Task Assignment Notification and Proposal Summary

This document comprises a Task Assignment Notification Form and detailed professional services proposal for the Florida Department of Environmental Protection (FDEP) under Contract CN225, Task Assignment #39. The project involves DRMP, Inc., as the primary consultant with multiple subconsultants including JBrown Professional Group, NOVA Engineering, Kever McKee Engineering, and Florida Environmental & Land Services Inc. The project is located at Ichetucknee Springs State Park in Columbia County, Florida, with project management oversight by FDEP personnel including Wayne Thomas (Project Manager) and Alyssa Skehan (Contract Manager).

The scope encompasses comprehensive design and permitting services for upgrading the midpoint route from the tram drop-off to the boardwalk terminus on the Ichetucknee River to achieve ADA accessibility. Services include topographic surveying ($10,267.88), geotechnical investigation ($5,708.21), hazardous materials assessment ($1,938.68), and phased design development from 30% through 100% completion ($25,915.62 combined). Regulatory permitting tasks total $20,064.02, including environmental resource permits, wetland permitting, and State Fire Marshal approval, with a permit fee allowance of $2,500. Construction administration services are budgeted at $9,914.41. The total task amount is $73,808.82, consisting of $71,308.82 in fixed price costs and $2,500.00 in reimbursable permit fees. Work is scheduled to begin upon execution with a completion date of June 30, 2023, incorporating approximately 24 weeks of estimated duration with two-week review periods built into subtask dependencies.

View the file

Other files

File Type Posted
CN-370000-CN204-TA7CO1.pdf PDF
CN-370000-CN225-CMC4.pdf PDF
CN-370000-CN225-T11.pdf PDF
CN-370000-CN225-T15CO2.pdf PDF
CN-370000-CN225-T19.pdf PDF
CN-370000-CN225-T22.pdf PDF
CN-370000-CN225-T28.pdf PDF
CN-370000-CN225-T29.pdf PDF
CN-370000-CN225-T30.pdf PDF
CN-370000-CN225-T32.pdf PDF
CN-370000-CN225-T36.pdf PDF
CN-370000-CN225-T38.pdf PDF
CN-370000-CN225-T38CO2.pdf PDF
CN-370000-CN225-T39CO3.pdf PDF
CN-370000-CN225-T41CO1.pdf PDF
CN-370000-CN225-T42.pdf PDF
CN-370000-CN225-T5.pdf PDF
CN-370000-CN225-T50.pdf PDF
CN-370000-CN225-T50CO1.pdf PDF
CN-370000-CN225-T6.pdf PDF
CN-370000-CN225-T6CO5.pdf PDF
CN-370000-CN225-T6CO6.pdf PDF
CN-370000-CN225-A1.pdf PDF
CN-370000-CN225-T10CO1.pdf PDF
CN-370000-CN225-T12.pdf PDF
CN-370000-CN225-T13.pdf PDF
CN-370000-CN225-T14.pdf PDF
CN-370000-CN225-T14CO1.pdf PDF
CN-370000-CN225-T14CO2.pdf PDF
CN-370000-CN225-T15.pdf PDF
CN-370000-CN225-T15CO3.pdf PDF
CN-370000-CN225-T15CO5.pdf PDF
CN-370000-CN225-T16.pdf PDF
CN-370000-CN225-T16CO1.pdf PDF
CN-370000-CN225-T17CO1.pdf PDF
CN-370000-CN225-T17CO2.pdf PDF
CN-370000-CN225-T18CO1.pdf PDF
CN-370000-CN225-T23.pdf PDF
CN-370000-CN225-T24CO2.pdf PDF
CN-370000-CN225-T27CO1.pdf PDF
CN-370000-CN225-T28CO1.pdf PDF
CN-370000-CN225-T32CO2.pdf PDF
CN-370000-CN225-T32CO5.pdf PDF
CN-370000-CN225-T34CO2.pdf PDF
CN-370000-CN225-T4.pdf PDF
CN-370000-CN225-T44.pdf PDF
CN-370000-CN225-T45.pdf PDF
CN-370000-CN225-T48.pdf PDF
CN-370000-CN225-T51.pdf PDF
CN-370000-CN225-T53.pdf PDF
Show 40 more

50 files listed here. See the rest on GovTribe.

