CN-370000-CN225-T6CO5.pdf
PDF 140 KB Posted
- Contract number
- CN225
- Issued by
- Florida
About this file
This is a Task Assignment Change Order Form issued by the Florida Department of Environmental Protection (FDEP) for Contract CN225, Task Assignment No. 6, Change Order No. 5, pertaining to the Big Lagoon State Park - DWH NRDA Phase III project located in Escambia County, Florida. The consulting firm DRMP, Inc., represented by Bryant King, P.E., is the contractor, with FDEP Contract Manager Jack Brady overseeing the agreement. The change order was digitally signed and approved by FDEP representatives including Janet Parramore (Budget Representative), James J. Oskowis (Project Manager), and Jack Brady (Contract Manager), as well as the consultant Trina Vielhauer.
The change order extends the task end date from December 30, 2019 to June 30, 2020, adding 183 days to accommodate delays in obtaining a US Army Corps of Engineers permit. The reimbursement component increases by $2,482.87, while the fixed fee portion increases by $4,232.53, resulting in a net increase of $6,715.40. The original task amount was $154,156.12, and with all change orders included, the total task amount is now $160,871.52. The net change in the task amount for this specific change order is $0.00, indicating that while the timeline was extended, the financial impact was offset by prior adjustments. The task originally commenced on February 22, 2017, and was initially scheduled to conclude on December 30, 2018, prior to this extension.
View the file
Other files
Show 40 more
50 files listed here. See the rest on GovTribe.
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
File details come from the government source that posted it. Updated .