This document is a Task Assignment (TA) executed between the State of Florida Department of Environmental Protection (FDEP) and CDM Smith Inc. under Contract Number HW681. The Task Assignment, designated as DC040C with an effective date of December 1, 2024, authorizes CDM Smith to conduct vapor extraction well (VEW) abandonment services at the Golden Touch Cleaners, Inc. facility located at 4034 Little Road, New Port Richey, Pasco County, Florida. The project is identified under FDEP project number ERIC_5242. Key personnel include Benjamin Aoki as the Department Project Manager and Kara Fincham as the Contractor's Project Manager.
The contract authorizes CDM Smith to properly abandon six (6) vapor extraction wells with a licensed Florida Water Well Contractor, including removal of flush-mounted 5" manhole (interior)/8" manhole (exterior) and 2" diameter PVC well casings, with all boreholes grouted properly and restored to preexisting conditions using asphalt or concrete patches. The total contract value is $5,794.58 on a fixed unit rate basis, comprised of 19 total labor hours ($0 rate shown in documents but calculated at 13% project management overhead), $120.00 vehicle costs, $1,500.00 in subcontractor drilling costs from Environmental Drilling Service, and $475.00 in equipment and expendable supplies. The primary deliverable, due October 1, 2024, consists of field documentation, paid invoices to subcontractors, and a technical memorandum. Subcontractor bids received from Environmental Drilling Service ($1,500.00), Groundwater Protection ($1,590.00), and Preferred Drilling Solutions ($1,590.00) were evaluated, with Environmental Drilling Service selected as the lowest responsive bidder.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Funding Information:
Org. Code E.O.
Object Code
Budget Entity Appropriation
Category Grant # Project # Year Amount
Additional Funding Information attached on separate page.
Rev. 8/26/2020
STATE OF FLORIDA
DEPARTMENT OF ENVIRONMENTAL PROTECTION
Task Assignment This Task Assignment (TA) is entered into between the Parties named below, pursuant to Contract Number: .
1. TA Number: TA Completion Date:
TA Description:
2. Parties State of Florida Department of Environmental Protection (Department)
Department Project Manager: Department Project Manager Phone:
Contractor Name: (Contractor ) ntractor’st ’s Project Manager: ontractor’s t’s Project Manager Phone:
3. Project Number:
(If different from TA Number)
Project Location(s):
Project Name:
4. As consideration for the services rendered by Contractor under the terms of this TA, the Department shall pay the Contractor on the following bases, up to the Total TA Value as indicated below:
Fixed Price:
Fixed Unit Rate: (Extended Price)
Cost Reimbursement:
Total TA Value:
5. The Parties agree to comply with the terms and conditions of the underlying the Contract, and the following attachments which are hereby incorporated by reference:
Attachment 1:
Additional Attachments (if necessary):
IN WITNESS WHEREOF, this TA shall be effective on the last date signed below.
State of Florida Department of Environmental Protection
CONTRACTOR Department
Name:
Title: Secretary or Designee
(Authorized Signature) (Authorized Signature)
Date:
Additional signatures attached on separate page.
HW681
DC040C December 1, 2024
This Task Assignment authorizes CDM Smith Inc. to conduct vapor extraction well
(VEW) abandonment per their proposed scope of work submitted on 13JUN2024.
Benjamin Aoki 850-245-7527 CDM Smith Inc.
Kara Fincham 904-527-6716
ERIC_5242
4034 Little Road, New Port Richey, Pasco County, FL
Golden Touch Cleaners, Inc.
$ 5,794.58
$ 5,794.58
Scope of Work
CDM Smith Inc.
Leslie Samel
CSL
Leslie Samel Digitally signed by Leslie Samel Date: 2024.06.27 20:25:47 -04'00'
Mubeen Darji
Mubeen Darji, P.E. Digitally signed by Mubeen Darji, P.E.
Date: 2024.06.24 09:40:48 -04'00'
N/A
Task Assignment Notification/Change Order Deliverables and Invoice Schedule Attachment
WC TAFORM
Contract Number:
Task Assignment #:
Deliverables:
Deliverable Deliverable Due Date
Invoice Schedule:
Requirements for Invoice Submittal Amount to be Invoiced
TOTAL COST
Ron DeSantis Governor
Jeanette Nuñez Lt. Governor
Shawn Hamilton Secretary
TO:
FROM:
DATE:
SUBJECT:
FLORIDA DEPARTMENT OF
Environmental Protection
Bob Martinez Center 2600 Blair Stone Road
Tallahassee, FL 32399-2400
P a g e
P a g e
LEVEL OF EFFORT/EXPENSE WORKSHEET
SITE : Golden Touch Cleaners SUBTASK 2: VEW Abandonment
DATE: 6/12/2024
LABOR CATEGORY *PROVIDE TIME REQUIRED FOR EACH PERSON
STAFF-TITLE WORK DESCRIPTION HOURS
Project Manager Preparation of Abandonment Memo 2