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Florida Department of Environmental Protection

TASK ASSIGNMENT NOTIFICATION FORM

Required Signatures: Adobe Signature

FDEP Contract No.: Task Assignment No.: Owner’s Name: Project No.:

Project Location: Project Name:

Consultant Name:

Consultant Representative: Phone: Email:

FDEP Contract Manager: Phone: Email:

Description of Task:

Project Manager:

Schedule Start Date: Fixed Price Cost:

Completion Date: Cost Reimbursement not to exceed:

Total Task Amount:

Approval Signatures:

Budget Representative, FDEP Signature Date

Project Manager, FDEP Signature Date

Contract Manager, FDEP Signature Date

Consultant Signature Date

Contract Authority, FDEP Signature Date

Project # Grant # Org Code Cat/Year Fund Module Object Code EO Amount

29 digit FLAIR Code: Total:

CN225 39 FDEP 61361C

Ichetucknee Springs State Park Mid Point ADA Access Improvement

DRMP

Benjamin Lennon PE 850.692.5659 blennon@drmp.com

Alyssa Skehan 850.245.2781 Alyssa.Skehan@FloridaDEP.gov

Consultant to provide design and permitting services to upgrade the existing midpoint route from the tram drop-off to the end of the boardwalk on the river to an accessible ADA route as per proposal dated 11/12/2021.

Wayne Thomas

Upon Execution $ 71,308.82 6/30/2023 $ 2,500.00

$ 73,808.82

Greg Turral Gregory Turral Digitally signed by Gregory Turral Date: 2021.11.23 09:34:10 -05'00'

Wayne Thomas Wayne Thomas Digitally signed by Wayne Thomas Date: 2021.11.23 10:30:56 -05'00'

Alyssa Skehan Alyssa Skehan Digitally signed by Alyssa Skehan Date: 2021.12.07 15:14:27 -05'00'

Bryant King PE Bryant A King

2021.12.09 17:07:25-05'00'

Michael W. Foster Jr, P.E. Michael W. Foster Jr.

Digitally signed by Michael W.

Foster Jr.

Date: 2022.01.21 08:52:55 -05'00'

61361C 37502000086 080039/22 423001 U3200 131500 QK $ 73,808.82

$ 73,808.82

2882 Remington Green Circle, Tallahassee, Florida 32308 Phone: 850.562.9600 | Fax: 850.575.5544

DRMP, INC.

PRINCIPALS

Lawrence L. Smith, Jr.

Donaldson K. Barton, Jr.

Glenn J. Lusink

Jon S. Meadows

Mark D. Prochak

Mark E. Puckett

OFFICES

Asheboro, North Carolina

Boca Raton, Florida

Cary, North Carolina

Charlotte, North Carolina

Chipley, Florida

DeLand, Florida

Fort Myers, Florida

Gainesville, Florida

Jacksonville, Florida

Lakeland, Florida

Melbourne, Florida

Merritt Island, Florida

Orlando, Florida

Panama City Beach, Florida

Pensacola, Florida

Stockbridge, Georgia

Tallahassee, Florida

Tampa, Florida

Troutman, North Carolina

1.833.811.3767 www.DRMP.com

November 12, 2021 DRMP Proposal #: 14-0210.M39

Wayne Thomas Project Manager Bureau of Design and Construction Florida Department of Environmental Protection 3900 Commonwealth Boulevard 260K, MS 520

Subject: Ichetucknee Springs State Park – Mid Point ADA Access

FDEP Agreement #CN225 – Task Assignment #39 Proposal for Professional Services

Dear Mr. Thomas:

Our understanding of the project is for the design and permitting to upgrade the midpoint route from the tram drop-ff to the end of the boardwalk on the river. For your review, DRMP, Inc., has provided a proposal summary and man-hour documentation for the services task identified below:

Please review the attached Proposal Summary and Deliverables.

Sincerely, Benjamin Lennon____ 11/4/2021

Benjamin Lennon, P.E. Date Project Engineer

Attachment(s): DRMP, Inc. Proposal

CC: Bryant King, P.E.

Mr. W. Thomas

Ichetucknee Springs State Park Mid Point ADA Access - Columbia County, Florida FDEP Agreement #CN225 – Task Assignment #39

Proposal for Professional Services

Background and Purpose The purpose of this project is to provide professional engineering services needed to design the following elements at Ichetucknee Springs State Park in Columbia County, Florida:

• Need ADA access from tram drop-off to floating dock on the river

• Up to 3000 people per day usage

• 8’-10’ wide concrete path – similar to Dampier’s Landing trail

• Need emergency access – path to support vehicular traffic

• Prefer not to have ditches or stormwater depressions (like Dampier’s).

