About this file

This document is a Task Assignment Change Order Form issued by the Florida Department of Environmental Protection (FDEP) for Contract No. CN225, Task Assignment No. 14, Change Order No. 4. The consultant on this contract is DRMP, Inc., represented by Benjamin Lennon, P.E., with FDEP Contract Manager Jeffrey Whitfield overseeing the work. The project involves the construction of a new prefabricated restroom facility at Colt Creek State Park.

This change order represents a time extension only with no cost increase to the task assignment. The original task end date of June 30, 2021 is extended 185 days to December 31, 2021 to allow the consultant to provide construction administrative services as outlined in the original task assignment. The total task amount remains $29,351.63, with a reimbursement component of $1,000.00 and a fixed fee of $28,351.63. The extension was requested by DRMP in their proposal dated June 14, 2021 and was approved by all required FDEP representatives, including the Budget Representative, Project Manager, Contract Manager, and Contract Authority, with signatures dated June 16 and June 29, 2021.

View the file

Other files

File Type Posted
CN-370000-CN225-A1.pdf PDF
CN-370000-CN225-T10CO1.pdf PDF
CN-370000-CN225-T12.pdf PDF
CN-370000-CN225-T13.pdf PDF
CN-370000-CN225-T14.pdf PDF
CN-370000-CN225-T14CO1.pdf PDF
CN-370000-CN225-T14CO2.pdf PDF
CN-370000-CN225-T15.pdf PDF
CN-370000-CN225-T15CO3.pdf PDF
CN-370000-CN225-T15CO5.pdf PDF
CN-370000-CN225-T16.pdf PDF
CN-370000-CN225-T16CO1.pdf PDF
CN-370000-CN225-T17CO1.pdf PDF
CN-370000-CN225-T17CO2.pdf PDF
CN-370000-CN225-T18CO1.pdf PDF
CN-370000-CN225-T23.pdf PDF
CN-370000-CN225-T24CO2.pdf PDF
CN-370000-CN225-T27CO1.pdf PDF
CN-370000-CN225-T28CO1.pdf PDF
CN-370000-CN225-T32CO2.pdf PDF
CN-370000-CN225-T32CO5.pdf PDF
CN-370000-CN225-T34CO2.pdf PDF
CN-370000-CN225-T39.pdf PDF
CN-370000-CN225-T4.pdf PDF
CN-370000-CN225-T44.pdf PDF
CN-370000-CN225-T45.pdf PDF
CN-370000-CN225-T48.pdf PDF
CN-370000-CN225-T51.pdf PDF
CN-370000-CN225-T53.pdf PDF
CN-370000-CN225-T54.pdf PDF
CN-370000-CN225-T54CO1.pdf PDF
CN-370000-CN225-T56.pdf PDF
CN-370000-CN225-T5CO1.pdf PDF
CN-370000-CN225-T6CO1.pdf PDF
CN-370000-CN225-T6CO2.pdf PDF
CN-370000-CN225-T9.pdf PDF
CN-370000-CN225-TA1.pdf PDF
CN-370000-CN225-TA27.pdf PDF
CN-370000-CN225-CMC1.pdf PDF
CN-370000-CN225-T10.pdf PDF
CN-370000-CN225-T10CO2.pdf PDF
CN-370000-CN225-T14CO3.pdf PDF
CN-370000-CN225-T14CO3.pdf.crdownload CRDOWNLOAD file
CN-370000-CN225-T17.pdf PDF
CN-370000-CN225-T17CO3.pdf PDF
CN-370000-CN225-T17CO4.pdf PDF
CN-370000-CN225-T18.pdf PDF
CN-370000-CN225-T20.pdf PDF
CN-370000-CN225-T20CO1.pdf PDF
CN-370000-CN225-T24.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Florida Department of Environmental Protection

TASK ASSIGNMENT CHANGE ORDER FORM

(Revised 9-26-2018) Page 1 of 1

Required Signatures: Adobe Signature

FDEP Contract No.: Task Assignment No.: Change Order No.: Project No.:

