPMENT $2,030.00

SUBTASK 3: Site Assessment Report Addendum

DATE: 11/12/2024

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Sr. Professional Engineer JH Conclusion and Recommendations 4

Project Manager JM Background Summary for Pok Fertilizer (SARA) 6 Project Manager JM Soil Sampling Methods (SARA) 6 Project Manager JM Soil Sampling Results (SARA) 6 Project Manager JM Dieldrin Delineation 4 Project Manager JM PAH Delineation 4 Project Manager JM Groundwater Sampling Methods (SARA) 4 Project Manager JM Laboratory Data Validation (soil) 4 Project Manager JM Conclusions and Recommendations 4

Drafting Technician PM Soil Analytical Results Figures 6 Drafting Technician PM Groundwater Flow Figure 2 Drafting Technician PM Groundwater Analytical Results Figure 2

Administrative Assistant JJ Data Entry (49 borings and 8 wells) 6 Administrative Assistant JJ Summary Tables (soil, groundwater) 3 Administrative Assistant JJ Finalize SARA (pdf) 3

TOTAL LABOR 64

VEHICLE TYPE RATE UNIT USEAGE

TOTAL VEHICLE $0.00

PER DIEM STAFF RATE UNIT USEAGE

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE COST

TOTAL $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

TOTAL LAB $0.00

EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS

TOTAL EQUIPMENT $0.00

Site Name: Site ID #:

Contract #: Contractor:

� Reason for Work Change Directive :

� Description of Work Change Directive :

� Attachments (if applicable, list documents supporting change):

� Costs (if negotiated unit costs, provide information below):

WCP WCD 07-2018

Authorized Contractor Signature:

Authorized FDEP Signature:

WORK CHANGE DIRECTIVE FORM

FDEP Supervisor Approval:

(if applicable)

Additional work is not authorized without prior FDEP approval as indicated by an approved Work Change Directive Form or Task Assignment Change Order Form. It is the Contractor's responsibility to ensure that additional costs associated with this WCD are resolved by a Task Assignment Change Order (TACO) prior to the completion date of the original Task Assignment or subsequent TACOs completed prior to the execution date of this WCD. Failure to do so will result in a loss of reimbursement for work associated with this WCD.

Task Assignment #: Work Change Directive #:

Maximum Estimated Increase in Task Amount:

Former Polk County Fertilizer ERIC_9970

HW684 GHD Services Inc.

BIL02D 1

dieldrin leachabilty-based SCTL exceedances

SPLP Testing

20 SPLP analysis ($45 extraction and $105 analysis of leachate) Rush extraction for 20 samples

$ 4,300.00

Brian Moore Digitally signed by Brian Moore Date: 2024.09.30 11:42:26 -04'00'

Megan R. Johnson Digitally signed by Megan R.

Johnson Date: 2024.09.30 11:59:22 -04'00'

Scott L Sweeney

Digitally signed by Scott L Sweeney Date: 2024.09.30 12:56:17 -04'00'

From: Brian Moore To: Johnson, Megan R Subject: RE: former Polk County Fertilizer Date: Tuesday, October 22, 2024 3:14:17 PM Attachments: image001.png image002.png image003.png image004.png image005.png TA_002D WCD#1.xlsx TA_002D final CO1.xlsx TA_002D Delta CO1.xlsx TA_002D.xlsx

EXTERNAL MESSAGE

This email originated outside of DEP. Please use caution when opening attachments, clicking links, or responding to this email.

Megan, A proposed change order is attached for consideration, which rectifies WCD#1 and adjust labor/expenses in subtask 2

Thank you

BRIAN MOORE PE

GHD

Proudly employee owned | ghd.com 5904 Hampton Oaks Parkway Suite F Tampa FL 33610 USA

O 813 971 3882 D 813 257 0658 M 813 335 2147 E brian.moore@ghd.com

The Power of Commitment

Connect

Please consider our environment before printing this email

From: Johnson, Megan R <Megan.R.Johnson@FloridaDEP.gov> Sent: Monday, September 30, 2024 2:13 PM To: Brian Moore <Brian.Moore@ghd.com> Cc: Cross, Justin L. <Justin.L.Cross@FloridaDEP.gov>; Sweeney, Scott L <Scott.L.Sweeney@dep.state.fl.us> Subject: RE: former Polk County Fertilizer

Hi Brian, Attached is the DEP signed WCD#1 for the Polk County Fertilizer site. Let me know if you have any questions.

Thanks, Megan

From: Brian Moore <Brian.Moore@ghd.com> Sent: Monday, September 30, 2024 11:43 AM

To: Johnson, Megan R <Megan.R.Johnson@FloridaDEP.gov> Subject: RE: former Polk County Fertilizer

EXTERNAL MESSAGE

This email originated outside of DEP. Please use caution when opening attachments, clicking links, or responding to this email.