• Remove and replace boardwalk to be ADA accessible.

• Replace floating dock – design similar to existing

Subtask 1: Topographic Survey

Description: The Consultant, through their subconsultant JBrown Professional Group, shall provide a topographic survey in order to facilitate engineering the project site. The Topographic Survey shall be prepared in accordance with the State of Florida Standards of Practice, Chapter 5J-17, Florida Administrative Code, as set forth by the Board of Professional Surveyors and Mappers, pursuant to Section 472.027, Florida Statues.

This survey information will be tied to the NAD83 horizontal datum and NAVD88 Vertical Datum Using GPS techniques. Spot elevations will be on a 50’ grid.Contours will be drawn to 1’ intervals. Trees larger than 8” DBH will also be located in the updlands, and trees larger than 4” DBH in the wetlands. Only utilities accessible from above ground access points will be located. As part of this survey JBPro will specifically locate Existing boardwalk with stairs, floating dock elements, edge of water, trail, and tram drop off area in the survey area.

Deliverable: The Consultant shall provide one (1) Topographic Survey (.pdf and dwg format) to the Department Project Manager.

Performance Measures: Deliverables shall be reviewed by the Department to confirm they are complete, accurate, and timely.

Schedule: The Consultant shall begin the Survey on the subject property within 2 weeks after the start of the project.

Firm Name Position Classification Hourly Rate Hours Total Fixed Price Cost

DRMP Project Manager $159.52 8 $1,276.16

JBPro Senior Project Surveyor $103.97 8 $831.76

JBPro Senior Survey Technician $61.37 25 $1,534.25

JBPro 2 Man Survey Crew $105.17 63 $6,625.71

$10,267.88

Subtask 1: Topographic Survey

SUBTASK 1 TOTAL:

Subtask 2: Geotechnical Investigation

Description: The Consultant shall perform geotechnical engineering services through their subconsultant NOVA Engineering. The proposed scope of services shall include the following components:

FIELD – Mobilize to site to perform five (5) 15’ SPT borings for the boardwalk, five (5) 5’ Hand Auger Borings with DCP Testing along the upland path for the proposed concrete trail, and four (4) Hand Auger Borings in the uplands with field percolation tests.

LABORATORY – budget includes (4) wash #200 sieve tests and (4) water content tests and (2) Atterberg Limits test.

NOVA will include design considerations for the proposed boardwalk and concrete trail.

Deliverable: The Consultant shall provide one signed and sealed geotechnical report in .pdf format to the department manager.

Schedule: The Consultant shall complete the services under Subtask 2 within 4 weeks of the start of the project.

Subtask 3: ACM, LBP and Pre-Demolition Survey

Description: The Consultant shall perform hazardous material survey services through their subconsultant NOVA engineering for the boardwalk to be demolished. The proposed scope of services shall include the following components:

FIELD - NOVA will conduct National Emissions Standards for Hazardous Air Pollutants (NESHAPs) pre-demolition survey on the requested buildings. The sampling strategy will be based on the Asbestos Hazard Emergency Response Act (AHERA) sampling method.

Sampling will be conducted by a Florida Certified Asbestos Inspector. Samples will be sent to our contracted National Voluntary Laboratory Accreditation Program (NVLAP) accredited laboratory. A minimum of three (3) samples are required per suspect asbestos containing material. Sampling will be destructive and will be performed on materials that will be disturbed or demolished per the Client. The scope does not include repairs to damaged building components.

NOVA will complete a lead-based paint (LBP) survey of the buildings located at the property noted above. Testing will be performed in accordance with methodology detailed in the 1995 Housing and Urban Development (HUD) Guidelines for the Evaluation and Control of Lead-Based Paint Hazards in Housing, Chapter 7, Lead-Based Paint Inspection, as amended in October of 1997.