Project Location: Project Name:

Consultant Name:

Consultant Representative: Phone: Email:

FDEP Contract Manager: Phone: Email:

Description and Justification of Change:

Change in Task Amount:

Item Reimbursement Fixed Fee Total

Original Task Amount:

Task amount including all previous Change Orders:

Net increase/decrease in task amount for this Change Order:

Total Amounts with all Change Orders:

Change in Task Time:

Original Task Execution Date:

Original Task End Date:

Present Task End Date:

Net Change in Days:

New Task End Date:

Approval Signatures:

Budget Representative, FDEP Signature Date

Project Manager, FDEP Signature Date

Contract Manager, FDEP Signature Date

Consultant Signature Date

Contract Authority, FDEP Signature Date

Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount

29 Digit FLAIR Code: Total:

CN225 14 4 61223C/61221C

Colt Creek State Park New Prefabricated Restroom

DRMP, Inc.

Benjamin Lennon, P.E. 850-692-5659 blennon@drmp.com

Jeffrey Whitfield 850-245-2630 jeffrey.whitfield@floridadep.gov

No cost change. Time extension only so consultant can provide construction administrative services included in the Task Assignment. Please see consultants proposal dated 06/14/2021.

$ 1,000.00 $ 27,822.13 $ 28,822.13 $ 1,000.00 $ 28,351.63 $ 29,351.63

$ 0.00 $ 0.00 $ 0.00 $ 1,000.00 $ 28,351.63 $ 29,351.63

02/11/2019

12/31/2019

06/30/2021

12/31/2021

Greg Turral Gregory Turral Digitally signed by Gregory Turral Date: 2021.06.16 11:56:18 -04'00'

Bill Brown William R Brown Digitally signed by William R Brown Date: 2021.06.16 14:19:22 -04'00'

Alyssa Skehan Alyssa Skehan Digitally signed by Alyssa Skehan Date: 2021.06.16 14:29:35 -04'00'

Benjamin Lennon P.E. Benjamin R Lennon

2021.06.25 13:06:57-04'00'

Michael W. Foster Jr. P.E. Michael W. Foster Jr.

Digitally signed by Michael W.

Foster Jr.

Date: 2021.06.29 14:55:48 -04'00'

$ 0.00

$ 0.00

1625 Summit Lake Drive, Suite 200, Tallahassee, Florida 32317 Phone: 850.562.9600 | Fax: 850.575.5544

DRMP, INC.

PRINCIPALS

Lawrence L. Smith, Jr.

Wayne D. Chalifoux

Donaldson K. Barton, Jr.

Glenn J. Lusink

Jon S. Meadows

Mark D. Prochak

Mark E. Puckett

OFFICES

Atlanta, Georgia

Boca Raton, Florida

Charlotte, North Carolina

Chipley, Florida

Fort Myers, Florida

Gainesville, Florida

Jacksonville, Florida

Lakeland, Florida

Melbourne, Florida

Orlando, Florida

Panama City, Florida

Pensacola, Florida

Raleigh, North Carolina

Tallahassee, Florida

Tampa, Florida

1.833.811.3767 www.DRMP.com

June 14, 2021 DRMP Proposal #: 14-0210.014

Bill Brown

Florida Department of Environmental Protection

Division of Recreation and Parks

Bureau of Design and Construction 3900 Commonwealth Boulevard 260K, MS 520

Subject: FDEP Agreement #CN225 – Task Assignment #14 – Change Order #4 Colt Creek State Park – New Prefabricated Restrooms; Project # 61223C Proposal for Time Extension

Dear Mr. Barreto:

The referenced task assignment is set to expire on 06/30/2021. Can you please extend this until 12/31/2021 for the project to be completed.

Sincerely, _____________________________06/14/21___ Benjamin Lennon, P.E. Date Project Engineer

CC: Richard Rowe, Project Manager (FDEP)