This document is a Task Assignment Change Order (TACO Number 2) issued by the State of Florida Department of Environmental Protection (FDEP) to CDM Smith Inc. for environmental remediation work at the Peterson Cleaners site (Project ERIC_5380). The change order was executed on July 12, 2024, with FDEP Project Manager Benjamin Aoki and CDM Smith Project Manager Kathy Leggoe as the primary points of contact. The original task assignment (DC011C) was established under Contract HW681 with an original completion date of September 27, 2024, which was extended to January 17, 2025.

This TACO authorizes a cost reduction of $7,625.04, bringing the total task assignment value from $37,821.33 to $30,196.29, while maintaining the same completion date. The scope modifications include personnel changes and a reduction in operations and maintenance activities. Specifically, field staff were switched from Kyle Turner to Melanie Blanton for annual groundwater monitoring, and from Kyle Turner to Mike Wines for operations and maintenance activities. Subtask 3 (Quarter 1 O&M and Optimization) was reduced from four to three events due to a scheduling conflict with a December 2023 monitoring date that had already passed before the original task assignment was executed, resulting in corresponding reductions in labor, truck/field expenses, and laboratory sampling. The contract includes five subtasks: Project Management ($2,232.91), Annual Groundwater Monitoring ($5,341.67), Quarter 1 O&M and Optimization ($7,136.09), Quarter 2 O&M and Optimization ($10,445.62), and Utilities ($5,040.00), totaling 170.9 man-hours. Deliverables are scheduled with specific due dates: groundwater monitoring reports due April 5, 2024; quarterly O&M submittal due May 3, 2024; semi-annual remedial action status report due August 2, 2024; and paid utility invoices due September 30, 2024.

View the file

Other files

File Type Posted
CN-370000-HW681-DC001A.pdf PDF
CN-370000-HW681-DC001C.pdf PDF
CN-370000-HW681-DC001D.pdf PDF
CN-370000-HW681-DC002B.pdf PDF
CN-370000-HW681-DC003D.pdf PDF
CN-370000-HW681-DC003E.pdf PDF
CN-370000-HW681-DC007C.pdf PDF
CN-370000-HW681-DC008A.pdf PDF
CN-370000-HW681-DC008C.pdf PDF
CN-370000-HW681-DC008D.pdf PDF
CN-370000-HW681-DC009B.pdf PDF
CN-370000-HW681-DC009C.pdf PDF
CN-370000-HW681-DC009D.pdf PDF
CN-370000-HW681-DC010B.pdf PDF
CN-370000-HW681-DC011E.pdf PDF
CN-370000-HW681-DC014A.pdf PDF
CN-370000-HW681-DC014B.pdf PDF
CN-370000-HW681-DC015B.pdf PDF
CN-370000-HW681-DC016A.pdf PDF
CN-370000-HW681-DC016B.pdf PDF
CN-370000-HW681-DC017A.pdf PDF
CN-370000-HW681-DC017C.pdf PDF
CN-370000-HW681-DC017D.pdf PDF
CN-370000-HW681-DC018A.pdf PDF
CN-370000-HW681-DC018B.pdf PDF
CN-370000-HW681-DC01ACO1.pdf PDF
CN-370000-HW681-DC01ACO2.pdf PDF
CN-370000-HW681-DC01ACO3.pdf PDF
CN-370000-HW681-DC025B.pdf PDF
CN-370000-HW681-DC025C.pdf PDF
CN-370000-HW681-DC026B.pdf PDF
CN-370000-HW681-DC026C.pdf PDF
CN-370000-HW681-DC027A.pdf PDF
CN-370000-HW681-DC027C.pdf PDF
CN-370000-HW681-DC028A.pdf PDF
CN-370000-HW681-DC028B.pdf PDF
CN-370000-HW681-DC028C.pdf PDF
CN-370000-HW681-DC029D.pdf PDF
CN-370000-HW681-DC02CCO1.pdf PDF
CN-370000-HW681-DC02DCO3.pdf PDF
CN-370000-HW681-DC032A.pdf PDF
CN-370000-HW681-DC032B.pdf PDF
CN-370000-HW681-DC032C.pdf PDF
CN-370000-HW681-DC033A.pdf PDF
CN-370000-HW681-DC038A.pdf PDF
CN-370000-HW681-DC03BCO1.pdf PDF
CN-370000-HW681-DC03ECO2.pdf PDF
CN-370000-HW681-DC040B.pdf PDF
CN-370000-HW681-DC040C.pdf PDF
CN-370000-HW681-DC041A.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Funding Information:

Org. Code E.O. Object Code Budget Entity Appropriation

Category Grant # Project # Year Amount

☐ Additional Funding Information attached on separate page.

Rev. 8/17/2020

STATE OF FLORIDA

DEPARTMENT OF ENVIRONMENTAL PROTECTION

Task Assignment Change Order This Change Order is entered into between the Parties named below and amends the Task Assignment (TA) and any previous TA Change Orders (TACO) as follows:

1. TA Number: TACO Number: Contract Number:

TACO Description:

2. Parties State of Florida Department of Environmental Protection (Department)

Department’s Project Manager: Department’s Project Manager Phone:

Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:

3. Project Number:

(If different from TA Number) Project Name:

4. ☐ There are no changes to the TA compensation.

☐ The compensation of the TA is changed to the amounts indicated below:

Amended Price Price Prior to TACO ☐ Fixed Price:

☐ Fixed Unit Rate: (Extended Price)

☐ Cost Reimbursement:

Total TA Value:

5. ☐ There are no changes to the TA Expiration Date.

☐ The TA Completion Date is changed from ______________ to ______________ (a total of ______ days).

6. ☐ There are no changes to the Attachments.

☐ Attachment ___ is replaced with Attachment -____.

7. ☐ No Additional Changes.

☐ Additional Changes:

8. All other terms and conditions of the TA remain in effect. If and to the extent that any inconsistencies may appear between the TA and this TACO, the provisions of this TACO shall control.

IN WITNESS WHEREOF, this TACO shall be effective on the last date signed below.

State of Florida Department of Environmental Protection

CONTRACTOR Department Name:

Title: Secretary or Designee

(Authorized Signature) (Authorized Signature) Date:

☐ Additional signatures attached on separate page.

DC011C 2 HW681

Benjamin Aoki 850-245-7527 Contractor Contractor

Contractor Contractor

Contractor

CDM Smith Inc.

Kathy Leggoe 904-527-6727

ERIC_5380

Peterson Cleaners

✔ $ 25,296.29 $ 32,921.33

$ 4,900.00 $ 4,900.00

$ 30,196.29 $ 37,821.33 ✔ Completion

Completion 01/17/2025 01/17/2025 0

✔ 1 1 1

CDM Smith Inc.

Leslie Samel

CDM Contract Manager

Leslie Samel Digitally signed by Leslie Samel Date: 2024.07.12 13:59:24 -04'00'

Jennifer Farrell

Digitally signed by Jennifer Farrell Date: 2024.07.12 12:16:18 -04'00'

This Task Assignment Change Order authorizes a change in personnel and the scope of work for CDM Smith Inc. per their request on 03MAY2024.

Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment

WCP TAFORM 01_18

Contract Number:

Task Assignment #:

Change Order #:

Deliverables:

Deliverable Deliverable Due Date

Invoice Schedule:

Requirements for Invoice Submittal Amount to be Invoiced

TOTAL COST

HW681

DC011C

$ 30,196.29

Subtask 2: Electronically submitted groundwater monitoring laboratory reports, field notes, and updated groundwater tables

Subtask 3: Electronically submitted Quarterly O&M submittal including field documentation, laboratory reports, and tables

Subtask 4 & 1: Semi-Annual Remedial Action Status Report; Project Management

Subtask 5: Paid Utility Invoices

Subtask 2: FDEP receipt and approval of laboratory reports, field notes, updated groundwater tables, submitted electronically

Subtask 4 & 1: FDEP receipt and approval of Semi-Annual Remedial Action Status Report; Project Management

Subtask 5: FDEP receipt of paid utility invoices for 7 months; Utilities (Cost Reimbursement) = not to exceed $4,900; Utilities Handling Fee = $140

Subtask 3: FDEP receipt and approval of Quarterly O&M submittal including field documentation, laboratory reports, and tables, submitted electronically

04/05/2024

05/03/2024

08/02/2024

09/30/2024

$ 7,136.09

$ 5,341.67

$ 12,678.53

$ 5,040.00

Ron DeSantis Governor

Jeanette Nuñez Lt. Governor

Shawn Hamilton Secretary

TO:

FROM:

DATE:

SUBJECT:

FLORIDA DEPARTMENT OF

Environmental Protection

Bob Martinez Center 2600 Blair Stone Road

Tallahassee, FL 32399-2400

HW681 Contract File

Benjamin Aoki, Project Manager

June 19th, 2024

Negotiation Summary Peterson Cleaners

ERIC_5380; DC011C-2

This Task Assignment Change Order authorizes a change in personnel and reduction in cost to the CDM Smith Inc. scope of work and cost estimate received on 03MAY2024. The total decrease is $7,625.04.

The previous cost total was $37,821.33. CDM Smith my invoice according to the Deliverables and Invoice Schedule Attachment.

Specific negotiated subtasks are as follows.

Subtask 2: Annual Groundwater Monitoring

Switched the field staff from Kyle Turner to Melanie Blanton

Subtask 3: Quarter 1 O&M and Optimization

Reduced from 4 to 3 O&M events because of date conflict between previous TA and December O&M. This includes a 1/4 reduction in labor, truck/field expenses, and removed 1 SV sample and shipping. Kyle Turner was replaced by Mike Wines for fieldwork/documentation for 3 events.

Subtask 4: Quarter 2 O&M and Optimization

Switched the field staff from Kyle Turner to Mike Wines.

The FDEP Project Manager agrees the scope of work and final cost associated with this Task Assignment Change Order. The final cost for the Task Assignment DC005C is $30,196.29 with

170.9 man hours.

FDEP COST ESTIMATEContractor: CDM Smith, Inc.

Date: 5/3/2024

Task #: DC011C TACO 1 SubTask 1 Project Management SubTask 6

Site: SubTask 2 Annual Groundwater Monitoring SubTask 7

Activity/Phase: SubTask 3 Quarter 1 O&M and Optimization SubTask 8

Project Manager: Kathy Leggoe, PMP SubTask 4 Quarter 2 O&M and Optimization SubTask 9

SubTask 5 Utilities SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category

$60.10 Project Manager K. leggoe 12.4 12.4 $0.00 Senior Officer 0 0 0 0 0 0 0 0 0 0

$71.37 Senior Technical Expert S Cobert 11.0 2.0 3.0 6.0 0 0 0 0 0 0 $60.10 Project Manager K. leggoe 8.0 2.0 3.0 3.0 0 0 0 0 0 0

$0.00 0.0 0.0 0.0 0.0 0 0 0 0 0 0 $43.05 Professional II K. Turner 36.5 6.0 6.5 24.0 0 0 0 0 0 0 $28.17 Professional I J. LeBlanc 15.0 4.0 5.0 6.0 0 0 0 0 0 0 $34.34 Professional I L. Mueller 6.0 0.0 0.0 6.0 0 0 0 0 0 0 $42.10 Professional II M. Blanton 16.0 16.0 0.0 0.0 0 0 0 0 0 0 $24.04 Professional I M. Wines 66 0.0 36.0 30.0 0 0 0 0 0 0

$0.00 Senior Support Services 0 0.0 0.0 0.0 0 0 0 0 0 0 $0.00 0 0.0 0.0 0.0 0 0 0 0 0 0 $0.00 0 0.0 0.0 0.0 0 0 0 0 0 0 $0.00 0 0.0 0.0 0.0 0 0 0 0 0 0 $0.00 0 0.0 0.0 0.0 0 0 0 0 0 0 $0.00 0 0.0 0.0 0.0 0 0 0 0 0 0 $0.00 0 0.0 0.0 0.0 0 0 0 0 0 0 $0.00 0 0.0 0.0 0.0 0 0 0 0 0 0 $0.00 0 0.0 0.0 0.0 0 0 0 0 0 0 $0.00 0 0.0 0.0 0.0 0 0 0 0 0 0 $0.00 0 0.0 0.0 0.0 0 0 0 0 0 0

$0.00 0 0.0 0.0 0.0 0 0 0 0 0 0 $0.00 0 0.0 0.0 0.0 0 0 0 0 0 0 $0.00 0 0.0 0.0 0.0 0 0 0 0 0 0 $0.00 0 0.0 0.0 0.0 0 0 0 0 0 0 $0.00 0 0.0 0.0 0.0 0 0 0 0 0 0

Total Hours 170.9 12.4 30.0 53.5 75.0 0 0 0 0 0 0

Direct Labor $6,470.41 $744.38 $1,307.52 $1,680.53 $2,737.98 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Overhead 135.00% $8,735.05 $1,004.91 $1,765.15 $2,268.72 $3,696.27 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 37.70% $2,439.35 $280.63 $492.94 $633.56 $1,032.22 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $17,644.81 $2,029.92 $3,565.61 $4,582.81 $7,466.47 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Operation and Maintenance

Petersons Cleaners

PetersonCleaners_OM_Final_HW681_DC011C T1

Task #: DC011C TACO 1 SubTask 1 Project Management SubTask 6

Site: SubTask 2 Annual Groundwater Monitoring SubTask 7

Activity/Phase: SubTask 3 Quarter 1 O&M and Optimization SubTask 8

Project Manager: Kathy Leggoe, PMP SubTask 4 Quarter 2 O&M and Optimization SubTask 9

SubTask 5 Utilities SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10

Operation and Maintenance

Petersons Cleaners

Travel Vehicle Rental $840.00 $120.00 $360.00 $360.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $840.00 $120.00 $360.00 $360.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 IDW - Erwin $125.00 $0.00 $0.00 $125.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Utilities $4,900.00 $0.00 $0.00 $0.00 $4,900.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $5,025.00 $0.00 $0.00 $125.00 $4,900.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $152.50 $0.00 $0.00 $12.50 $140.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $5,177.50 $0.00 $0.00 $137.50 $5,040.00 $0.00 $0.00 $0.00 $0.00 $0.00

Laboratory Analytical Costs $984.00 $584.00 $200.00 $200.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $376.50 $156.50 $110.00 $110.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $1,360.50 $740.50 $310.00 $310.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $280.00 $40.00 $120.00 $120.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drum $100.00 $100.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $3,029.00 $419.00 $1,305.00 $1,305.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $3,409.00 $559.00 $1,425.00 $1,425.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subtotal $28,431.81 $2,029.92 $4,985.11 $6,677.81 $9,698.97 $5,040.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $1,764.48 $202.99 $356.56 $458.28 $746.65 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Estimated Cost $30,196.29 $2,232.91 $5,341.67 $7,136.09 $10,445.62 $5,040.00 $0.00 $0.00 $0.00 $0.00 $0.00