Firm Name Position Classification Hourly Rate Hours Total Fixed Price

Cost

DRMP Project Manager $159.52 4 $638.08

NOVA Staff Engineer $78.03 20 $1,560.60

NOVA Project Manager $96.32 12 $1,155.84

NOVA Project Engineer $96.32 10 $963.20

NOVA Senior Project Engineer $141.61 9 $1,274.49

NOVA Administrator $58.00 2 $116.00

$5,708.21

Subtask 2: Geotechnical Engineering

SUBTASK 2 TOTAL:

Testing will be performed using an X-Ray Fluorescence (XRF) meter by individuals certified in its use by the manufacturer. Testing will be directed by individuals certified by the State of Florida and the Environmental Protection Agency (EPA) in Lead-Based Paint Inspection.

Real time field sheets will be prepared and submitted as an attachment to our final report.

REPORT – The report will be a summary of our findings and will include lab results to identify and confirm the presence of Asbestos Containing Materials, Lead Based Paint, and Mercury Switches, or lack thereof, at the subject buildings. An electronic version of the report will be delivered to the Client. Hardcopies of the report can be provided to the Client upon request

Deliverable: The Consultant shall provide one summary report report in .pdf format to the Department Project Manager.

Schedule: The Consultant shall complete the services under Subtask 3 within 4 weeks of the start of the

Subtask 4: 30% Design

Description: The Consultant and subconsultant Kever Mckee Engineering shall perform engineering services pertinent to 30% plans. The proposed scope of services shall include the following components:

Conceptual plans that include the paved trail in the uplands and boardwalk replacement in the wetlands.

Two new options will be proposed for the end structure of the boardwalk. The existing floating dock will be evaluated for consideration to remain (or be modified). The plans will include approximate route alignments, elevations (for ADA compliance), and conceptual stormwater management plan to meet permitting requirements.

Deliverable: The Consultant shall deliver 30% design plans and opinion of probable construction costs in .pdf format to the Department Project Manager.

Schedule: The Consultant shall complete the services under Subtask 3 within 3 weeks of the completion of Subtask 1.

Firm Name Position Classification Hourly Rate Hours Total Fixed Price

Cost

DRMP Project Manager $159.52 1.5 $239.28

NOVA Staff Engineer $78.03 10 $780.30

NOVA Principal Engineer $274.55 2 $549.10

NOVA Secretary/Clerical $58.00 1 $58.00

$1,626.68

Firm Name Field/Lab Expense Type Unit Price Quantity Total Fixed Price

Cost

NOVA Sample Analysis $12.00 26 $312.00

$312.00

$1,938.68

Subtask 3: ACM, LBP and Pre-Demolition Survey

LABOR SUBTOTAL:

FIELD/LABORATORY SUBTOTAL:

SUBTASK 3 TOTAL:

Subtask 5: 60% Design

Description: Based on the FDEP review of Subtask 3 (30% Design) deliverables, the Consultant shall prepare detailed construction drawings and specifications. Our services will include Demolition Plan, Site Plans, Grading and Drainage, Sections and Details to best describe the proposed work for permitting and construction. The design will utilize passive methods such as vegetated natural buffers to the extent allowed by the water management district. However, stormwater attenuation and treatment may be required and ponds, swales, or depressions will be designed.

Deliverable: The Consultant shall deliver 60% design plans and technical specifications, and opinion of probable construction costs in .pdf format to the Department Project Manager.

Schedule: The Consultant shall complete the services under Subtask 4 within 4 weeks of the completed review of the 30% design deliverables.

Subtask 6: 90% Design

Description: Based on the FDEP review of Subtask 6 (60% Design) deliverables, the Consultant shall perform final engineering analysis and prepare detailed construction drawings and technical specifications.

Cost

DRMP Project Manager $159.52 8 $1,276.16

DRMP Senior Project Engineer PE $141.12 2 $282.24

DRMP Staff Engineer EI $81.79 4 $327.16

DRMP CADD Designer $105.23 24 $2,525.52

KeverMcKee Project Manager $155.76 2.5 $389.40

KeverMcKee Senior Project Engineer $155.76 8 $1,246.08

KeverMcKee Staff Engineer $72.10 9 $648.90

KeverMcKee CAD Technician $40.50 16 $648.00

KeverMcKee Clerical $32.39 2 $64.78

$7,408.24

Subtask 4: 30% Design

SUBTASK 4 TOTAL:

Firm Name Position Classification Hourly Rate Hours Total Fixed Price

Cost

DRMP Project Manager $159.52 12 $1,914.24

DRMP Senior Project Engineer PE $141.12 2 $282.24

DRMP Project Engineer PE $110.01 4 $440.04

DRMP Staff Engineer EI $81.79 6 $490.74

DRMP CADD Designer $105.23 24 $2,525.52

KeverMcKee Project Manager $155.76 1 $155.76

KeverMcKee Senior Project Engineer $155.76 4 $623.04

KeverMcKee Staff Engineer $72.10 8 $576.80

KeverMcKee CAD Technician $40.50 10 $405.00

KeverMcKee Clerical $32.39 2 $64.78

$7,478.16

SUBTASK 5 TOTAL:

Deliverable: At a minimum, the deliverables shall include the following:

Electronic copies of the 90% Construction Document drawings in PDF file format. The documents shall be formatted for reproduction on 24x36 paper or half size at 12x18 paper.

Electronic copies of the 90% estimate of probable construction cost in PDF file format. The documents shall be formatted for reproduction on 8-1/2”x11” paper.

Electronic copies of all additional materials required to convey the 90% design intent.

Schedule: The Consultant shall complete the services under Subtask 5 within 3 weeks of the completed review of the 60% design deliverables.

Subtask 7: 100% Design

Description: Based on the FDEP review of the 90% Design deliverables, the Consultant shall perform final engineering analysis and prepare detailed construction drawings and technical specifications.

Deliverable: The Consultant shall deliver digitally signed and sealed 100% design plans and technical specifications to the Department Project Manager. The deliverable shall include digital PDFs of the construction drawings, technical specifications, Engineer’s Estimate of Quantities, opinion of probable construction costs, and Autocad (.dwg) file of the plans.

Schedule: The Consultant shall complete the services under Subtask 8 within 4 weeks of the completed review of the 90% design deliverables.

Firm Name Position Classification Hourly Rate Hours Total Fixed Price

Cost

DRMP Project Manager $159.52 15 $2,392.80

DRMP Senior Project Engineer PE $141.12 2 $282.24

DRMP Project Engineer PE $110.01 4 $440.04

DRMP Staff Engineer EI $81.79 6 $490.74

DRMP CADD Designer $105.23 24 $2,525.52

KeverMcKee Project Manager $155.76 1 $155.76

KeverMcKee Senior Project Engineer $155.76 2 $311.52

KeverMcKee Staff Engineer $72.10 6 $432.60

KeverMcKee CAD Technician $40.50 10 $405.00

$7,436.22

Subtask 6: 90% Design

SUBTASK 6 TOTAL:

Subtask 8: Regulatory Permitting Subtask 8A: Site Inspection and Environmental Summary

Description: The Consultant, through subconsultant Florida Environmental & Land Services Inc., will conduct a site assessment of the project area and map any environmental features such as wetland and/or listed species. FELSI will delineate the wetlands on the property based upon State and Federal guidelines.

The wetland line will be flagged using numbered flagging tape marked with ‘Wetland Delineation’. Wetland points or locations will be collected concurrent with the fieldwork using GPS. A general and protected species survey will also be conducted in conjunction with the fieldwork and GPS used to locate any observed environmental features. An environmental memo describing the results of the site assessment will be included in this task.

Deliverable: The Consultant shall deliver the Environmental Summary document in .pdf format to the

Schedule: The Environmental Summary will be submitted within 4 weeks of the start of the project.

Subtask 8B: Pre-Application Meetings

Description: The Consultant and subconsultant Florida Environmental & Land Services Inc., shall schedule and meet via teleconference with FDEP staff prior to submitting permit applications for Environmental

Resource Permitting (ERP) and State Section 404 Wetland Permitting. 30% Design plans will be sent to agency staff prior to the meeting.

Deliverable: The Consultant shall deliver meeting minutes of the pre-app meetings in .pdf format to the

Schedule: The pre-application meeting minutes will be submitted within 3 weeks of submitting the 30% Design.