I revised WCD#1 to include both, thank you

BRIAN MOORE PE

GHD

Proudly employee owned | ghd.com 5904 Hampton Oaks Parkway Suite F Tampa FL 33610 USA

O 813 971 3882 D 813 257 0658 M 813 335 2147 E brian.moore@ghd.com

The Power of Commitment

Connect

Please consider our environment before printing this email

From: Johnson, Megan R <Megan.R.Johnson@FloridaDEP.gov> Sent: Monday, September 30, 2024 11:33 AM To: Brian Moore <Brian.Moore@ghd.com> Subject: RE: former Polk County Fertilizer

Hi Brian, I received a WCD#1 on Saturday, this one is labeled as WCD#2. Are these two separate WCDs? Can we combine them into one, if so?

Thanks, Megan

From: Brian Moore <Brian.Moore@ghd.com> Sent: Monday, September 30, 2024 10:22 AM To: Johnson, Megan R <Megan.R.Johnson@FloridaDEP.gov> Subject: former Polk County Fertilizer

EXTERNAL MESSAGE

This email originated outside of DEP. Please use caution when opening attachments, clicking links, or responding to this email.

Megan, Please see attached proposed WCD for Polk County Fertilizer for some additional SPLP analysis for consideration.

Thank you

BRIAN MOORE PE

GHD

Proudly employee owned | ghd.com 5904 Hampton Oaks Parkway Suite F Tampa FL 33610 USA

O 813 971 3882 D 813 257 0658 M 813 335 2147 E brian.moore@ghd.com

The Power of Commitment

Connect

Please consider our environment before printing this email

CONFIDENTIALITY NOTICE: This email, including any attachments, is confidential and may be privileged. If you are not the intended recipient please notify the sender immediately, and please delete it; you should not copy it or use it for any purpose or disclose its contents to any other person. GHD and its affiliates reserve the right to monitor and modify all email communications through their networks.

Funding Information:

Org. Code E.O.

Object Code

Budget Entity Appropriation

Category Grant # Project # Year Amount

Additional Funding Information attached on separate page.

Rev. 8/17/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment Change Order This Change Order is entered into between the Parties named below and amends the Task Assignment (TA) and any previous TA Change Orders (TACO) as follows:

1. TA Number: TACO Number: Contract Number:

TACO Description:

2. Parties State of Florida Department of Environmental Protection (Department)

Department�s Project Manager: Department�s Project Manager Phone:

Contractor Name: (Contractor ) ntractor�st �s Project Manager: ontractor�s t�s Project Manager Phone:

3. Project Number:

(If different from TA Number)

Project Name:

4. There are no changes to the TA compensation.

The compensation of the TA is changed to the amounts indicated below:

Amended Price Price Prior to TACO

Fixed Price:

Fixed Unit Rate: (Extended Price)

Cost Reimbursement:

Total TA Value:

5. There are no changes to the TA Expiration Date.

The TA Completion Date is changed from ______________ to ______________ (a total of ______ days).

6. There are no changes to the Attachments.

Attachment ___ is replaced with Attachment -____.

7. No Additional Changes.

Additional Changes:

8. All other terms and conditions of the TA remain in effect. If and to the extent that any inconsistencies may appear between the TA and this TACO, the provisions of this TACO shall control.

IN WITNESS WHEREOF, this TACO shall be effective on the last date signed below.

State of Florida Department of Environmental Protection

CONTRACTOR Department

Name:

Title: Secretary or Designee

(Authorized Signature) (Authorized Signature)

Date:

Additional signatures attached on separate page.

BIL02D 1 HW684

The Department approves this Task Assignment Change Order (TACO) for changes to the TA Completion date.

Allison Hankins 850 245 8990 Contractor GHD Services, Inc. Contractor

Contractor Brian Moore Contractor 813 971 3882

ERIC_13343

Former Polk County Fertilizer

$ 41,735.09 $ 41,735.09

$ 41,735.09 $ 41,735.09

Completion Completion 09/30/2024 11/15/2024 46

1 1 1

GHD Services, Inc.

Contractor

Brian Moore

Vice President

Brian Moore Digitally signed by Brian Moore Date: 2024.07.11 16:52:14 -04'00'

Jennifer Farrell

Digitally signed by Jennifer Farrell Date: 2024.07.10 14:15:17 -04'00'

N/A

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

Contract Number:

Task Assignment #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

HW684

BIL02D

$ 41,735.09

Soil Data and Field Notes

Site Assessment Report Addendum

DEP approval of Soil Data and Field Notes

DEP approval of Site Assessment Report Addendum

09/18/2024

10/17/2024

$ 10,920.70

$ 30,814.39