Cost from Prior CEF: $37,821.33 Manual Entry Cost from Delta CEF; ($7,625.04) Manual Entry

Cost (Prior + Delta): $30,196.29 Auto-Calculated Rounding Error: $0.00 Auto-Calculated

Final Total Cost: $30,196.29 Auto-Calculated

PetersonCleaners_OM_Final_HW681_DC011C T1

LEVEL OF EFFORT/EXPENSE WORKSHEET

SITE : Petersons Cleaners SUBTASK: Annual Groundwater Monitoring

DATE: 5/3/2024

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Project Technical Lead S. Cobert Interpretation of Lab Data Eval 2

Project Manager K. Leggoe Prepare Field Scope of Work 1 Preparation of Data Summary 1

Professional II K. Turner Mobilization/Demobilization 0 Field Preparation 1 Arrange for Site Access with Owner 1 Prepare Sample Kit Request 1 Update HASP 1 Sample Monitoring Wells 0 Preparation of Data Summary 2

Professional II M. Blanton Mobilization/Demobilization 4 Sample Monitoring Wells 12

Professional I J. LeBlanc Data Tabulation/Data Package Preparation 4

Total Hours:

S.Cobert 2 K. Leggoe 2 K. Turner 6 M. Blanton 16 J. LeBlanc 4

TOTAL LABOR 30

VEHICLE TYPE RATE UNIT USEAGE

Truck $120.00 day 1 $120.00

TOTAL VEHICLE $120.00

PER DIEM STAFF RATE UNIT USEAGE

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE UNIT COST

disposal of 1 drum in Subtask 4 $0.00

TOTAL $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

EPA Method 8260 (VOHs) $73.00 8 $584.00 Shipping $150.00 1 $150.00 Ice $6.50 1 $6.50

TOTAL LAB $740.50

FIELD EXPENSES ITEM RATE COSTING UNIT USEAGE TOTALS

$0.00 Expendables $40.00 day 1 $40.00 Drum $100.00 each 1 $100.00 HDPE Tubing $0.30 foot 350 $105.00 Silicon Tubing (1/4") $3.00 foot 8 $24.00 Groundwater Sampling Kit $290.00 day 1 $290.00

TOTAL EQUIPMENT $559.00

FINAL --7/24/96

SUBTASK: Quarter 1 O&M and Optimization

DATE: 5/3/2024

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Project Technical Lead S. Cobert Interpretation of O&M Data Eval (3 events) 3

Project Manager K. Leggoe Field Correspondance (3 events) 3

Professional II K. Turner Field Preparation (3 events) 3 Arrange for Site Access with Owner (3 events) 1.5 Prepare Sample Kit Request 2

Professional I M. Wines Mobilization/Demobilization (3 trips) 6 O&M Activities (3 events) 24 Documentation of O&M Activities (3 events) 6

Professional I J. LeBlanc Data Tabulation/Data Package Preparation 5

Total Hours:

S.Cobert 3 K. Leggoe 3 K. Turner 6.5 M. Wines 36 J. LeBlanc 5

53.5

TOTAL LABOR 53.5

VEHICLE TYPE RATE UNIT USEAGE

Truck $120.00 day 3 $360.00

TOTAL VEHICLE $360.00

PER DIEM STAFF RATE UNIT USEAGE

$0.00

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE UNIT COST

TOTAL $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

EPA Method TO-15 (VOHs) $200.00 1 $200.00 Small Cooler/Shipping $110.00 1 $110.00

TOTAL LAB $310.00

FIELD EXPENSES ITEM RATE COSTING UNIT USEAGE TOTALS

Expendables $40.00 day 3 $120.00 $0.00

Construction/O&M/Pilot Kit $360.00 foot 3 $1,080.00 Construction/O&M Supplies $75.00 each 3 $225.00

TOTAL EQUIPMENT $1,425.00

SUBTASK: Quarter 2 O&M and Optimization

DATE: 5/3/2024

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Project Technical Lead S. Cobert Data interpretation/PE Review (3 events/RASR) 6

Project Manager K. Leggoe Field Correspondence (3 events) 3

Professional II K. Turner Field Preparation (3 events) 2 Arrange for Site Access with Owner (3 events) 1 Prepare Sample Kit Request 1 Remedial Action Status Report Preparation 20

Professional I M. Wines Mobilization/Demobilization (3 trips) 6 O&M Activities (3 events) 24

Professional I J. LeBlanc Remedial Action Status Report Preparation - Data Tabulation/Data Package Preparation 6

Professional I L. Mueller Figures 6

Total Hours:

S.Cobert 6 K. Leggoe 3 K. Turner 24 M. Wines 30 J. LeBlanc 6 L. Mueller 6

TOTAL LABOR 75

VEHICLE TYPE RATE UNIT USEAGE

Truck $120.00 day 3 $360.00

TOTAL VEHICLE $360.00

PER DIEM STAFF RATE UNIT USEAGE

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE UNIT COST

Erwin Remediation IDW Disposal Drum $125.00 $125.00

TOTAL $125.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

EPA Method TO-15 (VOHs) $200.00 1 $200.00 Small Cooler/Shipping $110.00 1 $110.00

TOTAL LAB $310.00

FIELD EXPENSES ITEM RATE COSTING UNIT USEAGE TOTALS

Expendables $40.00 day 3 $120.00

Construction/O&M/Pilot Kit $360.00 foot 3 $1,080.00 Construction/O&M Supplies $75.00 each 3 $225.00

TOTAL EQUIPMENT $1,425.00

SITE : Peterson's Dry Cleaners SUBTASK: Utilities

DATE: 5/3/2024

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

TOTAL LABOR 0

VEHICLE TYPE RATE UNIT USEAGE

TOTAL VEHICLE $0.00

PER DIEM STAFF RATE UNIT USEAGE

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE UNIT COST

TOTAL $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

TOTAL LAB $0.00

FIELD EXPENSES ITEM RATE COSTING UNIT USEAGE TOTALS

Quarter 1 Utilities Utility Charges (Electric) $700.00 month 4 $2,800.00 Quarter 1 Handling Fee Utility Handling Fee $20.00 month 4 $80.00

Quarter 2 Utilities Utility Charges (Electric) $700.00 month 3 $2,100.00 Quarter 2 Handling Fee Utility Handling Fee $20.00 month 3 $60.00

TOTAL EQUIPMENT $5,040.00

Task #: DC011C TACO 1 SubTask 1 Project Management SubTask 6

Site: SubTask 2 Annual Groundwater Monitoring SubTask 7

Activity/Phase: SubTask 3 Quarter 1 O&M and Optimization SubTask 8

Project Manager: Kathy Leggoe, PMP SubTask 4 Quarter 2 O&M and Optimization SubTask 9

SubTask 5 Utilities SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category

$60.10 Project Manager K. leggoe -4.3 -4.3 $0.00 Senior Officer 0 0 0 0 0 0 0 0 0 0

$71.37 Senior Technical Expert S Cobert -1.0 0.0 -1.0 0.0 0 0 0 0 0 0 $60.10 Project Manager K. leggoe -1.0 0.0 -1.0 0.0 0 0 0 0 0 0