Cost

DRMP Project Manager $159.52 4 $638.08

DRMP Senior Project Engineer PE $141.12 2 $282.24

DRMP Project Engineer PE $110.01 4 $440.04

DRMP CADD Designer $105.23 6 $631.38

KeverMcKee Project Manager $155.76 3 $467.28

KeverMcKee Senior Project Engineer $155.76 3 $467.28

KeverMcKee Staff Engineer $72.10 7 $504.70

KeverMcKee CAD Technician $40.50 4 $162.00

$3,593.00

Subtask 7: 100% Design

SUBTASK 7 TOTAL:

Subtask 8C: ERP Permitting

Description: The Consultant and subconsultant Florida Environmental & Land Services Inc., shall prepare the ERP application forms and supplemental information for submittal to the FDEP for state processing. We will coordinate with project managers to prepare a complete ERP application, including the submerged lands authorization, which is anticipated to be a Consent of Use. Information obtained during the completion of

Task 6A will be included in the application and design recommendations. Included in this task is preparation of mitigation or restoration plans if required. As part of this task, opportunities to eliminate or reduce wetland impacts will be identified and presented to the project managers.

The project area is within the floodway of the Itchetucknee River, and will require a zero-rise certification.

Such certification may include step-backwater calculations using the 100-year flood/one percent annual chance of flood discharge rate. The certification shall include, at a minimum, a location map showing existing and cross sections, a scaled graphical representation of channel geometry for each cross section used in the calculation, a scaled graphical representation of floodway encroachments for pre-development and post-development conditions, pre-development calculations matching existing conditions, and post-development calculations showing the rise in flood elevation.

The Consultant and FELSI will also prepare responses to requests for additional information.

Deliverable: The Consultant shall deliver the ERP and .pdf format to the Department Manager.

Schedule: The permits will be delivered with the 100% Design Documents.

Subtask 8D: Wetland Permitting

Description: The Consultant and subconsultant Florida Environmental & Land Services Inc., shall prepare and submit wetland permitting applications. Since the project is located within State assumed waters, the

Florida Department of Environmental Protection will process the application under Section 404 and not the

United States Corps of Engineers. The Suwannee River Water Management District will process the State

ERP portion of the application. Please note that due to the new State 404 processing guidelines and the amount of State 404 applications currently awaiting to processed by the FDEP, the timeframe of application issuance is unpredictable and lengthy. FELSI has experience with the process since it was instated in December of 2020. The FDEP normally requires a site visit and this is included in this proposal.

The Consultant and FELSI will also prepare responses to requests for additional information.

Deliverable: The Consultant shall deliver the ERP and .pdf format to the Department Manager.

Schedule: The permits will be delivered with the 100% Design Documents.

Subtask 8E: State Fire Marshall

Description: The Consultant wills submit plans to the State Fire Marshall for review and approval. This task includes preparation of the application, submittal and response to all comments.

Deliverable: The Permit will be delivered in hard copy or digital format consistent with the issuance policy of the regulatory agency.

Schedule: The permits will be delivered within 4 weeks of the 90% Design Document submittal.

Subtask 8E: Permit Fees

Description: The Consultant will pay all permit fees to be reimbursed directly up to a limiting amount of $2,500.00.

We estimate the following allowances:

• SRWMD ERP and Wetlands $1,000

• State Fire Marshal $1,500

Additional fees beyond this allowance will require additional fee or be paid the to the review agency directly or to the consultant via a supplemental agreement. Building permit fees will be the responsibility of the

Contractor.

Deliverable: The Consultant shall provide receipts for permit fees upon invoicing