Professional II Field Preparation 1 Site Access with Owner 1 Arrange for Site Accesss with owner 1 Mobilization (1 hour each way) 2 VEW Abandonment Oversight 8 Preparation of VEW Technical Memo 4
Hours:
PM 2
Professional II 17
TOTAL LABOR 19
VEHICLE TYPE RATE UNIT USEAGE
Truck (VEW Abandonment) $120.00 Day 1 $120.00
TOTAL VEHICLE $120.00
PER DIEM STAFF RATE UNIT USEAGE
TOTAL PER DIEM $0.00
SUBCONTRACTOR COSTS
NAME PURPOSE COST
Environmental Drilling Service VEW Abandonment $1,500.00 $1,500.00
TOTAL $1,500.00
LABORATORY COSTS
PARAMETER RATE # SAMPLES #QAQC
$0.00 $0.00 $0.00 $0.00
TOTAL LAB $0.00
EQUIPMENT ITEM RATE COSTING UNIT USEAGE TOTALS
Expendables $40.00 per day 1 $40.00 Construction/O&M/Pilot Kit $360.00 each 1 $360.00 Construction/O&M Supplies $75.00 each 1 $75.00
$0.00 $0.00
TOTAL EQUIPMENT $475.00
FINAL --7/24/96
DATE: 3/20/2024
ESTIMATE #: 324039
CDM Smith
ID QTY Unit Rate TOTAL
1 1 each 800.00$ 800.00$
2 night 300.00$ -$
3 2 each 350.00$ 700.00$
4 4 each 250.00$ 1,000.00$
5 Permits: (Not Applicable for VE Wells)
Subtotal 2,500.00$
Todd Hodgson
Todd Hodgson TOTAL 2,500.00$ Partner
"Actual quantities used and days onsite will be invoiced"
PROJECT
Golden Touch Cleaners 7034 Little Road
Kyle Turner, MS, GIT
CUSTOMER
Project Description:
Tampa, Florida 33607
Locations must be accessible with track mounted DPT Rig
Damage to utilities on private property are the responsibility of the client Utility Locates on Private Property are the responsibility of the client
2" x 4.5' Exterior VEW Abandonment w/Removal w/8" BD Completion in Donut Pad w/Concrete Patch
New Port Richey, Florida 4010 W Boy Scout Blvd
(813) 262-8851 2" Well Abandonment w/Removal of Surface Complietion
(4) 2"x 4' Exterior Well Abandonment w/Removal of 8" BD Manhole in Donut Pad, Concrete Patch
(2) 2"x 4.5' Interior Well Abandonment w/Removal of 8" BD Manhole in Donut Pad, Concrete Patch
If you have any questions concerning this proposal contact Todd Hodgson at (407) 426-7885 at Todd@drillprollc.com.
DESCRIPTION
Mobilization
Per Diem - 2 Man Crew Est. (Min. Hotel Cost + $50/per man)
Completion: 1 day
2" x 4.5' Interior VEW Abandonment w/Removal w/8" BD Completion in Donut Pad w/Concrete Patch
THANK YOU FOR YOUR BUSINESS!
2300 Silver Star Road, Orlando, Florida (407) 426-7885 fax (407) 426-7586
Preferred Drilling Solutions, Inc.
8820 66th St, Pinellas Park, FL 33782
Ph: 727-561-7477 Fax: 727-561-9028 www.pdsflorida.com
Date: 3/20/24 FAC ID#: ERIC_5242
*Note: It is against PDS policy to drill in Pea Gravel. Borings in Pea Gravel will be terminated or can proceed solely at the risk of the consultant, DEP or Property Owner
Unit Unit Rate Number of Units
Extended Price
Rig Type: Auger/Mud Rotary_____
HSA Drilling & Split Spoon Collection (continuous or 5' intervals) (can be used in conjunction with well installation)
<50 foot boring depth per foot $0.00 50 foot to 100 foot boring depth per foot $0.00 >100 foot boring depth per foot $0.00
Borehole Grouting
4 - inch borehole diameter per foot $0.00 6 - inch borehole diameter per foot $0.00 8 - inch borehole diameter per foot $0.00
1" - 2" Well Installation (includes screen, riser, sand pack, seal and grout)
<50 foot boring depth per foot $0.00 50 foot to 100 foot boring depth per foot $0.00 >100 foot boring depth per foot $0.00
4" Well Installation (includes screen, riser, sand pack, seal and grout)
<50 foot boring depth per foot $0.00 50 foot to 100 foot boring depth per foot $0.00 >100 foot boring depth per foot $0.00
Double Cased Well $0.00
6" Surface Casing per foot $0.00 per well $0.00
1"- 2" Well Abandonment (includes grouting) per foot $20.00 25 $500.00
3"- 4" Well Abandonment (includes grouting) per foot $0.00
5"- 6" Well Abandonment (includes grouting) per foot $0.00
2' x 2' Well Pad Removal and Patch each $65.00 6 $390.00
Mobilization roundtrip $700.00 1 $700.00
Per Diem per crew / per night $0.00
DOT Approved 55-gal Drum each $0.00 each $0.00
$0.00
$0.00
$0.00
Standby/Delay/Difficult Access Time per hour $0.00
Additional Development Time per hour $0.00
Additional Decontamination Time per hour $0.00
TOTAL QUOTE PRICE $1,590.00
Project No.:
Signature and Title of Person Submitting Quote: _________________________________ Austin Bonacum, Estimator Date: 3/20/24
Consultant Name: CDM Smith
Site Name & Location: Golden Touch Cleaners
PROPOSED SCOPE OF WORK:
Abandon (6) 2" VEW's, total depth: 25', remove manhole ring and lid, fill with concrete
Days to Complete Scope of Work: 0.5
7034 Little Road, New Port Richey, Pasco County, FL
Well Completion (includes MH w/ cover, concrete pad, locking well cap, DRILLING
MISCELLANEOUS
Permits
CDM Smith, Golden Touch Cleaners, New Port Richey, FL (abandonment)
File details come from the government source that posted it. Updated .