$0.00 0.0 0.0 0.0 0.0 0 0 0 0 0 0 $43.05 Professional II K. Turner -95.5 -16.0 -49.5 -30.0 0 0 0 0 0 0 $28.17 Professional I J. LeBlanc 0.0 0.0 0.0 0.0 0 0 0 0 0 0 $34.34 Professional I L. Mueller 0.0 0.0 0.0 0.0 0 0 0 0 0 0 $42.10 Professional II M. Blanton 16.0 16.0 0.0 0.0 0 0 0 0 0 0 $24.04 Professional I M. Wines 66 0.0 36.0 30.0 0 0 0 0 0 0

$0.00 Senior Support Services 0 0.0 0.0 0.0 0 0 0 0 0 0 $0.00 0 0.0 0.0 0.0 0 0 0 0 0 0 $0.00 0 0.0 0.0 0.0 0 0 0 0 0 0 $0.00 0 0.0 0.0 0.0 0 0 0 0 0 0 $0.00 0 0.0 0.0 0.0 0 0 0 0 0 0 $0.00 0 0.0 0.0 0.0 0 0 0 0 0 0 $0.00 0 0.0 0.0 0.0 0 0 0 0 0 0 $0.00 0 0.0 0.0 0.0 0 0 0 0 0 0 $0.00 0 0.0 0.0 0.0 0 0 0 0 0 0 $0.00 0 0.0 0.0 0.0 0 0 0 0 0 0 $0.00 0 0.0 0.0 0.0 0 0 0 0 0 0

$0.00 0 0.0 0.0 0.0 0 0 0 0 0 0 $0.00 0 0.0 0.0 0.0 0 0 0 0 0 0 $0.00 0 0.0 0.0 0.0 0 0 0 0 0 0 $0.00 0 0.0 0.0 0.0 0 0 0 0 0 0 $0.00 0 0.0 0.0 0.0 0 0 0 0 0 0

Total Hours -19.8 -4.3 0.0 -15.5 0.0 0 0 0 0 0 0

Direct Labor ($2,240.24) ($257.73) ($15.20) ($1,397.01) ($570.30) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Overhead 135.00% ($3,024.33) ($347.94) ($20.52) ($1,885.96) ($769.91) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 37.70% ($844.56) ($97.16) ($5.73) ($526.67) ($215.00) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor ($6,109.13) ($702.83) ($41.45) ($3,809.64) ($1,555.21) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Operation and Maintenance

PetersonCleaners_OM_Delta_HW681_DC011C T1

Task #: DC011C TACO 1 SubTask 1 Project Management SubTask 6

Site: SubTask 2 Annual Groundwater Monitoring SubTask 7

Activity/Phase: SubTask 3 Quarter 1 O&M and Optimization SubTask 8

Project Manager: Kathy Leggoe, PMP SubTask 4 Quarter 2 O&M and Optimization SubTask 9

SubTask 5 Utilities SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10

Operation and Maintenance

Petersons Cleaners

Travel Vehicle Rental ($120.00) $0.00 ($120.00) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel ($120.00) $0.00 ($120.00) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 IDW - Erwin $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Laboratory Analytical Costs ($200.00) $0.00 ($200.00) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping ($110.00) $0.00 ($110.00) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory ($310.00) $0.00 ($310.00) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables ($40.00) $0.00 ($40.00) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drum $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) ($435.00) $0.00 ($435.00) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses ($475.00) $0.00 ($475.00) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subtotal ($7,014.13) ($702.83) ($41.45) ($4,714.64) ($1,555.21) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee ($610.91) ($70.28) ($4.15) ($380.96) ($155.52) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Estimated Cost ($7,625.04) ($773.11) ($45.60) ($5,095.60) ($1,710.73) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

PetersonCleaners_OM_Delta_HW681_DC011C T1

SUBTASK: Annual Groundwater Monitoring

DATE: 5/3/2024

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Project Technical Lead S. Cobert Interpretation of Lab Data Eval 0

Project Manager K. Leggoe Prepare Field Scope of Work 0 Preparation of Data Summary 0

Professional II K. Turner Mobilization/Demobilization -4 Field Preparation 0 Arrange for Site Access with Owner 0 Prepare Sample Kit Request 0 Update HASP 0 Sample Monitoring Wells -12 Preparation of Data Summary 0

Professional II M. Blanton Mobilization/Demobilization 4 Sample Monitoring Wells 12

Professional I J. LeBlanc Data Tabulation/Data Package Preparation 0

Total Hours:

S.Cobert 0 K. Leggoe 0 K. Turner -16 M. Blanton 16 J. LeBlanc 0

TOTAL LABOR 0

VEHICLE TYPE RATE UNIT USEAGE

Truck $120.00 day 0 $0.00

TOTAL VEHICLE $0.00

PER DIEM STAFF RATE UNIT USEAGE

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE UNIT COST

disposal of 1 drum in Subtask 4 $0.00

TOTAL $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

EPA Method 8260 (VOHs) $73.00 0 $0.00 Shipping $150.00 0 $0.00 Ice $6.50 0 $0.00

TOTAL LAB $0.00

FIELD EXPENSES ITEM RATE COSTING UNIT USEAGE TOTALS

$0.00 Expendables $40.00 day 0 $0.00 Drum $100.00 each 0 $0.00 HDPE Tubing $0.30 foot 0 $0.00 Silicon Tubing (1/4") $3.00 foot 0 $0.00 Groundwater Sampling Kit $290.00 day 0 $0.00

TOTAL EQUIPMENT $0.00

SUBTASK: Quarter 1 O&M and Optimization

DATE: 5/3/2024

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Project Technical Lead S. Cobert Interpretation of O&M Data Eval (4 events) -1

Project Manager K. Leggoe Field Correspondance (4 events) -1

Professional II K. Turner Mobilization/Demobilization (4 trips) -8 Field Preparation (4 events) -1 Arrange for Site Access with Owner (4 events) -0.5 Prepare Sample Kit Request 0 O&M Activities (4 events) -32 Documentation of O&M Activities (4 events) -8

Professional I M. Wines Mobilization/Demobilization (3 trips) 6 O&M Activities (3 events) 24 Documentation of O&M Activities (3 events) 6

Professional I J. LeBlanc Data Tabulation/Data Package Preparation 0

Total Hours:

S.Cobert -1 K. Leggoe -1 K. Turner -49.5 M. Wines 36 J. LeBlanc 0

-15.5

TOTAL LABOR -15.5

VEHICLE TYPE RATE UNIT USEAGE

Truck $120.00 day -1 ($120.00)

TOTAL VEHICLE ($120.00)

PER DIEM STAFF RATE UNIT USEAGE

$0.00

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE UNIT COST

TOTAL $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

EPA Method TO-15 (VOHs) $200.00 -1 ($200.00) Small Cooler/Shipping $110.00 -1 ($110.00)

TOTAL LAB ($310.00)

FIELD EXPENSES ITEM RATE COSTING UNIT USEAGE TOTALS

Expendables $40.00 day -1 ($40.00) $0.00

Construction/O&M/Pilot Kit $360.00 foot -1 ($360.00) Construction/O&M Supplies $75.00 each -1 ($75.00)

TOTAL EQUIPMENT ($475.00)

SUBTASK: Quarter 2 O&M and Optimization

DATE: 5/3/2024

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Project Technical Lead S. Cobert Data interpretation/PE Review (3 events/RASR) 0

Project Manager K. Leggoe Field Correspondence (3 events) 0

Professional II K. Turner Mobilization/Demobilization (3 trips) -6 Field Preparation (3 events) 0 Arrange for Site Access with Owner (3 events) 0 Prepare Sample Kit Request 0 O&M Activities (3 events) -24 Remedial Action Status Report Preparation 0