Schedule: N/A

Cost

DRMP Project Manager $159.52 2 $319.04

FELS Principal Environment Consultant $109.54 10 $1,095.40

FELS Senior Environmental Tech $53.86 6 $323.16

FELS Staff/Project Assistant $77.92 6 $467.52

$2,205.12

Firm Name Position Classification Hourly Rate Hours Total Fixed Price

Cost

DRMP Project Manager $159.52 3 $478.56

FELS Principal Environment Consultant $109.54 3 $328.62

$807.18

Firm Name Position Classification Hourly Rate Hours Total Fixed Price

Cost

DRMP Project Manager $159.52 16 $2,552.32

DRMP Project Engineer PE $110.01 6 $660.06

DRMP Staff Engineer EI $81.79 20 $1,635.80

FELS Principal Environment Consultant $109.54 12 $1,314.48

FELS Senior Environmental Tech $53.86 15 $807.90

FELS Staff/Project Assistant $77.92 10 $779.20

$7,749.76

Firm Name Position Classification Hourly Rate Hours Total Fixed Price

Cost

DRMP Project Manager $159.52 8 $1,276.16

DRMP Project Engineer PE $110.01 6 $660.06

DRMP Staff Engineer EI $81.79 16 $1,308.64

FELS Principal Environment Consultant $109.54 14 $1,533.56

FELS Senior Environmental Tech $53.86 8 $430.88

FELS Staff/Project Assistant $77.92 8 $623.36

$5,832.66

Firm Name Position Classification Hourly Rate Hours Total Fixed Price

Cost

DRMP Project Manager $159.52 3 $478.56

DRMP Staff Engineer EI $81.79 6 $490.74

$969.30

Firm Name Expense Type Unit Price Quantity Total NTE Cost

DRMP Permit Fee(s) - Not to Exceed $2,500.00 NTE $2,500.00

$2,500.00

$2,500.00

$20,064.02

Subtask 8: Regulatory Permitting

Subtask 8B: Pre-Application Meetings

8B TOTAL:

Subtask 8C: Environmental Resource Permit (ERP)

8C TOTAL:

Subtask 8D: Wetland Permitting

8D TOTAL:

Subtask 8A: Site Assessment and Environmental Memo

8A TOTAL:

Subtask 8F: Permit Fees

REIMBURSABLE EXPENSE SUBTOTAL:

SUBTASK 8F Total:

SUBTASK 8 Grand Total:

Subtask 8E: State Fire Marshall

8E TOTAL:

Subtask 9: Construction Administration Services

Subtask 9A: Bidding Support

Description: The Consultant shall answer bid questions provided by the Department and issue any Addenda needed for issuance. The Consultant or respective Subconsultants shall not answer any bid questions directly from Contractors, subcontractors or vendors and will direct all questions to the Purchasing Agent at the Department.

Subtask 9B: Shop Drawings and RFI’s

Description: The Consultant shall review shop drawings pertaining to Site/Civil work and verify their accuracy with the plans and documents. The Consultant shall respond to the contractor with red line mark ups if the shop drawings are not in accordance with the plans. Markups may be approved as noted or require resubmittal. All shop drawings shall be returned to the Department for concurrence. The Consultant shall respond to contractor related questions and requests for information pertaining to Site/Civil work and verify their accuracy with the plans and documents. The Consultant shall respond to the contractor requests for information (RFI) in writing and provide this to BDC for concurrence.

Subtask 9C: Construction Phase Site Visit

Description: The Consultant shall make a site visit at the 75% phase of construction or as requested by the FDEP project manager to observe as an experienced and qualified design professional the progress and quality of the executed work and to determine in general if the work is proceeding in accordance with the contract documents and permit conditions for the site work.

Subtask 9D: Substantial Completion Site Visit and As-built Review

Description: The Consultant will review contractor provided as-built construction survey completed by a registered surveyor and mapper in the State of Florida, for conformance to the permitted construction plans. This survey must be signed and sealed by a State of Florida Professional Surveyor and Mapper. As-Built plans shall be submitted prior to the Substantial completion site review. The Consultant shall attend the inspection for substantial completion when requested by the contractor and prepare a punch list of those items not completed and that do not meet the intent of the plans and technical specifications or need minor adjustment. The Consultant shall sign the DEP certification of substantial completion for setting forth the date of substantial completion for this

Deliverable(s): (These are payment triggers – what items will consultant provide to FDEP, including format, size, number, minimum content, due date, etc.)

• Subtask 9A: Bidding - Documentation of any responses to RFI’s (.pdf format).

• Subtask 9B: Shop Drawings and RFI’s – Copies of Stamped Shop Drawings and Documentation of any RFI’s (.pdf format).

• Subtask 9C: Construction Site Visit – Observation Report of the Site Visit (.pdf format).

• Subtask 9D: Substantial Completion Site Visit – Written Summary of the As-built Review, Meeting and Certification and punch list (.pdf format).

Performance Measure: Deliverables shall be reviewed by the Department to confirm they are complete, accurate, and timely.

NOTE: Should work effort vary from proposed professional services / anticipated agency requirements, the Consultant shall submit an additional services proposal for the Department Project Manager’s consideration to modify the agreed upon task assignment (scope of services, schedule, and fees) accordingly.