Professional I M. Wines Mobilization/Demobilization (3 trips) 6 O&M Activities (3 events) 24

Professional I J. LeBlanc Remedial Action Status Report Preparation - Data Tabulation/Data Package Preparation 0

Professional I L. Mueller Figures 0

Total Hours:

S.Cobert 0 K. Leggoe 0 K. Turner -30 M. Wines 30 J. LeBlanc 0 L. Mueller 0

TOTAL LABOR 0

VEHICLE TYPE RATE UNIT USEAGE

Truck $120.00 day 0 $0.00

TOTAL VEHICLE $0.00

PER DIEM STAFF RATE UNIT USEAGE

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE UNIT COST

Erwin Remediation IDW Disposal Drum $0.00 $0.00

TOTAL $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

EPA Method TO-15 (VOHs) $200.00 0 $0.00 Small Cooler/Shipping $110.00 0 $0.00

TOTAL LAB $0.00

FIELD EXPENSES ITEM RATE COSTING UNIT USEAGE TOTALS

Expendables $40.00 day 0 $0.00

Construction/O&M/Pilot Kit $360.00 foot 0 $0.00 Construction/O&M Supplies $75.00 each 0 $0.00

TOTAL EQUIPMENT $0.00

Date: 11/9/2023

Task #: SubTask 1 Project Management SubTask 6

Site: SubTask 2 Annual Groundwater Monitoring SubTask 7

Activity/Phase: SubTask 3 Quarter 1 O&M and Optimization SubTask 8

Project Manager: Kathy Leggoe, PMP SubTask 4 Quarter 2 O&M and Optimization SubTask 9

SubTask 5 Utilities SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10 Labor Rate Category

$60.10 Project Manager K. leggoe 16.7 16.7 $0.00 Senior Officer 0 0 0 0 0 0 0 0 0 0

$71.37 Senior Technical Expert S Cobert 12.0 2.0 4.0 6.0 0 0 0 0 0 0 $60.10 Project Manager K. leggoe 9.0 2.0 4.0 3.0 0 0 0 0 0 0

$0.00 0.0 0.0 0.0 0.0 0 0 0 0 0 0 $43.05 Professional II K. Turner 132.0 22.0 56.0 54.0 0 0 0 0 0 0 $28.17 Professional I J. LeBlanc 15.0 4.0 5.0 6.0 0 0 0 0 0 0 $34.34 Professional I L. Mueller 6.0 0.0 0.0 6.0 0 0 0 0 0 0

$0.00 Professional II 0.0 0.0 0.0 0.0 0 0 0 0 0 0 $0.00 Project Administration 0 0.0 0.0 0.0 0 0 0 0 0 0 $0.00 Senior Support Services 0 0.0 0.0 0.0 0 0 0 0 0 0 $0.00 0 0.0 0.0 0.0 0 0 0 0 0 0 $0.00 0 0.0 0.0 0.0 0 0 0 0 0 0 $0.00 0 0.0 0.0 0.0 0 0 0 0 0 0 $0.00 0 0.0 0.0 0.0 0 0 0 0 0 0 $0.00 0 0.0 0.0 0.0 0 0 0 0 0 0 $0.00 0 0.0 0.0 0.0 0 0 0 0 0 0 $0.00 0 0.0 0.0 0.0 0 0 0 0 0 0 $0.00 0 0.0 0.0 0.0 0 0 0 0 0 0 $0.00 0 0.0 0.0 0.0 0 0 0 0 0 0 $0.00 0 0.0 0.0 0.0 0 0 0 0 0 0

$0.00 0 0.0 0.0 0.0 0 0 0 0 0 0 $0.00 0 0.0 0.0 0.0 0 0 0 0 0 0 $0.00 0 0.0 0.0 0.0 0 0 0 0 0 0 $0.00 0 0.0 0.0 0.0 0 0 0 0 0 0 $0.00 0 0.0 0.0 0.0 0 0 0 0 0 0

Total Hours 190.7 16.7 30.0 69.0 75.0 0 0 0 0 0 0

Direct Labor $8,710.64 $1,002.11 $1,322.72 $3,077.53 $3,308.28 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Overhead 135.00% $11,759.37 $1,352.85 $1,785.67 $4,154.67 $4,466.18 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fringe 37.70% $3,283.92 $377.80 $498.67 $1,160.23 $1,247.22 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Labor $23,753.93 $2,732.76 $3,607.06 $8,392.43 $9,021.68 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Operation and Maintenance

PetersonCleaners_OM_Original_HW681_DC011C T1

Date: 11/9/2023

Task #: SubTask 1 Project Management SubTask 6

Site: SubTask 2 Annual Groundwater Monitoring SubTask 7

Activity/Phase: SubTask 3 Quarter 1 O&M and Optimization SubTask 8

Project Manager: Kathy Leggoe, PMP SubTask 4 Quarter 2 O&M and Optimization SubTask 9

SubTask 5 Utilities SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10

Operation and Maintenance

Petersons Cleaners

Travel Vehicle Rental $960.00 $120.00 $480.00 $360.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Travel $960.00 $120.00 $480.00 $360.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement) Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 IDW - Erwin $125.00 $0.00 $0.00 $125.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Utilities $5,040.00 $0.00 $0.00 $0.00 $5,040.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $5,165.00 $0.00 $0.00 $125.00 $5,040.00 $0.00 $0.00 $0.00 $0.00 $0.00 Handling Fee $12.50 $0.00 $0.00 $12.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Subcontractor Cost $5,177.50 $0.00 $0.00 $137.50 $5,040.00 $0.00 $0.00 $0.00 $0.00 $0.00

Laboratory Analytical Costs $1,184.00 $584.00 $400.00 $200.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Sample Shipping $486.50 $156.50 $220.00 $110.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Laboratory $1,670.50 $740.50 $620.00 $310.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Field Expenses Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Expendables $320.00 $40.00 $160.00 $120.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Drum $100.00 $100.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Analytical related) $3,464.00 $419.00 $1,740.00 $1,305.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 Total Field Expenses $3,884.00 $559.00 $1,900.00 $1,425.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subtotal $35,445.93 $2,732.76 $5,026.56 $11,392.43 $11,254.18 $5,040.00 $0.00 $0.00 $0.00 $0.00 $0.00 Completion Fee $2,375.40 $273.28 $360.71 $839.24 $902.17 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Estimated Cost $37,821.33 $3,006.04 $5,387.27 $12,231.67 $12,156.35 $5,040.00 $0.00 $0.00 $0.00 $0.00 $0.00

PetersonCleaners_OM_Original_HW681_DC011C T1

From: Leggoe, Kathy R.

To: Aoki, Benjamin Cc: Fincham, Kara E.; Grubbs, Benjamin Subject: Peterson Cleaners DC011C TACO1 Date: Friday, May 3, 2024 4:50:05 PM Attachments: PetersonCleaners_OM_Original_HW681_DC011C T1.xlsx

PetersonCleaners_OM_Delta_HW681_DC011C T1.xlsx PetersonCleaners_OM_Final_HW681_DC011C T1.xlsx

EXTERNAL MESSAGE

This email originated outside of DEP. Please use caution when opening attachments, clicking links, or responding to this email.

Please find the TACO for Peterson Cleaners DC011C attached. This TACO will be needed to approve Subtask 2 and 3 deliverables for invoicing.

The changes are as follows:

ST 2: Switch field staff from KT to MB.

ST 3: Reduced from 4 to 3 O&M events. The planned extra month (December 2023) had already passed by the time the TA was executed. This includes a ¼ labor reduction for PM, PTL, Pro II etc.., a ¼ reduction for truck/field expenses, removed 1 SV sample and shipping, replaced KT with MW for fieldwork/documentation for 3 events.

ST 4: Switched field staff from KT to MW ST 5: No changes (utilities)

Very Respectfully, Kathy R. Leggoe, PG, PMP Geologist Project Manager CDM Smith 4651 Salisbury Road, Suite 420 Jacksonville, Florida 32256 (office) 904.527.6727, (cell) 904.651.0740 cdmsmith.com mailto:leggoekr@cdmsmith.com mailto:Benjamin.Aoki@FloridaDEP.gov mailto:finchamke@cdmsmith.com mailto:Benjamin.Grubbs@FloridaDEP.gov http://secure-web.cisco.com/1MSahjFQ5LR_cecwmqh2JPla4tT52zOoLtlLBqHNmIQz2oyNUHgf1HibFeJfnx9qhYjFQST-B3KlhnSRoflTA1WtIfu_U4mSkQ-FBhMuJwS-J36eFkTuh8yMYdt8u11W1l2QP3pH9Bsy858Q672hszVDO5Y20yKaFltj6cU5WUeMGrcKOvaA5wAj_qUN_gNNrDmLL1AL1lp7jCTWRbl2Lt2RcWfNw6hjle2YTkit_IZYrzsFkQqdMg5yK5xaTvHnB9bnMtglv24xAIFGe3Mk0okrEs-1f7VB_lPDZvY3SwmaSiKkGCu85vlcw_bum0TfV/http%3A%2F%2Fwww.cdmsmith.com%2F https://secure-web.cisco.com/1oampsHkCne3ZpBh3Zo4pVQ_a4cwyiwxjEOn7tBwB2u65-yQj7wAG3Kxz0R9RZF8Ok7NLn6hGEBNCq47yQVTiBqDYdH_4upbTxUpclQttrOEirJ0RPIVGg62-Xu6Rr4a4AzSVMOJvX-XGwsStIO01q1LhdEY2mdzJ_tVnFfLDS3m5fqMfY-2uYba4q5Vpljw9F4B3a3x6OwAW6KvjZKTQmByxzUZaGjrEW34t63tA4GbrsISxc-NJ1vkj21lcNCn95UqDacfmYB2xI-nb5GWHzvT-DL12w6CXIlBRI3spqGDQoB6VrwuI2A9riEhKf2Qp/https%3A%2F%2Fwww.facebook.com%2FCDMSmith%2F https://secure-web.cisco.com/1jxnB6dGvk2glvH5Iid5EUTAz8P8Fa9hmQVYB2P249qURWoCY6Ccim1do19fsFewWsmSUmcaS852NoS8il_VYL1UqrVPIiK82eXBB6BJlBp0AZxHnWU1KVKx4WGT30PhAkQAzQdKkBnjlVsHoxJf195Q_iBqDBv3WLyhmGfITdfh-VgvMwWsscJM0iuDvXkprc_3JJvSYOW97k25d7k-B4mAK0l-Z5Tm-5F0TbEOizihd72JcgzGB5boAsrah4k9xXzVVwl3_3b7KDjf9NYa61Azejey3V6YU8ytKJ-u1BmZyo0WWzlfrakkbaC1XNk9J/https%3A%2F%2Ftwitter.com%2FCDMSmith https://secure-web.cisco.com/1p3z1DPuDNKHRu2gJjt8SaGUug_QWhwMxwSr6gzxLObh-1EJ6v6OmFGmk06QmgoRYmyn4dHqdiz6wUdtJianOGMxKS3lkDLixhWlVBOBTChkT25HE0w-lZKJYtKen4ZGLWd1gBMq9X-apXVh8JhIJpZIeeU8FX0-hWn3AkXNbKq9qOFZByKxhbntQFr1DTIU8NhIvi2aVEkeMmIEvhgBULwLGYEyKIIcJjbEjgdX-DUOX0iTaumvZp8NqSGNiFZyp56xF3utEyiqEVaxrIgOGDQE9RwWwV6dNUBwGbBxahjQZfiFtQvnSEqky1RKQT_OQ/https%3A%2F%2Fwww.instagram.com%2Fcdmsmith%2F%3Fhl%3Den https://secure-web.cisco.com/1waayNDtdSWmsYplw0WXt3SeAARi8ojflX_9nKQWfCP27HLffnpaitt1Q0bBbUohI3QyVubyYmuDe2lUZ5W_QXmhO9VUepUWpyAXaVQfUaQ1rm77MqsOFsqF6mcC4KpSkvYZ5_7u3j2rHxs8o4Pj0b-RBna832a0zswhOthYahvYDcqLQ3gQx2wl0xmPdMvfpy4dgP6jW9Ydion2Njg_SoO_ed6VeZWxh56aw1GtWLQIZXsoQozHmHFdlOzhV6hJ956z4cXo5paqgCfHCK6ImP-834U7HLv1DjNnJ2KtUyCkJT0w1ovrGVnrsW2t6Yo-G/https%3A%2F%2Fwww.linkedin.com%2Fcompany%2Fcdmsmith%2F https://secure-web.cisco.com/1SUzbb7fEuAAHQWBbAKq1C7Upu8giJXkB_i5X4n9zTTBLqycvMcO60fYqd22PBbX9DvPsZtEGU0I7YoziioPBKAnOuT7aDv20av2wnC89Z-yqk11380uFvMqlARvZubyLAc7MMDmmJsTfEvegplz5GR-6BA_B_4lC6IC7JPmV9A-lCLfiiim2aLTRAOujHa5mgbrvxprtn2bP6B4g0XHU727nqk7wqxXGqa65aDZSeyGOtLHvnI0ea3JktCGo8IfTIAgfmuEDZZNu4FaJ2UOejx9M30wjhgF4Q7ECdmBDIZutmfeLXK8YBbiWMpcbxM0Q/https%3A%2F%2Fwww.youtube.com%2Fuser%2FCDMSmith

Cost Estimate

Contractor: CDM Smith, Inc.

Date: 11/9/23

Task #: SubTask 1 Project Management SubTask 6

Site: Petersons Cleaners SubTask 2 Annual Groundwater Monitoring SubTask 7

Activity/Phase: Operation and Maintenance SubTask 3 Quarter 1 O&M and Optimization SubTask 8

Project Manager: Kathy Leggoe, PMP SubTask 4 Quarter 2 O&M and Optimization SubTask 9