Cost

DRMP Project Manager $159.52 3 $478.56

DRMP Project Engineer PE $110.01 2 $220.02

KeverMcKee Project Manager $155.76 1 $155.76

KeverMcKee Staff Engineer $72.10 1.5 $108.15

KeverMcKee Clerical $32.39 1 $32.39

SUBTASK 9A TOTAL: $994.88

Firm Name Position Classification Hourly Rate Hours Total Fixed Price

Cost

DRMP Project Manager $159.52 4 $638.08

DRMP Sr Project Engineer PE $141.12 0.5 $70.56

DRMP Project Engineer PE $110.01 8 $880.08

DRMP Staff Engineer EI $81.79 4 $327.16

DRMP Secretary $47.83 2 $95.66

KeverMcKee Senior Project Engineer $155.76 6.5 $1,012.44

KeverMcKee Staff Engineer $72.10 3 $216.30

SUBTASK 9B TOTAL: $3,240.28

Firm Name Position Classification Hourly Rate Hours Total Fixed Price

Cost

DRMP Project Manager $159.52 8 $1,276.16

KeverMcKee Senior Project Engineer $155.76 8 $1,246.08

SUBTASK 9C TOTAL: $2,522.24

Firm Name Position Classification Hourly Rate Hours Total Fixed Price

Cost

DRMP Project Manager $159.52 8 $1,276.16

DRMP Staff Engineer EI $81.79 3 $245.37

KeverMcKee Senior Project Engineer $155.76 10.5 $1,635.48

SUBTASK 9D TOTAL: $3,157.01

$9,914.41SUBTASK 9 GRAND TOTAL:

Subtask 9: Construction Administration Services

Subtask 9A - Bidding

Subtask 9B: Shop Drawings and RFI’s

Subtask 9C: Construction Phase Site Visit

Subtask 9D: Substantial Completion Site Visit & As-built Review

Reimbursable

Subtask 8A: Site Assessment and Environmental Memo $2,205.12

Subtask 8B: Pre-Application Meetings $807.18

Subtask 8C: Environmental Resource Permit (ERP) $7,749.76

Subtask 8D: Wetland Permitting $5,832.66

Subtask 8E: State Fire Marshall $969.30

Subtask 8F: Permit Fees $2,500.00

Subtask 8B: Pre-Application Meetings 3 weeks from Subtask 4

Subtask 8C: Environmental Resource Permit (ERP)

Subtask 8D: Wetland Permitting

Subtask 8F: Permit Fees N/A

All Subtasks with Predecessors Include 2 Week Review Period from Client Built in to Duration

Total Estimated time = 24 weeks

N/A

Subtask 7: 100% Design

Subtask 8A: Site Assessment and Environmental Memo

Subtask 10: Construction Administration Services (Not in this

Task Assignment)

Subtask 6: 90% Design 5 weeks from Subtask 5

Subtask 2: Geotechnical Engineering 4 weeks from Start

Subtask 4: 30% Design 8 weeks from Start

Subtask 5: 60% Design 6 weeks from Subtask 4

Subtask 3: ACM, LBP and Pre-Demolition Survey 4 weeks from Start

Subtask 2: Geotechnical Engineering $5,708.21

Total Fixed Price Cost: $61,394.41

Subtask 4: 30% Design $7,408.24

Subtask 6: 90% Design $7,436.22

Summary of Fees

Subtask: Fixed Price Cost

Subtask 1: Topographic Survey $10,267.88

Subtask 7: 100% Design $3,593.00

Subtask 3: ACM, LBP and Pre-Demolition Survey $1,938.68

$7,478.16

Subtask 9: Construction Administration Services $9,914.41

GRAND TOTAL: $73,808.82

6 weeks from Subtask 6

6 weeks from Subtask 6

Total Reimbursable Cost: $2,500.00

TOTAL DESIGN AND PERMITTING: $63,894.41

Project Schedule

Subtask: Duration

Subtask 1: Topographic Survey 4 weeks from Start

6 weeks from Subtask 6

4 weeks from Start

© 2021 Microsoft Corporation © 2021 Maxar ©CNES (2021) Distribution Airbus DS

EXISTING BOARDWALK

W/STAIRS. REPLACE,

MAKE ADA

COMPLIANT

EXISTING FLOATING

DOCK

EXISTING TRAIL - NEW

CONCRETE PATH (ADA,

EMERGENCY VEHICLE

ACCESS)

EXISITNG TRAM

DROP-OFF (PAVED

LOOP). IMPROVE ADA

SURVEY AREA, 1.5

ACRES

AutoCAD SHX Text

ITCHETUCKNEE MID-POINT ADA IMPROVEMENTS

File details come from the government source that posted it. Updated .