SubTask 5 Utilities SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10

Labor Rate Category

$60.10 Project Manager K. leggoe 16.7 16.7

$0.00 Senior Officer 0 0 0 0 0 0 0 0 0 0

$71.37 Senior Technical Expert S Cobert 12.0 2.0 4.0 6.0 0 0 0 0 0 0

$60.10 Project Manager K. leggoe 9.0 2.0 4.0 3.0 0 0 0 0 0 0

$0.00 0.0 0.0 0.0 0.0 0 0 0 0 0 0

$43.05 Professional II K. Turner 132.0 22.0 56.0 54.0 0 0 0 0 0 0

$28.17 Professional I J. LeBlanc 15.0 4.0 5.0 6.0 0 0 0 0 0 0

$34.34 Professional I L. Mueller 6.0 0.0 0.0 6.0 0 0 0 0 0 0

$0.00 Professional II 0.0 0.0 0.0 0.0 0 0 0 0 0 0

$0.00 Project Administration 0 0.0 0.0 0.0 0 0 0 0 0 0

$0.00 Senior Support Services 0 0.0 0.0 0.0 0 0 0 0 0 0

$0.00 0 0.0 0.0 0.0 0 0 0 0 0 0

$0.00 0 0.0 0.0 0.0 0 0 0 0 0 0

$0.00 0 0.0 0.0 0.0 0 0 0 0 0 0

$0.00 0 0.0 0.0 0.0 0 0 0 0 0 0

$0.00 0 0.0 0.0 0.0 0 0 0 0 0 0

$0.00 0 0.0 0.0 0.0 0 0 0 0 0 0

$0.00 0 0.0 0.0 0.0 0 0 0 0 0 0

$0.00 0 0.0 0.0 0.0 0 0 0 0 0 0

$0.00 0 0.0 0.0 0.0 0 0 0 0 0 0

$0.00 0 0.0 0.0 0.0 0 0 0 0 0 0

$0.00 0 0.0 0.0 0.0 0 0 0 0 0 0

$0.00 0 0.0 0.0 0.0 0 0 0 0 0 0

$0.00 0 0.0 0.0 0.0 0 0 0 0 0 0

$0.00 0 0.0 0.0 0.0 0 0 0 0 0 0

$0.00 0 0.0 0.0 0.0 0 0 0 0 0 0

Total Hours 190.7 16.7 30.0 69.0 75.0 0 0 0 0 0 0

Direct Labor $8,710.64 $1,002.11 $1,322.72 $3,077.53 $3,308.28 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Overhead 135.00% $11,759.37 $1,352.85 $1,785.67 $4,154.67 $4,466.18 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Fringe 37.70% $3,283.92 $377.80 $498.67 $1,160.23 $1,247.22 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Labor $23,753.93 $2,732.76 $3,607.06 $8,392.43 $9,021.68 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Travel

Vehicle Rental $960.00 $120.00 $480.00 $360.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Mileage Costs $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Air Fare $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Per diem + Hotel $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Travel $960.00 $120.00 $480.00 $360.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Equipment Procurement)

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Procurement Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Subcontractor Cost $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor (Services Procurement)

Drilling (Conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Drilling (Non-conventional) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Mobile Laboratory $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Surveying $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

IDW - Erwin $125.00 $0.00 $0.00 $125.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Utilities $5,040.00 $0.00 $0.00 $0.00 $5,040.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor Subtotal $5,165.00 $0.00 $0.00 $125.00 $5,040.00 $0.00 $0.00 $0.00 $0.00 $0.00

Handling Fee $12.50 $0.00 $0.00 $12.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Subcontractor Cost $5,177.50 $0.00 $0.00 $137.50 $5,040.00 $0.00 $0.00 $0.00 $0.00 $0.00

Laboratory

Analytical Costs $1,184.00 $584.00 $400.00 $200.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Fast Turnaround Charges $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Sample Shipping $486.50 $156.50 $220.00 $110.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Laboratory $1,670.50 $740.50 $620.00 $310.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Field Expenses

Personal Protection $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Expendables $320.00 $40.00 $160.00 $120.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Drum $100.00 $100.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Equipment (Analytical related) $3,464.00 $419.00 $1,740.00 $1,305.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Equipment (IDW related) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Equipment (Other) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Field Expenses $3,884.00 $559.00 $1,900.00 $1,425.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subtotal $35,445.93 $2,732.76 $5,026.56 $11,392.43 $11,254.18 $5,040.00 $0.00 $0.00 $0.00 $0.00 $0.00

Completion Fee $2,375.40 $273.28 $360.71 $839.24 $902.17 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Estimated Cost $37,821.33 $3,006.04 $5,387.27 $12,231.67 $12,156.35 $5,040.00 $0.00 $0.00 $0.00 $0.00 $0.00

&"CG Times,Bold"&16FDEP COST ESTIMATE

LOE WORKSHEET_Subtask 2

SITE : Petersons Cleaners

SUBTASK: Annual Groundwater Monitoring

DATE: 11/9/23

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Project Technical Lead S. Cobert Interpretation of Lab Data Eval 2

Project Manager K. Leggoe Prepare Field Scope of Work 1

Preparation of Data Summary 1

Professional II K. Turner Mobilization/Demobilization 4

Field Preparation 1

Arrange for Site Access with Owner 1

Prepare Sample Kit Request 1

Update HASP 1

Sample Monitoring Wells 12

Preparation of Data Summary 2

Professional I J. LeBlanc Data Tabulation/Data Package Preparation 4

Total Hours:

S.Cobert 2

K. Leggoe 2

K. Turner 22

J. LeBlanc 4

TOTAL LABOR 30

VEHICLE TYPE RATE UNIT USEAGE

Truck $120.00 day 1 $120.00

TOTAL VEHICLE $120.00

PER DIEM STAFF RATE UNIT USEAGE

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE UNIT COST

disposal of 1 drum in Subtask 4 $0.00

TOTAL $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

EPA Method 8260 (VOHs) $73.00 8 $584.00

Shipping $150.00 1 $150.00

Ice $6.50 1 $6.50

TOTAL LAB $740.50

FIELD EXPENSES ITEM RATE COSTING UNIT USEAGE TOTALS

$0.00

Expendables $40.00 day 1 $40.00

Drum $100.00 each 1 $100.00

HDPE Tubing $0.30 foot 350 $105.00

Silicon Tubing (1/4") $3.00 foot 8 $24.00

Groundwater Sampling Kit $290.00 day 1 $290.00

TOTAL EQUIPMENT $559.00

&"Times New Roman,Regular"&12LEVEL OF EFFORT/EXPENSE WORKSHEET

Page &P

LOE WORKSHEET_Subtask 3

SITE : Petersons Cleaners

SUBTASK: Quarter 1 O&M and Optimization

DATE: 11/9/23

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Project Technical Lead S. Cobert Interpretation of O&M Data Eval (4 events) 4

Project Manager K. Leggoe Field Correspondance (4 events) 4

Professional II K. Turner Mobilization/Demobilization (4 trips) 8

Field Preparation (4 events) 4

Arrange for Site Access with Owner (4 events) 2

Prepare Sample Kit Request 2

O&M Activities (4 events) 32

Documentation of O&M Activities (4 events) 8

Professional I J. LeBlanc Data Tabulation/Data Package Preparation 5

Total Hours:

S.Cobert 4

K. Leggoe 4

K. Turner 56

J. LeBlanc 5

TOTAL LABOR 69

VEHICLE TYPE RATE UNIT USEAGE

Truck $120.00 day 4 $480.00

TOTAL VEHICLE $480.00

PER DIEM STAFF RATE UNIT USEAGE

$0.00

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE UNIT COST

TOTAL $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

EPA Method TO-15 (VOHs) $200.00 2 $400.00

Small Cooler/Shipping $110.00 2 $220.00

TOTAL LAB $620.00

FIELD EXPENSES ITEM RATE COSTING UNIT USEAGE TOTALS

Expendables $40.00 day 4 $160.00

$0.00

Construction/O&M/Pilot Kit $360.00 foot 4 $1,440.00

Construction/O&M Supplies $75.00 each 4 $300.00

TOTAL EQUIPMENT $1,900.00

&"Times New Roman,Regular"&12LEVEL OF EFFORT/EXPENSE WORKSHEET

Page &P

LOE WORKSHEET_Subtask 4

SITE : Petersons Cleaners

SUBTASK: Quarter 2 O&M and Optimization

DATE: 11/9/23

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

Project Technical Lead S. Cobert Data interpretation/PE Review (3 events/RASR) 6

Project Manager K. Leggoe Field Correspondence (3 events) 3

Professional II K. Turner Mobilization/Demobilization (3 trips) 6

Field Preparation (3 events) 2

Arrange for Site Access with Owner (3 events) 1

Prepare Sample Kit Request 1

O&M Activities (3 events) 24

Remedial Action Status Report Preparation 20

Professional I J. LeBlanc Remedial Action Status Report Preparation - Data Tabulation/Data Package Preparation 6

Professional I L. Mueller Figures 6

Total Hours:

S.Cobert 6

K. Leggoe 3

K. Turner 54

J. LeBlanc 6

L. Mueller 6

TOTAL LABOR 75

VEHICLE TYPE RATE UNIT USEAGE

Truck $120.00 day 3 $360.00

TOTAL VEHICLE $360.00

PER DIEM STAFF RATE UNIT USEAGE

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE UNIT COST

Erwin Remediation IDW Disposal Drum $125.00 $125.00

TOTAL $125.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

EPA Method TO-15 (VOHs) $200.00 1 $200.00

Small Cooler/Shipping $110.00 1 $110.00

TOTAL LAB $310.00

FIELD EXPENSES ITEM RATE COSTING UNIT USEAGE TOTALS

Expendables $40.00 day 3 $120.00

Construction/O&M/Pilot Kit $360.00 foot 3 $1,080.00

Construction/O&M Supplies $75.00 each 3 $225.00

TOTAL EQUIPMENT $1,425.00

&"Times New Roman,Regular"&12LEVEL OF EFFORT/EXPENSE WORKSHEET

Page &P

LOE WORKSHEET_Subtask 5

SITE : Peterson's Dry Cleaners

SUBTASK: Utilities

DATE: 11/9/23

LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON

STAFF-TITLE WORK DESCRIPTION HOURS

TOTAL LABOR 0

VEHICLE TYPE RATE UNIT USEAGE

TOTAL VEHICLE $0.00

PER DIEM STAFF RATE UNIT USEAGE

TOTAL PER DIEM $0.00

SUBCONTRACTOR COSTS

NAME PURPOSE UNIT COST

TOTAL $0.00

LABORATORY COSTS

PARAMETER RATE # SAMPLES #QAQC

TOTAL LAB $0.00

FIELD EXPENSES ITEM RATE COSTING UNIT USEAGE TOTALS

Quarter 1 Utilities Utility Charges (Electric) $700.00 month 4 $2,800.00

Quarter 1 Handling Fee Utility Handling Fee $20.00 month 4 $80.00

Quarter 2 Utilities Utility Charges (Electric) $700.00 month 3 $2,100.00

Quarter 2 Handling Fee Utility Handling Fee $20.00 month 3 $60.00

TOTAL EQUIPMENT $5,040.00

&"Times New Roman,Regular"&12LEVEL OF EFFORT/EXPENSE WORKSHEET

Page &P

Formula Sheet

Project Management

Subtask 1 Subtask 2 Subtask 3 Subtask 4 Subtask 5 Subtask 6 Subtask 7 Subtask 8 Subtask 9 Subtask 10

Labor Costs $1,003.67 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$142.74 $285.48 $428.22 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$120.20 $240.40 $180.30 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$947.10 $2,410.80 $2,324.70 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$112.68 $140.85 $169.02 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $206.04 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 total labor dollars $1,003.67 $1,322.72 $3,077.53 $3,308.28 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Project Management $7,708.53 = sum of Direct Labor Costs from Subtasks 2 through 10

$1,002.11 =13% of Direct Labor Costs (Project Management)

16.674 = Hours of Project Management (based on hourly salary of the Contractor Project Manager)

Subcontractor $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Handling Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Subcontractor $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Service Fee $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $12.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Utilities $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

$0.00 $0.00 $12.50 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Contractor: CDM Smith, Inc.

Date: 5/3/24

Task #: DC011C TACO 1 SubTask 1 Project Management SubTask 6

Site: Petersons Cleaners SubTask 2 Annual Groundwater Monitoring SubTask 7

Activity/Phase: Operation and Maintenance SubTask 3 Quarter 1 O&M and Optimization SubTask 8

Project Manager: Kathy Leggoe, PMP SubTask 4 Quarter 2 O&M and Optimization SubTask 9

SubTask 5 Utilities SubTask 10

Totals 1 2 3 4 5 6 7 8 9 10

Labor Rate Category

$60.10 Project Manager K. leggoe -4.3 -4.3

$0.00 Senior Officer 0 0 0 0 0 0 0 0 0 0

$71.37 Senior Technical Expert S Cobert -1.0 0.0 -1.0 0.0 0 0 0 0 0 0

$60.10 Project Manager K. leggoe -1.0 0.0 -1.0 0.0 0 0 0 0 0 0

$0.00 0.0 0.0 0.0 0.0 0 0 0 0 0 0

$43.05 Professional II K. Turner -95.5 -16.0 -49.5 -30.0 0 0 0 0 0 0

$28.17 Professional I J. LeBlanc 0.0 0.0 0.0 0.0 0 0 0 0 0 0

$34.34 Professional I L. Mueller 0.0 0.0 0.0 0.0 0 0 0 0 0 0

$42.10 Professional II M. Blanton 16.0 16.0 0.0 0.0 0 0 0 0 0 0

$24.04 Professional I M. Wines 66 0.0 36.0 30.0 0 0 0 0 0 0

$0.00 Senior Support Services 0 0.0 0.0 0.0 0 0 0 0 0 0

$0.00 0 0.0 0.0 0.0 0 0 0 0 0 0

$0.00 0 0.0 0.0 0.0 0 0 0 0 0 0

$0.00 0 0.0 0.0 0.0 0 0 0 0 0 0

$0.00 0 0.0 0.0 0.0 0 0 0 0 0 0

$0.00 0 0.0 0.0 0.0 0 0 0 0 0 0

$0.00 0 0.0 0.0 0.0 0 0 0 0 0 0

$0.00 0 0.0 0.0 0.0 0 0 0 0 0 0

$0.00 0 0.0 0.0 0.0 0 0 0 0 0 0

$0.00 0 0.0 0.0 0.0 0 0 0 0 0 0

$0.00 0 0.0 0.0 0.0 0 0 0 0 0 0

$0.00 0 0.0 0.0 0.0 0 0 0 0 0 0

$0.00 0 0.0 0.0 0.0 0 0 0 0 0 0

$0.00 0 0.0 0.0 0.0 0 0 0 0 0 0

$0.00 0 0.0 0.0 0.0 0 0 0 0 0 0

$0.00 0 0.0 0.0 0.0 0 0 0 0 0 0

Total Hours -19.8 -4.3 0.0 -15.5 0.0 0 0 0 0 0 0

Direct Labor ($2,240.24) ($257.73) ($15.20) ($1,397.01) ($570.30) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Overhead 135.00% ($3,024.33) ($347.94) ($20.52) ($1,885.96) ($769.91) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Gen & Admin 0.00% $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Fringe 37.70% ($844.56) ($97.16) ($5.73) ($526.67) ($215.00) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Total Labor ($6,109.13) ($702.83) ($41.45) ($3,809.64) ($1,555.21) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Travel

Vehicle Rental ($120.00) $0.00 ($120.00) $0.00 $0.00 $0.00 $0.00 $0.00 $0.00 $0.00

Mileage Costs…

This is the start of the file's text. The full file is on GovTribe.

File details come from the government source that posted it. Updated .